Implementation Plan for Refurbishment of Care Room - Desklib
Verified
Added on 2023/06/04
|53
|8768
|421
AI Summary
This project aims to provide an implementation plan for the refurbishment of the organization care room. The plan includes roles and responsibilities, resources and budget, stakeholders and analysis, communication plan, project plan, and more.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Undertake Project Work
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents 1Introduction.......................................................................................................................2 2AT1 Project.......................................................................................................................2 2.1Roles and Responsibilities.........................................................................................3 2.2Resources and budget................................................................................................3 2.3Stakeholders and Analysis........................................................................................4 3AT2 Project.......................................................................................................................4 3.1Communication Plan.................................................................................................4 3.2Project Plan................................................................................................................4 3.3Gantt chart Mind Tools and Work breakdown structure...................................17 3.4Workgroup Planning...............................................................................................19 3.5Risk register.............................................................................................................20 3.6Resource and cost plan............................................................................................20 4AT3 Project.....................................................................................................................24 5Conclusion.......................................................................................................................46 1
1Introduction Main objective of this project is to provide the implementation plan for refurbishment of the organization care room because the care room owner asked user to organise the refurbishment of the one of the care rooms for a single age care resident. So, user needs to provide the implementation plan for care rooms.The implementation plan is maintain a positive experience, clearly communicate and consult with all stakeholders. The Project implementation is done by using the Microsoft Project 2016. These are will be implemented and discussed in detail. 2AT1 Project This project implement the existing care room to organise the refurbishment of the one of the care rooms for a single age care resident. Because, the existing care rooms has following issues (A guide to the project management body of knowledge, 2017). From Staff, 1.Unaware of legal obligations 2.Conflict handling difficulty 3.Stressed and confused and feel they have not been kept up to date with information. For Builders, 1.Insufficient Barriers 2.Residents/clients seeking information from them 3.Lack of wastage bins and space. 4.Unrealistic time frames set by the organization From Clients, 1.Have a wastage issues, noise and dust. 2.Diverse languages and clients do not understand the information they have received 3.Upset at delays to having the dining room back to normal operations 4.Unsure who is in charge as to satisfy a complaint And, this project include some conditions such as, Refurbishment completion of Budget is $40,000 including repainting of resident room EST $4000, replacement and removal of old build in furniture EST $20000 and old or damage equipment replacement EST%15000. The resources are included in budget (Biafore, 2013). 2
2.1Roles and Responsibilities To assign the roles and responsibilities for this project is to important part. It is the process for selecting the right people to hiring the organisation or the constructional process management. It is used to ensure with the fulfil business needs to the employee. We must take into the internal and external changes with the company business plan. 2.2Resources and budget The identified resources are listed below (Shtub, 2016). Project Engineer Site Foreman Plant operator General laborer Principal Surveyor (Registered) Senior Surveyor Surveyor Survey Draftsperson Survey Assistant Arborist Hygienist Asbestos Removals Supervisor Asbestos Removals Laborer Senior Environmental Consultant Environmental Consultant Structural Engineer Contractor Contractor Assistant The budget for this project is illustrated as below (Cicala, 2013). NameRemainingActualCostACWPBCWPBCWS 3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
