This assignment delves into the core principles of project management. It covers fundamental concepts like project planning, scheduling, risk management, and communication. Students will examine various project management methodologies, including Agile and Waterfall, and analyze their strengths and weaknesses. The assignment also highlights essential tools and techniques used in project management for effective execution and monitoring.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/4d5eb065-64b2-4a46-ab50-8e120ca427f1-page-1.webp)
Running head: EDI FINAL SOFTWARE IMPLEMENTATION
Proposal for the installation of
SWAGGIES NEW EDI SOFTWARE
SYSTEM
Project management: EDI Final Software Implementation Plan into all Swaggies
Name of the student:
Name of the university:
Proposal for the installation of
SWAGGIES NEW EDI SOFTWARE
SYSTEM
Project management: EDI Final Software Implementation Plan into all Swaggies
Name of the student:
Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/cf0b80f4-650d-4269-b21c-d3a7ca3e987d-page-2.webp)
1EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Table of Contents
Stage 2: Project Plan........................................................................................................................2
2.1 Preparation of project plan.....................................................................................................2
2.2 Management strategies developed for the project.................................................................2
2.3 Required resources.................................................................................................................3
2.4 Gantt chart.............................................................................................................................4
2.5 Development of communication plan....................................................................................7
2.6 Detailed budget plan..............................................................................................................8
Stage 3: Mid Project Report..........................................................................................................10
3.1 Project task completed.........................................................................................................10
3.2 Milestone reached recorded in the Gantt chart....................................................................11
3.3 Actual Vs Budget expenditure to date.................................................................................12
3.4 Deviation from the project plan or budget for which action plans are taken......................15
3.5 Communication made with the stakeholders.......................................................................16
Stage 4: Project Evaluation and Completion.................................................................................17
4.1 The project progress details and project deliverables..........................................................17
4.2 Problems those have been identified...................................................................................17
4.3 Project documentation.........................................................................................................18
4.4 Financial report....................................................................................................................18
4.5 Lesson have been learned....................................................................................................19
4.6 Evaluation of the project......................................................................................................19
References......................................................................................................................................20
Table of Contents
Stage 2: Project Plan........................................................................................................................2
2.1 Preparation of project plan.....................................................................................................2
2.2 Management strategies developed for the project.................................................................2
2.3 Required resources.................................................................................................................3
2.4 Gantt chart.............................................................................................................................4
2.5 Development of communication plan....................................................................................7
2.6 Detailed budget plan..............................................................................................................8
Stage 3: Mid Project Report..........................................................................................................10
3.1 Project task completed.........................................................................................................10
3.2 Milestone reached recorded in the Gantt chart....................................................................11
3.3 Actual Vs Budget expenditure to date.................................................................................12
3.4 Deviation from the project plan or budget for which action plans are taken......................15
3.5 Communication made with the stakeholders.......................................................................16
Stage 4: Project Evaluation and Completion.................................................................................17
4.1 The project progress details and project deliverables..........................................................17
4.2 Problems those have been identified...................................................................................17
4.3 Project documentation.........................................................................................................18
4.4 Financial report....................................................................................................................18
4.5 Lesson have been learned....................................................................................................19
4.6 Evaluation of the project......................................................................................................19
References......................................................................................................................................20
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/ab858744-4358-4ac6-8b16-76555f5e8e9e-page-3.webp)
2EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Stage 2: Project Plan
2.1 Preparation of project plan
In order to resolve the issues of traditional data management Swaggies has developed
new EDI software for interchanging the confidential information without any kind of error. The
overall time and budget needed for the development of EDI system, proper time, key stakeholder
and communication plan is required to be adopted by the project executive of the company. In
order to install the EDI software for the company, the necessary steps those are needed to be
followed are as follows:
Understanding the project scope and value of the project plan
Extensive research is conducted by the project manager and project team member
Tough set of questions should be asked to make the project requirements clearer
Gathering software, hardware, physical and security requirements
Analyzing the gathered requirements
The project plan is outlined by the project manager
Discussion among the project manager and project team members
The entire project plan should be documented
The plan is executed in the teamGantt
The final plan is published officially
2.2 Management strategies developed for the project
In order to accomplish the project successfully, different strategies are required to be
adopted. For this particular project the strategies those have been undertaken are as follows:
Stage 2: Project Plan
2.1 Preparation of project plan
In order to resolve the issues of traditional data management Swaggies has developed
new EDI software for interchanging the confidential information without any kind of error. The
overall time and budget needed for the development of EDI system, proper time, key stakeholder
and communication plan is required to be adopted by the project executive of the company. In
order to install the EDI software for the company, the necessary steps those are needed to be
followed are as follows:
Understanding the project scope and value of the project plan
Extensive research is conducted by the project manager and project team member
Tough set of questions should be asked to make the project requirements clearer
Gathering software, hardware, physical and security requirements
Analyzing the gathered requirements
The project plan is outlined by the project manager
Discussion among the project manager and project team members
The entire project plan should be documented
The plan is executed in the teamGantt
The final plan is published officially
2.2 Management strategies developed for the project
In order to accomplish the project successfully, different strategies are required to be
adopted. For this particular project the strategies those have been undertaken are as follows:
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/2103d5a3-88a8-447a-a328-02265a0627d6-page-4.webp)
3EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Accurate project planning: In this phase the project manager should ensure the total
budget and time needed to successfully complete the project. With the help of project feasibility
study the manager will get to know about the total expenditure and investment needed to be done
for the successful implementation of the project. Not only this but also, the other elements those
are adopted by the project manager include project objective, scope, assumptions, risk
management, approaches and duration as well.
Project work-plan: In this phase the project planning that has been done, are outlined in
such way so that project definition can be prepared. In order to manage the project accurately the
project manager should provide a work plan to the project manager with step by step instruction.
An accurate Work Breakdown Structure (WBS) and Network Diagram (ND) are also developed
for creating planning horizon.
