Detailed Project Progress Report<Insert Project Name> <Name of Sponsoring Organisation> <PROJECT TITLE> DETAILED PROJECT PROGRESS REPORT DETAILS Project Title Project ID Document ID Date Produced Project Manager Sponsor REPORTING PERIOD From To DISTRIBUTION This document has been distributed to: NameTitle page1of20
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Progress Report<Insert Project Name> 1.0 Project Manager’s Report 1.1.Summary of Performance - Overall Schedule – The project will be delayed by 6 days due to implementation of fingerprint scanner in the system before system design a data migration. However, the 6 days delay cannot be mitigated by starting any other activity early or re-scheduling other activities. Budget – The project has shifted to $24,240 from approved baseline project of $20,000. The increase can be covered under the contingency plan approved by the project sponsor. Quality – All work has been managed as per the standards and metrics of quality management plan. 1.2.Summary of Performance – This Reporting Period The planning activities have been done as per the schedule. No delay was reported in planning activities. No team conflict was reported during the period. Project plan was completed 100% with the approval of project sponsor. 1.3.Corrective Actions Undertaken–This Reporting Period Security cover was identified during this period which is required to be implemented to avoid any illegal access to the patient’s data. In order to do this, fingerprint scanner needs to be implemented which results in delay in project’s completion. Data migration – Hospital management decided to handover the data migration to the development team. 2.0. Benefits Status since last report All benefits remain unchanged as per the table given below: StatusComments Unchanged Reduced Enhance No delay in the initiation phase where in all planning related to the proposed system had been done. - A positive attitude towards the new IS has been observed among the staff of the hospital. Increase in number of registrations as the patients are early waiting for the new IS to store their data and they want to know how can they access data from any location. page2of20
Project Progress Report<Insert Project Name> 3.0.Scope Status 3.1.Work packages progress to date – Completed & Approved in this Reporting Period Work Packages completed in the reporting period (14/03/2019 to 29/04/2019) WBSTask Name 1Project initiation phase 1.1Assemble the project team 1.2Create a business case 1.3Feasibility study 1.4Prepare a project charter 1.5Assign the resources to project tasks 1.6Schedule the plan 1.7Estimate the project cost 1.8Kick off the project meetings 1.9Development and approval of project plan 2Software designing phase 2.1Analyze the performance of software 2.2Making notes on additional system requirements 2.3Building architecture of the project plan 2.4Identifydesignandworkflowsfor information system 3.2.Scope Changes since last report 3.2.1.Data migration of existing system into new system Initially it was not deicide to include the migration of current data into new system. The hospital management was reluctant in providing access to the old and manual system. They decided to transfer it manually to the new system. But the estimated cost of manually doing it turned out to be very high and time-consuming. So they have proposed to get it done along with the new system development at the fixed cost of $20,000. This increase in the project budget was approved in change request mentioned in section 1. 3.2.2.Fingerprint installation During the development of the project and data migration, this data may get be assessed by illegal or unauthorized staff. This risk was analysed by the project management team and it was then decided that a fingerprint security is required to be installed whenever an access to the data is required. Also, it has been decided that the data cannot be modified by any staff unless approved by the hospital management. The scope of the work includes installation of additional page4of20