CostCost CareRoom Implementation Plan $109,900.00$0.00$109,900.00$0.00$0.00$0.00 2.3Stakeholders and Analysis The stake holders are most important responsibility for a project. The stakeholders are has the power to change and respond the strategic and future of the project. The stakeholders are play vital role on the project like external or internal and senior or junior level roles. 3AT2 Project 3.1Communication Plan In project, the communication plan is an essential thinks to provide the effective project for an organization. The communication plan included the project related plan like project topics, project delivery date or delay date information. And, also this plan handles the immediate decision based on the project and sensitive issues (Happy, 2010). 3.2Project Plan The project plan included the project tasks, resources and cost information. Project Tasks The project Task is illustrated as below Task Name Care Room Implementation Plan Initialization Gather the Project Requirements Analysis the project requirements Gather and Analysis the Existing Care Room Issues Preliminaries Site establishment & maintenance site office and amenities Survey Control Preparation and submission and approval of PQP, ITPs, Project WHS Plan, Environmental and Waste Management Plan 4
Preparation of Project Plans Preparation of Construction and Environmental Management Plan Liaison and Approvals from all Authorities Liaison and Co‐ordination with adjoining work sites / residential / business dwellings Approvals and Fees for Required Technical Support Compliance and Audit Testing as Directed by the Principal's Authorised Person PS Additional Work as Directed by the Principals Authorised Person (PAP) PS Work‐as‐executed Information Provision for traffic Legal obligations Monitor and follow the quality standards and legal obligations Use professional language at all times Be fair and allow for flexibility with your audience Ensure you maintain privacy and confidentiality Design Target Location Building Profile Capacity Space Requirements Layout - Room Plan Furniture Construction Plan Infrastructure Building Permits Amenities First Review 5
Development Earth works Protection of the Works Clearing and grubbing Removal of Tree Removal of Pavement Extra over Pay Item for Saw Cutting Pavement Removal of Concrete Kerbs Removal of Paths and Driveways Removal and Stockpiling topsoil Removal and Stockpiling topsoil on site General Earthworks Disposal of Spoil Material Off Site Imported Fill Removal of hazardous materials and remediation of areas of environmental concern and providing clearance Underground Services Excavation & Backfilling Backfilling Under Roads, Paths and Driveways Existing Services Location Sewer Storm water Gas Electricity Water Telecommunication Sewerage Works by the Sewer Authority (ICON) Works by the Sewer Authority to existing sewer services Works by the Contractor on existing sewer services, 6
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
excluding works by the Sewer Authority Removal of all internal in ground sewer services Water Supply Mains Works by the Water Authority (ICON) Works by the Water Authority to existing sewer services (ICON) Works by the Contractor on existing water services, excluding works by the Sewer Authority Removal of all internal in ground water services Incidentals Fencing Fence Type T Removal of Existing Fences Power Supply Disconnection Works by Actew AGL Works by the Contractor Comms Supply Disconnection Works by Telstra Works by the Contractor Site Establishment Supply, install, and maintain hoardings and temporary fences Undertake a full dilapidation survey of the site Install and maintain clearly signposted and safe site access gates. Approvals and Documentation Prepare and submit a Building Application and engage Building Certifier for works The Contractor shall prepare and submit a TTM plan The Contractor is to provide program and methodology Submit for approval a demolition method statement 7
Second Review Refurbishment Hazardous Materials Removal Asbestos Containing Materials (ACM’s) Air Monitoring Environmental Clearances to proceed with the demolition works. Underground Fuel Storage Tank (UST) Establish and maintain environmental controls in accordance with RAP Excavate and stockpile spoil at AEC (UST) Remove and dispose of pipes, valves and vent lines associated with UST Remove and dispose of UST Validation sampling of stockpile (1 round) Removal and disposal of stockpile spoil including all fees Additional validation sampling Additional spoil disposal Unexpected Finds Demolition Works Demolition of Buildings Demolition of Minor Structures Retaining Walls (Brick) Courtyard Walls (Brick) Concrete Stairs Light Poles, Light Bollards, log barriers & Signs etc. Gas Meter Brick Enclosure Implementation and Evaluation Add Hazardous Materials Asbestos Containing Materials (ACM’s) Air Monitoring 8
