This article provides a detailed overview of the scope and time management plans for The Bungalow Project, including project goals and objectives, project scope statement, work breakdown structure, and project schedule. The article also includes information on project assumptions, constraints, and success criteria.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Scope and Time Management Plans
The Bungalow Project
Name of the Student:
Student ID:
Name of the University:
Author’s note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Part B – Scope and Time Management Plans
Project Goals and Objectives
The Bungalow Project is developed for constructing a bungalow on the strip footings by
aligning with the construction project management principles and techniques. The project would
be completed in order to develop the final bungalow construction for activities. The project
would support the alignment of the effective and smart development activities for aligning with
the utilization of the successful building construction. The following are the goals and objectives
of the project,
Project Goals
The Bungalow Project is developed for aligning with the development of the successful
integration of the construction project. The construction project principles and techniques would
support the alignment of the improved project construction and development. The Bungalow
Project has the primitive goal of constructing the bungalow in the estimated time duration and
budget. It would align the construction of the building by aligning with the development of the
specific construction materials. The completion of the construction activities for the Bungalow
Project would be aligned for involving the formation of the effective project goals. The project
goal is the completion of the construction activities for the complete project.
Project Objectives
The Bungalow Project is aligned with the development of the construction activities that
would be aligned with the completion of the infrastructure development of the bungalow with 6
rooms. The objectives of the Bungalow Project are given below,
Document Page
ï‚· To develop a project plan that would bind the construction of the
bungalow in an effective manner
ï‚· To complete the project by aligning with the scope trio constraint and
meeting the WHS policy and guidelines
ï‚· To perform the significant development of the activities for the specific
construction development
ï‚· To align the construction principles and project management techniques
successfully for the project
Project Scope Statement
Project Scope Statement
Project Name: ‘The Bungalow Project’
Product Needs: The construction of the bungalow would involve the listing of specific
bungalow for the lines of the alignment of construction. The construction of the bungalow would
include the strip footings, double brick veneer, and timber studwork. The bungalow wall
construction would involve the utilization of the external development model. The utilization of
the constructed walls would support the development of the effective and improved analysis of
the specific construction project activities. The floor development would support the
infrastructure development of the bungalow. The deployment of the effective structure for the
bungalow would support the alignment of the effective construction of the building.
Product Description: The construction of the building would be aligned with the successful
alignment of the operations and formation of the successful development of the activities. The
development of the bungalow would be aligned for the alignment of the functional development
of the construction activities. The construction of the bungalow would be supported by the
Document Page
labourers and tradesperson. The completion of the project would be financed by the loan from
the banks as the bank would plan the role of investor in the project.
Deliverables: The deliverables for the project are,
Complete bungalow infrastructure aligned with the development at the strip footings
The double brick veneer external walls and timber studwork internal walls are also developed
Supporting Material of brick piers and timber joists for the floor
Tiled roofs that had been laid upon the external gutters
Scope
In-scope
Construction of the bungalow
Project Plan Development
Budget Estimation Report
Schedule Development for the project
execution
Out of Scope
Transportation Requirements
Alignment of the change management plan
Assumptions
The project would include the following assumptions,
ï‚· Resource acquisition for the project
ï‚· Team workers would work in harmony
ï‚· No major problem would be faced during the project
Constraints
The project would include the following constraints,
Time Constraint
Budget Constraint

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Quality Constraint
Climatic Condition Constraint
Success Criteria
