An Examination of the Effects of Variations on Construction Projects
VerifiedAdded on 2019/10/09
|29
|9934
|268
Report
AI Summary
The article discusses the concept of variations in construction projects, particularly in traditional and non-traditional procurement methods. Traditional procurement methods involve consulting consultants to develop designs, while non-traditional methods require a more collaborative approach between clients, designers, and contractors. The study by Segawa et al (2002) suggests that traditional procurement methods lead to increased variations compared to other methods.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Client causes of variation in construction projects in United
Arab Emirates
By
Student ID number:
Dissertation submitted in partial fulfillment of the requirements for the degree of
MSc. Project Management
Faculty of Engineering & IT
Dissertation Supervisor:
July-2017
Arab Emirates
By
Student ID number:
Dissertation submitted in partial fulfillment of the requirements for the degree of
MSc. Project Management
Faculty of Engineering & IT
Dissertation Supervisor:
July-2017
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Declaration Release From
Student Name Student ID Programme
MSc. Construction
Management
Date
Jul 2017
Title:
Client causes of variation in construction projects in United Arab Emirates
I hereby warrant that the content of this dissertation is the direct result of my own work and
that any use made in it of published or unpublished copyright material falls within the limits
permitted by international copyright conventions.
I understand that one copy of my dissertation will be deposited in the University Library for
permanent retention.
I hereby agree that the material mentioned above for which I am author and copyright holder
may be copied and distributed by The University for the purposes of research, private study
or education and that The University may recover from purchasers the costs incurred in such
copying and distribution, where appropriate.
I understand that The University may make that copy available in digital format if
appropriate.
I understand that I may apply to the University to retain the right to withhold or to restrict
access to my dissertation for a period which shall not normally exceed four calendar years
from the congregation at which the degree is conferred, the length of the period to be
specified in the application, together with the precise reasons for making that application.
Student Name Student ID Programme
MSc. Construction
Management
Date
Jul 2017
Title:
Client causes of variation in construction projects in United Arab Emirates
I hereby warrant that the content of this dissertation is the direct result of my own work and
that any use made in it of published or unpublished copyright material falls within the limits
permitted by international copyright conventions.
I understand that one copy of my dissertation will be deposited in the University Library for
permanent retention.
I hereby agree that the material mentioned above for which I am author and copyright holder
may be copied and distributed by The University for the purposes of research, private study
or education and that The University may recover from purchasers the costs incurred in such
copying and distribution, where appropriate.
I understand that The University may make that copy available in digital format if
appropriate.
I understand that I may apply to the University to retain the right to withhold or to restrict
access to my dissertation for a period which shall not normally exceed four calendar years
from the congregation at which the degree is conferred, the length of the period to be
specified in the application, together with the precise reasons for making that application.
1
Acknowledgement
Page 1
Student ID #:
Acknowledgement
Page 1
Student ID #:
2
Abstract
\
keywords:
Page 2
Student ID #:
Abstract
\
keywords:
Page 2
Student ID #:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
3
Abbreviations
Page 3
Student ID #:
Abbreviations
Page 3
Student ID #:
4
Table of Contents
Acknowledgement......................................................................................................................1
Abstract......................................................................................................................................2
Abbreviations.............................................................................................................................3
Table of Contents.......................................................................................................................4
Chapter 1: Introductory Chapter................................................................................................5
1.1 Introduction.................................................................................................................5
1.2 Background: The United Arab Emirates.....................................................................5
1.3 Research Background.......................................................................................................6
1.4 Research Problem.............................................................................................................8
1.5 Research Aim...................................................................................................................9
1.6 Research Objectives.........................................................................................................9
1.7 Research Scope..............................................................................................................10
1.8 Research Questions........................................................................................................11
1.9 Dissertation Overview....................................................................................................12
1.10 Summary......................................................................................................................12
Chapter 2: Literature Review...................................................................................................14
2.1 Introduction....................................................................................................................14
References................................................................................................................................24
Introduction................................................................................................................................2
Research Background.............................................................................................................4
Research Problem...................................................................................................................5
Research Aim.........................................................................................................................7
Research Objectives...............................................................................................................8
Page 4
Student ID #:
Table of Contents
Acknowledgement......................................................................................................................1
Abstract......................................................................................................................................2
Abbreviations.............................................................................................................................3
Table of Contents.......................................................................................................................4
Chapter 1: Introductory Chapter................................................................................................5
1.1 Introduction.................................................................................................................5
1.2 Background: The United Arab Emirates.....................................................................5
1.3 Research Background.......................................................................................................6
1.4 Research Problem.............................................................................................................8
1.5 Research Aim...................................................................................................................9
1.6 Research Objectives.........................................................................................................9
1.7 Research Scope..............................................................................................................10
1.8 Research Questions........................................................................................................11
1.9 Dissertation Overview....................................................................................................12
1.10 Summary......................................................................................................................12
Chapter 2: Literature Review...................................................................................................14
2.1 Introduction....................................................................................................................14
References................................................................................................................................24
Introduction................................................................................................................................2
Research Background.............................................................................................................4
Research Problem...................................................................................................................5
Research Aim.........................................................................................................................7
Research Objectives...............................................................................................................8
Page 4
Student ID #:
5
Research Scope......................................................................................................................9
Research Questions..............................................................................................................10
Summary..............................................................................................................................10
Literature Review.....................................................................................................................12
References................................................................................................................................19
Page 5
Student ID #:
Research Scope......................................................................................................................9
Research Questions..............................................................................................................10
Summary..............................................................................................................................10
Literature Review.....................................................................................................................12
References................................................................................................................................19
Page 5
Student ID #:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6
Chapter 1: Introductory Chapter
1.1 Introduction
The aim of this research or dissertation research paper is to investigate client causes of
variation in the construction projects in United Arab Emirates. The understanding of this
aspect is important as it is directly associated with the failure or success of particular project.
The parties that are generally involved in the construction project are client, consultants, and
contractors. The variations in the construction projects occur due to various reasons and the
involvement of these three entities are considered as important (Abdul Rahman et al, 2012).
Variations are the deviations that occur within the projects from what has been agreed among
the stakeholders at the beginning of the project. The deviation from the actual planned project
can be of various forms such as removal of certain activity, reduction in the amount defined
for the budget, or any changes in what has been written in the contracts (Wang, 2000). Some
of the variations can be visible to the stakeholders, while others cannot be seen or assessed.
The current paper will investigate the variations in the project in the United Arab Emirates
using the various research techniques discussed in the research methodology section.
1.2 Background: The United Arab Emirates
The United Arab Emirates is the combination of seven states and is ruled by the Supreme
Council of Rulers. The seven states that are under the United Arab Emirates are Abu Dhabi,
Dubai, Sharjah, Ajman, Um al-Qaywayn , Fujayrah, and Ra’s al-Khayma. In the past
decades, the government has invested in various governments run construction projects. The
focus has been on improving the economic situation of the entire country by further bringing
them together with the help of infrastructural development.
Page 6
Student ID #:
Chapter 1: Introductory Chapter
1.1 Introduction
The aim of this research or dissertation research paper is to investigate client causes of
variation in the construction projects in United Arab Emirates. The understanding of this
aspect is important as it is directly associated with the failure or success of particular project.
The parties that are generally involved in the construction project are client, consultants, and
contractors. The variations in the construction projects occur due to various reasons and the
involvement of these three entities are considered as important (Abdul Rahman et al, 2012).
Variations are the deviations that occur within the projects from what has been agreed among
the stakeholders at the beginning of the project. The deviation from the actual planned project
can be of various forms such as removal of certain activity, reduction in the amount defined
for the budget, or any changes in what has been written in the contracts (Wang, 2000). Some
of the variations can be visible to the stakeholders, while others cannot be seen or assessed.
The current paper will investigate the variations in the project in the United Arab Emirates
using the various research techniques discussed in the research methodology section.
1.2 Background: The United Arab Emirates
The United Arab Emirates is the combination of seven states and is ruled by the Supreme
Council of Rulers. The seven states that are under the United Arab Emirates are Abu Dhabi,
Dubai, Sharjah, Ajman, Um al-Qaywayn , Fujayrah, and Ra’s al-Khayma. In the past
decades, the government has invested in various governments run construction projects. The
focus has been on improving the economic situation of the entire country by further bringing
them together with the help of infrastructural development.
Page 6
Student ID #:
7
As briefed earlier, the variations can be signified by various forms of changes in the
construction projects. One of them can be changes in the schedule (Alzahrani and Emsley,
2013). Schedule refers to the overall duration that has been assigned for the completion of
project. The changes in the schedule can occur due to factors such as lack of resources, or the
sudden occurrence of any kind of risks (Aminbakhsh et al, 2013). It might be related to the
desire of some of the stakeholder to extend the deadline or stretch the duration without any
reason. In some cases, the variations occur when the parties vary on the requirements that
have been defined for the project. The requirements or the things that are to be achieved by
the end of the project are generally defined in the beginning of the project. However, due to
some changes in the mind of stakeholders or occurrence of any kind of situation leads to the
change in the requirements which eventually creates variations in the project.
The understanding of the client causes of variations in the construction projects in United
Arab Emirates will be at the core of this entire research paper. The next sub-section briefly
states the research background upon which the entire research study is based. The research
background is followed by the research problem that is likely to be resolved through the
conduction of this research. The research problem is followed by the research aim which
states where the entire research project is heading. The research objectives, after the research
aim discusses the aspects that will be touched while moving towards the achievement of the
research aim. The research scope will define the premise within which the research will be
conducted. The research scope is likely to help understand the limitations of this research
paper. The research questions discussed after the research scope will showcase the questions
that are to be answered by the end of this research project. This chapter has been summarized
in end under Summary section.
1.3 Research Background
The existence of variations among the construction project activities is inevitable, and any
effort to eliminate the variations is unlikely to be successful. The variations have impacted
almost all the associated individuals or entities with the construction projects. The individuals
or entities can be project owner, the individual who has monetary investment in the project;
the consultant, these are the individuals or entities who acts as bridge between the owner and
contractors; and the contractors, who are the individuals or entities who undertake the
construction project activities (Brockmann, 2012). The variations associated with the project
are defined as the difference between the time when the particular tasks has to be completed
Page 7
Student ID #:
As briefed earlier, the variations can be signified by various forms of changes in the
construction projects. One of them can be changes in the schedule (Alzahrani and Emsley,
2013). Schedule refers to the overall duration that has been assigned for the completion of
project. The changes in the schedule can occur due to factors such as lack of resources, or the
sudden occurrence of any kind of risks (Aminbakhsh et al, 2013). It might be related to the
desire of some of the stakeholder to extend the deadline or stretch the duration without any
reason. In some cases, the variations occur when the parties vary on the requirements that
have been defined for the project. The requirements or the things that are to be achieved by
the end of the project are generally defined in the beginning of the project. However, due to
some changes in the mind of stakeholders or occurrence of any kind of situation leads to the
change in the requirements which eventually creates variations in the project.