Environmental Clearances to proceed the implementation works. Third Review Underground Fuel Storage Tank (UST) Establish and maintain environmental controls in accordance with RAP Excavate and stockpile spoil at AEC (UST) Add of pipes, valves and vent lines associated with UST Validation sampling of stockpile (1 round) Additional validation sampling Unexpected Finds Implementation of Buildings Retaining Walls (Brick) Courtyard Walls (Brick) Concrete Stairs Light Poles, Light Bollards, log barriers & Signs etc. Reports and Completion Minutes of the meeting Handover report Post-project review report Project completion The Project plan is illustrated as below (Heerkens, 2015). Task NameDurationStartFinishResource Names Care Room Implementation Plan180 daysThu 1/1/15Wed 9/9/15 Initialization3 daysThu 1/1/15Mon 1/5/15 Gather the Project Requirements1 dayThu 1/1/15Thu 1/1/15 Analysis the project requirements1 dayFri 1/2/15Fri 1/2/15 Gather and Analysis the Exisiting Care Room Issues1 dayMon 1/5/15Mon 1/5/15 9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Preliminaries32 daysTue 1/6/15Wed 2/18/15 Site establishment & maintenance site office and amenities 2 daysTue 1/6/15Wed 1/7/15 Project Engineer ,Site Foreman Survey Control2 daysThu 1/8/15Fri 1/9/15 Survey Assistant ,Surveyor, Senior Surveyor Preparation and submission and approval of PQP, ITPs, Project WHS Plan, Environmental and Waste Management Plan 2 daysMon 1/12/15Tue 1/13/15 Principal Surveyor (Registered) ,Project Engineer Preparation of Project Plans2 daysWed 1/14/15Thu 1/15/15 Project Engineer ,Contractor , Contractor Assistant Preparation of Construction and Environmental Management Plan2 daysFri 1/16/15Mon 1/19/15 Contractor, Contractor Assistant, Project Engineer Liaison and Approvals from all Authorities2 daysTue 1/20/15 Wed 1/21/15 Principal Surveyor (Registered) ,Senior Environmental Consultant ,Senior Surveyor Liaison and Co‐ordination with adjoining work sites / residential / business dwellings 2 daysThu 1/22/15Fri 1/23/15 Senior Environmental Consultant ,Senior Surveyor Approvals and Fees for Required Technical Support2 daysMon 1/26/15Tue 1/27/15Contractor, Project Engineer Compliance and Audit Testing as Directed by the Principal's Authorised Person PS 2 daysWed 1/28/15 Thu 1/29/15Senior Surveyor ,Survey Draftsperson ,Survey 10
or Additional Work as Directed by the Principals Authorised Person (PAP) PS 2 daysFri 1/30/15Mon 2/2/15Principal Surveyor (Registered) Work‐as‐executed Information4 daysTue 2/3/15Fri 2/6/15 Project Engineer ,Structural Engineer Provision for traffic4 daysMon 2/9/15Thu 2/12/15 General labourer ,Senior Environmental Consultant Legal obligations4 daysFri 2/13/15Wed 2/18/15 Monitor and follow the quality standards and legal obligations1 dayFri 2/13/15Fri 2/13/15Project Engineer Use professional language at all times1 dayMon 2/16/15 Mon 2/16/15Project Engineer Be fair and allow for flexibility with your audience1 dayTue 2/17/15Tue 2/17/15Project Engineer Ensure you maintain privacy and confidentiality1 dayWed 2/18/15 Wed 2/18/15Project Engineer Design10 daysThu 2/19/15Wed 3/4/15 Target Location1 dayThu 2/19/15Thu 2/19/15Project Engineer Building Profile2 daysFri 2/20/15Mon 2/23/15 Capacity1 dayFri 2/20/15Fri 2/20/15 Contractor, Contractor Assistant, Project Engineer ,Site Foreman 11
Space Requirements1 dayMon 2/23/15 Mon 2/23/15 Contractor, Contractor Assistant, Site Foreman Layout - Room Plan1 dayTue 2/24/15Tue 2/24/15 Contractor, Contractor Assistant, Project Engineer Furniture1 dayWed 2/25/15 Wed 2/25/15 Contractor, Project Engineer Construction Plan1 dayThu 2/26/15Thu 2/26/15Contractor, Project Engineer Infrastructure1 dayFri 2/27/15Fri 2/27/15 Contractor, General labourer ,Project Engineer Building Permits1 dayMon 3/2/15Mon 3/2/15 Contractor, Contractor Assistant, Project Engineer Amenities1 dayTue 3/3/15Tue 3/3/15 Contractor, General labourer ,Site Foreman First Review1 dayWed 3/4/15Wed 3/4/15 Contractor, Contractor Assistant, Project Engineer Development67 daysThu 3/5/15Fri 6/5/15 Earth works10 daysThu 3/5/15Wed 3/18/15 Protection of the Works1 dayThu 3/5/15Thu 3/5/15 Project Engineer ,Structural Engineer Clearing and grubbing1 dayFri 3/6/15Fri 3/6/15 Removal of Tree1 dayFri 3/6/15Fri 3/6/15 General labourer ,Plant operator 12
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Engineer Water1 dayFri 3/27/15Fri 3/27/15 General labourer ,Senior Environmental Consultant ,Structura l Engineer Telecommunication1 dayMon 3/30/15 Mon 3/30/15 Site Foreman ,Survey Assistant ,Survey Draftsperson Sewerage4 daysTue 3/31/15Fri 4/3/15 Works by the Sewer Authority (ICON)1 dayTue 3/31/15Tue 3/31/15 Survey Assistant ,Survey Draftsperson ,Survey or Works by the Sewer Authority to existing sewer services1 dayWed 4/1/15Wed 4/1/15 Senior Surveyor ,Survey Assistant ,Survey Draftsperson ,Survey or Works by the Contractor on existing sewer services, excluding works by the Sewer Authority 1 dayThu 4/2/15Thu 4/2/15 Senior Surveyor ,Survey Assistant ,Survey Draftsperson ,Survey or Removal of all internal in ground sewer services1 dayFri 4/3/15Fri 4/3/15 Senior Environmental Consultant ,Senior Surveyor ,Structural Engineer, Survey Assistant 15
