1 CONSTRUCTION DESIGN DOCUMENT 1.0.Project definition and scope: The deliverables that are provided in the project within the project scope are the followings and this is considered throughout the project execution. ďˇEngineering Report: Engineering report provides technical information about an ongoing construction project. This report consists of some clear objective, which will be showing all the tested and compiled data and must contain a summary of the results. ďˇProduct quality enhancement: The product quality enhancement can be achieved through optimization of the raw material fitness, raw mix design and intermediate and final enhancement of the products. ďˇProposals: Proposal is detailed description of the activities that will be performed within a project. The proposal provides logical presentation of some research idea provides significance of the idea. Through the project proposal the feasibility of the project is determined. ďˇDesigndrawings:Designdrawingisverymuchimportantwhichisusedfor developing and communicating the ideas about a design which is being developed. ďˇDesign documents: In the construction project the design document is considered as the starting point of a working on a construction related project. This design document is prepared before performing any type of actual work. ďˇA completed product: Here the completed product refers to the construction project on which the organization was working on. It means the project has been successfully executed by the organisation. ďˇA site investigation report: The site investigation report documents the collected information, the data regarding the appraisal. This report also includes demonstration of the hazards without which ground beneath the site will be unknown.
2 CONSTRUCTION DESIGN DOCUMENT ďˇAny design reviews: The design reviews is considered as the milestone regarding the product development process in which the design is evaluated against the requirement of the design for the verification of the outcomes of some previous activities for the identification of the issues. ďˇProgress reports: The progress report is used for informing the supervisor, customer or the associate about a project progress over a definite period of time. 2.0.Major challenges: 2.1. Challenges specific to the project in context of architecture discipline: ďˇDesign that is made for construction often has issues. Sometimes design are often complicated to execute ort need modification accordingly. ďˇDesigns are not made with project requirements. This might happen as designs requirements were communicated with the designer and architects are not properly interpreted (Jetty 2016). This leads to a design document that is not consistent with construction materials ďˇArchitects often lacks proper knowledge that is required to develop a feasible plan to implement it in real world project. reasons are ether they are not well accounted with design procedures due to lack of practical experience which is required to develop plan for complex construction project (Salvatierraet al.2019) ďˇSometimes approved design needs changes and modification due to construction site issues like adverse weather conditions, project budget, and schedule. This often creates challenges for designer and architects 2.2. Challenges specific to the project in context of construction industry:
3 CONSTRUCTION DESIGN DOCUMENT Execution of construction projects are challenging as it has various issues which needs strategic evaluation (Mubarak 2015).According to Lin, Ho and Shen (2017), some of the common issues of constructions project are: ďˇWorkforce shortage might be an issue in the project, which is one of the critical issues in the construction industry today (Walker 2015) ďˇLabour cost is another significant issue in the construction industry as labour shortage is there. Hence, this might be a challenge during the construction phase of the building ďˇWaste of construction material due to adverse conditions in project site delay project implementation and increase project cost as well. Hence, this is a possible challenge for construction of the building (Searset al.2015) ďˇLabour injury is another significant challenge in the construction industry. Labour injury not only delay the project but project authority has to face legal consequences. This