Comparison between different EDI software systems: In the initiation phase Swaggies
has traditional data management system which is not that much compatible according to the
business and project requirements. In order to enhance the level of consumer services for the
clients different available EDI systems are compared by the project manager. It is found that with
the help of the comparison resultant the effectiveness and efficiency of the system can be
measured. In order to gain competitive advantages and high level economic success installation
of accurate EDIS software is very much necessary.
2.3 Required resources
In order to accomplish the project both human and physical resources are necessary to be
adopted by the project manager. For this particular project the required resources are as follows:
Human resource Project sponsor
Accurate project planning: In this phase the project manager should ensure the total
budget and time needed to successfully complete the project. With the help of project feasibility
study the manager will get to know about the total expenditure and investment needed to be done
for the successful implementation of the project. Not only this but also, the other elements those
are adopted by the project manager include project objective, scope, assumptions, risk
management, approaches and duration as well.
Project work-plan: In this phase the project planning that has been done, are outlined in
such way so that project definition can be prepared. In order to manage the project accurately the
project manager should provide a work plan to the project manager with step by step instruction.
An accurate Work Breakdown Structure (WBS) and Network Diagram (ND) are also developed
for creating planning horizon.
Comparison between different EDI software systems: In the initiation phase Swaggies
has traditional data management system which is not that much compatible according to the
business and project requirements. In order to enhance the level of consumer services for the
clients different available EDI systems are compared by the project manager. It is found that with
the help of the comparison resultant the effectiveness and efficiency of the system can be
measured. In order to gain competitive advantages and high level economic success installation
of accurate EDIS software is very much necessary.
2.3 Required resources
In order to accomplish the project both human and physical resources are necessary to be
adopted by the project manager. For this particular project the required resources are as follows:
Human resource Project sponsor
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/69add75f-06e6-478f-b19b-51364a831ff7-page-5.webp)
4EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Project administrator
Technical team member
Quality assurance tem member
Finance team member
Physical resource Equipments
Facility
Expenditure and total funding
Equipments
2.4 Gantt chart
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0
Schedule for
EDI software
adoption
131 days Sat
9/1/18
Fri
3/1/19 $93,682.00
1
Project
initiation
phase
56 days Sat
9/1/18
Fri
11/16/18 $51,942.00
1.1
Preparing
project
proposal
5 days Sat
9/1/18
Thu
9/6/18
Project
manager ,software
[1],others [1]
$3,402.00
1.2
Project
proposal for
approval
10 days Fri
9/7/18
Thu
9/20/18 2
quality assurance
team ,hardware[1],sof
tware [1],technical
team
$9,002.00
1.3
Project
team
formation and
meeting plan
development
15 days Fri
9/21/18
Thu
10/11/18 3
Project
manager ,technical
team ,software [1]
$16,912.00
Project administrator
Technical team member
Quality assurance tem member
Finance team member
Physical resource Equipments
Facility
Expenditure and total funding
Equipments
2.4 Gantt chart
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0
Schedule for
EDI software
adoption
131 days Sat
9/1/18
Fri
3/1/19 $93,682.00
1
Project
initiation
phase
56 days Sat
9/1/18
Fri
11/16/18 $51,942.00
1.1
Preparing
project
proposal
5 days Sat
9/1/18
Thu
9/6/18
Project
manager ,software
[1],others [1]
$3,402.00
1.2
Project
proposal for
approval
10 days Fri
9/7/18
Thu
9/20/18 2
quality assurance
team ,hardware[1],sof
tware [1],technical
team
$9,002.00
1.3
Project
team
formation and
meeting plan
development
15 days Fri
9/21/18
Thu
10/11/18 3
Project
manager ,technical
team ,software [1]
$16,912.00
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/8f53116a-786d-4a5e-baa6-9b24753244bc-page-6.webp)
5EDI FINAL SOFTWARE IMPLEMENTATION PLAN
1.4 Software
purchase 9 days Fri
9/21/18
Wed
10/3/18 3 finance team ,project
sponsor, software [1] $7,312.00
1.5
Research
on required
hardware
9 days Fri
10/12/18
Wed
10/24/18 4,5
project sponsor,
quality assurance
team ,others [1]
$8,010.00
1.6
Meeting
with IT
company and
development
of discussion
plan
8 days Thu
10/25/18
Mon
11/5/18 6,5
others [1],technical
team ,hardware[1],sof
tware [1]
$4,132.00
1.7
Project
budget
planning
9 days Tue
11/6/18
Fri
11/16/18 7
finance
team ,hardware[1],sof
tware [1],others [1]
$3,172.00
2
Milestone
1:
Completion
of project
initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 8 others [0] $0.00
3
Project
planning
phase
43 days Mon
11/19/18
Wed
1/16/19 $25,412.00
3.1
Installatio
n of
networking
throughout
warehouse
department
6 days Mon
11/19/18
Mon
11/26/18 9
Project
manager ,project
sponsor
$6,720.00
3.2
Software
fixing and
hardware
problem
identification
15 days Tue
11/27/18
Mon
12/17/18 11 technical team $7,200.00
3.3
Removing
old system
and installing
new system
12 days Tue
12/18/18
Wed
1/2/19 11,12
quality assurance
team ,hardware[1],ot
hers [1],software [1]
$5,092.00
1.4 Software
purchase 9 days Fri
9/21/18
Wed