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Water Supply Mains6 daysMon 4/6/15Mon 4/13/15 Works by the Water Authority (ICON)1 dayMon 4/6/15Mon 4/6/15 Senior Surveyor ,Site Foreman ,Survey Assistant Works by the Water Authority to existing sewer services (ICON) 1 dayTue 4/7/15Tue 4/7/15 Site Foreman ,Structural Engineer, Survey Draftsperson ,Survey or Works by the Contractor on existing water services, excluding works by the Sewer Authority 2 daysWed 4/8/15Thu 4/9/15 Senior Surveyor ,Structural Engineer, Survey Assistant ,Survey Draftsperson Removal of all internal in ground water services2 daysFri 4/10/15Mon 4/13/15 Principal Surveyor (Registered) ,Project Engineer ,Survey Assistant ,Survey Draftsperson Incidentals14 daysTue 4/14/15Fri 5/1/15 Fencing1 dayTue 4/14/15Tue 4/14/15 Fence Type T1 dayTue 4/14/15Tue 4/14/15 Survey Assistant ,Survey Draftsperson ,Survey or Removal of Existing Fences1 dayWed 4/15/15 Wed 4/15/15 Project Engineer ,Structural Engineer, Survey 16
Assistant Power Supply Disconnection2 daysThu 4/16/15Fri 4/17/15 Works by ActewAGL1 dayThu 4/16/15Thu 4/16/15 Survey Assistant ,Survey Draftsperson Works by the Contractor1 dayFri 4/17/15Fri 4/17/15 Project Engineer ,Structural Engineer, Survey Assistant ,Survey Draftsperson Comms Supply Disconnection2 daysMon 4/20/15Tue 4/21/15 Works by Telstra1 dayMon 4/20/15 Mon 4/20/15 Project Engineer ,Survey Assistant ,Survey Draftsperson Works by the Contractor1 dayTue 4/21/15Tue 4/21/15Contractor, Contractor Assistant Site Establishment3 daysWed 4/22/15Fri 4/24/15 Supply, install, and maintain hoardings and temporary fences1 dayWed 4/22/15 Wed 4/22/15 Site Foreman ,Survey Assistant ,Survey Draftsperson Undertake a full dilapidation survey of the site1 dayThu 4/23/15Thu 4/23/15 Contractor, Contractor Assistant, General labourer ,Project Engineer Install and maintain clearly signposted and safe site access 1 dayFri 4/24/15Fri 4/24/15Contractor, Contractor Assistant, 17
gates. General labourer ,Project Engineer ,Structural Engineer Approvals and Documentation4 daysMon 4/27/15Thu 4/30/15 Prepare and submit a Building Application and engage Building Certifier for works 1 dayMon 4/27/15 Mon 4/27/15 Contractor, Project Engineer ,Structural Engineer The Contractor shall prepare and submit a TTM plan1 dayTue 4/28/15Tue 4/28/15Contractor, Contractor Assistant The Contractor is to provide program and methodology1 dayWed 4/29/15 Wed 4/29/15 Contractor, Contractor Assistant, Project Engineer Submit for approval a demolition method statement1 dayThu 4/30/15Thu 4/30/15 Contractor, Contractor Assistant, Project Engineer ,Senior Environmental Consultant ,Structura l Engineer Second Review1 dayFri 5/1/15Fri 5/1/15 Refurbishment25 daysMon 5/4/15Fri 6/5/15 Hazardous Materials Removal1 dayMon 5/4/15Mon 5/4/15 Asbestos Removals Labourer ,Asbestos Removals Supervisor, Contractor, Project Engineer Asbestos Containing Materials (ACM’s) 1 dayTue 5/5/15Tue 5/5/15Arborist ,Asbestos Removals Labourer ,Contractor 18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
IDTask Name 1Care Room Implementation Plan 2Initialization 3Gather the Project Requirements 4Analysis the project requirements 5Gather and Analysis the Exisiting Care Room Issues 6Preliminaries 7Site establishment & maintenance site office and amenities 8Survey Control 9Preparation and submission and approval of PQP, ITPs, Project WHS Plan, Environmental and Waste Management Plan10Preparation of Project Plans 11Preparation of Construction and Environmental Management Plan 12Liaison and Approvals from all Authorities 13Liaison and Co‐ ordination with adjoining work sites / residential / business dwellings14Approvals and Fees for Required Technical Support 15Compliance and Audit Testing as Directed by the Principal's Authorised Person PS16Additional Work as Directed by the Principals Authorised Person (PAP) PS17Work‐ as‐ executed Information 18Provision for traffic 19Legal obligations 20Monitor and follow the quality standards and legal obligations 21Use professional language at all times 22Be fair and allow for flexibility with your audience 23Ensure you maintain privacy and confidentiality 24Design Project Engineer ,Site Foreman Survey Assistant ,Surveyorr,Senior Surveyor Principal Surveyor (Registered) ,Project Engineer Project Engineer ,Contractor,Contractor Assistant Contractor,Contractor Assistant,Project Engineer Principal Surveyor (Registered) ,Senior Environmental Consultant ,Senio Senior Environmental