Development of a project plan that would bind the construction of the bungalow in an effective
manner
Completion the project by aligning with the scope trio constraint and meeting the WHS policy
and guidelines
Performing the significant development of the activities for the specific construction
development
Alignment of the construction principles and project management techniques successfully for the
project
Document Page
Work Breakdown Structure
The work breakdown structure for ‘The Bungalow Project’ is given below,
WBS Task Name Duration Start Finish
0 The Bungalow Project 36 wks Mon 7/2/18 Fri 3/8/19
A Clear Ground 2 wks Mon 7/2/18 Fri 7/13/18
B Lay Foundations 3 wks Mon 7/16/18 Fri 8/3/18
C Build Dwarf Walls 2 wks Mon 8/6/18 Fri 8/17/18
D Oversite Concrete 1 wk Mon 8/6/18 Fri 8/10/18
E Floor Joists 2 wks Mon 8/20/18 Fri 8/31/18
F Main Walls 5 wks Mon 9/3/18 Fri 10/5/18
G Door and Windows Frames 3 wks Mon 9/3/18 Fri 9/21/18
H Ceiling Joists 2 wks Mon 10/8/18 Fri 10/19/18
J Roof Timbers 6 wks Mon 10/8/18 Fri 11/16/18
K Tiles 2 wks Mon 11/19/18 Fri 11/30/18
L Floorboards 3 wks Mon 11/19/18 Fri 12/7/18
M Ceiling Boards 2 wks Mon 12/10/18 Fri 12/21/18
N Skirting 1 wk Mon 12/10/18 Fri 12/14/18
P Glazing 2 wks Mon 12/24/18 Fri 1/4/19
Q Plastering 2 wks Mon 1/7/19 Fri 1/18/19
R Electrics 3 wks Mon 1/7/19 Fri 1/25/19
S Plumbing and heating 4 wks Mon 1/7/19 Fri 2/1/19
T Painting 5 wks Mon 2/4/19 Fri 3/8/19
Document Page
The Bungalow Project
Clear Ground
Lay Foundations
Build Dwarf Walls
Oversite Concrete
Floor Joists
Main Walls
Door and Windows
Frames
Ceiling Joists
Roof Timbers
Tiles
Floorboards
Ceiling Boards
Skirting
Glazing
Plastering
Electrics
Plumbing and
heating
Painting

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Project Schedule
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 The Bungalow Project 36 wks Mon 7/2/18Fri 3/8/19
1 A Clear Ground 2 wks Mon 7/2/18 Fri 7/13/18
2 B Lay Foundations 3 wks Mon 7/16/18Fri 8/3/18
3 C Build Dwarf Walls 2 wks Mon 8/6/18 Fri 8/17/18
4 D Oversite Concrete 1 wk Mon 8/6/18 Fri 8/10/18
5 E Floor Joists 2 wks Mon 8/20/18Fri 8/31/18
6 F Main Walls 5 wks Mon 9/3/18 Fri 10/5/18
7 G Door and Windows Frames3 wks Mon 9/3/18 Fri 9/21/18
8 H Ceiling Joists 2 wks Mon 10/8/18Fri 10/19/18
9 J Roof Timbers 6 wks Mon 10/8/18Fri 11/16/18
10 K Tiles 2 wks Mon 11/19/18Fri 11/30/18
11 L Floorboards 3 wks Mon 11/19/18Fri 12/7/18
12 M Ceiling Boards 2 wks Mon 12/10/18Fri 12/21/18
13 N Skirting 1 wk Mon 12/10/18Fri 12/14/18
14 P Glazing 2 wks Mon 12/24/18Fri 1/4/19
15 Q Plastering 2 wks Mon 1/7/19 Fri 1/18/19
16 R Electrics 3 wks Mon 1/7/19 Fri 1/25/19
17 S Plumbing and heating 4 wks Mon 1/7/19 Fri 2/1/19
18 T Painting 5 wks Mon 2/4/19 Fri 3/8/19
Resource A Labourers[600%],Material and Plant @2[100]
Resource A Labourers[400%],Resource B Tradesmen[200%],Material and Plant @3[1,200]
Resource A Labourers[200%],Resource B Tradesmen[400%],Material and Plant @2[700]
Resource A Labourers[400%],Material and Plant @1[800]
Resource B Tradesmen[200%],Material and Plant @2[500]
Resource A Labourers[200%],Resource B Tradesmen[400%],Material and Plant @5[1,400]
Resource B Tradesmen[200%],Material and Plant @3[600]
Resource B Tradesmen[200%],Material and Plant @2[600]
Resource B Tradesmen[200%],Material and Plant @6[600]
Resource A Labourers[200%],Resource B Tradesmen[300%],Material and Plant @2[1,200]
Resource B Tradesmen[200%],Material and Plant @3[700]
Resource B Tradesmen[200%],Material and Plant @2[200]
Resource B Tradesmen[200%],Material and Plant @1[200]
Resource B Tradesmen[200%],Material and Plant @2[400]
Resource A Labourers,Resource B Tradesmen[300%],Material and Plant @2[300]
Resource B Tradesmen[200%],Material and Plant @3[600]
Resource A Labourers,Resource B Tradesmen[300%],Material and Plant @4[900]
Resource B Tradesmen[400%],Material and Plant @3[300]
T M F T S W S T M F T S W S T M F T
Apr 22, '18 Jul 1, '18 Sep 9, '18 Nov 18, '18 Jan 27, '19 Apr 7, '19 Jun 16, '19 Aug 25, '19 Nov 3, '19
0 1 2 2 2 5 5 3 7 7 5 9 9 6 14 14 9 20 20 11 23 23 12 25 25 14 27 27 17 31 31 18 34
0 2 2 2 3 5 5 2 7 7 2 9 9 5 14 14 6 20 20 3 23 23 2 25 25 2 27 27 4 31 31 3 34
5 4 6 9 7 12 12 8 14 20 10 22 23 13 24 27 15 29
6 1 7 11 3 14 18 2 20 22 2 24 24 1 25 29 2 31
27 16 30
28 3 31
Document Page
Bibliography
Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach.
Routledge.
Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt
Assn.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley &
Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
McGowan, J., Sampson, M., Salzwedel, D. M., Cogo, E., Foerster, V., & Lefebvre, C. (2016).
PRESS peer review of electronic search strategies: 2015 guideline statement. Journal of
clinical epidemiology, 75, 40-46.
Pheng, L. S. (2018). Project Scope Management. In Project Management for the Built
Environment (pp. 63-77). Springer, Singapore.
Schwalbe, K. (2015). Information technology project management. Cengage Learning.