10/3/18 3 finance team ,project
sponsor, software [1] $7,312.00
1.5
Research
on required
hardware
9 days Fri
10/12/18
Wed
10/24/18 4,5
project sponsor,
quality assurance
team ,others [1]
$8,010.00
1.6
Meeting
with IT
company and
development
of discussion
plan
8 days Thu
10/25/18
Mon
11/5/18 6,5
others [1],technical
team ,hardware[1],sof
tware [1]
$4,132.00
1.7
Project
budget
planning
9 days Tue
11/6/18
Fri
11/16/18 7
finance
team ,hardware[1],sof
tware [1],others [1]
$3,172.00
2
Milestone
1:
Completion
of project
initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 8 others [0] $0.00
3
Project
planning
phase
43 days Mon
11/19/18
Wed
1/16/19 $25,412.00
3.1
Installatio
n of
networking
throughout
warehouse
department
6 days Mon
11/19/18
Mon
11/26/18 9
Project
manager ,project
sponsor
$6,720.00
3.2
Software
fixing and
hardware
problem
identification
15 days Tue
11/27/18
Mon
12/17/18 11 technical team $7,200.00
3.3
Removing
old system
and installing
new system
12 days Tue
12/18/18
Wed
1/2/19 11,12
quality assurance
team ,hardware[1],ot
hers [1],software [1]
$5,092.00
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/d85fde3c-6d92-4507-8eea-df591b0d0247-page-7.webp)
6EDI FINAL SOFTWARE IMPLEMENTATION PLAN
3.4
Meeting
with
stakeholders
10 days Thu
1/3/19
Wed
1/16/19 13,11 Project manager $6,400.00
4
Milestone
2:
Completion
of project
planning
phase
0 days Wed
1/16/19
Wed
1/16/19 14 Project manager $0.00
5
Project
execution
phase
23 days Thu
1/17/19
Mon
2/18/19 $12,676.00
5.1
Compariso
n between
EDI system
5 days Thu
1/17/19
Wed
1/23/19 15 technical team ,others
[1],software [1] $2,602.00
5.2
project
outline
execution
4 days Thu
1/24/19
Tue
1/29/19 17
Project
manager ,project
sponsor
$4,480.00
5.3 prototype
unit testing 2 days Wed
1/30/19
Thu
1/31/19 18 technical
team ,software [1] $1,072.00
5.4
prototype
integrated
testing
3 days Fri
2/1/19
Tue
2/5/19 19 technical team ,others
[1] $1,530.00
5.5
Affordabil
ity testing of
EDI system
9 days Wed
2/6/19
Mon
2/18/19 20 finance
team ,software [1] $2,992.00
6
Milestone
3:
Completion
of project
execution
phase
0 days Mon
2/18/19
Mon
2/18/19 21 Project manager $0.00
7 Project
closure phase 9 days Tue
2/19/19
Fri
3/1/19 $3,652.00
7.1 Stakeholde
r signoff 3 days Tue
2/19/19
Thu
2/21/19 22 project sponsor $1,440.00
7.2 Project 3 days Fri Tue 24 Project $2,122.00
3.4
Meeting
with
stakeholders
10 days Thu
1/3/19
Wed
1/16/19 13,11 Project manager $6,400.00
4
Milestone
2:
Completion
of project
planning
phase
0 days Wed
1/16/19
Wed
1/16/19 14 Project manager $0.00
5
Project
execution
phase
23 days Thu
1/17/19
Mon
2/18/19 $12,676.00
5.1
Compariso
n between
EDI system
5 days Thu
1/17/19
Wed
1/23/19 15 technical team ,others
[1],software [1] $2,602.00
5.2
project
outline
execution
4 days Thu
1/24/19
Tue
1/29/19 17
Project
manager ,project
sponsor
$4,480.00
5.3 prototype
unit testing 2 days Wed
1/30/19
Thu
1/31/19 18 technical
team ,software [1] $1,072.00
5.4
prototype
integrated
testing
3 days Fri
2/1/19
Tue
2/5/19 19 technical team ,others
[1] $1,530.00
5.5
Affordabil
ity testing of
EDI system
9 days Wed
2/6/19
Mon
2/18/19 20 finance
team ,software [1] $2,992.00
6
Milestone
3:
Completion
of project
execution
phase
0 days Mon
2/18/19
Mon
2/18/19 21 Project manager $0.00
7 Project
closure phase 9 days Tue
2/19/19
Fri
3/1/19 $3,652.00
7.1 Stakeholde
r signoff 3 days Tue
2/19/19
Thu
2/21/19 22 project sponsor $1,440.00
7.2 Project 3 days Fri Tue 24 Project $2,122.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/75dbabe5-abe2-40b8-bb65-d10e5515f110-page-8.webp)
7EDI FINAL SOFTWARE IMPLEMENTATION PLAN
documentation 2/22/19 2/26/19 manager ,others
[1],software [1]
7.3
Post
project
maintenance
plan
3 days Wed
2/27/19
Fri
3/1/19 24,25 others [1] $90.00
8
Milestone
4:
Completion
of project
closure phase
0 days Fri
3/1/19
Fri
3/1/19 26 Project manager $0.00
9
Milestone
1:
Completion
of project
initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 8 others [0] $0.00
10
Milestone
3:
Completion
of project
planning
phase
0 days Wed
1/16/19
Wed
1/16/19 14 Project manager $0.00
11
Milestone
3:
Completion
of project
execution
phase
0 days Mon
2/18/19
Mon
2/18/19 21 Project manager $0.00
12
Milestone
4:
Completion
of project
closure phase
0 days Fri
3/1/19
Fri
3/1/19 26 Project manager $0.00
2.5 Development of communication plan
Purpose Report to Frequency Medium Time duration
documentation 2/22/19 2/26/19 manager ,others
[1],software [1]
7.3
Post
project
maintenance
plan
3 days Wed
2/27/19
Fri
3/1/19 24,25 others [1] $90.00
8
Milestone
4:
Completion
of project
closure phase
0 days Fri
3/1/19
Fri
3/1/19 26 Project manager $0.00
9
Milestone
1:
Completion
of project
initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 8 others [0] $0.00
10
Milestone
3:
Completion
of project
planning
phase
0 days Wed
1/16/19
Wed
1/16/19 14 Project manager $0.00
11
Milestone
3:
Completion
of project
execution
phase
0 days Mon
2/18/19
Mon
2/18/19 21 Project manager $0.00
12
Milestone
4:
Completion
of project
closure phase
0 days Fri
3/1/19
Fri
3/1/19 26 Project manager $0.00
2.5 Development of communication plan
Purpose Report to Frequency Medium Time duration
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/cfb94a75-9acd-47d1-adc2-1eb952030dde-page-9.webp)
8EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Discussion
between the
project
administrator and
project team
members about
the details of
software
Project
administrator
Weekly Face to face
meeting., email
and PPPT
2 hours
QA team will be
reporting to the
project manager
about the project
quality that has
to be
implemented
Project manager Daily Face to face
meeting, PPT
and emails
1 hour
Technical team
members will