Consultant ,Senior Surveyor Contractor,Project Engineer Senior Surveyor ,Survey Draftsperson ,Surveyo Principal Surveyor (Registered) Project Engineer ,Stru Ge FSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTF Dec 28, '14Jan 4, '15Jan 11, '15Jan 18, '15Jan 25, '15Feb 1, '15 IDTask Name 4Analysis the project requirements 5Gather and Analysis the Exisiting Care Room Issues 6Preliminaries 7Site establishment & maintenance site office and amenities 8Survey Control 9Preparation and submission and approval of PQP, ITPs, Project WHS Plan, Environmental and Waste Management Plan10Preparation of Project Plans 11Preparation of Construction and Environmental Management Plan 12Liaison and Approvals from all Authorities 13Liaison and Co‐ ordination with adjoining work sites / residential / business dwellings14Approvals and Fees for Required Technical Support 15Compliance and Audit Testing as Directed by the Principal's Authorised Person PS16Additional Work as Directed by the Principals Authorised Person (PAP) PS17Work‐ as‐ executed Information 18Provision for traffic 19Legal obligations 20Monitor and follow the quality standards and legal obligations 21Use professional language at all times 22Be fair and allow for flexibility with your audience 23Ensure you maintain privacy and confidentiality 24Design 25Target Location 26Building Profile 27Capacity Project Engineer ,Site Foreman Survey Assistant ,Surveyorr,Senior Surveyor Principal Surveyor (Registered) ,Project Engineer Project Engineer ,Contractor,Contractor Assistant Contractor,Contractor Assistant,Project Engineer Principal Surveyor (Registered) ,Senior Environmental Consultant ,Senior Surveyor Senior Environmental Consultant ,Senior Surveyor Contractor,Project Engineer Senior Surveyor ,Survey Draftsperson ,Surveyorr Principal Surveyor (Registered) Project Engineer ,Structural Engineer General labourer ,Senior Environmental Consultant Project Engineer Project Engineer Project Engineer Project Engineer Project Engineer Contractor,Contractor Assistant,Project Engineer ,Site Foreman TFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWT Jan 25, '15Feb 1, '15Feb 8, '15Feb 15, '15Feb 22, '15Mar 1, '15 25
IDTask Name 25Target Location 26Building Profile 27Capacity 28Space Requirements 29Layout - Room Plan 30Furniture 31Construction Plan 32Infrastructure 33Building Permits 34Amenities 35First Review 36Development 37Earth works 38Protection of the Works 39Clearing and grubbing 40Removal of Tree 41Removal of Pavement 42Extra over Pay Item for Saw Cutting Pavement 43Removal of Concrete Kerbs 44Removal of Paths and Driveways 45Removal and Stockpiling topsoil 46Removal and Stockpiling topsoil on site 47General Earthworks 48Disposal of Spoil Material Off Site 49Imported Fill 50Removal of hazardous materials and remediation of areas of environmental concern and providing clearance51Underground Services Project Engineer Contractor,Contractor Assistant,Project Engineer ,Site Foreman Contractor,Contractor Assistant,Site Foreman Contractor,Contractor Assistant,Project Engineer Contractor,Project Engineer Contractor,Project Engineer Contractor,General labourer ,Project Engineer Contractor,Contractor Assistant,Project Engineer Contractor,General labourer ,Site Foreman Contractor,Contractor Assistant,Project Engineer Project Engineer ,Structural Engineer General labourer ,Plant operator Environmental Consultant ,General labourer ,Plant operator Plant operator ,General labourer ,Senior Environmental Consultant Plant operator ,General labourer Asbestos Removalist Labourer ,Asbestos Removalist Supervisor Asbestos Removalist Labourer ,Asbestos Removalist Supervisor,Envir General labourer Senior Surveyor General labourer ,Project Engineer SSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFS Feb 15, '15Feb 22, '15Mar 1, '15Mar 8, '15Mar 15, '15Mar 22, '15 3.4Workgroup Planning The work group planning is shown below (Kerzner, n.d.). Resource Status NameStartFinishRemaining Work Project EngineerTue 1/6/15Wed 9/9/151,000 hrs Site ForemanTue 1/6/15Wed 4/22/1592 hrs Plant operatorFri 3/6/15Fri 5/22/1540 hrs General laborerMon 2/9/15Wed 8/12/15280 hrs PrincipalSurveyor (Registered) Mon 1/12/15Mon 4/13/1564 hrs Senior SurveyorThu 1/8/15Fri 7/17/15152 hrs SurveyorThu 1/8/15Wed 7/22/15104 hrs Survey DraftspersonWed 1/28/15Wed 4/22/15128 hrs Survey AssistantThu 1/8/15Wed 4/22/15144 hrs ArboristTue 5/5/15Wed 6/24/1548 hrs HygienistNANA0 hrs 26
Asbestos Removals SupervisorThu 3/12/15Tue 8/4/15112 hrs Asbestos Removals LabourerThu 3/12/15Wed 6/24/15152 hrs SeniorEnvironmental Consultant Tue 1/20/15Wed 7/22/15296 hrs Environmental ConsultantMon 3/9/15Wed 7/22/15232 hrs Structural EngineerTue 2/3/15Thu 9/3/15496 hrs ContractorWed 1/14/15Tue 9/8/15672 hrs Contractor AssistantWed 1/14/15Thu 9/3/15384 hrs 3.5Risk Register This implementation has the risks and it needs to reduce by using the risk register method. It is illustrated as below. 3.6Resource and cost plan Resource Plan The resource information is shown below (Marchewka, n.d.). Resource NameTypeInitialsMax. UnitsStd. RateAccrue At Base Calendar 27