The understanding of the client causes of variations in the construction projects in United
Arab Emirates will be at the core of this entire research paper. The next sub-section briefly
states the research background upon which the entire research study is based. The research
background is followed by the research problem that is likely to be resolved through the
conduction of this research. The research problem is followed by the research aim which
states where the entire research project is heading. The research objectives, after the research
aim discusses the aspects that will be touched while moving towards the achievement of the
research aim. The research scope will define the premise within which the research will be
conducted. The research scope is likely to help understand the limitations of this research
paper. The research questions discussed after the research scope will showcase the questions
that are to be answered by the end of this research project. This chapter has been summarized
in end under Summary section.
1.3 Research Background
The existence of variations among the construction project activities is inevitable, and any
effort to eliminate the variations is unlikely to be successful. The variations have impacted
almost all the associated individuals or entities with the construction projects. The individuals
or entities can be project owner, the individual who has monetary investment in the project;
the consultant, these are the individuals or entities who acts as bridge between the owner and
contractors; and the contractors, who are the individuals or entities who undertake the
construction project activities (Brockmann, 2012). The variations associated with the project
are defined as the difference between the time when the particular tasks has to be completed
Page 7
Student ID #:
8
and the time that was actually invested to complete that task. In any form of civil or private
construction projects, it is expected in the beginning that the task will be completed within
the defined duration and allotted project budgets. However, this is not how things turnout
every time. The changes in the activities, resources, and other factors are always observed
(Guo and Shang, 2012). The projects that are of huge size, the changes can be observed easily
and their impacts are huge.
It is important that the variations in the construction projects are understood clearly to ensure
that the variations can be reduced or controlled, if not completely eliminated. The changes in
the construction projects occur due to various reasons. The variations in construction projects
have negative impact on the entire economy of the particular country along with the
individuals who are engaged in the construction projects such as consultants, contractors, and
the owners (Halwatura and Ranasinghe, 2013). The variation in the construction activities is
an issue. The occurrence of deviations, being a common phenomenon, is the indication that
the entire construction sector is being challenged with certain causes that are to be identified
and appropriately managed.
In general, the works that are started by the engineers or the contractors for the particular
client, if faces any kind of changes in the schedule, resources, or other aspects, then such
alteration results into the unnecessary extension of the entire project duration and the budget
that has been spent on the project. This is very demotivating for all the stakeholders (Hobbs
and Besner, 2016). If the government is investing in particular civil construction project
considering that the project will be completed in certain time period and within the defined
budget, and if it does not happen, then it is likely that the credibility of the government in the
eyes of the pubic falls down. This situation is not only with the government projects. If the
private construction projects are considered, then it can be stated if the projects fail to be
completed within the certain duration and within the defined budget, then it is likely that the
parties will never meet again to work on other similar projects due to the lack of credibility or
faith in one another (Hwang and Ng, 2013). Therefore, it can be stated from here that the
completion of construction projects within the defined duration and given budget is necessary
to ensure that the credibility is built and better projects are developed.
The United Arab Emirates has witnessed numerous construction projects in past few decades
as it is clearly visible the way entire country has developed its infrastructure (Kang and Kim,
2015). Moreover, not only the government, but the private entities have largely invested in
Page 8
Student ID #:
and the time that was actually invested to complete that task. In any form of civil or private
construction projects, it is expected in the beginning that the task will be completed within
the defined duration and allotted project budgets. However, this is not how things turnout
every time. The changes in the activities, resources, and other factors are always observed
(Guo and Shang, 2012). The projects that are of huge size, the changes can be observed easily
and their impacts are huge.
It is important that the variations in the construction projects are understood clearly to ensure
that the variations can be reduced or controlled, if not completely eliminated. The changes in
the construction projects occur due to various reasons. The variations in construction projects
have negative impact on the entire economy of the particular country along with the
individuals who are engaged in the construction projects such as consultants, contractors, and
the owners (Halwatura and Ranasinghe, 2013). The variation in the construction activities is
an issue. The occurrence of deviations, being a common phenomenon, is the indication that
the entire construction sector is being challenged with certain causes that are to be identified
and appropriately managed.
In general, the works that are started by the engineers or the contractors for the particular
client, if faces any kind of changes in the schedule, resources, or other aspects, then such
alteration results into the unnecessary extension of the entire project duration and the budget
that has been spent on the project. This is very demotivating for all the stakeholders (Hobbs
and Besner, 2016). If the government is investing in particular civil construction project
considering that the project will be completed in certain time period and within the defined
budget, and if it does not happen, then it is likely that the credibility of the government in the
eyes of the pubic falls down. This situation is not only with the government projects. If the
private construction projects are considered, then it can be stated if the projects fail to be
completed within the certain duration and within the defined budget, then it is likely that the
parties will never meet again to work on other similar projects due to the lack of credibility or
faith in one another (Hwang and Ng, 2013). Therefore, it can be stated from here that the
completion of construction projects within the defined duration and given budget is necessary
to ensure that the credibility is built and better projects are developed.
The United Arab Emirates has witnessed numerous construction projects in past few decades
as it is clearly visible the way entire country has developed its infrastructure (Kang and Kim,
2015). Moreover, not only the government, but the private entities have largely invested in
Page 8
Student ID #:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
9
the construction projects around the country. At present, there are hundreds of construction
projects that are on-going and there are many yet to come in existence. In such scenario, it is
important that the variations in construction projects are understood to ensure that the future
or existing projects progress successfully.
1.4 Research Problem
The variations in the construction projects are a major challenge for all the construction
activities that are being conducted in the United Arab Emirates. The construction projects
face challenge in appropriately managing the construction projects and leading the project
activities towards successful completion. The variations in the construction projects have
been considered as the challenge that is being faced by the stakeholders. There are various
studies that have been conducted with reference to the variations in the construction projects
(Lee et al, 2015; Lindhard, 2015; Muhammad et al, 2015). The projects have resulted into
poor quality output, completion of the projects far from their intended duration, and the
excess expenditure of money on the project which is generally beyond the recommendation
of any of the associated stakeholders. In the United Arab Emirates, some of the projects are
still on hold because the duration of the project passed beyond thinking and now require
unprecedented amount of investment which is not acceptable to any of the stakeholders.
One of the major reasons behind the increased investment in the construction projects from
the one estimated is the continuously changing economic situation of the country and the
world (Taroun, 2014). It has been identified that in some cases, the construction projects are
of such a huge duration that the prices of raw materials are witnessed to varying much during
that duration. These fluctuations generally increase the overall cost of investment in the
project from what has been intended. There are multiple studies undertaken to ensure that
causes of variations are understood. However, it can be observed that many of the researches
have been generic and provide limited core understanding of the issue. The lack of specificity
in the causes that are resulting in the research project variations is likely impacting the
decisions that are made the stakeholders that are associated with the construction project
management.
The client of any construction project is an integral part as it is the sole investor in the project
and for whom the other two major stakeholders – consultants and contractors – conduct the
various activities (Walker, 2007). Therefore, it becomes important that the requirements of
the clients are met while attempting to complete the construction project activities. It has
Page 9
Student ID #:
the construction projects around the country. At present, there are hundreds of construction
projects that are on-going and there are many yet to come in existence. In such scenario, it is
important that the variations in construction projects are understood to ensure that the future
or existing projects progress successfully.
1.4 Research Problem
The variations in the construction projects are a major challenge for all the construction
activities that are being conducted in the United Arab Emirates. The construction projects
face challenge in appropriately managing the construction projects and leading the project
activities towards successful completion. The variations in the construction projects have
been considered as the challenge that is being faced by the stakeholders. There are various
studies that have been conducted with reference to the variations in the construction projects
(Lee et al, 2015; Lindhard, 2015; Muhammad et al, 2015). The projects have resulted into
poor quality output, completion of the projects far from their intended duration, and the
excess expenditure of money on the project which is generally beyond the recommendation
of any of the associated stakeholders. In the United Arab Emirates, some of the projects are
still on hold because the duration of the project passed beyond thinking and now require
unprecedented amount of investment which is not acceptable to any of the stakeholders.
One of the major reasons behind the increased investment in the construction projects from
the one estimated is the continuously changing economic situation of the country and the
world (Taroun, 2014). It has been identified that in some cases, the construction projects are
of such a huge duration that the prices of raw materials are witnessed to varying much during
that duration. These fluctuations generally increase the overall cost of investment in the
project from what has been intended. There are multiple studies undertaken to ensure that
causes of variations are understood. However, it can be observed that many of the researches
have been generic and provide limited core understanding of the issue. The lack of specificity
in the causes that are resulting in the research project variations is likely impacting the
decisions that are made the stakeholders that are associated with the construction project
management.
The client of any construction project is an integral part as it is the sole investor in the project
and for whom the other two major stakeholders – consultants and contractors – conduct the
various activities (Walker, 2007). Therefore, it becomes important that the requirements of
the clients are met while attempting to complete the construction project activities. It has
Page 9
Student ID #:
10
been identified that the effective coordination among these individuals or entities are
important to ensure that the project completes successfully and within the planned resources.
However, it has been witnessed that the challenge in the project variation occurs when there
is some input from the client when the project is progressing. This creates major challenge in
completing the project within the stipulated time and defined budget. Therefore, it becomes
an important aspect to understand the client causes of variation in construction projects. As
the focus of the current research project is the United Arab Emirates, therefore it is likely that
the client of causes of variations will be understood from this country’s point of view.
The variation challenges can occur from any side or anywhere, either it can occur due to the
changes in the external environment which might be related to the economic, political,
environmental, societal, technological, or others, or it can be internal to the construction
project that is from the stakeholders (Walker, 2007; Wambeke et al, 2017). The focus of the
current research project is to understand the client causes of variations, therefore limited
focus will be given on the other associated factors that are likely to cause the variations. The
reason is that it is important to understand one important reason for the project variations
appropriately then generalizing the entire research project objectives that is less likely to
yield any fruitful output.