make discussion
about the
software details
and its
implementation
Project manager Daily Meeting,
conferences and
PPT, email
2 hour
Discussion
between the
project
administrator and
project team
members about
the details of
software
Project
administrator
Weekly Face to face
meeting., email
and PPPT
2 hours
QA team will be
reporting to the
project manager
about the project
quality that has
to be
implemented
Project manager Daily Face to face
meeting, PPT
and emails
1 hour
Technical team
members will
make discussion
about the
software details
and its
implementation
Project manager Daily Meeting,
conferences and
PPT, email
2 hour
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/628517da-55a9-41ab-80cf-4dd42bc3b72b-page-10.webp)
9EDI FINAL SOFTWARE IMPLEMENTATION PLAN
plan
Project
administrator
provided the
details of EDI
software their
features and
other
requirements
accurately in the
organized
meeting
General manager Weekly Meeting, PPT,
conferences
1 hour
2.6 Detailed budget plan
WBS Task Name Resource Names Cost
0 Schedule for EDI software
adoption $93,682.00
1 Project initiation phase $51,942.00
1.1 Preparing project
proposal
Project manager ,software [1],others
[1] $3,402.00
1.2 Project proposal for
approval
quality assurance
team ,hardware[1],software
[1],technical team
$9,002.00
1.3
Project team formation
and meeting plan
development
Project manager ,technical
team ,software [1] $16,912.00
plan
Project
administrator
provided the
details of EDI
software their
features and
other
requirements
accurately in the
organized
meeting
General manager Weekly Meeting, PPT,
conferences
1 hour
2.6 Detailed budget plan
WBS Task Name Resource Names Cost
0 Schedule for EDI software
adoption $93,682.00
1 Project initiation phase $51,942.00
1.1 Preparing project
proposal
Project manager ,software [1],others
[1] $3,402.00
1.2 Project proposal for
approval
quality assurance
team ,hardware[1],software
[1],technical team
$9,002.00
1.3
Project team formation
and meeting plan
development
Project manager ,technical
team ,software [1] $16,912.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/d727a526-c12b-4a17-a9e6-4872f2936ddf-page-11.webp)
10EDI FINAL SOFTWARE IMPLEMENTATION PLAN
1.4 Software purchase finance team ,project sponsor,
software [1] $7,312.00
1.5 Research on required
hardware
project sponsor, quality assurance
team ,others [1] $8,010.00
1.6
Meeting with IT
company and development of
discussion plan
others [1],technical
team ,hardware[1],software [1] $4,132.00
1.7 Project budget planning finance team ,hardware[1],software
[1],others [1] $3,172.00
2 Milestone 1: Completion
of project initiation phase others [0] $0.00
3 Project planning phase $25,412.00
3.1
Installation of
networking throughout
warehouse department
Project manager ,project sponsor $6,720.00
3.2
Software fixing and
hardware problem
identification
technical team $7,200.00
3.3 Removing old system
and installing new system
quality assurance
team ,hardware[1],others
[1],software [1]
$5,092.00
3.4 Meeting with
stakeholders Project manager $6,400.00
4 Milestone 2: Completion
of project planning phase Project manager $0.00
5 Project execution phase $12,676.00
5.1 Comparison between
EDI system
technical team ,others [1],software
[1] $2,602.00
5.2 project outline execution Project manager ,project sponsor $4,480.00
5.3 prototype unit testing technical team ,software [1] $1,072.00
5.4 prototype integrated
testing technical team ,others [1] $1,530.00
1.4 Software purchase finance team ,project sponsor,
software [1] $7,312.00
1.5 Research on required
hardware
project sponsor, quality assurance
team ,others [1] $8,010.00
1.6
Meeting with IT
company and development of
discussion plan
others [1],technical
team ,hardware[1],software [1] $4,132.00
1.7 Project budget planning finance team ,hardware[1],software
[1],others [1] $3,172.00
2 Milestone 1: Completion
of project initiation phase others [0] $0.00
3 Project planning phase $25,412.00
3.1
Installation of
networking throughout
warehouse department
Project manager ,project sponsor $6,720.00
3.2
Software fixing and
hardware problem
identification
technical team $7,200.00
3.3 Removing old system
and installing new system
quality assurance
team ,hardware[1],others
[1],software [1]
$5,092.00
3.4 Meeting with
stakeholders Project manager $6,400.00
4 Milestone 2: Completion
of project planning phase Project manager $0.00
5 Project execution phase $12,676.00
5.1 Comparison between
EDI system
technical team ,others [1],software
[1] $2,602.00
5.2 project outline execution Project manager ,project sponsor $4,480.00
5.3 prototype unit testing technical team ,software [1] $1,072.00
5.4 prototype integrated
testing technical team ,others [1] $1,530.00
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/944c770a-ae6c-4668-b951-01df1d0dbcb1-page-12.webp)
11EDI FINAL SOFTWARE IMPLEMENTATION PLAN
5.5 Affordability testing of
EDI system finance team ,software [1] $2,992.00
6 Milestone 3: Completion
of project execution phase Project manager $0.00
7 Project closure phase $3,652.00
7.1 Stakeholder signoff project sponsor $1,440.00
7.2 Project documentation Project manager ,others [1],software
[1] $2,122.00
7.3 Post project maintenance
plan others [1] $90.00
8 Milestone 4: Completion
of project closure phase Project manager $0.00
9 Milestone 1: Completion
of project initiation phase others [0] $0.00
10 Milestone 3: Completion
of project planning phase Project manager $0.00
11 Milestone 3: Completion
of project execution phase Project manager $0.00
12 Milestone 4: Completion
of project closure phase Project manager $0.00
Stage 3: Mid Project Report
3.1 Project task completed
