This project management plan focuses on the level crossing removal of Buckley Street, Essendon. The paper covers scope management, schedule and time management, cost/budget management, quality management, human resource management, communication management, risk management, procurement management, and more.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMMENT PLAN Topic- Essendon & Buckley Street level crossing removal. Name of the Student Name of the University Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1 PROJECT MANAGEMMENT PLAN Table of Contents Project management plan.................................................................................................................3 1. Introduction..............................................................................................................................3 2. Scope management..................................................................................................................3 2.1 Work breakdown Structure................................................................................................3 2.2 Change control management.............................................................................................4 3. Schedule and time management..............................................................................................5 3.1 Milestones..........................................................................................................................5 3.2 Project Schedule................................................................................................................5 3.3 Dependencies.....................................................................................................................8 4. Cost/Budget management......................................................................................................11 5. Quality management..............................................................................................................16 6. Human resource management................................................................................................17 7. Communication management................................................................................................19 8. Risk management...................................................................................................................22 9. Procurement management.....................................................................................................27 10. Quality baseline...................................................................................................................27 Bibliography..................................................................................................................................29
2 PROJECT MANAGEMMENT PLAN Project management plan 1.Introduction The paper mainly focuses on the level crossing removal of Buckley Street, Essondon that is considered as one of the key arterials in inner North West of Melbourne that mainly connects Keilor as well as Avondale heights in the west. The boom gates of the Buckley Street are down for about 78 minutes in the morning and as result, the traveller faces congestion as well as disruption while passing. In order to resolve this problem, the Victorian government took an important step and as per it, they wants to remove the level crossing at Buckley Street so that the passengers can easily travel and which further can be able to reduce traffic congestion as well as assists in improving safety. 2. Scope management 2.1 Work breakdown Structure Figure 1: WBS
3 PROJECT MANAGEMMENT PLAN (Source: Created by Author) 2.2 Change control management Change identification PurposeChange analysis Change request approval Change tracking Utilizing technically advanced equipments Itisidentified thatuseof technically advanced equipments helpsin removingthe level crossing at BuckleyStreet quite easily. The construction engineers understandthe change viability. Thechange viabilityinthe project is mainly approved by the project managers Propermaster logbookis maintainedin ordertoensure thatthe construction engineersuse proper equipment. Utilizing appropriate qualityof materials It is very much necessary to use proper quality of materialsin orderto constructthe pathways. Thequality analyst understandsthe viabilityof proper quality of materials in the project. The request for maintainproper quality materials ismainly approved by the project manager Appropriate logbookis generally maintainedin ordertomake sure those proper qualitymaterials isusedinthe project.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4 PROJECT MANAGEMMENT PLAN 3. Schedule and time management 3.1 Milestones Task NameStart Milestone 1: Completion of project initiation phaseMon 23-05-16 Milestone 2: Completion of planning phaseThu 15-12-16 Milestone 3 : Completion of procurement phaseWed 06-12-17 Milestone 4: Completion of Construction phaseThu 08-08-19 Milestone 4: Completion of project closure phaseWed 20-11-19 3.2 Project Schedule Task NameDurationStartFinish% Complete Essendon & Buckley Street level crossing removal 985 daysThu 11-02-16Wed 20-11-1957% Initiation phase of the project 73 daysThu 11-02-16Mon 23-05-16100% Identifying objectives of the project 15 daysThu 11-02-16Wed 02-03-16100% Undertaking feasibility study 20 daysThu 03-03-16Wed 30-03-16100% Establishing project16 daysThu 31-03-16Thu 21-04-16100%