1.5 Research Aim
The aim of this research is to understand the client causes of variation in the construction
projects in the United Arab Emirates. Understanding the client causes of variation is
important to understand as it is likely to give insight into areas that are leading to the
variation in the construction projects. The client of any construction projects is an integral
part and understanding this aspect is likely to help reduce the magnitude of variations
occurring from this aspect. In general, the clients are found to be suggesting changes when
the construction projects have taken off or the construction projects are about to complete
(Yan and Chen, 2013). Such changes create issue for the other stakeholders such as the
contractors or the consultants. The issue is associated with the various aspects of the projects
such as required changes in the human resources, extension of the budgets, extension of
timeline, and other such aspects. Therefore, it has been considered to pursue this aim through
this research project.
Page 10
Student ID #:
been identified that the effective coordination among these individuals or entities are
important to ensure that the project completes successfully and within the planned resources.
However, it has been witnessed that the challenge in the project variation occurs when there
is some input from the client when the project is progressing. This creates major challenge in
completing the project within the stipulated time and defined budget. Therefore, it becomes
an important aspect to understand the client causes of variation in construction projects. As
the focus of the current research project is the United Arab Emirates, therefore it is likely that
the client of causes of variations will be understood from this country’s point of view.
The variation challenges can occur from any side or anywhere, either it can occur due to the
changes in the external environment which might be related to the economic, political,
environmental, societal, technological, or others, or it can be internal to the construction
project that is from the stakeholders (Walker, 2007; Wambeke et al, 2017). The focus of the
current research project is to understand the client causes of variations, therefore limited
focus will be given on the other associated factors that are likely to cause the variations. The
reason is that it is important to understand one important reason for the project variations
appropriately then generalizing the entire research project objectives that is less likely to
yield any fruitful output.
1.5 Research Aim
The aim of this research is to understand the client causes of variation in the construction
projects in the United Arab Emirates. Understanding the client causes of variation is
important to understand as it is likely to give insight into areas that are leading to the
variation in the construction projects. The client of any construction projects is an integral
part and understanding this aspect is likely to help reduce the magnitude of variations
occurring from this aspect. In general, the clients are found to be suggesting changes when
the construction projects have taken off or the construction projects are about to complete
(Yan and Chen, 2013). Such changes create issue for the other stakeholders such as the
contractors or the consultants. The issue is associated with the various aspects of the projects
such as required changes in the human resources, extension of the budgets, extension of
timeline, and other such aspects. Therefore, it has been considered to pursue this aim through
this research project.
Page 10
Student ID #:
11
1.6 Research Objectives
Based on the research aim discussed above, there are certain research objectives that have
been considered for this research project. These research objectives are likely to act as guide
in completing this research paper. Given below are the research objectives devised for this
research paper:
1. The first research objective is to understand the main factors or the causes that are leading
to the variations in the construction projects, with the particular focus on the client causes of
variations and the civil engineering projects.
2. The second research objective is to understand the factors that are mostly impacting or
prevalent in the occurrences of variations in the construction projects.
3. The third research objective is to understand the impact of the variation causes on the civil
construction projects in the United Arab Emirates.
4. The fourth research objective is to identify the strategies that might be adopted so that the
variations in the civil construction projects can be reduced. The focus is on the reduction and
not on the complete the elimination as the client causes of variations is not the only factor
impacting the uncalled for changes.
1.7 Research Scope
The scope of the research in focused on understanding the premise that has been considered
while moving ahead with this research project. The aspects that are outside the defined
premise, despite their indirect relationship with this research paper, have not been considering
the available duration and budget of this project. The scope is oriented towards keeping the
research paper feasible enough for conduction. Given below are some of the research scopes
that have been developed for this research project:
1. The first scope is to understand past researches that have been conducted in association
with the research topic under consideration in this paper. This will be conducted to
understand what has been identified by the previous researchers and only those papers have
been picked that are likely to aide in the achievement of the research aims and objectives.
2. The second research scope is to understand the methodology that is to be adopted in
conduction of this research. There are multitudes of methodologies that can be adopted for
particular research and selection of suitable ones is important.
Page 11
Student ID #:
1.6 Research Objectives
Based on the research aim discussed above, there are certain research objectives that have
been considered for this research project. These research objectives are likely to act as guide
in completing this research paper. Given below are the research objectives devised for this
research paper:
1. The first research objective is to understand the main factors or the causes that are leading
to the variations in the construction projects, with the particular focus on the client causes of
variations and the civil engineering projects.
2. The second research objective is to understand the factors that are mostly impacting or
prevalent in the occurrences of variations in the construction projects.
3. The third research objective is to understand the impact of the variation causes on the civil
construction projects in the United Arab Emirates.
4. The fourth research objective is to identify the strategies that might be adopted so that the
variations in the civil construction projects can be reduced. The focus is on the reduction and
not on the complete the elimination as the client causes of variations is not the only factor
impacting the uncalled for changes.
1.7 Research Scope
The scope of the research in focused on understanding the premise that has been considered
while moving ahead with this research project. The aspects that are outside the defined
premise, despite their indirect relationship with this research paper, have not been considering
the available duration and budget of this project. The scope is oriented towards keeping the
research paper feasible enough for conduction. Given below are some of the research scopes
that have been developed for this research project:
1. The first scope is to understand past researches that have been conducted in association
with the research topic under consideration in this paper. This will be conducted to
understand what has been identified by the previous researchers and only those papers have
been picked that are likely to aide in the achievement of the research aims and objectives.
2. The second research scope is to understand the methodology that is to be adopted in
conduction of this research. There are multitudes of methodologies that can be adopted for
particular research and selection of suitable ones is important.
Page 11
Student ID #:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
12
3. The third research scope is to understand the individuals who will be selected for the
conduction of this research. The respondents are likely to be from the United Arab Emirates
and further understanding of them will dealt with latter.
4. The fourth research scope is to understand the statistical tools that will be applicable on the
research data that are likely to be collected during the research process.
5. The fifth research scope is to understand the way data will be analysed and suitable
conclusions will be reached that are likely to be of benefit to the individuals or entities that
are active in the construction industry in the United Arab Emirates.
6. The sixth research scope is to recommend strategies or ways that can be implemented to
improve the issues associated with the variations in the civil construction projects in the
United Arab Emirates.
1.8 Research Questions
The research questions that have been identified for this research paper is likely to keep the
researcher on track to achieve the research aim. The research questions are likely to be
answered by the end of this research through the processes to be discussed in the
methodology section. There is high possibility that some of the answers to some of the
research questions might be achieved during the conduction of detailed literature review.
Given below are the research questions that have been developed for this research paper
1. What are the main reasons or the causes that are leading to the variations in the
construction projects and the client causes of variations in the civil construction
projects in the United Arab Emirates?
2. What are the factors that are mostly impacting or prevalent in the occurrences of
variations in the construction projects?
3. What is the impact of the variation causes on the civil construction projects in the
United Arab Emirates?
4. What are the strategies or ways that might be adopted so that the variations in the civil
construction projects can be reduced?
These research questions will be the focus of this research paper. The research questions
will be answered by the end of this research in the conclusion section.
The current research paper has been designed as shown in the diagram below:
Page 12
Student ID #:
3. The third research scope is to understand the individuals who will be selected for the
conduction of this research. The respondents are likely to be from the United Arab Emirates
and further understanding of them will dealt with latter.
4. The fourth research scope is to understand the statistical tools that will be applicable on the
research data that are likely to be collected during the research process.
5. The fifth research scope is to understand the way data will be analysed and suitable
conclusions will be reached that are likely to be of benefit to the individuals or entities that
are active in the construction industry in the United Arab Emirates.
6. The sixth research scope is to recommend strategies or ways that can be implemented to
improve the issues associated with the variations in the civil construction projects in the
United Arab Emirates.
1.8 Research Questions
The research questions that have been identified for this research paper is likely to keep the
researcher on track to achieve the research aim. The research questions are likely to be
answered by the end of this research through the processes to be discussed in the
methodology section. There is high possibility that some of the answers to some of the
research questions might be achieved during the conduction of detailed literature review.
Given below are the research questions that have been developed for this research paper
1. What are the main reasons or the causes that are leading to the variations in the
construction projects and the client causes of variations in the civil construction
projects in the United Arab Emirates?
2. What are the factors that are mostly impacting or prevalent in the occurrences of
variations in the construction projects?
3. What is the impact of the variation causes on the civil construction projects in the
United Arab Emirates?
4. What are the strategies or ways that might be adopted so that the variations in the civil
construction projects can be reduced?
These research questions will be the focus of this research paper. The research questions
will be answered by the end of this research in the conclusion section.
The current research paper has been designed as shown in the diagram below:
Page 12
Student ID #:
13
In the current paper,
1.9 Dissertation Overview
Chapter 1: the first chapter will focus on giving the reader an overview of entire research
paper.
Chapter 2: The second chapter is on literature review and will review the past research
studies that are associated with this research to understand the various key dimensions. The
third chapter will discuss the methodology of the paper where the entire research design will
be understood that will be undertaken for this research. The fourth chapter assesses the data
collected from the primary research and the fifth chapter provides conclusive remarks on
overall study.
1.10 Summary
The consideration of client causes of variation in the construction projects in the United Arab
Emirates is important to understand as the variations in the construction projects have
become a challenging aspect within the construction projects to be managed. The
stakeholders associated with any kind of construction projects are finding it challenging to
ensure that the variations do not occur. The variations in the construction projects are
Page 13
Student ID #:
Review the literature
Identify gaps and contribution to
knowledge
In the current paper,
1.9 Dissertation Overview
Chapter 1: the first chapter will focus on giving the reader an overview of entire research
paper.
Chapter 2: The second chapter is on literature review and will review the past research
studies that are associated with this research to understand the various key dimensions. The
third chapter will discuss the methodology of the paper where the entire research design will
be understood that will be undertaken for this research. The fourth chapter assesses the data
collected from the primary research and the fifth chapter provides conclusive remarks on
overall study.