Training and development program: In order to make the project manager familiar to
the project details, proper training and development program is needed to be arranged by the
project manager for the project team members. It is expected that with the help of the organized
5.5 Affordability testing of
EDI system finance team ,software [1] $2,992.00
6 Milestone 3: Completion
of project execution phase Project manager $0.00
7 Project closure phase $3,652.00
7.1 Stakeholder signoff project sponsor $1,440.00
7.2 Project documentation Project manager ,others [1],software
[1] $2,122.00
7.3 Post project maintenance
plan others [1] $90.00
8 Milestone 4: Completion
of project closure phase Project manager $0.00
9 Milestone 1: Completion
of project initiation phase others [0] $0.00
10 Milestone 3: Completion
of project planning phase Project manager $0.00
11 Milestone 3: Completion
of project execution phase Project manager $0.00
12 Milestone 4: Completion
of project closure phase Project manager $0.00
Stage 3: Mid Project Report
3.1 Project task completed
Training and development program: In order to make the project manager familiar to
the project details, proper training and development program is needed to be arranged by the
project manager for the project team members. It is expected that with the help of the organized
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/dd999a67-8912-4e35-8cc4-35b569f739f3-page-13.webp)
12EDI FINAL SOFTWARE IMPLEMENTATION PLAN
training program, the project team member will get to know more about the project requirements
and project goal.
Development of encryption program: In order to mitigate the issues of data loss it is
necessary for the project manager to implement proper security aspects in terms of encryption,
firewall and string password. While transferring data, it is necessary for the project manager to
keep it within the boundary to avoid data hijacking. In order to maintain data security proper
encryption algorithm is required to be adopted.
Risk transfer strategy: For mitigating the risks fours different strategies are there those
are required to be adopted such as accept the risk, avoid the risk, transfer the risk and exploit the
risk. However, among these four aspects based on the requirement and project goal proper risk
mitigation strategy is needed to be adopted by the project manager and project team members.
Software and hardware testing: In order to ensure that, all the adopted hardware and
software are accurate for the EDI system. It is necessary for the project manager to go through
both unit and integrated hardware and software testing session. It will help the project manager
and project team member about the necessary additional components those should be adopted to
get successful revenue.
3.2 Milestone reached recorded in the Gantt chart
The reached milestones those have been recorded in the Gant chart are as follows:
Task Name Duration Start Finish Resource Names
Milestone 1: Completion of
project initiation phase 0 days Fri 11/16/18 Fri 11/16/18 others [0]
Milestone 3: Completion of
project planning phase 0 days Wed 1/16/19 Wed 1/16/19 Project manager
training program, the project team member will get to know more about the project requirements
and project goal.
Development of encryption program: In order to mitigate the issues of data loss it is
necessary for the project manager to implement proper security aspects in terms of encryption,
firewall and string password. While transferring data, it is necessary for the project manager to
keep it within the boundary to avoid data hijacking. In order to maintain data security proper
encryption algorithm is required to be adopted.
Risk transfer strategy: For mitigating the risks fours different strategies are there those
are required to be adopted such as accept the risk, avoid the risk, transfer the risk and exploit the
risk. However, among these four aspects based on the requirement and project goal proper risk
mitigation strategy is needed to be adopted by the project manager and project team members.
Software and hardware testing: In order to ensure that, all the adopted hardware and
software are accurate for the EDI system. It is necessary for the project manager to go through
both unit and integrated hardware and software testing session. It will help the project manager
and project team member about the necessary additional components those should be adopted to
get successful revenue.
3.2 Milestone reached recorded in the Gantt chart
The reached milestones those have been recorded in the Gant chart are as follows:
Task Name Duration Start Finish Resource Names
Milestone 1: Completion of
project initiation phase 0 days Fri 11/16/18 Fri 11/16/18 others [0]
Milestone 3: Completion of
project planning phase 0 days Wed 1/16/19 Wed 1/16/19 Project manager
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/210a7c4f-c9da-42a4-a385-2e98267025ac-page-14.webp)
13EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Milestone 3: Completion of
project execution phase 0 days Mon 2/18/19 Mon 2/18/19 Project manager
Milestone 4: Completion of
project closure phase 0 days Fri 3/1/19 Fri 3/1/19 Project manager
3.3 Actual Vs Budget expenditure to date
Task Name Duration Start Finish Cost Actual Cost % Work
Complete
Schedule for EDI
software
adoption
131 days Sat 9/1/18 Fri 3/1/19 $93,682.00 $52,084.19 56%
Milestone 1:
Completion of
project initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 $0.00 $0.00 0%
Milestone 2:
Completion of
project planning
phase
0 days Wed
1/16/19
Wed
1/16/19 $0.00 $0.00 0%
Milestone 3:
Completion of
project execution
phase
0 days Mon
2/18/19
Mon
2/18/19 $0.00 $0.00 0%