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Cash Flow chart is illustrated as below. 123 $0.00 $5,000.00 $10,000.00 $15,000.00 $20,000.00 $25,000.00 $30,000.00 $35,000.00 $40,000.00 $45,000.00 $50,000.00 $0.00 $20,000.00 $40,000.00 $60,000.00 $80,000.00 $100,000.00 $120,000.00 CostCumulative Cost 12/21/14 1/18/15 2/15/15 3/15/15 4/12/15 5/10/15 6/7/15 7/5/15 8/2/15 8/30/15 0% 1% 1% $0.00 $20,000.00 $40,000.00 $60,000.00 $80,000.00 $100,000.00 $120,000.00 Chart Title Cumulative Percent CompleteCumulative Cost % Complete Cumulative Cost 4AT3 Project The Final Project is illustrated as below (Schwalbe, n.d.). Task ModeTask NameDurationStartFinishPredecessorsResource Names Auto Scheduled Care Room Implementation Plan180 daysThu 1/1/15 Wed 9/9/15 Auto ScheduledInitialization3 daysThu 1/1/15 Mon 1/5/15 Auto Scheduled Gather the Project Requirements1 dayThu 1/1/15 Thu 1/1/15 31
Auto Scheduled Analysis the project requirements1 dayFri 1/2/15 Fri 1/2/153 Auto Scheduled Gather and Analysis the Existing Care Room Issues 1 dayMon 1/5/15 Mon 1/5/154 Auto ScheduledPreliminaries32 daysTue 1/6/15 Wed 2/18/152 Auto Scheduled Site establishment & maintenance site office and amenities 2 daysTue 1/6/15 Wed 1/7/15 Project Engineer ,Site Foreman Auto ScheduledSurvey Control2 daysThu 1/8/15 Fri 1/9/157 Survey Assistant ,Surv eyor, Senior Surveyor Auto Scheduled Preparation and submission and approval of PQP, ITPs, Project WHS Plan, Environmental and Waste Management Plan 2 daysMon 1/12/15 Tue 1/13/158 Principal Surveyor (Registered) ,P roject Engineer Auto Scheduled Preparation of Project Plans2 daysWed 1/14/15 Thu 1/15/159 Project Engineer ,Cont ractor, Contractor Assistant Auto Scheduled Preparation of Construction and Environmental Management Plan 2 daysFri 1/16/15 Mon 1/19/1510 Contractor, Contractor Assistant, Project Engineer Auto Scheduled Liaison and Approvals from all Authorities 2 daysTue 1/20/15 Wed 1/21/15 11Principal Surveyor (Registered) ,S 32
enior Environmental Consultant ,Se nior Surveyor Auto Scheduled Liaison and Co‐ ordination with adjoining work sites / residential / business dwellings 2 daysThu 1/22/15 Fri 1/23/1512 Senior Environmental Consultant ,Se nior Surveyor Auto Scheduled Approvals and Fees for Required Technical Support 2 daysMon 1/26/15 Tue 1/27/1513 Contractor, Project Engineer Auto Scheduled Compliance and Audit Testing as Directed by the Principal's Authorised Person PS 2 daysWed 1/28/15 Thu 1/29/1514 Senior Surveyor ,Surv ey Draftsperson ,S urveyor Auto Scheduled Additional Work as Directed by the Principals Authorised Person (PAP) PS 2 daysFri 1/30/15 Mon 2/2/1515 Principal Surveyor (Registered) Auto Scheduled Work‐as‐executed Information4 daysTue 2/3/15 Fri 2/6/1516 Project Engineer ,Struc tural Engineer Auto ScheduledProvision for traffic4 daysMon 2/9/15 Thu 2/12/1517 General labourer ,Senio r Environmental Consultant Auto ScheduledLegal obligations4 daysFri 2/13/15 Wed 2/18/1518 Auto Scheduled Monitor and follow the quality standards and 1 dayFriFriProject 33
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
legal obligations2/13/152/13/15Engineer Auto Scheduled Use professional language at all times1 dayMon 2/16/15 Mon 2/16/1520Project Engineer Auto Scheduled Be fair and allow for flexibility with your audience 1 dayTue 2/17/15 Tue 2/17/1521Project Engineer Auto Scheduled Ensure you maintain privacy and confidentiality 1 dayWed 2/18/15 Wed 2/18/1522Project Engineer Auto ScheduledDesign10 daysThu 2/19/15 Wed 3/4/156 Auto ScheduledTarget Location1 dayThu 2/19/15 Thu 2/19/15 Project Engineer Auto ScheduledBuilding Profile2 daysFri 2/20/15 Mon 2/23/1525 Auto ScheduledCapacity1 dayFri 2/20/15 Fri 2/20/15 Contractor, Contractor Assistant, Project Engineer ,Site Foreman Auto Scheduled Space Requirements1 dayMon 2/23/15 Mon 2/23/1527 Contractor, Contractor Assistant, Site Foreman Auto ScheduledLayout - Room Plan1 dayTue 2/24/15 Tue 2/24/1526 Contractor, Contractor Assistant, Project Engineer Auto Scheduled Furniture1 dayWed 2/25/15 Wed 2/25/15 29Contractor, Project 34
Engineer Auto ScheduledConstruction Plan1 dayThu 2/26/15 Thu 2/26/1530 Contractor, Project Engineer Auto ScheduledInfrastructure1 dayFri 2/27/15 Fri 2/27/1531 Contractor, General labourer ,Proje ct Engineer Auto ScheduledBuilding Permits1 dayMon 3/2/15 Mon 3/2/1532 Contractor, Contractor Assistant, Project Engineer Auto ScheduledAmenities1 dayTue 3/3/15 Tue 3/3/1533 Contractor, General labourer ,Site Foreman Auto ScheduledFirst Review1 dayWed 3/4/15 Wed 3/4/1534 Contractor, Contractor Assistant, Project Engineer Auto ScheduledDevelopment67 daysThu 3/5/15 Fri 6/5/1524 Auto ScheduledEarth works10 daysThu 3/5/15 Wed 3/18/156 Auto Scheduled Protection of the Works1 dayThu 3/5/15 Thu 3/5/15 Project Engineer ,Struc tural Engineer Auto Scheduled Clearing and grubbing1 dayFri 3/6/15 Fri 3/6/1538 AutoRemoval of Tree1 dayFriFriGeneral 35