1.10 Summary
The consideration of client causes of variation in the construction projects in the United Arab
Emirates is important to understand as the variations in the construction projects have
become a challenging aspect within the construction projects to be managed. The
stakeholders associated with any kind of construction projects are finding it challenging to
ensure that the variations do not occur. The variations in the construction projects are
Page 13
Student ID #:
Review the literature
Identify gaps and contribution to
knowledge
14
impacting the timeline of the projects and budgets that are predefined for the projects. The
unnecessary delays in the budget and timeline also lead to loss in credibility and bad
relationship among individuals and entities. The United Arab Emirates has numerous on-
going construction projects that require adequate understanding of the variations that take
place. These construction projects are either government financed or of private companies.
Though the major focus of this paper is to understand the variations in terms of civil
construction projects, it is most likely that the private construction projects will be equally
benefitted from this research assessment.
The second chapter of this research paper is focused towards assessment of various research
papers and books developed by researchers and academicians that address the variations in
the construction projects. This chapter conducts the literature review of the past researches
that are directly or indirectly associated with the current research topic. The purpose of this
chapter would be to identify the variables of variations along with the development of
suitable framework. The third chapter of this research paper is focused towards understanding
the research methodology that has been considered for the conduction of this research. This
chapter is followed by the results and analysis chapter that details on the analysis of the data
collected from the respondents. The chapter on recommendation details on the ways or the
strategies that should be adopted to counter the client causes of variations identified in the
results and analysis section. The final chapter gives conclusive remarks on the entire research
study with the answers to the research questions identified earlier.
Page 14
Student ID #:
impacting the timeline of the projects and budgets that are predefined for the projects. The
unnecessary delays in the budget and timeline also lead to loss in credibility and bad
relationship among individuals and entities. The United Arab Emirates has numerous on-
going construction projects that require adequate understanding of the variations that take
place. These construction projects are either government financed or of private companies.
Though the major focus of this paper is to understand the variations in terms of civil
construction projects, it is most likely that the private construction projects will be equally
benefitted from this research assessment.
The second chapter of this research paper is focused towards assessment of various research
papers and books developed by researchers and academicians that address the variations in
the construction projects. This chapter conducts the literature review of the past researches
that are directly or indirectly associated with the current research topic. The purpose of this
chapter would be to identify the variables of variations along with the development of
suitable framework. The third chapter of this research paper is focused towards understanding
the research methodology that has been considered for the conduction of this research. This
chapter is followed by the results and analysis chapter that details on the analysis of the data
collected from the respondents. The chapter on recommendation details on the ways or the
strategies that should be adopted to counter the client causes of variations identified in the
results and analysis section. The final chapter gives conclusive remarks on the entire research
study with the answers to the research questions identified earlier.
Page 14
Student ID #:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
15
Chapter 2 :Literature2: Literature Review
2.1 Introduction
The literature review chapter makes an investigation of the client cause of variation in the
construction projects in United Arab Emirates in order to identify gaps in the literature
research papers and other form of studies that have been conducted in relation to the research
topic. The purpose of this chapter is to come up with the variables that are associated with the
variations.
2.2
The researchers have identified that the construction project variations has become a
challenging aspect that requires proper attention before it worsens the situations further (El-
Sayegh, 2008). The variations are referred to as the difference that takes place among the
actual and decided durations of the project. The variations have been identified to be
occurring in various aspects of the construction projects such as schedule, budget, human
resources, risks, and others. The variations have been found to as the alteration in the
situation from what was intended. It has been identified that the challenges associated with
the variations is dire in the countries that are still developing and lacks enough proper system
and procedure to handle and maintain the large sized construction projects. Some of the
researchers have showcased concern regarding the negative impact that is placed on the
construction projects. The presence of limited resources is sometime attributed as the reason
for the unnecessary variations (Faridi and El-Sayegh, 2006; Wang, 2000). If all the factors
are ideal, then it is expected that the project under consideration will finish as per the plan.
However, the countries like United Arab Emirates have witnessed construction projects that
run late in terms of cost and timeline.
There are various researches that have taken place in order to understand the causes behind
the variations in the construction activities. These studies have defined variations as the
change that is not in line to the intention of the stakeholders who are associated with the
particular project. The variations in the construction projects have become so common that
Page 15
Student ID #:
Chapter 2 :Literature2: Literature Review
2.1 Introduction
The literature review chapter makes an investigation of the client cause of variation in the
construction projects in United Arab Emirates in order to identify gaps in the literature
research papers and other form of studies that have been conducted in relation to the research
topic. The purpose of this chapter is to come up with the variables that are associated with the
variations.
2.2
The researchers have identified that the construction project variations has become a
challenging aspect that requires proper attention before it worsens the situations further (El-
Sayegh, 2008). The variations are referred to as the difference that takes place among the
actual and decided durations of the project. The variations have been identified to be
occurring in various aspects of the construction projects such as schedule, budget, human
resources, risks, and others. The variations have been found to as the alteration in the
situation from what was intended. It has been identified that the challenges associated with
the variations is dire in the countries that are still developing and lacks enough proper system
and procedure to handle and maintain the large sized construction projects. Some of the
researchers have showcased concern regarding the negative impact that is placed on the
construction projects. The presence of limited resources is sometime attributed as the reason
for the unnecessary variations (Faridi and El-Sayegh, 2006; Wang, 2000). If all the factors
are ideal, then it is expected that the project under consideration will finish as per the plan.
However, the countries like United Arab Emirates have witnessed construction projects that
run late in terms of cost and timeline.
There are various researches that have taken place in order to understand the causes behind
the variations in the construction activities. These studies have defined variations as the
change that is not in line to the intention of the stakeholders who are associated with the
particular project. The variations in the construction projects have become so common that
Page 15
Student ID #:
16
the stakeholders rarely get bothered by its occurrence. The stakeholders that are integral to
the construction projects are clients, consultants, and contractors (Abdul Rahman et al, 2012).
There are also other types of stakeholders, but these are the key ones. These stakeholders
have been found to be creating variations in the construction projects at various levels.
Though deep assessment has rarely been made on any of the particular stakeholders, the
generic understanding of the causes is available in few of the researches (Gamal et al, 2000).
It can be stated here that the better understanding of the variables impacting the variations
require deeper assessment of each aspects.
The variations in the construction projects have been found having adverse impacts on
carrying out the particular projects. This aspect is common to any project that is being
undertaken, whether smaller or bigger in size. The countries like United Arab Emirates are
hugely oriented towards development of strong infrastructure for the public which requires
substantial resources (Zaneldin, 2006; Halwatura and Ranasinghe, 2013). The development
of multi-stage infrastructures leads to the complex environments. Moreover, it has been
identified that the large construction projects require requires resources that are substantial in
quantity and investment. Therefore, any likely changes due to potential variation causes,
heavily impact the on-going project on the financial aspect. The implementation of the
construction projects also requires better relationship among the project stakeholders. This is
important as it ensures that the each of the stakeholders understand and communicate the
project requirement carefully. The presence of limited communication mechanism within the
project has also been found as impacting the project progress.
The client has been considered as the most important entity in the construction project
activities. The clients are those for whom particular project is being developed or who is
making monetary contribution to the project development (Halloum and Bajracharya, 2012).
The projects, either it is associated with the civil construction or any other field, are required
to fulfil the requirements that have been laid down by the clients. In such scenario, it is
imperative to understand the client requirements carefully as it become the key reason behind
the variation in the project management. Apart from the successful development of the
project requirements, it is also important that these are successfully communicated to the
other important stakeholders such as consultants and the contractors (De Meyer et al, 2002).
The project contractors are the acting partner of any particular construction projects, and
therefore it is important that they understand the requirement carefully. It has been identified
that the failure of contractors to understand the requirements of the clients has also resulted
Page 16
Student ID #:
the stakeholders rarely get bothered by its occurrence. The stakeholders that are integral to
the construction projects are clients, consultants, and contractors (Abdul Rahman et al, 2012).
There are also other types of stakeholders, but these are the key ones. These stakeholders
have been found to be creating variations in the construction projects at various levels.
Though deep assessment has rarely been made on any of the particular stakeholders, the
generic understanding of the causes is available in few of the researches (Gamal et al, 2000).
It can be stated here that the better understanding of the variables impacting the variations
require deeper assessment of each aspects.
The variations in the construction projects have been found having adverse impacts on
carrying out the particular projects. This aspect is common to any project that is being
undertaken, whether smaller or bigger in size. The countries like United Arab Emirates are
hugely oriented towards development of strong infrastructure for the public which requires
substantial resources (Zaneldin, 2006; Halwatura and Ranasinghe, 2013). The development
of multi-stage infrastructures leads to the complex environments. Moreover, it has been
identified that the large construction projects require requires resources that are substantial in
quantity and investment. Therefore, any likely changes due to potential variation causes,
heavily impact the on-going project on the financial aspect. The implementation of the
construction projects also requires better relationship among the project stakeholders. This is
important as it ensures that the each of the stakeholders understand and communicate the
project requirement carefully. The presence of limited communication mechanism within the
project has also been found as impacting the project progress.
The client has been considered as the most important entity in the construction project
activities. The clients are those for whom particular project is being developed or who is
making monetary contribution to the project development (Halloum and Bajracharya, 2012).
The projects, either it is associated with the civil construction or any other field, are required
to fulfil the requirements that have been laid down by the clients. In such scenario, it is
imperative to understand the client requirements carefully as it become the key reason behind
the variation in the project management. Apart from the successful development of the
project requirements, it is also important that these are successfully communicated to the
other important stakeholders such as consultants and the contractors (De Meyer et al, 2002).
The project contractors are the acting partner of any particular construction projects, and
therefore it is important that they understand the requirement carefully. It has been identified
that the failure of contractors to understand the requirements of the clients has also resulted
Page 16
Student ID #:
17
into major variations. Such variations are considered as huge as in some cases it requires
redevelopment (Kang and Kim, 2015). Therefore, the lack of proper communication of
requirements has been identified as one of the causes of variations in the construction
projects.
Some of the researchers have identified that if the schedules of project activities are changed
then it is likely to vary the project (Shuan, 2007). The reason is that the rescheduling requires
reallocation of resources which in case of huge construction projects are time consuming. The
change of schedule can be initiated on any end, it can be either the client willing to change
the duration or the contractor is unable to complete the predefined project duration. It has
been identified that such changes require engagement of additional resources in most of the
cases and some of the resources have been found to be getting redundant. Another important
aspect that leads to the variations is the changes in the scope. Some of the researchers have
identified that the reframing the project scope has been significant reason behind the
variations in the construction project (Chan and Chan, 2004). The changes in the scope are
generally initiated by the client for whom the project is being developed. In most cases, the
contractors rarely engage in the scope changes as it most likely impacts the project cost. The
changes in scope occur mostly due to the failure of the concerned parties in developing
appropriate plan in the beginning of the project. It has been asserted by some of the
researchers that if the owner or the client of the project is not involved adequately when the
project is being designed, then it is likely that the scope will require changes in the later
stages.