Milestone 1:
Completion of
project initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 $0.00 $0.00 0%
Milestone 3:
Completion of
project planning
phase
0 days Wed
1/16/19
Wed
1/16/19 $0.00 $0.00 0%
Milestone 3:
Completion of
project execution
phase
0 days Mon
2/18/19
Mon
2/18/19 $0.00 $0.00 0%
Milestone 3: Completion of
project execution phase 0 days Mon 2/18/19 Mon 2/18/19 Project manager
Milestone 4: Completion of
project closure phase 0 days Fri 3/1/19 Fri 3/1/19 Project manager
3.3 Actual Vs Budget expenditure to date
Task Name Duration Start Finish Cost Actual Cost % Work
Complete
Schedule for EDI
software
adoption
131 days Sat 9/1/18 Fri 3/1/19 $93,682.00 $52,084.19 56%
Milestone 1:
Completion of
project initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 $0.00 $0.00 0%
Milestone 2:
Completion of
project planning
phase
0 days Wed
1/16/19
Wed
1/16/19 $0.00 $0.00 0%
Milestone 3:
Completion of
project execution
phase
0 days Mon
2/18/19
Mon
2/18/19 $0.00 $0.00 0%
Milestone 1:
Completion of
project initiation
phase
0 days Fri
11/16/18
Fri
11/16/18 $0.00 $0.00 0%
Milestone 3:
Completion of
project planning
phase
0 days Wed
1/16/19
Wed
1/16/19 $0.00 $0.00 0%
Milestone 3:
Completion of
project execution
phase
0 days Mon
2/18/19
Mon
2/18/19 $0.00 $0.00 0%
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/413d1047-5308-4ff6-a4e2-57029ab19925-page-15.webp)
14EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Milestone 4:
Completion of
project closure
phase
0 days Fri 3/1/19 Fri 3/1/19 $0.00 $0.00 0%
Milestone 4:
Completion of
project closure
phase
0 days Fri 3/1/19 Fri 3/1/19 $0.00 $0.00 20%
Project closure
phase 9 days Tue
2/19/19 Fri 3/1/19 $3,652.00 $1,061.00 25%
Stakeholder
signoff 3 days Tue
2/19/19
Thu
2/21/19 $1,440.00 $0.00 0%
Post project
maintenance plan 3 days Wed
2/27/19 Fri 3/1/19 $90.00 $0.00 0%
Project
documentation 3 days Fri 2/22/19 Tue
2/26/19 $2,122.00 $1,061.00 50%
Project
execution phase 23 days Thu
1/17/19
Mon
2/18/19 $12,676.00 $5,184.39 40%
Comparison
between EDI
system
5 days Thu
1/17/19
Wed
1/23/19 $2,602.00 $780.60 30%
Affordability
testing of EDI
system
9 days Wed
2/6/19
Mon
2/18/19 $2,992.00 $897.60 30%
project outline
execution 4 days Thu
1/24/19
Tue
1/29/19 $4,480.00 $1,792.00 40%
prototype unit
testing 2 days Wed
1/30/19
Thu
1/31/19 $1,072.00 $643.20 60%
prototype
integrated testing 3 days Fri 2/1/19 Tue 2/5/19 $1,530.00 $1,070.99 70%
Project
planning phase 43 days Mon
11/19/18
Wed
1/16/19 $25,412.00 $12,543.20 50%
Installation of
networking
throughout
6 days Mon
11/19/18
Mon
11/26/18
$6,720.00 $2,688.00 40%
Milestone 4:
Completion of
project closure
phase
0 days Fri 3/1/19 Fri 3/1/19 $0.00 $0.00 0%
Milestone 4:
Completion of
project closure
phase
0 days Fri 3/1/19 Fri 3/1/19 $0.00 $0.00 20%
Project closure
phase 9 days Tue
2/19/19 Fri 3/1/19 $3,652.00 $1,061.00 25%
Stakeholder
signoff 3 days Tue
2/19/19
Thu
2/21/19 $1,440.00 $0.00 0%
Post project
maintenance plan 3 days Wed
2/27/19 Fri 3/1/19 $90.00 $0.00 0%
Project
documentation 3 days Fri 2/22/19 Tue
2/26/19 $2,122.00 $1,061.00 50%
Project
execution phase 23 days Thu
1/17/19
Mon
2/18/19 $12,676.00 $5,184.39 40%
Comparison
between EDI
system
5 days Thu
1/17/19
Wed
1/23/19 $2,602.00 $780.60 30%
Affordability
testing of EDI
system
9 days Wed
2/6/19
Mon
2/18/19 $2,992.00 $897.60 30%
project outline
execution 4 days Thu
1/24/19
Tue
1/29/19 $4,480.00 $1,792.00 40%
prototype unit
testing 2 days Wed
1/30/19
Thu
1/31/19 $1,072.00 $643.20 60%
prototype
integrated testing 3 days Fri 2/1/19 Tue 2/5/19 $1,530.00 $1,070.99 70%
Project
planning phase 43 days Mon
11/19/18
Wed
1/16/19 $25,412.00 $12,543.20 50%
Installation of
networking
throughout
6 days Mon
11/19/18
Mon
11/26/18
$6,720.00 $2,688.00 40%
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/31e7d443-7ab9-44d8-81c7-8b675c38b9c3-page-16.webp)
15EDI FINAL SOFTWARE IMPLEMENTATION PLAN
warehouse
department
Software
fixing and
hardware problem
identification
15 days Tue
11/27/18
Mon
12/17/18 $7,200.00 $3,600.00 50%
Meeting with
stakeholders 10 days Thu 1/3/19 Wed
1/16/19 $6,400.00 $3,200.00 50%
Removing old
system and
installing new
system
12 days Tue
12/18/18
Wed
1/2/19 $5,092.00 $3,055.20 60%
Project
initiation phase 56 days Sat 9/1/18 Fri
11/16/18 $51,942.00 $33,295.60 64%
Project
proposal for
approval
10 days Fri 9/7/18 Thu
9/20/18 $9,002.00 $4,501.00 50%
Meeting with
IT company and
development of
discussion plan
8 days Thu
10/25/18
Mon
11/5/18 $4,132.00 $2,066.00 50%
Preparing
project proposal 5 days Sat 9/1/18 Thu 9/6/18 $3,402.00 $2,041.20 60%
Software
purchase 9 days Fri 9/21/18 Wed
10/3/18 $7,312.00 $4,387.20 60%
Project team
formation and
meeting plan
development
15 days Fri 9/21/18 Thu
10/11/18 $16,912.00 $11,838.40 70%
Research on
required hardware 9 days Fri
10/12/18
Wed
10/24/18 $8,010.00 $5,607.00 70%
Project budget
planning 9 days Tue
11/6/18
Fri
11/16/18 $3,172.00 $2,854.80 90%
warehouse
department
Software
fixing and
hardware problem
identification
15 days Tue
11/27/18
Mon
12/17/18 $7,200.00 $3,600.00 50%
Meeting with
stakeholders 10 days Thu 1/3/19 Wed
1/16/19 $6,400.00 $3,200.00 50%
Removing old
system and
installing new
system
12 days Tue
12/18/18
Wed
1/2/19 $5,092.00 $3,055.20 60%
Project
initiation phase 56 days Sat 9/1/18 Fri
11/16/18 $51,942.00 $33,295.60 64%
Project
proposal for
approval
10 days Fri 9/7/18 Thu
9/20/18 $9,002.00 $4,501.00 50%
Meeting with
IT company and
development of
discussion plan
8 days Thu
10/25/18
Mon
11/5/18 $4,132.00 $2,066.00 50%
Preparing
project proposal 5 days Sat 9/1/18 Thu 9/6/18 $3,402.00 $2,041.20 60%
Software
purchase 9 days Fri 9/21/18 Wed
10/3/18 $7,312.00 $4,387.20 60%