5 PROJECT MANAGEMMENT PLAN charter Appointing team members of the project 22 daysFri 22-04-16Mon 23-05-16100% Milestone 1: Completion of project initiation phase 0 daysMon 23-05-16Mon 23-05-16100% Planning phase of the project 148 daysTue 24-05-16Thu 15-12-16100% Site investigations22 daysTue 24-05-16Wed 22-06-16100% Solution announced20 daysThu 23-06-16Wed 20-07-16100% Community information sessions 25 daysThu 21-07-16Wed 24-08-16100% Trader consultation26 daysThu 25-08-16Thu 29-09-16100% Assessment of design options 26 daysFri 30-09-16Fri 04-11-16100% Lowering Buckley street under rail line 29 daysMon 07-11-16Thu 15-12-16100% Milestone 2: Completion of planning phase 0 daysThu 15-12-16Thu 15-12-16100% Procurement phase254 daysFri 16-12-16Wed 06-12-17100%
6 PROJECT MANAGEMMENT PLAN Community input on design elements 32 daysFri 16-12-16Mon 30-01-17100% North west alliance project partner announced 39 daysTue 31-01-17Fri 24-03-17100% Construction partner announced 44 daysMon 27-03-17Thu 25-05-17100% Community consultation47 daysFri 26-05-17Mon 31-07-17100% Refinement of design including community inputs 50 daysTue 01-08-17Mon 09-10-17100% Finalizing design42 daysTue 10-10-17Wed 06-12-17100% Milestone 3 : Completion of procurement phase 0 daysWed 06-12-17Wed 06-12-17100% Construction phase436 daysThu 07-12-17Thu 08-08-1919% On-going community consultation 32 daysThu 07-12-17Fri 19-01-18100% Construction commences 34 daysMon 22-01-18Thu 08-03-18100% Preparatory work commenced 43 daysFri 09-03-18Tue 08-05-1842% Finalized design released to the community 45 daysWed 09-05-18Tue 10-07-180% Contract awarded for52 daysWed 11-07-18Thu 20-09-180%
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7 PROJECT MANAGEMMENT PLAN Buckley street level crossing removal project Early works commence57 daysFri 21-09-18Mon 10-12-180% Major works commence48 daysTue 11-12-18Thu 14-02-190% Boom gates removed60 daysFri 15-02-19Thu 09-05-190% Finalizing landscapes65 daysFri 10-05-19Thu 08-08-190% Milestone 4: Completion of Construction phase 0 daysThu 08-08-19Thu 08-08-190% Closure phase74 daysFri 09-08-19Wed 20-11-190% Post-project review20 daysFri 09-08-19Thu 05-09-190% Stakeholder-sign off30 daysFri 06-09-19Thu 17-10-190% Documentation24 daysFri 18-10-19Wed 20-11-190% Milestone 4: Completion of project closure phase 0 daysWed 20-11-19Wed 20-11-190% 3.3 Dependencies Task NameDurationPredecessors Essendon & Buckley Street level crossing removal 985 days Initiation phase of the project73 days
8 PROJECT MANAGEMMENT PLAN Identifying objectives of the project15 days Undertaking feasibility study20 days2 Establishing project charter16 days3 Appointing team members of the project 22 days4 Milestone 1: Completion of project initiation phase 0 days5 Planning phase of the project148 days Site investigations22 days6 Solution announced20 days8 Community information sessions25 days9 Trader consultation26 days10 Assessment of design options26 days11 Lowering Buckley street under rail line 29 days12 Milestone 2: Completion of planning phase 0 days13 Procurement phase254 days Community input on design elements32 days14 North west alliance project partner announced 39 days16 Construction partner announced44 days17
9 PROJECT MANAGEMMENT PLAN Community consultation47 days18 Refinement of design including community inputs 50 days19 Finalizing design42 days20 Milestone 3 : Completion of procurement phase 0 days21 Construction phase436 days On-going community consultation32 days22 Construction commences34 days24 Preparatory work commenced43 days25 Finalized design released to the community 45 days26 Contract awarded for Buckley street level crossing removal project 52 days27 Early works commence57 days28 Major works commence48 days29 Boom gates removed60 days30 Finalizing landscapes65 days31 Milestone 4: Completion of Construction phase 0 days32 Closure phase74 days Post-project review20 days33