Apart from the above, researchers have identified that in some cases, the owners’ financial
challenge lead to the variations in the project progress. If the owner is failing to fulfil the
financial requirement of the contractors that are required to procure the resources or to meet
the other need of the contractors, then it is most likely that the project will suffer with
variations. The financial challenges impact the work schedules and also the quality that is
expected from the particular construction project (Akintoye and MacLeod, 1997). It has been
also identified that if the concerned stakeholders of the project are unable to make decisions
as quickly as possible, then it is most likely to impact the project progress. The quick decision
making ability among the stakeholders ensure that the project does not suffer any form of
delay. The failure to do so is most likely to increase the duration of the projects and
eventually the cost. The decision making delay can be from the client, consultant or
contractor side.
Page 17
Student ID #:
into major variations. Such variations are considered as huge as in some cases it requires
redevelopment (Kang and Kim, 2015). Therefore, the lack of proper communication of
requirements has been identified as one of the causes of variations in the construction
projects.
Some of the researchers have identified that if the schedules of project activities are changed
then it is likely to vary the project (Shuan, 2007). The reason is that the rescheduling requires
reallocation of resources which in case of huge construction projects are time consuming. The
change of schedule can be initiated on any end, it can be either the client willing to change
the duration or the contractor is unable to complete the predefined project duration. It has
been identified that such changes require engagement of additional resources in most of the
cases and some of the resources have been found to be getting redundant. Another important
aspect that leads to the variations is the changes in the scope. Some of the researchers have
identified that the reframing the project scope has been significant reason behind the
variations in the construction project (Chan and Chan, 2004). The changes in the scope are
generally initiated by the client for whom the project is being developed. In most cases, the
contractors rarely engage in the scope changes as it most likely impacts the project cost. The
changes in scope occur mostly due to the failure of the concerned parties in developing
appropriate plan in the beginning of the project. It has been asserted by some of the
researchers that if the owner or the client of the project is not involved adequately when the
project is being designed, then it is likely that the scope will require changes in the later
stages.
Apart from the above, researchers have identified that in some cases, the owners’ financial
challenge lead to the variations in the project progress. If the owner is failing to fulfil the
financial requirement of the contractors that are required to procure the resources or to meet
the other need of the contractors, then it is most likely that the project will suffer with
variations. The financial challenges impact the work schedules and also the quality that is
expected from the particular construction project (Akintoye and MacLeod, 1997). It has been
also identified that if the concerned stakeholders of the project are unable to make decisions
as quickly as possible, then it is most likely to impact the project progress. The quick decision
making ability among the stakeholders ensure that the project does not suffer any form of
delay. The failure to do so is most likely to increase the duration of the projects and
eventually the cost. The decision making delay can be from the client, consultant or
contractor side.
Page 17
Student ID #:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
18
The researchers have also identified that the distribution of power among the stakeholders
directly engaged in the project development is important to ensure that project moves ahead
successfully (Lee et al, 2015). The development of construction project requires that the key
stakeholders such as client, consultant, and contractor work together in conjunction to
achieve the project output. However, it has been found that the clients hold more power than
the other stakeholders and unnecessary assertion of power leads to disruption in the
conduction of project activities which eventually convert to variations in the project activities
(Wang, 2000). Moreover, if the client or owner puts forth certain changes in the
specifications, then it is most likely to alter the project path and bring huge variations. The
alteration in the project specifications have been identified as being common in the
construction projects. Such specifications are generally the resultant of poor project
objectives. The attention to the new specifications certainly impact the project brings
variation.
On one hand, the role of client is crucial to variations in the construction projects, the actions
of consultants also result into the project variations (Oladapo, 2007). It has been identified
that the consultants bring changes in the construction designs as the factor of design
improvements. The changes in the project designs are considered mostly in the projects that
take off without clear consideration on the design aspects. Those are generally come in the
category of design and build construction projects with numerous alterations or variations
from the actual. Such changes heavily impact the project duration and budget. Moreover, the
conflicts that occur in the documentation of the contracts also sometime result in the
variations. It has been identified that the clients interpret particular statements in a contract
differently than what has been interpreted by the contractors. This leads to the conflict and
the resultant settlements of conflict generally leads to variation in project. The lack of clarity
in the construction documents with less sufficient details also creates confusion among the
stakeholders.
It has been identified that the consultants engage in the changes of the project specifications.
This aspect has become a major concern as clients and consultants, both engage in some form
of changes in the specifications, and collectively it hugely varies the project. In some cases, it
has been found that the equipment that is required by the contractors is not available with the
concerned parties or not available in the market. This leads to unnecessary delay in the
project duration. Apart from that, the less number of human resources working on the project
is also the common challenge. The presence of unskilled labour is less challenging than the
Page 18
Student ID #:
The researchers have also identified that the distribution of power among the stakeholders
directly engaged in the project development is important to ensure that project moves ahead
successfully (Lee et al, 2015). The development of construction project requires that the key
stakeholders such as client, consultant, and contractor work together in conjunction to
achieve the project output. However, it has been found that the clients hold more power than
the other stakeholders and unnecessary assertion of power leads to disruption in the
conduction of project activities which eventually convert to variations in the project activities
(Wang, 2000). Moreover, if the client or owner puts forth certain changes in the
specifications, then it is most likely to alter the project path and bring huge variations. The
alteration in the project specifications have been identified as being common in the
construction projects. Such specifications are generally the resultant of poor project
objectives. The attention to the new specifications certainly impact the project brings
variation.
On one hand, the role of client is crucial to variations in the construction projects, the actions
of consultants also result into the project variations (Oladapo, 2007). It has been identified
that the consultants bring changes in the construction designs as the factor of design
improvements. The changes in the project designs are considered mostly in the projects that
take off without clear consideration on the design aspects. Those are generally come in the
category of design and build construction projects with numerous alterations or variations
from the actual. Such changes heavily impact the project duration and budget. Moreover, the
conflicts that occur in the documentation of the contracts also sometime result in the
variations. It has been identified that the clients interpret particular statements in a contract
differently than what has been interpreted by the contractors. This leads to the conflict and
the resultant settlements of conflict generally leads to variation in project. The lack of clarity
in the construction documents with less sufficient details also creates confusion among the
stakeholders.
It has been identified that the consultants engage in the changes of the project specifications.
This aspect has become a major concern as clients and consultants, both engage in some form
of changes in the specifications, and collectively it hugely varies the project. In some cases, it
has been found that the equipment that is required by the contractors is not available with the
concerned parties or not available in the market. This leads to unnecessary delay in the
project duration. Apart from that, the less number of human resources working on the project
is also the common challenge. The presence of unskilled labour is less challenging than the
Page 18
Student ID #:
19
presence of skilled man power (Keane et al, 2010). The United Arab Emirates have recently
witnessed influx of number of skilled and unskilled manpower from outside the country on
short term contract. The manpower is the key in the development of various construction
projects around the country. It has been identified in most of the cases, the lack of manpower
to adapt to the improved processes of constructions lead to the changes in the duration that is
taken to complete the projects.
In some cases it has been found that the contractors lack enough financial backing to
complete the project at hand. The construction projects, being labour intensive activities,
require that the contractors keep paying the hired labour even if they do not have projects in
hand. Moreover, in some cases, the contractors have been found paying the labours when the
project is stalled for certain period of time. These generally create financial challenges to
most of the contractors which in turn impact their ability to procure resources when they get
new project or when the stalled project take off (Thomas, 1995). Apart from this, if
workmanship displayed by the responsible party is not adequate and of quality, then it is
likely that the construction might have to be demolished for redevelopment. Also, it has been
identified that the resources that are to be procured from the suppliers should be of high
quality and must reach the construction venue on stipulated time to ensure that it does not
lead to the delay in the project development. However, if there is fault in the procurement
activity, then it is mostly likely that the variation in the construction project is occurring.
The position of project planning in the construction project is very high. If the project is not
strategically planned, then it is most likely that the project will suffer delay or budget
challenges. The strategic planning refers to the adequate allocation of resources and actions
considering various challenges that are likely to impact the construction project progress. The
strategic planning should be done considering the various stakeholders that are directly or
indirectly associated with the project and likely to have adverse or positive impact on the
project progress (Guo and Shang, 2012). It has been identified that the adequate designing of
the construction project is important as it directly impacts the variation in the project. The
designs that are not adequately designed, that is, the design that has not covered all project
requirements are likely to attract attention from the clients which might lead to variations.
The researchers have identified that the variations associated with the construction projects
are normal phenomenon. Despite efforts from the concerned stakeholders, the variations
surfaces in some way or the other. It is an inevitable element that impacts the productivity
Page 19
Student ID #:
presence of skilled man power (Keane et al, 2010). The United Arab Emirates have recently
witnessed influx of number of skilled and unskilled manpower from outside the country on
short term contract. The manpower is the key in the development of various construction
projects around the country. It has been identified in most of the cases, the lack of manpower
to adapt to the improved processes of constructions lead to the changes in the duration that is
taken to complete the projects.
In some cases it has been found that the contractors lack enough financial backing to
complete the project at hand. The construction projects, being labour intensive activities,
require that the contractors keep paying the hired labour even if they do not have projects in
hand. Moreover, in some cases, the contractors have been found paying the labours when the
project is stalled for certain period of time. These generally create financial challenges to
most of the contractors which in turn impact their ability to procure resources when they get
new project or when the stalled project take off (Thomas, 1995). Apart from this, if
workmanship displayed by the responsible party is not adequate and of quality, then it is
likely that the construction might have to be demolished for redevelopment. Also, it has been
identified that the resources that are to be procured from the suppliers should be of high
quality and must reach the construction venue on stipulated time to ensure that it does not
lead to the delay in the project development. However, if there is fault in the procurement
activity, then it is mostly likely that the variation in the construction project is occurring.