Project team
formation and
meeting plan
development
15 days Fri 9/21/18 Thu
10/11/18 $16,912.00 $11,838.40 70%
Research on
required hardware 9 days Fri
10/12/18
Wed
10/24/18 $8,010.00 $5,607.00 70%
Project budget
planning 9 days Tue
11/6/18
Fri
11/16/18 $3,172.00 $2,854.80 90%
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/ece82c8d-70a0-4e22-b96b-3d559e21d189-page-17.webp)
16EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Figure 1: Total schedule of EDI software development
(Source: created by author)
Figure 1: Total schedule of EDI software development
(Source: created by author)
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/4f79263b-9495-4f77-bea6-91e3a1b5a2d7-page-18.webp)
17EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Figure 2: Gantt chart during the installation of EDI software
(Source: created by author)
3.4 Deviation from the project plan or budget for which action plans are taken
Different reasons are defined for which the project manager has to undertake different
action plan. In order to accomplish the project the project managers are require to make certain
action plan in the project initiation phase and even after the execution of the project. For this
particular project an action plan that has been undertaken is as follows:
Figure 2: Gantt chart during the installation of EDI software
(Source: created by author)
3.4 Deviation from the project plan or budget for which action plans are taken
Different reasons are defined for which the project manager has to undertake different
action plan. In order to accomplish the project the project managers are require to make certain
action plan in the project initiation phase and even after the execution of the project. For this
particular project an action plan that has been undertaken is as follows:
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/6b67fde0-5943-4583-9a2b-37ecea9aafe8-page-19.webp)
18EDI FINAL SOFTWARE IMPLEMENTATION PLAN
Identification of tasks
Analysis and delegate the tasks
Considering standard schemes double checking
On the other hand, there are certain reasons for which during the implementation of the
EDI software in Swaggies the project head to take the action plan. The respective reasons for the
action plans are as follows:
Bring clarity to the vision
The ideas should be turned to the reality
The project team members were failing to meet their responsibilities rather job
roles
The project manager failed to track the contribution of the project members
properly
3.5 Communication made with the stakeholders
After the identification of the reasons for which the project manager has undertaken
certain action plan, the executives have developed an advanced communication plan. It is
expected that with the help of this accurate action plan the stakeholders and the project manager
will be able to understand about the project goal objectives properly. The purpose of
communication and the set of topic those have been discussed in these meetings are as follows:
Current status of the project report
The basic security aspects to be undertaken to keep the EDI system secured from
external attacks
The difference between the estimated cost and the actual expenditure
Identification of tasks
Analysis and delegate the tasks
Considering standard schemes double checking
On the other hand, there are certain reasons for which during the implementation of the
EDI software in Swaggies the project head to take the action plan. The respective reasons for the
action plans are as follows:
Bring clarity to the vision
The ideas should be turned to the reality
The project team members were failing to meet their responsibilities rather job
roles
The project manager failed to track the contribution of the project members
properly
3.5 Communication made with the stakeholders
After the identification of the reasons for which the project manager has undertaken
certain action plan, the executives have developed an advanced communication plan. It is
expected that with the help of this accurate action plan the stakeholders and the project manager
will be able to understand about the project goal objectives properly. The purpose of
communication and the set of topic those have been discussed in these meetings are as follows:
Current status of the project report
The basic security aspects to be undertaken to keep the EDI system secured from
external attacks
The difference between the estimated cost and the actual expenditure
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/928d9f11-31ad-44ac-afa2-f5cc082b7c48-page-20.webp)
19EDI FINAL SOFTWARE IMPLEMENTATION PLAN
The expenditure budget and the actual cost of the project elements
Additional time might be required or successful completion of the project
Stage 4: Project Evaluation and Completion
4.1 The project progress details and project deliverables
The aim of the project is to install and implement Electronic Data Interchange (EDI)
software for Swaggies. The warehouse department of Swaggies does not have proper managerial
aspects and due to this reason the company was continuously failing to meet the requirements. In
order to resolve this issue, they have thought of installing advanced software to improve their
existing customer service. It is expected that with the successful implementation of the project,
the company will be able to gain a team of professionally trained staffs. Swaggies will also get
economic support and with the time management the rate of staff efficiency will also increase
accordingly. In addition to this, Swaggies can gain competitive advantages from the market place
with an enhanced customer service management system.