Scheduled3/6/153/6/15labourer ,Plant operator Auto Scheduled Removal of Pavement1 dayMon 3/9/15 Mon 3/9/1539 Auto Scheduled Extra over Pay Item for Saw Cutting Pavement 1 dayMon 3/9/15 Mon 3/9/15 Environmental Consultant ,Ge neral labourer ,Plant operator Auto Scheduled Removal of Concrete Kerbs1 dayTue 3/10/15 Tue 3/10/1541 Plant operator ,Gene ral labourer ,Senio r Environmental Consultant Auto Scheduled Removal of Paths and Driveways1 dayWed 3/11/15 Wed 3/11/1543 Plant operator ,Gene ral labourer Auto Scheduled Removal and Stockpiling topsoil1 dayThu 3/12/15 Thu 3/12/1544 Auto Scheduled Removal and Stockpiling topsoil on site 1 dayThu 3/12/15 Thu 3/12/15 Asbestos Removals Labourer ,Asbe stos Removals Supervisor Auto Scheduled General Earthworks 1 dayFri 3/13/15 Fri 3/13/15 45Asbestos Removals Labourer ,Asbe stos Removals Supervisor, Environmental 36
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Consultant Auto Scheduled Disposal of Spoil Material Off Site1 dayMon 3/16/15 Mon 3/16/1547General labourer Auto ScheduledImported Fill1 dayTue 3/17/15 Tue 3/17/1548Senior Surveyor Auto Scheduled Removal of hazardous materials and remediation of areas of environmental concern and providing clearance 1 dayWed 3/18/15 Wed 3/18/1549 General labourer ,Proje ct Engineer Auto Scheduled Underground Services18 daysThu 3/19/15 Mon 4/13/1537 Auto Scheduled Excavation & Backfilling8 daysThu 3/19/15 Mon 3/30/15 Auto Scheduled Backfilling Under Roads, Paths and Driveways 1 dayThu 3/19/15 Thu 3/19/15 Contractor, Contractor Assistant, Environmental Consultant ,Sit e Foreman Auto Scheduled Existing Services Location1 dayFri 3/20/15 Fri 3/20/1553Site Foreman [150%] Auto ScheduledSewer1 dayMon 3/23/15 Mon 3/23/1554 Project Engineer ,Struc tural Engineer Auto ScheduledStorm water1 dayTue 3/24/15 Tue 3/24/1555 Contractor, Contractor Assistant, Project Engineer ,Struc tural Engineer AutoGas1 dayWedWed56Contractor, 37
Scheduled3/25/153/25/15 Contractor Assistant, Project Engineer ,Struc tural Engineer Auto ScheduledElectricity1 dayThu 3/26/15 Thu 3/26/1557 Contractor, Contractor Assistant, General labourer ,Proje ct Engineer ,Struc tural Engineer Auto ScheduledWater1 dayFri 3/27/15 Fri 3/27/1558 General labourer ,Senio r Environmental Consultant ,Str uctural Engineer Auto ScheduledTelecommunication1 dayMon 3/30/15 Mon 3/30/1559 Site Foreman ,Surv ey Assistant ,Surv ey Draftsperson Auto ScheduledSewerage4 daysTue 3/31/15 Fri 4/3/1552 Auto Scheduled Works by the Sewer Authority (ICON)1 dayTue 3/31/15 Tue 3/31/15 Survey Assistant ,Surv ey Draftsperson ,S urveyor 38
Auto Scheduled Works by the Sewer Authority to existing sewer services 1 dayWed 4/1/15 Wed 4/1/1562 Senior Surveyor ,Surv ey Assistant ,Surv ey Draftsperson ,S urveyor Auto Scheduled Works by the Contractor on existing sewer services, excluding works by the Sewer Authority 1 dayThu 4/2/15 Thu 4/2/1563 Senior Surveyor ,Surv ey Assistant ,Surv ey Draftsperson ,S urveyor Auto Scheduled Removal of all internal in ground sewer services 1 dayFri 4/3/15 Fri 4/3/1564 Senior Environmental Consultant ,Se nior Surveyor ,Stru ctural Engineer, Survey Assistant Auto Scheduled Water Supply Mains6 daysMon 4/6/15 Mon 4/13/1561 Auto Scheduled Works by the Water Authority (ICON)1 dayMon 4/6/15 Mon 4/6/15 Senior Surveyor ,Site Foreman ,Surv ey Assistant Auto Scheduled Works by the Water Authority to existing sewer services (ICON) 1 dayTue 4/7/15 Tue 4/7/15 67Site Foreman ,Struc tural Engineer, Survey 39
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Draftsperson ,S urveyor Auto Scheduled Works by the Contractor on existing water services, excluding works by the Sewer Authority 2 daysWed 4/8/15 Thu 4/9/1568 Senior Surveyor ,Stru ctural Engineer, Survey Assistant ,Surv ey Draftsperson Auto Scheduled Removal of all internal in ground water services 2 daysFri 4/10/15 Mon 4/13/1569 Principal Surveyor (Registered) ,P roject Engineer ,Survey Assistant ,Surv ey Draftsperson Auto ScheduledIncidentals14 daysTue 4/14/15 Fri 5/1/1551 Auto ScheduledFencing1 dayTue 4/14/15 Tue 4/14/15 Auto ScheduledFence Type T1 dayTue 4/14/15 Tue 4/14/15 Survey Assistant ,Surv ey Draftsperson ,S urveyor Auto Scheduled Removal of Existing Fences1 dayWed 4/15/15 Wed 4/15/1572 Project Engineer ,Struc tural Engineer, Survey Assistant 40