is hence a significant challenge in this project 2.3. Challenges specific to the project in context of project management: ďˇProject scope is poorly defined. Even if sometimes, the project scope is well defined, project execution often lacks consistency with project objectives due to lack of proper planning and coordination. ďˇStakeholder conflict is a major issue in construction project management. The construction project has done many stakeholders that it often becomes impossible to manage each stakeholder while ensuring their interest in the project. ďˇSchedule delay is often a significant issue, which makes it challenging to finish project without compromising in quality of construction. ďˇIt often becomes challenging to restrict project execution within approved budget, as there are chances of schedule variation.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 CONSTRUCTION DESIGN DOCUMENT 3.0.Recommend feasible project team:
5 CONSTRUCTION DESIGN DOCUMENT 4.0.Feasible construction method for the LC-01A building project: Task Mode ID Task NameDurationStartFinishPredecessors Auto Schedule d 1 construction planning 368 days Fri26-04- 19 Tue22- 09-20 Auto Schedule d 2 contract26 days Fri26-04- 19 Fri 31-05- 19 Auto Scheduled 3agreement for supply 4 days Fri26-04- 19 Wed01- 05-19 Auto Scheduled 4Construction Agreement 3 days Thu 02-05- 19 Mon06- 05-19 2 Auto Scheduled 5Plansfor Supply Contract 3 days Tue 07-05- 19 Thu09- 05-19 3 Auto Scheduled 6Specifications foracquiring Supply Contract 4 days Fri10-05- 19 Wed15- 05-19 4 Auto Scheduled 7SitePlan regardingSupply Contract 5 days Thu 16-05- 19 Wed22- 05-19 5 Auto Scheduled 8Secure Financing 3 days Thu 23-05- 19 Mon27- 05-19 6 Auto Scheduled 9Settlement for loanfor 4 daysTue 28-05-Fri 31-05-7
6 CONSTRUCTION DESIGN DOCUMENT construction1919 Auto Schedule d 10 Document Review & Revision 30 days Mon03- 06-19 Fri 12-07- 19 Auto Scheduled 11 plan review5 days Mon03- 06-19 Fri 07-06- 19 8 Auto Scheduled 12Specifications finalization 11 days Mon10- 06-19 Mon24- 06-19 10 Auto Scheduled 13SitePlan finalization 3 days Tue 25-06- 19 Thu27- 06-19 11 Auto Scheduled 14Drawings printing 4 days Fri28-06- 19 Wed03- 07-19 12 Auto Scheduled 15plan modificationand approval 6 days Fri28-06- 19 Fri 05-07- 19 12 Auto Scheduled 16Specifications modificationsand approval 7 days Thu 04-07- 19 Fri 12-07- 19 13 Auto Schedule d 17 Site Work12 days Mon15- 07-19 Tue30- 07-19 Auto Scheduled 18 Clear Lot4 days Mon15- 07-19 Thu18- 07-19 15
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 CONSTRUCTION DESIGN DOCUMENT Auto Scheduled 19Stockpile stripping 5 days Fri19-07- 19 Thu25- 07-19 17 Auto Scheduled 20 Excavation4 days Fri19-07- 19 Wed24- 07-19 17 Auto Scheduled 21gradelot roughing 3 days Fri26-07- 19 Tue30- 07-19 18 Auto Scheduled 22excavation requiredfor foundation 2 days Thu 25-07- 19 Fri 26-07- 19 19 Auto Schedule d 23 foundation80 days Mon29- 07-19 Fri 15-11- 19 Auto Scheduled 24Dig Footings andReinforcing installation 10 days Mon29- 07-19 Fri 09-08- 19 21 Auto Scheduled 25Footing Inspection 12 days Mon12- 08-19 Tue27- 08-19 23 Auto Scheduled 26 Pour footings13 days Wed28- 08-19 Fri 13-09- 19 24 Auto Scheduled 27 Pin Footings14 days Wed28- 08-19 Mon16- 09-19 24 Auto Scheduled 28Stock Block, Mortar, Sand 14 days Mon16- 09-19 Thu03- 10-19 25
8 CONSTRUCTION DESIGN DOCUMENT Auto Scheduled 29Build Block Foundation 10 days Mon16- 09-19 Fri 27-09- 19 25 Auto Scheduled 30Foundation Certification 9 days Tue 17-09- 19 Fri 27-09- 19 26 Auto Scheduled 31Fill Block Cores w/ Concrete 12 days Fri04-10- 19 Mon21- 10-19 27 Auto Scheduled 32 Steel Delivery9 days Mon30- 09-19 Thu10- 10-19 28 Auto Scheduled 33Set Lintels, Bolts, Cap Block 10 days Mon30- 09-19 Fri 11-10- 19 29 Auto Scheduled 34Lumber Delivery 12 days Tue 22-10- 19 Wed06- 11-19 30 Auto Scheduled 35 Waterproofing7 days Thu 07-11- 19 Fri 15-11- 19 33 Auto Schedule d 36 rough carpentry53 days Mon18- 11-19 Wed29- 01-20 Auto Scheduled 37setting of steel structure 10 days Mon18- 11-19 Fri 29-11- 19 34 Auto Scheduled 38deck framing for first floor 12 days Mon02- 12-19 Tue17- 12-19 36 Auto Scheduled 39framing of wall for first floor 10 days Wed18- 12-19 Tue31- 12-19 37