4.2 Problems those have been identified
The problems those have been identified by the project manager during the existing data
warehouse application are as follows:
Failure of the software system
Negative response from the staffs
The system fails to deliver service to the consumers on time
Budget over allocation
Inappropriate backup process used by the project manager
The expenditure budget and the actual cost of the project elements
Additional time might be required or successful completion of the project
Stage 4: Project Evaluation and Completion
4.1 The project progress details and project deliverables
The aim of the project is to install and implement Electronic Data Interchange (EDI)
software for Swaggies. The warehouse department of Swaggies does not have proper managerial
aspects and due to this reason the company was continuously failing to meet the requirements. In
order to resolve this issue, they have thought of installing advanced software to improve their
existing customer service. It is expected that with the successful implementation of the project,
the company will be able to gain a team of professionally trained staffs. Swaggies will also get
economic support and with the time management the rate of staff efficiency will also increase
accordingly. In addition to this, Swaggies can gain competitive advantages from the market place
with an enhanced customer service management system.
4.2 Problems those have been identified
The problems those have been identified by the project manager during the existing data
warehouse application are as follows:
Failure of the software system
Negative response from the staffs
The system fails to deliver service to the consumers on time
Budget over allocation
Inappropriate backup process used by the project manager
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/fa1f915d-fff4-419b-89df-e60b3fc490dd-page-21.webp)
20EDI FINAL SOFTWARE IMPLEMENTATION PLAN
4.3 Project documentation
This is one of the most vital parts in project management that helps the project manager
to ensure about the project requirements and current status of the project as well. Based on the
requirement of the project it has been found that, 6 months are needed to complete the project
however, after 3 months the status of the project is also defines that total 60% as to be
completed.
4.4 Financial report
Figure 2: Details cost report of Swaggies EDI software
4.3 Project documentation
This is one of the most vital parts in project management that helps the project manager
to ensure about the project requirements and current status of the project as well. Based on the
requirement of the project it has been found that, 6 months are needed to complete the project
however, after 3 months the status of the project is also defines that total 60% as to be
completed.
4.4 Financial report
Figure 2: Details cost report of Swaggies EDI software
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/693544f4-daf7-4105-b1b8-9d3615c3689a-page-22.webp)
21EDI FINAL SOFTWARE IMPLEMENTATION PLAN
(Source: created by author)
4.5 Lesson have been learned
From the detail study of the project it has been learned that only identification of the
resources are not enough rather after that both the human resources and physical resources
should be analyzed. In addition to this, before initiating the project the feasibility study must be
done accordingly so that the project manager get to know about the total expenditure to be
achieved. Apart from this, during the project development phase, appropriate time to time
progress report is also needed to be developed.
4.6 Evaluation of the project
If all the identified steps are maintained accurately then, it can be assumed that the
project manager will be able to meet the requirements accordingly. The identified risks will be
minimized, the productivity of Swaggies will increase and the other features that the company
would be able to get include the following:
Data backup, disaster recovery and application resilience are the features those the
company will be able to achieve
The stock level of the warehouse will enhance to meet the requirements of the
consumers
In addition to this, with secured on time service the level of customer satisfaction
will also increase
(Source: created by author)
4.5 Lesson have been learned
From the detail study of the project it has been learned that only identification of the
resources are not enough rather after that both the human resources and physical resources
should be analyzed. In addition to this, before initiating the project the feasibility study must be
done accordingly so that the project manager get to know about the total expenditure to be
achieved. Apart from this, during the project development phase, appropriate time to time
progress report is also needed to be developed.
4.6 Evaluation of the project
If all the identified steps are maintained accurately then, it can be assumed that the
project manager will be able to meet the requirements accordingly. The identified risks will be
minimized, the productivity of Swaggies will increase and the other features that the company
would be able to get include the following:
Data backup, disaster recovery and application resilience are the features those the
company will be able to achieve
The stock level of the warehouse will enhance to meet the requirements of the
consumers
In addition to this, with secured on time service the level of customer satisfaction
will also increase
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/35003a01-3786-4c53-92e8-22bacd7a1b3c-page-23.webp)
22EDI FINAL SOFTWARE IMPLEMENTATION PLAN
![Document Page](https://desklib.com/media/document/docfile/pages/edi-final-software-implementation/2024/09/05/0c2bd58b-6c89-44e2-8f64-75bb95675bec-page-24.webp)
23EDI FINAL SOFTWARE IMPLEMENTATION PLAN
References
Bresnen, M., 2016. Institutional development, divergence and change in the discipline of project
management. International journal of project management, 34(2), pp.328-338.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Guo, F., Chang-Richards, Y., Wilkinson, S. and Li, T.C., 2014. Effects of project governance
structures on the management of risks in major infrastructure projects: A comparative
analysis. International Journal of Project Management, 32(5), pp.815-826.
Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated
for the 2015 Exam. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Leach, L.P., 2014. Critical chain project management. Artech House.
Lock, M.D., 2014. The essentials of project management. Ashgate Publishing, Ltd.. Lock, M.D.,
2014. The essentials of project management. Ashgate Publishing, Ltd..
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
References
Bresnen, M., 2016. Institutional development, divergence and change in the discipline of project
management. International journal of project management, 34(2), pp.328-338.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Guo, F., Chang-Richards, Y., Wilkinson, S. and Li, T.C., 2014. Effects of project governance
structures on the management of risks in major infrastructure projects: A comparative
analysis. International Journal of Project Management, 32(5), pp.815-826.
Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated
for the 2015 Exam. John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Leach, L.P., 2014. Critical chain project management. Artech House.
Lock, M.D., 2014. The essentials of project management. Ashgate Publishing, Ltd.. Lock, M.D.,
2014. The essentials of project management. Ashgate Publishing, Ltd..
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
1 out of 24
Related Documents
![[object Object]](/_next/image/?url=%2F_next%2Fstatic%2Fmedia%2Flogo.6d15ce61.png&w=640&q=75)
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.