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10 PROJECT MANAGEMMENT PLAN Stakeholder-sign off30 days35 Documentation24 days36 Milestone 4: Completion of project closure phase 0 days37 4. Cost/Budget management Task NameDurationResource NamesCost Essendon & Buckley Street level crossing removal 985 days$114,664,480.00 Initiation phase of the project 73 days$254,480.00 Identifying objectives of the project 15 daysProject manager$34,800.00 Undertaking feasibility study 20 daysProject manager$46,400.00 Establishing project charter16 days Project manager, Project planner $72,960.00 Appointing team members of the project 22 days Project manager, Project planner $100,320.00 Milestone 1: Completion of project initiation phase 0 days$0.00
11 PROJECT MANAGEMMENT PLAN Planning phase of the project 148 days$7,765,120.00 Site investigations22 days Supervisor, Construction manager $89,760.00 Solution announced20 days Construction technician, Contractor, Equipment cost[1] $7,081,600.00 Community information sessions 25 days Construction manager, Contractor $102,000.00 Trader consultation26 days Construction manager, Contractor $106,080.00 Assessment of design options 26 days Construction manager, Contractor, Sub- contractor $156,000.00 Lowering Buckley street under rail line 29 days Architect, Construction manager, Construction technician, Sub- contractor $229,680.00 Milestone 2: Completion of planning phase 0 days$0.00 Procurement phase254 days$34,070,960.00 Community input on design elements 32 daysCost for removing level crossing[1], Supervisor, $16,194,560.00
12 PROJECT MANAGEMMENT PLAN Architect, Construction technician, Equipment cost[1] North west alliance project partner announced 39 days Supervisor, Architect, Construction manager, Contractor, Procurement manager $396,240.00 Construction partner announced 44 days Supervisor, Architect, Construction technician, Contractor, Procurement manager $447,040.00 Community consultation47 days Cost for removing level crossing[1],Architect, Construction technician, Contractor $9,285,760.00 Refinement of design including community inputs 50 days Architect, Construction technician, Contractor, Financial manager, Procurement manager $492,000.00 Finalizing design42 days Supervisor, Architect, Equipment cost[1],Procurement manager $7,255,360.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13 PROJECT MANAGEMMENT PLAN Milestone 3 : Completion of procurement phase 0 days$0.00 Construction phase436 days$72,236,480.00 On-going community consultation 32 days Supervisor, Architect, Contractor, Procurement manager, Sub-contractor $322,560.00 Construction commences34 days Cost for removing level crossing[1], Project manager, Architect, Construction technician, Procurement manager $9,282,880.00 Preparatory work commenced 43 days Cost for removing level crossing[1], Supervisor, Architect, Construction technician, Contractor, Equipment cost[1],Sub- contractor $16,433,440.00 Finalized design released to the community 45 days Supervisor, Architect, Construction manager, Construction technician, Procurement manager $453,600.00 Contract awarded for Buckley street level crossing 52 daysCost for removing level crossing[1], Project $9,536,640.00
14 PROJECT MANAGEMMENT PLAN removal project manager, Architect, Construction technician, Contractor, Sub- contractor Early works commence57 days Cost for removing level crossing[1],Architect, Construction manager, Construction technician, Equipment cost[1] $16,342,000.00 Major works commence48 days Cost for removing level crossing[1], Project manager, Supervisor, Architect, Construction manager, Construction technician, Sub- contractor $9,591,360.00 Boom gates removed60 days Cost for removing level crossing[1], Project manager, Architect, Construction manager, Construction technician, Contractor $9,624,000.00 Finalizing landscapes65 daysArchitect ,Construction$650,000.00
15 PROJECT MANAGEMMENT PLAN manager, Construction technician Contractor, Sub-contractor Milestone 4: Completion of Construction phase 0 days$0.00 Closure phase74 days$337,440.00 Post-project review20 days Project manager, Project planner $91,200.00 Stakeholder-sign off30 days Project manager, Project planner $136,800.00 Documentation24 days Project manager, Project planner $109,440.00 Milestone 4: Completion of project closure phase 0 days$0.00 5. Quality management Identification of factors PurposeMeasurement ofproject quality Analyzing project quality Quality control Training to the project stakeholders Proper training totheproject stakeholders would be helpful Proper training facilityisnot providedtothe workersofthe Dueto unavailability of trainingitis reflects that the Proper training facility not only helps in managing the