The position of project planning in the construction project is very high. If the project is not
strategically planned, then it is most likely that the project will suffer delay or budget
challenges. The strategic planning refers to the adequate allocation of resources and actions
considering various challenges that are likely to impact the construction project progress. The
strategic planning should be done considering the various stakeholders that are directly or
indirectly associated with the project and likely to have adverse or positive impact on the
project progress (Guo and Shang, 2012). It has been identified that the adequate designing of
the construction project is important as it directly impacts the variation in the project. The
designs that are not adequately designed, that is, the design that has not covered all project
requirements are likely to attract attention from the clients which might lead to variations.
The researchers have identified that the variations associated with the construction projects
are normal phenomenon. Despite efforts from the concerned stakeholders, the variations
surfaces in some way or the other. It is an inevitable element that impacts the productivity
Page 19
Student ID #:
20
and project progress of the construction activities. The key element of the project that is most
impacted by the variation is time taken to start the project and the overall duration of the
project. In this, the project deviates from what has been assigned or planned in actual. In any
construction activities, there are numerous activities that are completed before moving onto
the next activity. Therefore, it seems an obvious understanding that the variation in the
duration of one activity subsequently impacts the other activities in the project. In addition to
this, the extended duration considered by a particular task impacts the progress of the other
tasks. It is the responsibility of the project manager of the project and the executives to ensure
that the effective coordination is maintained in the project and to ensure that the project
completes as per the planned duration and the budget. Moreover, it has been identified that
the project manager should be considering the effort and coordination of the project team
members and ensuring that resources are performing their tasks appropriately. The project
manager should be assessing the perceptions of the project members and responding in
accordance to it. The perceptions of the employees whenever there are changes or variations
in the project from the external entities such as the client. This eventually slows down the
overall project progress as it might impact the motivation level of the employees. The reason
for this consideration is that their efforts if combined together will help complete the project
on time.
As per the Thomas et al (2002), the variation in the construction project is the absolute value
obtained after differencing the daily and the baseline productivity of the resources. There are
various entities within a construction project that impacts the variability in the project apart
from the client and they are consultant, contractor, and mixture of various causes (Arain,
2005). The similar entities have been identified by Gbeleyi (2002) that causes the variability
in the construction projects. The researcher identified that the contractor impact the variation
due to the presence of defects in the construction. The similar defects are the reason that calls
for contribution in variation from consultants (such as architects and the designers). Some
other causes of variations identified here are unseen situations, conditions of the site where
the construction is being done, financing of the project, delayed material supply, local laws
and associated challenges, routes acquired to bringing in the resources, mistakes in
developing the construction designs, and others.
In addition to the above causes of variation, Ramus and Birchall (1998) came up with certain
form of situations that sometime becomes the reason behind the variation. The first situation
is the desire of the architect to bring any changes in the earlier construction design due to
Page 20
Student ID #:
and project progress of the construction activities. The key element of the project that is most
impacted by the variation is time taken to start the project and the overall duration of the
project. In this, the project deviates from what has been assigned or planned in actual. In any
construction activities, there are numerous activities that are completed before moving onto
the next activity. Therefore, it seems an obvious understanding that the variation in the
duration of one activity subsequently impacts the other activities in the project. In addition to
this, the extended duration considered by a particular task impacts the progress of the other
tasks. It is the responsibility of the project manager of the project and the executives to ensure
that the effective coordination is maintained in the project and to ensure that the project
completes as per the planned duration and the budget. Moreover, it has been identified that
the project manager should be considering the effort and coordination of the project team
members and ensuring that resources are performing their tasks appropriately. The project
manager should be assessing the perceptions of the project members and responding in
accordance to it. The perceptions of the employees whenever there are changes or variations
in the project from the external entities such as the client. This eventually slows down the
overall project progress as it might impact the motivation level of the employees. The reason
for this consideration is that their efforts if combined together will help complete the project
on time.
As per the Thomas et al (2002), the variation in the construction project is the absolute value
obtained after differencing the daily and the baseline productivity of the resources. There are
various entities within a construction project that impacts the variability in the project apart
from the client and they are consultant, contractor, and mixture of various causes (Arain,
2005). The similar entities have been identified by Gbeleyi (2002) that causes the variability
in the construction projects. The researcher identified that the contractor impact the variation
due to the presence of defects in the construction. The similar defects are the reason that calls
for contribution in variation from consultants (such as architects and the designers). Some
other causes of variations identified here are unseen situations, conditions of the site where
the construction is being done, financing of the project, delayed material supply, local laws
and associated challenges, routes acquired to bringing in the resources, mistakes in
developing the construction designs, and others.
In addition to the above causes of variation, Ramus and Birchall (1998) came up with certain
form of situations that sometime becomes the reason behind the variation. The first situation
is the desire of the architect to bring any changes in the earlier construction design due to
Page 20
Student ID #:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
21
some potential reason. The second situation is the identification of discrepancies in the
contract documents. The third situation is the difference arising in the clauses placed in the
contract documents and the statutory requirements. The fourth is that if there is any error in
any part of the contract, then it can be reason for the variation in the project.
In addition to the above, Atkinson (1999) has identified that if bringing variations in the
project is providing benefit a party in the project, then it is likely that the variation will take
place. The similar observation has been made by Al-Seadan (2004) that in the case of
variations contractors would always make effort to increase their profit from the project and
reduce the cost, and this leads to challenging negotiations. The contractors would prefer to
increase the costs associated with the variation orders. The variation in the orders are
happening in almost all forms of construction projects due to various factors and from which
some of them were mentioned earlier. However, all the factors do not come into play at the
same time or at the same pace. These factors change depending on the project types and
associated elements (Arain and Pheng, 2005). The level of intensity with which particular
factor brings in project variability depends on the project nature, level of complexity of the
project, and the methods that are used to procure the required resources of the project.
Segawa et al (2002) asserts that if the construction project is complex, then the associated
stakeholders of the project should expect potential variation in the project. The variation can
begin from the design phase and might traverse to the implementation phase. The
construction designs and specifications are likely to change depending on the orientation of
the client of the project or the other stakeholders. It might be possible that the project owner
or client does not like the project design or the contractors, who will be handling the
implementation, will not be able to deliver what has been specified in the design. The
variation of such form are not common in the construction projects however the frequency
with which they occur might be different from project to project. As per Charoenngam et al.
(2003), the variation of the project can also be characterised in different way. That is, it is
possible that the change brought on the project by the contractor is not mentioned in the
contractor and thus the contractor would not be liable to get paid for the same. A study
conducted by Love (2002) led to the identification that the projects that require huge amount
of renovation activities witness increased frequency of variation. The reason is the level of
complexity related with such activities.
Page 21
Student ID #:
some potential reason. The second situation is the identification of discrepancies in the
contract documents. The third situation is the difference arising in the clauses placed in the
contract documents and the statutory requirements. The fourth is that if there is any error in
any part of the contract, then it can be reason for the variation in the project.
In addition to the above, Atkinson (1999) has identified that if bringing variations in the
project is providing benefit a party in the project, then it is likely that the variation will take
place. The similar observation has been made by Al-Seadan (2004) that in the case of
variations contractors would always make effort to increase their profit from the project and
reduce the cost, and this leads to challenging negotiations. The contractors would prefer to
increase the costs associated with the variation orders. The variation in the orders are
happening in almost all forms of construction projects due to various factors and from which
some of them were mentioned earlier. However, all the factors do not come into play at the
same time or at the same pace. These factors change depending on the project types and
associated elements (Arain and Pheng, 2005). The level of intensity with which particular
factor brings in project variability depends on the project nature, level of complexity of the
project, and the methods that are used to procure the required resources of the project.
Segawa et al (2002) asserts that if the construction project is complex, then the associated
stakeholders of the project should expect potential variation in the project. The variation can
begin from the design phase and might traverse to the implementation phase. The
construction designs and specifications are likely to change depending on the orientation of
the client of the project or the other stakeholders. It might be possible that the project owner
or client does not like the project design or the contractors, who will be handling the
implementation, will not be able to deliver what has been specified in the design. The
variation of such form are not common in the construction projects however the frequency
with which they occur might be different from project to project. As per Charoenngam et al.
(2003), the variation of the project can also be characterised in different way. That is, it is
possible that the change brought on the project by the contractor is not mentioned in the
contractor and thus the contractor would not be liable to get paid for the same. A study
conducted by Love (2002) led to the identification that the projects that require huge amount
of renovation activities witness increased frequency of variation. The reason is the level of
complexity related with such activities.
Page 21
Student ID #:
22
The study conducted by Gidado (1996) led to the understanding that the more the project will
be complex, more there will be chances of variation. Moreover, the variations in the project
occur due to the demand from the client to increase the speed with which the construction
activities are going on or demand to reduce the cost being incurred on the project activities.
In addition to these, the concerns associated with the health and safety of the workers
performing at the site also impacts the project variation. This element mostly comes into play
when the project planning does not successfully consider the risks associated with conducting
the project. The project complexity level can be either low medium or high depending on the
factors associated with it (Ireland, 2007). Moreover, Ireland asserts that the increasing
complexity of the project similarly increases the chances of variation. It has been found that if
the variation occurring in the project is due to the complex nature of the project, then it is
likely that the stakeholders of the project will take comparatively longer duration in
understanding the situation to come out with a viable plan or solution
In addition to the above, if the project size is huge, then the instances of variations occurs
significantly (Hao et al, 2008). The project size is considered as the key element that leads to
the variation due to the inclusion of various factors such as increased number of stakeholders,
routes to procure resources, budget, timeline, and others. It has been stated that if the size of
the project is huge, then the project strategies should be considered in detail along with the
inclusion of ample contingency provisions. Sidwell (1993) asserts that the size of the project
is among the key factors that impact the level of variability. The size of the projects can be
defined based on the value it carries or in its physical characteristics. The projects that are
large carries increased complexity which eventually leads to variation (Akinsola, 1997).
There are various studies conducted to understand the impact of the variations in the project
(CII, 1994; Arian and Pheng, 2005). Any form of variations that occur in the project, first
impacts the overall progress of the project is the impacted activity has no slack time (Assaf et
al, 1995). In another word, if there is variation in the project then there is high chance that the
project will be delayed from what was planned. However, the impact on the duration varies
from project to project depending on the project size and the level of variation occurred. In
addition to the impact on the time, the project variation also impacts the costs associated with
the project. The cost varies widely depending on the variation occurred. As for instance, the
change in the project design is likely to impact the cost and the contingencies associated with
it (Clough and Sears, 1994; Assaf et al, 1995). In such situations, it is important that right
amount of contingency funds are pre-planned before engaging into the project.