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project Progress Report<Insert Project Name> hardware and software for fingerprint checking technique. This additional change request has been approved in the change request section 2. This additional work has resulted in halting the software designing phase and delaying the entire project by 6 days. 3.3.Work packages/Tasks to be completed in next reporting period (dd/mm/yyyy- dd/mm/yyyy) WBSTask Name 2.5Create a data model 2.6Identify tools used to create the software 3Fingerprint scanner implementation 3.1Market research 3.1.1Study available fingerprint scanners 3.1.2Consult the brands 3.1.3Arrange for demo 3.1.4Prepare POC 3.2Vendor selection 3.2.1Discuss requirements with the vendors 3.2.2Discuss budget with vendors 3.2.3Finalize vendor 3.2.4Purchase from selected vendor 3.3Integrate fingerprint scanner 3.4System development 3.4.1Detailed identification of project requirements 3.4.2Identify the project resources 3.4.3Documentation of project requirements and designs 3.5Completion of software designing 4Software coding phase 4.1Produce the code for software development 4.2Convert design into code using programming language 4.3Developing error free executable programs 4.4Completion of software coding 5Software testing 5.1Identify the issues in the system 5.2Perform testing 5.2.1Program testing 5.2.2Product testing 5.2.3User acceptance testing 5.3Finding the test results 5.4Fixing the issues 5.5Approve for release page5of20
Project Progress Report<Insert Project Name> 5.6Document the internal design of software 5.7Maintenance of the software and deployment 5.8Completion of software testing 6Data migration 6.1Finalize data to migrate 6.2Run migration scripts 6.3Test migrated data 7Training and support to the staffs 7.1Planning a development team 7.2Training classes for software users 7.3Incorporate the organization to adopt new software 7.4Implementation of training program 7.4.1E-learning modules 7.4.2Seminars 7.5Completion of training to the staffs 8Project closure phase 8.1Making project documents and deliverables 8.2Formal acceptance of project deliverables 8.3Closing the project accounts 8.4Update and achieve the documents 8.5Release of the resources 8.6Review the final project plan 8.7Finalize the lessons learned 8.8Development of the project closure report 4.0. Time Status 4.1. Overall Time Performance Original Baseline Completion date (as PM Plan)15thJuly 2019 Forecast Completion date – last Report15thJuly 2019 Forecast Completion date – this Report23rdJuly 2019 Variance: Baseline v Forecast Completion date6 days CommentsThe project has incurred a 6-day delay which cannot be mitigated by re-scheduling any other activity. page6of20
Project Progress Report<Insert Project Name> 4.2. Detailed Time Performance Task NameStartFinishBaseline Start Baseline Finish % Comple te Finish Var.Actual StartActual Finish Development of Information System in Healthcare Industry Thu 14/03/19 Tue 23/07/19 Thu 14/03/1 9 Tue 23/07/1 9 35%0 daysThu 14/03/19NA Project initiation phase Thu 14/03/19Fri 29/03/19Thu 14/03/19 Fri 29/03/19 100%0 daysThu 14/03/19Fri 29/03/19 Assemble the project team Thu 14/03/19Fri 15/03/19Thu 14/03/19 Fri 15/03/19 100%0 daysThu 14/03/19Fri 15/03/19 Create a business case Mon 18/03/19Thu 21/03/19Mon 18/03/19 Thu 21/03/19 100%0 daysMon 18/03/19Thu 21/03/19 Feasibility studyFri 22/03/19Thu 28/03/19Fri 22/03/19 Thu 28/03/19 100%0 daysFri 22/03/19Thu 28/03/19 Prepare a project charter Fri 22/03/19Mon 25/03/19Fri 22/03/19 Mon 25/03/19 100%0 daysFri 22/03/19Mon 25/03/19 Assign the resources to project tasks Mon 18/03/19Wed 20/03/19Mon 18/03/19 Wed 20/03/19 100%0 daysMon 18/03/19Wed 20/03/19 Schedule the plan Mon 25/03/19Wed 27/03/19Mon 25/03/19 Wed 27/03/19 100%0 daysMon 25/03/19Wed 27/03/19 Estimate the project cost Thu 28/03/19Fri 29/03/19Thu 28/03/19 Fri 29/03/19 100%0 daysThu 28/03/19Fri 29/03/19 Kick off the project meetings Thu 21/03/19Tue 26/03/19Thu 21/03/19 Tue 26/03/19 100%0 daysThu 21/03/19Tue 26/03/19 Development and approval of project plan Tue 26/03/19Tue 26/03/19Tue 26/03/19 Tue 26/03/19 100%0 daysTue 26/03/19Tue 26/03/19 Software designing phase Wed 27/03/19Tue 21/05/19Wed 27/03/19 Tue 21/05/19 61%0 daysWed 27/03/19NA Analyze the performance of software Wed 27/03/19Fri 29/03/19Wed 27/03/19 Fri 29/03/19 100%0 daysWed 27/03/19Fri 29/03/19 Making notes on additional system requirements Mon 01/04/19Tue 21/05/19Mon 01/04/19 Tue 21/05/19 50%0 daysMon 01/04/19NA Building architecture of the project plan Thu 28/03/19Wed 17/04/19Thu 28/03/19 Wed 17/04/19 100%0 daysThu 28/03/19Wed 17/04/19 Identify design and workflows for information system Thu 18/04/19Mon 22/04/19Thu 18/04/19 Mon 22/04/19 100%0 daysThu 18/04/19Mon 22/04/19 Create a data model Tue 23/04/19Mon 13/05/19Tue 23/04/19 Mon 13/05/19 33%0 daysTue 23/04/19NA Identify toolsTue 14/05/19Tue 21/05/19TueTue0%0 daysNANA page7of20
