This project is based on the development of rental residential buildings (including several housing / boarding units) in Newcastle, NSW. A suitable work breakdown structure has been developed that includes the work specifications in each phase of the project along with the proposed durations and related costs in each of the work packages.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running Head: CONSTRUCTION PLANNING Construction Planning: Construction of Boarding Houses in NSW Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1CONSTRUCTION PLANNING Table of Contents Task 1...............................................................................................................................................2 Introduction..................................................................................................................................2 Project Scope and Objectives......................................................................................................2 Work Breakdown Structure.........................................................................................................3 Conclusion.................................................................................................................................14 Bibliography..................................................................................................................................15
2CONSTRUCTION PLANNING Task 1 Introduction This project is based on the development of rental residential buildings (including several housing / boarding units) in Newcastle, NSW. The proposed project is proposed to be completed in a period of the next two years within a feasible budget investment. In addition to the proposed plan of the boarding units, there are several other specifications that are required to be met in the project. These specifications include the placement of the rooms inside the building units, number of floors, facilities and services, parking areas and others. For executing the project, all these requirements are to be met and based on the requirements, a suitable budget and schedule plan is to be developed. In this report, with the help of the analysis of the project requirements, a suitable work breakdown structure has been developed that includes the work specifications in each phase of the project along with the proposed durations and related costs in each of the work packages. Project Scope and Objectives The main scope of the project is to clear a certain piece of property and build 27 boarding units that will be provided as rentals. The scope statement of the project is defined by the following points. Clearing of the entire land property for constructing the housing units is within the scope of the project. Constructing the foundations of the buildings is within the scope of the project. Building of the framework of the buildings is within the scope of the project.
3CONSTRUCTION PLANNING Development of the buildings as well as their utilities and services is within the scope of the project. Development of external utilities and perimeter walls is within the scope of the project. From the scope statement, the project objectives are determined as follows. To survey the entire land and take measurements To clear the land and prepare it for the construction To build foundations of the buildings To build 27 housing units including all the design specifications as provided earlier To install utilities like electrical and drainage systems in each of the units To hand over the finished project to the authority Work Breakdown Structure The work breakdown structure of the project is shown in the following table. WB S Task Name Duratio n StartFinish Predecessor s Resource NamesCost 1 Site Preparation 80 days Mon 5/28/18 Fri 9/14/18 $888,000.00 1.1Survey of the Entire Site 10 daysMon 5/28/18 Fri 6/8/18 Construction Manager,Project $44,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4CONSTRUCTION PLANNING Supervisor 1.2 Take Measurements of the Site 5 days Mon 6/11/18 Fri 6/15/18 2 Construction Manager $10,000.00 1.3 Assign Workersto Preparethe Site 5 days Mon 6/18/18 Fri 6/22/18 3 Construction Manager $10,000.00 1.4 Allocate Resources for Site Preparation 5 days Mon 6/25/18 Fri 6/29/18 4 Procurement Manager $6,000.00 1.5 Hire Equipments forSite Preparation 15 days Mon 7/2/18 Fri 7/20/18 5 Procurement Manager $18,000.00 1.6 Start Preparingthe Selected Site 5 days Mon 7/23/18 Fri 7/27/18 6 Construction Workers $100,000.00 1.7Start Digging of the 10 daysMonFri7Construction$200,000.00
5CONSTRUCTION PLANNING Land7/30/188/10/18Workers 1.8 Remove Existing Plantsand Grasses 5 days Mon 8/13/18 Fri 8/17/18 8 Construction Workers $100,000.00 1.9 Remove Existing Concrete Structures and Walls if Any 5 days Mon 8/20/18 Fri 8/24/18 9 Construction Workers $100,000.00 1.10 Check Soil Quality 5 days Mon 8/27/18 Fri 8/31/18 10 Construction Workers $100,000.00 1.11 Add Strong Soil 5 days Mon 9/3/18 Fri 9/7/18 11 Construction Workers $100,000.00 1.12 Preparation of Foundation 5 days Mon 9/10/18 Fri 9/14/18 12 Construction Workers $100,000.00 2Foundation65 days Mon 9/17/18 Fri 12/14/1 8 $1,300,000.00