Page 22
Student ID #:
The study conducted by Gidado (1996) led to the understanding that the more the project will
be complex, more there will be chances of variation. Moreover, the variations in the project
occur due to the demand from the client to increase the speed with which the construction
activities are going on or demand to reduce the cost being incurred on the project activities.
In addition to these, the concerns associated with the health and safety of the workers
performing at the site also impacts the project variation. This element mostly comes into play
when the project planning does not successfully consider the risks associated with conducting
the project. The project complexity level can be either low medium or high depending on the
factors associated with it (Ireland, 2007). Moreover, Ireland asserts that the increasing
complexity of the project similarly increases the chances of variation. It has been found that if
the variation occurring in the project is due to the complex nature of the project, then it is
likely that the stakeholders of the project will take comparatively longer duration in
understanding the situation to come out with a viable plan or solution
In addition to the above, if the project size is huge, then the instances of variations occurs
significantly (Hao et al, 2008). The project size is considered as the key element that leads to
the variation due to the inclusion of various factors such as increased number of stakeholders,
routes to procure resources, budget, timeline, and others. It has been stated that if the size of
the project is huge, then the project strategies should be considered in detail along with the
inclusion of ample contingency provisions. Sidwell (1993) asserts that the size of the project
is among the key factors that impact the level of variability. The size of the projects can be
defined based on the value it carries or in its physical characteristics. The projects that are
large carries increased complexity which eventually leads to variation (Akinsola, 1997).
There are various studies conducted to understand the impact of the variations in the project
(CII, 1994; Arian and Pheng, 2005). Any form of variations that occur in the project, first
impacts the overall progress of the project is the impacted activity has no slack time (Assaf et
al, 1995). In another word, if there is variation in the project then there is high chance that the
project will be delayed from what was planned. However, the impact on the duration varies
from project to project depending on the project size and the level of variation occurred. In
addition to the impact on the time, the project variation also impacts the costs associated with
the project. The cost varies widely depending on the variation occurred. As for instance, the
change in the project design is likely to impact the cost and the contingencies associated with
it (Clough and Sears, 1994; Assaf et al, 1995). In such situations, it is important that right
amount of contingency funds are pre-planned before engaging into the project.
Page 22
Student ID #:
23
In addition to the above, if the project requires addition of few more trained professionals,
then it also impacts the project variation. Moreover, if the project has employed new
professionals, then the variations in the projects require that more trained professionals are
taken board to resolve the issues. In such scenario, the new professionals are removed from
the project (Fisk, 1997). The project variation also increases costs that are not directly
associated with the construction such as costs incurred in conducting reviews of the situation
and framing the new plan, use of other collaterals like paper work, and others. These are
called overhead costs of the projects (O’Brien, 1998). The payment delays are the other
resultant that occurs due to the variations in the project. If the variations in the project are
taking place in increased frequency, then along the whole project progress almost stalls for a
while and the associated resource providers fail to get timely payment. Here, this can also
have some serious implication such as complete non-payment to the subcontractors as the
project is delayed from what was defined (CII, 1990 and 1995).
Moreover, the variation impacts the final output of the project. As per CII (1995), if the
variations occurring in the project are frequent, then it is likely that the quality of the project
will be impacted and there is high probability that the project output will not be something
that was decided in the beginning. Also, the productivity of the human resources employed in
the project fall down. The variability causes the unnecessary shortage of materials and
particularly information on which the resource will work. The work starts to lose sequence
and creates confusion. Ibbs (1997) asserts that the variation orders of the project and the level
of productivity is negatively associated with each other. Thomas and Napolitan (1995) came
to the conclusion that the disruptions are caused in the project due to the variations which is
closely associated with the productivity. These disruptions can be caused by internal factors
or external entities such as client. The variations also lead to the delayed procurement and it
is a common resultant (Haster et al, 1991; O’Brien, 1998).
The variation of the project also leads to demolishing something which was built and
rebuilding the same thing with new specifications. It is obvious that considering the
occurrences of variations in the project implementation leads to destruction and
reconstruction of particular part. However, it has been observed that in some cases the project
has been demolished at particular part even after the completion (CII, 1990; Clough and
Sears, 1994). Moreover, the variations in the project also lead to the delays in the logistical
process of the project (Hester et al, 1991). The new tools, equipment, and materials required
for the project are generally reaches the site late when the variability takes place. In addition,
Page 23
Student ID #:
In addition to the above, if the project requires addition of few more trained professionals,
then it also impacts the project variation. Moreover, if the project has employed new
professionals, then the variations in the projects require that more trained professionals are
taken board to resolve the issues. In such scenario, the new professionals are removed from
the project (Fisk, 1997). The project variation also increases costs that are not directly
associated with the construction such as costs incurred in conducting reviews of the situation
and framing the new plan, use of other collaterals like paper work, and others. These are
called overhead costs of the projects (O’Brien, 1998). The payment delays are the other
resultant that occurs due to the variations in the project. If the variations in the project are
taking place in increased frequency, then along the whole project progress almost stalls for a
while and the associated resource providers fail to get timely payment. Here, this can also
have some serious implication such as complete non-payment to the subcontractors as the
project is delayed from what was defined (CII, 1990 and 1995).
Moreover, the variation impacts the final output of the project. As per CII (1995), if the
variations occurring in the project are frequent, then it is likely that the quality of the project
will be impacted and there is high probability that the project output will not be something
that was decided in the beginning. Also, the productivity of the human resources employed in
the project fall down. The variability causes the unnecessary shortage of materials and
particularly information on which the resource will work. The work starts to lose sequence
and creates confusion. Ibbs (1997) asserts that the variation orders of the project and the level
of productivity is negatively associated with each other. Thomas and Napolitan (1995) came
to the conclusion that the disruptions are caused in the project due to the variations which is
closely associated with the productivity. These disruptions can be caused by internal factors
or external entities such as client. The variations also lead to the delayed procurement and it
is a common resultant (Haster et al, 1991; O’Brien, 1998).
The variation of the project also leads to demolishing something which was built and
rebuilding the same thing with new specifications. It is obvious that considering the
occurrences of variations in the project implementation leads to destruction and
reconstruction of particular part. However, it has been observed that in some cases the project
has been demolished at particular part even after the completion (CII, 1990; Clough and
Sears, 1994). Moreover, the variations in the project also lead to the delays in the logistical
process of the project (Hester et al, 1991). The new tools, equipment, and materials required
for the project are generally reaches the site late when the variability takes place. In addition,
Page 23
Student ID #:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
24
this also damages the reputation of the organization that is handling the project planning and
implementation. The reason is that the variations in the projects are considered as the
beginning to the different claims or the disputes made by the concerned parties.
The project variations also challenge the safety provision for the employees working in the
project. The level of safety for the employees can be impacted if the frequent variations take
place (O’Brien, 1998). As for instance, for the heavy construction, if there is variation, then it
might require changes in the tools and equipment which will further require that the
equipment specific safety measures are considered (Arain et al, 2004). As stated previously,
the variations in the project progress damages the reputation and along with it, it also impacts
the relationships among the various parties engaged in the project. In such situation it
becomes important that a middle ground is identified instead of moving towards the court
(Arain et al, 2014). Moreover, the pay for the contractor increases if the change has been
induced from the client’s side or from the consultant’s side. In both these situations, the client
has to pay the price. Therefore, it has been found that contractors prefer to suggest client of
variations and it is considered as the usual source of increased work and source of income
earned by the contractor.
The professionals engaged in the project also strain their mutual relationship due to the
variations in the project. The variations lead to the state of confusion in projects that are of
complex nature and the pressure from external entities to resolve the situation lead to poor
relationship. Along with this, as stated earlier, the project also impacts the time required to
complete the overall project. The impact on the schedule is considered as the direct output
generating from the project variations (Ibbs, 1997; Zeitoun and Oberlender, 1993). A study
conducted by Kumaraswamy (1998) led to the finding that the around 50% of the
construction projects that have been delayed are the result of the variations occurring in the
project in some way or the other.
The project variation orders occurring in the project can be of various types. As per Cox
(1999), there are three forms of variation orders, namely, formal, productive and principal
change. The formal change refers to the use of document to be sent to the client to approve
the required project changes. In this change order, the modifications in terms and plans of the
contract can be witnessed. Another is productive change where the workers perform extra
work as directed by the client due to the changes brought in by the client. The third change
order takes place when it is found that the project requires huge change consideration. On the
Page 24
Student ID #:
this also damages the reputation of the organization that is handling the project planning and
implementation. The reason is that the variations in the projects are considered as the
beginning to the different claims or the disputes made by the concerned parties.
The project variations also challenge the safety provision for the employees working in the
project. The level of safety for the employees can be impacted if the frequent variations take
place (O’Brien, 1998). As for instance, for the heavy construction, if there is variation, then it
might require changes in the tools and equipment which will further require that the
equipment specific safety measures are considered (Arain et al, 2004). As stated previously,
the variations in the project progress damages the reputation and along with it, it also impacts
the relationships among the various parties engaged in the project. In such situation it
becomes important that a middle ground is identified instead of moving towards the court
(Arain et al, 2014). Moreover, the pay for the contractor increases if the change has been
induced from the client’s side or from the consultant’s side. In both these situations, the client
has to pay the price. Therefore, it has been found that contractors prefer to suggest client of
variations and it is considered as the usual source of increased work and source of income
earned by the contractor.
The professionals engaged in the project also strain their mutual relationship due to the
variations in the project. The variations lead to the state of confusion in projects that are of
complex nature and the pressure from external entities to resolve the situation lead to poor
relationship. Along with this, as stated earlier, the project also impacts the time required to
complete the overall project. The impact on the schedule is considered as the direct output
generating from the project variations (Ibbs, 1997; Zeitoun and Oberlender, 1993). A study
conducted by Kumaraswamy (1998) led to the finding that the around 50% of the
construction projects that have been delayed are the result of the variations occurring in the
project in some way or the other.