Auto Scheduled Power Supply Disconnection2 daysThu 4/16/15 Fri 4/17/1574 Auto Scheduled Works by ActewAGL1 dayThu 4/16/15 Thu 4/16/15 Survey Assistant ,Surv ey Draftsperson Auto Scheduled Works by the Contractor1 dayFri 4/17/15 Fri 4/17/1576 Project Engineer ,Struc tural Engineer, Survey Assistant ,Surv ey Draftsperson Auto Scheduled Comms Supply Disconnection2 daysMon 4/20/15 Tue 4/21/1575 Auto ScheduledWorks by Telstra1 dayMon 4/20/15 Mon 4/20/15 Project Engineer ,Surv ey Assistant ,Surv ey Draftsperson Auto Scheduled Works by the Contractor1 dayTue 4/21/15 Tue 4/21/1579 Contractor, Contractor Assistant Auto Scheduled Site Establishment3 daysWed 4/22/15 Fri 4/24/1578 Auto Scheduled Supply, install, and maintain hoardings and temporary fences 1 dayWed 4/22/15 Wed 4/22/15 Site Foreman ,Surv ey Assistant ,Surv ey Draftsperson AutoUndertake a full1 dayThuThu82Contractor, 41
Scheduleddilapidation survey of the site4/23/154/23/15 Contractor Assistant, General labourer ,Proje ct Engineer Auto Scheduled Install and maintain clearly signposted and safe site access gates. 1 dayFri 4/24/15 Fri 4/24/1583 Contractor, Contractor Assistant, General labourer ,Proje ct Engineer ,Struc tural Engineer Auto Scheduled Approvals and Documentation4 daysMon 4/27/15 Thu 4/30/1581 Auto Scheduled Prepare and submit a Building Application and engage Building Certifier for works 1 dayMon 4/27/15 Mon 4/27/15 Contractor, Project Engineer ,Struc tural Engineer Auto Scheduled The Contractor shall prepare and submit a TTM plan 1 dayTue 4/28/15 Tue 4/28/1586 Contractor, Contractor Assistant Auto Scheduled The Contractor is to provide program and methodology 1 dayWed 4/29/15 Wed 4/29/1587 Contractor, Contractor Assistant, Project Engineer Auto Scheduled Submit for approval a demolition method statement 1 dayThu 4/30/15 Thu 4/30/15 88Contractor, Contractor Assistant, Project Engineer ,Seni 42
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
nior Surveyor Auto Scheduled Excavate and stockpile spoil at AEC (UST) 3 daysMon 7/20/15 Wed 7/22/15121 Contractor, Environmental Consultant ,Pro ject Engineer ,Seni or Environmental Consultant ,Sur veyor Auto Scheduled Add of pipes, valves and vent lines associated with UST 3 daysThu 7/23/15 Mon 7/27/15122 General labourer ,Contr actor Assistant Auto Scheduled Validation sampling of stockpile (1 round)4 daysTue 7/28/15 Fri 7/31/15123 Contractor, Contractor Assistant, General labourer ,Proje ct Engineer ,Struc tural Engineer Auto Scheduled Additional validation sampling2 daysMon 8/3/15 Tue 8/4/15124 Asbestos Removals Supervisor, Contractor, Contractor Assistant, Project Engineer ,Struc tural Engineer Auto Scheduled Unexpected Finds4 daysWed 8/5/15 Mon 8/10/15 125General labourer ,Proje ct 49
Engineer ,Struc tural Engineer Auto Scheduled Implementation of Buildings2 daysTue 8/11/15 Wed 8/12/15126 Contractor, Contractor Assistant, General labourer ,Proje ct Engineer ,Struc tural Engineer Auto Scheduled Retaining Walls (Brick)6 daysThu 8/13/15 Thu 8/20/15127 Contractor Assistant, Project Engineer ,Struc tural Engineer Auto Scheduled Courtyard Walls (Brick)4 daysFri 8/21/15 Wed 8/26/15128 Project Engineer ,Struc tural Engineer Auto ScheduledConcrete Stairs3 daysThu 8/27/15 Mon 8/31/15129 Contractor, Project Engineer ,Struc tural Engineer Auto Scheduled Light Poles, Light Bollards, log barriers & Signs etc. 3 daysTue 9/1/15 Thu 9/3/15130 Contractor, Contractor Assistant, Project Engineer ,Struc tural Engineer Auto Scheduled Reports and Completion4 daysFri 9/4/15 Wed 9/9/15114 Auto Scheduled Minutes of the meeting 1 dayFri 9/4/15 Fri 9/4/15 Contractor, Project 50
Engineer Auto ScheduledHandover report1 dayMon 9/7/15 Mon 9/7/15133 Contractor, Project Engineer Auto Scheduled Post-project review report1 dayTue 9/8/15 Tue 9/8/15134 Contractor, Project Engineer Auto ScheduledProject completion1 dayWed 9/9/15 Wed 9/9/15135Project Engineer 5Conclusion This project successfully implemented the care room plan for organization care room because the care room because owner asked user to organise the refurbishment of the one of the care rooms for a single age care resident. The Project implementation is done by using the Microsoft Project 2016. These are implemented and discussed in detail. 51
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
References A guide to the project management body of knowledge. (2017). Newtown Square, Pennsylvania, USA: Project Management Institute. Biafore, B. (2013).Microsoft Project 2013. Sebastopol: O'Reilly Media. Cicala, G. (2013).Project management using Microsoft Project 2013. Wilmington, DE: Project Assistants, Inc. Happy, R. (2010).Project 2010 Project Management. Hoboken: John Wiley & Sons. Heerkens, G. (2015).Project management. [Place of publication not identified]: Mcgraw-Hill Education. Horine, G. (n.d.).Project management. Kerzner, H. (n.d.).Project management. Marchewka, J. (n.d.).Information technology project management. Meredith, J., Mantel, S. and Shafer, S. (n.d.).Project management. Portny, S. (n.d.).Project management for dummies. Schwalbe, K. (n.d.).Information technology project management. Shtub, A. (2016).Project management. [Place of publication not identified]: Pearson. 52