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Progress Report<Insert Project Name> 5.0. Cost Status 5.1. Overall Cost Performance Original Baseline Budget (as in PM Plan)20,000 Forecast Final Cost – Last Report20,000 Forecast Final Cost – This Report24,240 Variance: Baseline v Forecast Final Costs4,240 CommentsThere has been an increase of $4,240 which can be bear by the approved contingency and hence will not have much impact on the forecasted overrun. Change Request No. TitleEstimated Cost impact 1aFingerprint cost2000 1bResources required for fingerprint scanner2000 1cData migration240 5.2 Detailed Cost Performance Task NameTotal CostBaselineVarianceActualRemaining Development of Information System in Healthcare Industry $24,240.00$20,000.00$4,240.00$7,523.20$16,716.80 Project initiation phase$3,200.00$3,200.00$0.00$3,200.00$0.00 Assemble the project team $240.00$240.00$0.00$240.00$0.00 Create a business case$640.00$640.00$0.00$640.00$0.00 Feasibility study$600.00$600.00$0.00$600.00$0.00 Prepare a project charter$240.00$240.00$0.00$240.00$0.00 Assign the resources to project tasks $600.00$600.00$0.00$600.00$0.00 Schedule the plan$240.00$240.00$0.00$240.00$0.00 Estimate the project cost$160.00$160.00$0.00$160.00$0.00 Kick off the project meetings $480.00$480.00$0.00$480.00$0.00 Development and approval of project plan $0.00$0.00$0.00$0.00$0.00 Software designing phase$2,600.00$2,600.00$0.00$1,803.20$796.80 page11of20
Project Progress Report<Insert Project Name> Analyze the performance of software $240.00$240.00$0.00$240.00$0.00 Making notes on additional system requirements $320.00$320.00$0.00$160.00$160.00 Building architecture of the project plan $1,200.00$1,200.00$0.00$1,200.00$0.00 Identify design and workflows for information system $120.00$120.00$0.00$120.00$0.00 Create a data model$240.00$240.00$0.00$83.20$156.80 Identify tools used to create the software $480.00$480.00$0.00$0.00$480.00 Fingerprint scanner implementation $4,520.00$4,520.00$0.00$400.00$4,120.00 Market research$920.00$920.00$0.00$0.00$920.00 Study available fingerprint scanners $240.00$240.00$0.00$0.00$240.00 Consult the brands$360.00$360.00$0.00$0.00$360.00 Arrange for demo$80.00$80.00$0.00$0.00$80.00 Prepare POC$240.00$240.00$0.00$0.00$240.00 Vendor selection$2,880.00$2,880.00$0.00$0.00$2,880.00 Discuss requirements with the vendors $360.00$360.00$0.00$0.00$360.00 Discuss budget with vendors $240.00$240.00$0.00$0.00$240.00 Finalize vendor$120.00$120.00$0.00$0.00$120.00 Purchase from selected vendor $2,160.00$2,160.00$0.00$0.00$2,160.00 Integrate fingerprint scanner $200.00$200.00$0.00$0.00$200.00 System development$520.00$520.00$0.00$400.00$120.00 Detailed identification of project requirements $120.00$120.00$0.00$0.00$120.00 Identify the project resources $240.00$240.00$0.00$240.00$0.00 Documentation of project requirements and designs $160.00$160.00$0.00$160.00$0.00 Completion of software designing $0.00$0.00$0.00$0.00$0.00 Software coding phase$1,760.00$1,760.00$0.00$1,000.00$760.00 Produce the code for software development $520.00$520.00$0.00$440.00$80.00 page12of20
Project Progress Report<Insert Project Name> Convert design into code using programming language $680.00$680.00$0.00$0.00$680.00 Developing error free executable programs $560.00$560.00$0.00$560.00$0.00 Completion of software coding $0.00$0.00$0.00$0.00$0.00 Software testing$8,680.00$8,680.00$0.00$1,120.00$7,560.00 Identify the issues in the system $0.00$0.00$0.00$0.00$0.00 Perform testing$3,360.00$3,360.00$0.00$0.00$3,360.00 Program testing$1,200.00$1,200.00$0.00$0.00$1,200.00 Product testing$1,600.00$1,600.00$0.00$0.00$1,600.00 User acceptance testing$560.00$560.00$0.00$0.00$560.00 Finding the test results$3,200.00$3,200.00$0.00$1,120.00$2,080.00 Fixing the issues$320.00$320.00$0.00$0.00$320.00 Approve for release$800.00$800.00$0.00$0.00$800.00 Document the internal design of software $360.00$360.00$0.00$0.00$360.00 Maintenance of the software and deployment $640.00$640.00$0.00$0.00$640.00 Completion of software testing $0.00$0.00$0.00$0.00$0.00 Data migration$240.00$240.00$0.00$0.00$240.00 Finalize datato migrate$120.00$120.00$0.00$0.00$120.00 Run migration scripts$80.00$80.00$0.00$0.00$80.00 Test migrated data$40.00$40.00$0.00$0.00$40.00 Training and suppot to the staffs $1,840.00$1,840.00$0.00$0.00$1,840.00 Planning a development team $480.00$480.00$0.00$0.00$480.00 Training classess for software users $240.00$240.00$0.00$0.00$240.00 Incorporate the organization to adopt new software $320.00$320.00$0.00$0.00$320.00 Implementation of training program $800.00$800.00$0.00$0.00$800.00 E-learning modules$400.00$400.00$0.00$0.00$400.00 Seminars$400.00$400.00$0.00$0.00$400.00 Completion of training to the staffs $0.00$0.00$0.00$0.00$0.00 Project closure phase$1,400.00$1,400.00$0.00$0.00$1,400.00 page13of20