6CONSTRUCTION PLANNING 2.1 Complete Diggingthe Site 10 days Mon 9/17/18 Fri 9/28/18 13 Construction Workers $200,000.00 2.2 Place Concrete Structures insidethe Area 10 days Mon 10/1/18 Fri 10/12/1 8 15 Construction Workers $200,000.00 2.3 Build Foundation 15 days Mon 10/15/1 8 Fri 11/2/18 16 Construction Workers $300,000.00 2.4 Install Foundation Support 15 days Mon 11/5/18 Fri 11/23/1 8 17 Construction Workers $300,000.00 2.5 Strengthen Foundation 10 days Mon 11/26/1 8 Fri 12/7/18 18 Construction Workers $200,000.00 2.6 Fill Rest of Area with Soil 5 days Mon 12/10/1 8 Fri 12/14/1 8 19 Construction Workers $100,000.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7CONSTRUCTION PLANNING 3Structure165 days Mon 12/17/1 8 Fri 8/2/19 $3,300,000.00 3.1 Start Buildingthe Structure 5 days Mon 12/17/1 8 Fri 12/21/1 8 20 Construction Workers $100,000.00 3.2 Procure Building Materials 5 days Mon 12/24/1 8 Fri 12/28/1 8 22 Construction Workers $100,000.00 3.3 Hire Construction Equipments 5 days Mon 12/31/1 8 Fri 1/4/19 23 Construction Workers $100,000.00 3.4 Hire Construction Workers 5 days Mon 1/7/19 Fri 1/11/19 24 Construction Workers $100,000.00 3.5 SetUp Construction Camp 10 days Mon 1/14/19 Fri 1/25/19 25 Construction Workers $200,000.00
8CONSTRUCTION PLANNING 3.6 Start Buildingthe Infrastructures 20 days Mon 1/28/19 Fri 2/22/19 26 Construction Workers $400,000.00 3.7 Install Steel Bars 15 days Mon 2/25/19 Fri 3/15/19 27 Construction Workers $300,000.00 3.8 Place Bricks Alongthe Framework 25 days Mon 3/18/19 Fri 4/19/19 28 Construction Workers $500,000.00 3.9 Apply Concreteto Fix the Bricks 25 days Mon 4/22/19 Fri 5/24/19 29 Construction Workers $500,000.00 3.10 Place Concrete Layeron Innerand OuterLayers of the Walls 30 days Mon 5/27/19 Fri 7/5/19 30 Construction Workers $600,000.00 3.11 Apply Plaster On the Walls 20 days Mon 7/8/19 Fri 8/2/19 31 Construction Workers $400,000.00
9CONSTRUCTION PLANNING 4Services90 days Mon 8/5/19 Fri 12/6/19 $360,000.00 4.1 Install Electrical Connections through Every Wallofthe Housing Units 15 days Mon 8/5/19 Fri 8/23/19 32Technical Workers$60,000.00 4.2 Install WaterPipes and Plumbing Works 15 days Mon 8/26/19 Fri 9/13/19 34Technical Workers$60,000.00 4.3 Connect to Main Lines 5 days Mon 9/16/19 Fri 9/20/19 35Technical Workers$20,000.00 4.4 Install Water Tanks 15 days Mon 9/23/19 Fri 10/11/1 9 36Technical Workers$60,000.00 4.5 Build Elevator Boxes 20 days Mon 10/14/1 9 Fri 11/8/19 37Technical Workers$80,000.00 4.6Install20 daysMonFri38Technical Workers$80,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13CONSTRUCTION PLANNING 7.5 Builda Swimming Pool 20 days Mon 4/27/20 Fri 5/22/20 58 Construction Workers, Technical Workers $480,000.00 7.6 Builda Leisure Area 5 days Mon 5/25/20 Fri 5/29/20 59 Construction Workers, Technical Workers $120,000.00 7.7 Finishing Touches 10 days Mon 6/1/20 Fri 6/12/20 60 Construction Workers, Technical Workers $240,000.00 Figure 1: Work Breakdown Structure of the Project (Source: Created by Author)
14CONSTRUCTION PLANNING The human resources that have been allocated to each of the work packages of the work breakdown structure are shown in the following table. Resource NameType Max. Units Std. RateOvt. RateCost/UseAccrue At Base Calendar Construction Manager Work100%$250.00/hr$0.00/hr$0.00ProratedStandard Project Supervisor Work100%$300.00/hr$0.00/hr$0.00ProratedStandard Construction Workers Work100%$2,500.00/hr$0.00/hr$0.00ProratedStandard Procurement Manager Work100%$150.00/hr$0.00/hr$0.00ProratedStandard Technical Workers Work100%$500.00/hr$0.00/hr$0.00ProratedStandard Conclusion This report contains the details of the project scope, objectives and the overall work breakdown structure that will be followed. The work breakdown structure has been developed by dividing the entire project into several phases, sub-phases and work packages. As per the development, the work packages have been linked together using predecessor relationship as
15CONSTRUCTION PLANNING appropriate in the context of the project. The links between the work packages of the work breakdown structure are essential in determining the durations of each of the work packages. From the work breakdown structure provided above, the estimated duration for the project is 535 days and the estimated budget is $8,848,000. However, these are only preliminary estimations and will be changed in the near future in order to adjust with the project feasibility and the limitations the organization which is undertaking this particular project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16CONSTRUCTION PLANNING Bibliography Banihashemi, S., Hosseini, M.R., Golizadeh, H. and Sankaran, S., 2017. Critical success factors (CSFs) for integration of sustainability into construction project management practices in developing countries.International Journal of Project Management,35(6), pp.1103-1119. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Harrison, F. andLock,D., 2017.Advancedprojectmanagement:astructuredapproach. Routledge. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Nasir,N.,Nawi,M.N.M.andRadzuan,K.,2016,August.Relationshipbetweentime management in construction industry and project management performance. InAIP Conference Proceedings(Vol. 1761, No. 1, p. 020079). AIP Publishing. Schwalbe, K., 2015.Information technology project management. Cengage Learning. Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015.Construction project management. John Wiley & Sons. Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming psychologicalsafetyclimateinconstructionprojectmanagement.Internationaljournalof project management,33(1), pp.223-235. Walker, A., 2015.Project management in construction. John Wiley & Sons.
17CONSTRUCTION PLANNING Zheng, X., Le, Y., Chan, A.P., Hu, Y. and Li, Y., 2016. Review of the application of social network analysis (SNA) in construction project management research.International journal of project management,34(7), pp.1214-1225.