9 CONSTRUCTION DESIGN DOCUMENT Auto Scheduled 40deck framing of second floor 8 days Wed01- 01-20 Fri 10-01- 20 38 Auto Scheduled 41framing of wall for second floor 8 days Wed01- 01-20 Fri 10-01- 20 38 Auto Scheduled 42setting trusses on the roof 8 days Mon13- 01-20 Wed22- 01-20 39 Auto Scheduled 43 framing roof5 days Mon13- 01-20 Fri 17-01- 20 40 Auto Scheduled 44windows and door installation 5 days Thu 23-01- 20 Wed29- 01-20 41 Auto Scheduled 45basementslab setup 2 days Mon20- 01-20 Tue21- 01-20 42 Auto Scheduled 46 inspection for slab4 days Thu 30-01- 20 Tue04- 02-20 43 Auto Scheduled 47Pour Basement Slab 3 days Wed22- 01-20 Fri 24-01- 20 44 Auto Scheduled 48 Prep Garage Slab2 days Wed05- 02-20 Thu06- 02-20 45 Auto Scheduled 49garageslab setting 2 days Wed05- 02-20 Thu06- 02-20 45 Auto Scheduled 50 pour garage slab2 days Mon27- 01-20 Tue28- 01-20 46 Auto Scheduled 51 H.V.A.C.18 days Fri07-02- 20 Tue03- 03-20 47 Auto52HVAC rough-in10 daysFri07-02-Thu20-48
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10 CONSTRUCTION DESIGN DOCUMENT Scheduled2002-20 Auto Scheduled 53HVACindoor units setup 10 days Wed29- 01-20 Tue11- 02-20 49 Auto Scheduled 54HVAC temporary heating 10 days Wed04- 03-20 Tue17- 03-20 50 Auto Scheduled 55 HVAC4 days Wed12- 02-20 Mon17- 02-20 52 Auto Schedule d 56 plumbing8 days Tue 18-02- 20 Thu27- 02-20 Auto Scheduled 57 fixtures setting2 days Tue 18-02- 20 Wed19- 02-20 52,54 Auto Scheduled 58appliance connections 3 days Thu 20-02- 20 Mon24- 02-20 56 Auto Scheduled 59plumbing inspection 3 days Tue 25-02- 20 Thu27- 02-20 57 Auto Schedule d 60 exterior landscaping 7 days Fri28-02- 20 Mon09- 03-20 Auto Scheduled 61Rough Final Grade 1 day Fri28-02- 20 Fri 28-02- 20 58 Auto Scheduled 62 Patios1 day Mon02- 03-20 Mon02- 03-20 60
11 CONSTRUCTION DESIGN DOCUMENT Auto Scheduled 63 Porches1 day Tue 03-03- 20 Tue03- 03-20 61 Auto Scheduled 64 Sidewalks1 day Wed04- 03-20 Wed04- 03-20 62 Auto Scheduled 65 Decks1 day Thu 05-03- 20 Thu05- 03-20 63 Auto Scheduled 66 Driveways1 day Fri06-03- 20 Fri 06-03- 20 64 Auto Scheduled 67Final Grade and Seed 1 day Mon09- 03-20 Mon09- 03-20 65 Auto Schedule d 68 electrical work120 days Tue 10-03- 20 Mon24- 08-20 Auto Scheduled 69 switch and plug40 days Tue 10-03- 20 Mon04- 05-20 66 Auto Scheduled 70fixture installation 50 days Tue 05-05- 20 Mon13- 07-20 68 Auto Scheduled 71appliance connection 30 days Tue 14-07- 20 Mon24- 08-20 69 Auto Schedule d 72 hardware work8 days Tue 25-08- 20 Thu03- 09-20 Auto Scheduled 73door hardware works 5 days Tue 25-08- 20 Mon31- 08-20 70 Auto74washroom1 dayTue 01-09-Tue01-72
12 CONSTRUCTION DESIGN DOCUMENT Scheduledhardware works2009-20 Auto Scheduled 75 mirrors1 day Wed02- 09-20 Wed02- 09-20 73 Auto Scheduled 76 shower doors1 day Thu 03-09- 20 Thu03- 09-20 74 Auto Schedule d 77 cleaning works16 days Tue 01-09- 20 Tue22- 09-20 Auto Scheduled 78windows cleaning 5 days Tue 01-09- 20 Mon07- 09-20 72 Auto Scheduled 79 rough cleaning3 days Tue 08-09- 20 Thu10- 09-20 77 Auto Scheduled 80final cleaning before completion 5 days Fri11-09- 20 Thu17- 09-20 78 Auto Scheduled 81 project closure3 days Fri18-09- 20 Tue22- 09-20 79
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13 CONSTRUCTION DESIGN DOCUMENT References: Arditi, D., Nayak, S. and Damci, A., 2017. Effect of organizational culture on delay in construction.International journal of project management,35(2), pp.136-147. Burtonshaw-Gunn, S.A., 2017.Risk and financial management in construction. Routledge. Jetty, A.C.R., 2016. Design Informations Management in Architecture Engineering and Construction Industry.Asian Journal of Research in Social Sciences and Humanities,6(5), pp.73-84. Lin, X., Ho, C.M. and Shen, G.Q., 2017. Who should take the responsibility? Stakeholders' poweroversocialresponsibilityissuesinconstructionprojects.Journalofcleaner production,154, pp.318-329. Mubarak, S.A., 2015.Construction project scheduling and control. John Wiley & Sons. Nicholas, J.M. and Steyn, H., 2017.Project management for engineering, business and technology. Routledge. Salvatierra, J.L., GĂĄlvez, M.Ă., BastĂas, F., Castillo, T., Herrera, R.F. and AlarcĂłn, L.F., 2019.Developingabenchmarkingsystemforarchitecturedesignfirms.Engineering, Construction and Architectural Management,26(1), pp.139-152. Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015.Construction project management. John Wiley & Sons. Walker, A., 2015.Project management in construction. John Wiley & Sons.