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Progress Report<Insert Project Name> Making project documents and deliverables $480.00$480.00$0.00$0.00$480.00 Formal acceptance of project deliverables $120.00$120.00$0.00$0.00$120.00 Closing the project accounts $240.00$240.00$0.00$0.00$240.00 Update and achieve the documents $120.00$120.00$0.00$0.00$120.00 Release of the resources$80.00$80.00$0.00$0.00$80.00 Review the final project plan $120.00$120.00$0.00$0.00$120.00 Finalize the lessons learned $240.00$240.00$0.00$0.00$240.00 Development of the project closure report $0.00$0.00$0.00$0.00$0.00 page14of20
Project Progress Report<Insert Project Name> 6.0Review of Team Performance The coordination and interaction among the team members has been improving day by day. This is because of weekly meetings of the team. In the meetings, conflicts among them are discussed and appropriate actions are being taken. Project manager also holds one-to-one meetings with the team members. Developers and testers have coordinated with each other to minimize the delay in accommodating bugs arisen in the project. Also, after resolving the bugs, the updated project is reviewed by analyst and project manager. This results in updating the entire team about the progress of project. The analyst and design team also respond to any issue begin faced by the developers while developing the system. Hospital management is being involved from requirement analysis phase. No negative performance issues have been reported in this period. page15of20
Project Progress Report<Insert Project Name> 7.0 Stakeholders Status 7.1. Stakeholder issues that have eventuated since last report Project sponsor held an urgent meeting with the team to review the performance review. However, no negative variance was found in the work. The system was in designing phase hence it did not create any halting in work of the hospital. Hence, staff is yet to face the issues during the dat a migration and they are still in accepting mode. The need of fingerprint system was identified in the beginning but it will result in delaying of the project. Hence, there will be a negative impact on the project’s schedule and budget. 7.2. Stakeholder issues requiring focus in next reporting period When data migration begins, the staff may have to halt their working for couple of hours which may change their Avoiding delays in time line and increase in cost of overall project of the Information System development 7.3. Stakeholders Actions – Status/Comment StakeholderStake/InterestActionResponsibilityBy WhenStatus Project SponsorCreate the business case and approve the project release Sign off the key decisions and project phases Facilitate the stakeholder meetings By 28th March, 2019 Positive Project ManagerAssemble the project team members, Feasibility study on the project areas Prepare an agenda which allows the sources to discuss and prepare the project charter By 4thApril, 2019 Positive Project technical lead Making the project documents and deliverables Review the project deliverables Technical skills to analyze existing information system By 15th April, 2019 Positive Training ManagerPerforming training classes for the software users Incorporate the organization for adopting new software Performing training programs such as E- learning modules and seminars By end of month April, 2019 Positive Functional LeadIdentification of design andPlan a team forFunction entireBy firstPositive page16of20
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Project Progress Report<Insert Project Name> workflows for the information system development of information system development of healthcare information system week of June, 2019 Software DeveloperAnalyze the performance of the software Creating a data modelsMaintenance of the system and deployment By 9thApril, 2019 Positive System AnalystMaking notes on additional information system requirements Building architecture of the project plan Document the requirements of information system and its designs By 20th April, 2019 Positive Business AnalystCreate the business case on healthcare information system Document the internal design of the software Analyze current operations of healthcare organization By end week of April, 2019 Positive Software TesterPerform the information system testing Perform product, program and user acceptance testing Findings the test results as per