The project variation orders occurring in the project can be of various types. As per Cox
(1999), there are three forms of variation orders, namely, formal, productive and principal
change. The formal change refers to the use of document to be sent to the client to approve
the required project changes. In this change order, the modifications in terms and plans of the
contract can be witnessed. Another is productive change where the workers perform extra
work as directed by the client due to the changes brought in by the client. The third change
order takes place when it is found that the project requires huge change consideration. On the
Page 24
Student ID #:
25
other hand, Ndihokubwayo (2008) puts the variations in two categories. The first is beneficial
variation where the variation takes place to improve the project quality or to reduce the cost
being incurred. The second is detrimental variation where the variation negatively impacts
the project quality, progress, cost, and other aspects of the project.
Along with the impact on the project variation caused by the client’s desire, the method
approved by the client for the procurement also impacts the project variation. The
understanding of the mechanics behind the variation orders and the management of such
variation, it would be preferable to understand the methods of procurements considered. It
has been stated earlier that a particular construction project consists of multiple stakeholders
such as clients, consultants (comprising architects or designers), contractors, and others. The
methods that are adopted to implement the project are different. The procurement routes
considered by the project development states the type of contract agreement among the
concerned parties of the contract. It has been found that the different procurement routes
leads to different level of variations in the project (Love, 2002). As per research conducted by
Love (2002), the procurement route that is non-traditional is witnessing more variation.
However, it has been found that the variability in the costs associated with the project
procurement routes are not of major difference.
The variation orders are issued by any party involved in the project. However, it should be
ensured that the variation order should be in the written form (Charoengngam et al, 2003).
The approval of variation orders takes time depending on the size of the project and the
number of stakeholders involved in the project directly. After the approval of the particular
change order, the new change order acts as the replacement for that particular clause
mentioned in the original contract. The characteristics of a good construction project contract
is that it includes all the appropriate measures that deals with the variation orders of the
project and the processes required for dispute settlement.
As stated earlier, there are two methods for procurement. First is traditional and another is
non-traditional. Segawa et al (2002) asserts that the traditional procurement methods
witnesses increased variations in comparison to other procurement methods. In the traditional
method the client would generally consult the consultants to develop the required design for
construction and the use of quantity surveyor is facilitated who engage in documentations
that will be later used by the contractor.
[to continue]
Page 25
Student ID #:
other hand, Ndihokubwayo (2008) puts the variations in two categories. The first is beneficial
variation where the variation takes place to improve the project quality or to reduce the cost
being incurred. The second is detrimental variation where the variation negatively impacts
the project quality, progress, cost, and other aspects of the project.
Along with the impact on the project variation caused by the client’s desire, the method
approved by the client for the procurement also impacts the project variation. The
understanding of the mechanics behind the variation orders and the management of such
variation, it would be preferable to understand the methods of procurements considered. It
has been stated earlier that a particular construction project consists of multiple stakeholders
such as clients, consultants (comprising architects or designers), contractors, and others. The
methods that are adopted to implement the project are different. The procurement routes
considered by the project development states the type of contract agreement among the
concerned parties of the contract. It has been found that the different procurement routes
leads to different level of variations in the project (Love, 2002). As per research conducted by
Love (2002), the procurement route that is non-traditional is witnessing more variation.
However, it has been found that the variability in the costs associated with the project
procurement routes are not of major difference.
The variation orders are issued by any party involved in the project. However, it should be
ensured that the variation order should be in the written form (Charoengngam et al, 2003).
The approval of variation orders takes time depending on the size of the project and the
number of stakeholders involved in the project directly. After the approval of the particular
change order, the new change order acts as the replacement for that particular clause
mentioned in the original contract. The characteristics of a good construction project contract
is that it includes all the appropriate measures that deals with the variation orders of the
project and the processes required for dispute settlement.
As stated earlier, there are two methods for procurement. First is traditional and another is
non-traditional. Segawa et al (2002) asserts that the traditional procurement methods
witnesses increased variations in comparison to other procurement methods. In the traditional
method the client would generally consult the consultants to develop the required design for
construction and the use of quantity surveyor is facilitated who engage in documentations
that will be later used by the contractor.
[to continue]
Page 25
Student ID #:
26
References
Alsaedan, B. (2004). The effect of construction management procurement method on the
cost overrun of private construction projects in Saudi Arabia, PhD thesis,
Department of civil engineering, University of Dundee.
Arain, F. and Pheng, L., (2007) Modeling for management of variations in building
projects. Engineering, Construction and Architectural Management, 14(5),
420-433.
Arain, F. M. and Pheng, L.S. and Assaf, S.A., (2006). Contractors' views of the
potential causes of inconsistencies between design and construction in Saudi
Arabia. Journal of Performance of Constructed Facilities, 20(1), 74-83.
Charoenngam, C. Coquince, S. T. and Hadikusumo, B. H. W. (2003). Web-based
application for managing change orders in construction projects. J.
Construction Innovation, 3, pp. 197-215.
Choy, W.K. and Sidwell, A.C. (1991) Source of Variations in Australian Construction
Contracts. Building Economist, Vol. 30, No. 3, pp. 25-30.
Ibbs, C. W. (1997). Quantitative impacts of project change: size issues. Journal of
Construction Engineering and Management, 123(3), 308-311.
Ibbs, C. W., Wong, C. K., and Kwak, Y. H. (2001). Project change management system.
J. Mgmt. in Engrg. ASCE, 17 (3), pp. 159-165.
Ibbs, C.W., Lee, S.A. and Li, M.I. (1998). Fast tracking’s impact on project change,
Project Management Journal, 29(4), pp. 35-41.
Ireland, L. (2007). ‘Project Complexity: A Brief Exposure to Difficult Situations’,
Retrieved on May 15, 2017, from
http://www.asapm.org/asapmag/articles/PrezSez10-07.pdf
Kumaraswamy, M H (1998) Consequences of construction conflict: a Hong Kong
perspective. Journal of Management in Engineering, 14(3), 66–74.
Love, P.E.D. (2002). 'Influence of Project Type and Procurement Method on Rework
Costs in Building Construction Projects', Journal of Construction Engineering
and Management, vol. 128, no. 1, pp 1-29
Page 26
Student ID #:
References
Alsaedan, B. (2004). The effect of construction management procurement method on the
cost overrun of private construction projects in Saudi Arabia, PhD thesis,
Department of civil engineering, University of Dundee.
Arain, F. and Pheng, L., (2007) Modeling for management of variations in building
projects. Engineering, Construction and Architectural Management, 14(5),
420-433.
Arain, F. M. and Pheng, L.S. and Assaf, S.A., (2006). Contractors' views of the
potential causes of inconsistencies between design and construction in Saudi
Arabia. Journal of Performance of Constructed Facilities, 20(1), 74-83.
Charoenngam, C. Coquince, S. T. and Hadikusumo, B. H. W. (2003). Web-based
application for managing change orders in construction projects. J.
Construction Innovation, 3, pp. 197-215.
Choy, W.K. and Sidwell, A.C. (1991) Source of Variations in Australian Construction
Contracts. Building Economist, Vol. 30, No. 3, pp. 25-30.
Ibbs, C. W. (1997). Quantitative impacts of project change: size issues. Journal of
Construction Engineering and Management, 123(3), 308-311.
Ibbs, C. W., Wong, C. K., and Kwak, Y. H. (2001). Project change management system.
J. Mgmt. in Engrg. ASCE, 17 (3), pp. 159-165.
Ibbs, C.W., Lee, S.A. and Li, M.I. (1998). Fast tracking’s impact on project change,
Project Management Journal, 29(4), pp. 35-41.
Ireland, L. (2007). ‘Project Complexity: A Brief Exposure to Difficult Situations’,
Retrieved on May 15, 2017, from
http://www.asapm.org/asapmag/articles/PrezSez10-07.pdf
Kumaraswamy, M H (1998) Consequences of construction conflict: a Hong Kong
perspective. Journal of Management in Engineering, 14(3), 66–74.
Love, P.E.D. (2002). 'Influence of Project Type and Procurement Method on Rework
Costs in Building Construction Projects', Journal of Construction Engineering
and Management, vol. 128, no. 1, pp 1-29
Page 26
Student ID #:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
27
Newcombe, R., (2003). From client to project stakeholders: a stakeholder mapping
approach. Construction Management and Economics 22 (9/10), 762–784.
O’Brien, J. J. (1998). Construction change orders, McGraw-Hill, New York.
Segawa, J.K., Mfolwe, K.M., Makuke, B. and Kutua, B. (2002). “Construction
variations: a scourge or a necessity”, Proceedings of the 1st CIB-W107
International Conference on Creating a Sustainable Construction Industry in
Developing Countries, Cape Town, South Africa.
Smith, J. and Love, P.E.D. (2004) Stakeholder Management During Project Inception:
Strategic Needs Analysis. ASCE Journal of Architectural Engineering, 10 (1)
pp. 22-33. ISSN: 1076-0431
Turner, J. R., V. Kristoffer, and L. Thurloway, Eds. (2002). The Project Manager as
Change Agent. London, McGraw-Hill Publishing Co.
Weiss, J.W. (2006) Business Ethics- A Stakeholder and Issues Management Approach
(4th edn.). Mason: Thomson Higher Education.
Zimmerman, L. W., and Hart, G. D. (1982). Value engineering: A practical approach
for owners, designers, and contractors (Vol. 134). New York: Van Nostrand
Reinhold.
Page 27
Student ID #:
Newcombe, R., (2003). From client to project stakeholders: a stakeholder mapping
approach. Construction Management and Economics 22 (9/10), 762–784.
O’Brien, J. J. (1998). Construction change orders, McGraw-Hill, New York.
Segawa, J.K., Mfolwe, K.M., Makuke, B. and Kutua, B. (2002). “Construction
variations: a scourge or a necessity”, Proceedings of the 1st CIB-W107
International Conference on Creating a Sustainable Construction Industry in
Developing Countries, Cape Town, South Africa.
Smith, J. and Love, P.E.D. (2004) Stakeholder Management During Project Inception:
Strategic Needs Analysis. ASCE Journal of Architectural Engineering, 10 (1)
pp. 22-33. ISSN: 1076-0431
Turner, J. R., V. Kristoffer, and L. Thurloway, Eds. (2002). The Project Manager as
Change Agent. London, McGraw-Hill Publishing Co.
Weiss, J.W. (2006) Business Ethics- A Stakeholder and Issues Management Approach
(4th edn.). Mason: Thomson Higher Education.
Zimmerman, L. W., and Hart, G. D. (1982). Value engineering: A practical approach
for owners, designers, and contractors (Vol. 134). New York: Van Nostrand
Reinhold.
Page 27
Student ID #:
1 out of 29
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.