project requirements On 15th May, 2019 Positive Human Resource Manager Assign the project resources to the project tasks Schedule the project team members Hire more team members based on the skills and knowledge required to perform the project tasks By last week of May,2019 Positive Financial ManagerEstimate the project costPrepare a budget planKick off the project meetings By first week of June, 2019 Positive ProgrammerProduce code for the development of software Develop error free executable programs Coding the information system for healthcare industry By 19th June, 2019 Positive DesignerConvert design into code by means of programming language Document the internal design of the software Design the information system based on project requirements By 29th June, 2019 Positive page17of20
Project Progress Report<Insert Project Name> 8.0.Risks Status 8.1. Risks/Issues that have eventuated since last report New two risks have been identified R8 and R9. R8 is a cost risk and R9 is a technical risk. The treatment of the risk includes purchase of scanner at that time of approval of change request. Further changes in the risk register are also noted in the register. 8.2. Risks/Issues requiring focus in next reporting period Lack of training to the staff Concurrent operations i.e. monitoring whether the technical risks are not occurring because they will increase the time and cost of the project. 7.3. Risk Treatments – Status/Comment Risk Id Risk EventLikelih ood Conseque nce Ratin g TreatmentResponsibl e Officer By Date Status R1Schedulerisk:Itisoccurredwhenthe project is implemented in constricted project timeframe. LikelyMinorHighAproperprojectplanis developedtoconsiderall theprojectactivities required and completed in the project work. Project Manager 15th April, 2019 Solved R2Unavailability of project resources: Proper andrequiredprojectresourcesarenot involved and hired to perform the project work. PossibleMajorHighSkilledaswellas knowledgeableresources are required to be chosen. Human resource manager 29th April, 2019 Changed to Closed page18of20
Project Progress Report<Insert Project Name> R3System failure: The implemented healthcare information system is failed as the software beingimplementedinmuchconstricted timeframe. Unlikel yCatastrophi c Moder ate Asignificantamountof time is allocated for testing thehealthcareinformation system. System Analyst 3rd May, 2019 In progress R4Lack of proper training: There is lack of trainingprovidedtotheprojectteam membersasthestaffsarenewto implementation of information system. PossibleMajorHigh Trainingprogramshould require developing as part ofthisparticularproject work. Training Manager 16th May, 2019 In progress R5Operational risk: There is improper testing of the information system.LikelyMajorHigh Testingofthehealthcare information system should require to done properly. Tester25th May, 2019 In progress R6Budgetrisk:Duetoadditionofextra resources to the project plan, there is an increase in project budget over the planned cost. LikelyMinorHighThereisrequiredtouse projectschedulefor estimating the cost based on the project plan. Project Manager 13rd June, 2019 In progress R7Technical risk: The system is not operated as per planned project requirements due to wrong coding of the information system.PossibleModerateModer ate Propercodingofthe softwareshouldrequire performingbasedon system’s requirements. Programmer15th June, 2019 In progress R8Budget risk: The cost of the project will be increased because of change in scope by having fingerprint scanner. PossibleModerateHigh Thescannershouldbe acquired as soon as change request is approved. Programmer30th April 2019 In progress R9Technicalrisk:Thereisachancethat developed code has been implemented in a way that it is not open for modification in future which can lead to all investment in vain. LikelyHighHigh Thedevelopershouldbe consultedregularlyto ensurethatindustry standardsarebeing followed. ProgrammerWeekl y In progress 8.0 Lessons Identified What went well in this reporting period. page19of20
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Project Progress Report<Insert Project Name> Increase in the delay of the project due to implementation of fingerprint scanner implementation led to analysis over the data breach threats in the future. Areas for improvement in this reporting period Most of the risks are either to avoid or transfer. However, this may not be the situation every time. Mitigation plans are required to be implemented in the project. END OF DETAILED PROGRESS REPORT page20of20