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16 PROJECT MANAGEMMENT PLAN incompleting theproject successfullyon timeby managingthe challengesand issuesproperly on time. project team.projectteam membersfaces littlebitof challengesin completingthe projectwork successfully. project work but will also help in maintaining the quality of the project. Useofproper qualityoff materials Properuseof quality materials wouldbequite advantageous for the project. Thematerials that are supplied by the suppliers forthe constructionof thepathwayis of poor quality. Thematerials that are used in the project must bechecked beforeusingit forconstruction purpose. Proper quality ofmaterials must be used in orderto enhancethe qualityofthe project. 6. Human resource management Role Project Responsibility Skills RequiredNumber of Staff Required Duration Required Project Team4 years
17 PROJECT MANAGEMMENT PLAN Project managerTheproject manager is the personwhois mainly responsibleof initiating, planning, managingas wellas executingthe project successfully. Project management3 Financial managerThefinancial manager is the personwho mainly reviews thefinancial requirementof the project Construction44 years ContractorThe contractor istheperson whomainly involvesin Construction14 years
18 PROJECT MANAGEMMENT PLAN constructing thepathways afterthe removalof level crossing Site supervisorSite supervisor istheperson whomainly helpsin providing proper guidance to the various organizational staffs. Construction104 years 7. Communication management Communicati on Type ObjectiveMediumFrequenc y AudienceOwnerDeliverab le Project status report The meetingis mainly Audio and video conferencin WeeklyProject manager Project stakeholde rs Meeting minutes
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
19 PROJECT MANAGEMMENT PLAN arranged in order to gather informatio n about the project statusin orderto makesure thatthe projectis onright track g, Project team meeting The project meetings is mainly arranged in orderto know aboutthe various challenges Face to faceWhenever required Project manager Project team Agenda
20 PROJECT MANAGEMMENT PLAN thatthe workersof theproject arefacing while working withthe project. Kickoff meetings Itis arranged before initiation ofthe projectin order to get informatio n about the schedule, budgetas wellas resources required in orderto Faceto face OnceStakeholde rsofthe project Project manager Meeting minutes as wellas agenda
21 PROJECT MANAGEMMENT PLAN execute the project successfull y. Monthly project meetings Monthly meetings is necessary inthe projectin orderto makesure thatthe budgetof theproject are correctly utilized Faceto face conversatio n MonthlyProject manager Finance manager Budget report 8. Risk management RiskTypeof risk Risk statement ImpactProbabilityRisk exposure Risk mitigation Budget shortfall Negative risk Ifthe project MajorProbableMediumItis necessary for
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
22 PROJECT MANAGEMMENT PLAN managers doesnot estimate the budgetof theproject then during theproject progress the project managers canface budget shortfall, whichcan create numberof financial as wellas budget related issues withinthe project. theproject managersto undertake market analysis properlyin orderto knowthe currentcost ofproject resources that are used inthe project.
23 PROJECT MANAGEMMENT PLAN Extending project schedule Positive risk Itis identified that sometimes theproject managers generally extendsthe schedule of theproject inorderto provide quality based outcome withinthe project. ModerateProbableLowThe changes thatre needed withinthe projectmust bedone appropriately inorderto bring positive outcome withinthe project. Useof improper quality materials Negative risk Itis necessary touse proper quality materials in ModerateLikelyMediumProper qualityof materials must be used in the project sothatthe
24 PROJECT MANAGEMMENT PLAN orderto construct the pathways afterthe removalof thelevel crossing. projectcan be completed successfully without facingany typeof quality related challenges. Improper managemen t Negative risk Ifthe project managers are not able tomanage theproject successfully thenthey generally faces issues in executing theproject MajorVery likelyHighItis necessaryto hire experienced project managers who will be ableto managethe project successfully sothatthe entire project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
26 PROJECT MANAGEMMENT PLAN Firmfixed price Unrealistic scheduleThe schedule must be created with the help of experiencedproject managers. Acceptable Firmfixed price Improperframework forthelevelcrossing removal Properframework must be created for the level crossing removal Acceptable Firmfixed price Conflictrelatedon contract Conflictmustbe resolvedbyarranging meetings Acceptable 10. Quality baseline MetricsStandardFrequencyReport Successful completion of project on time The project will be successfully completed by 2019. OnceQualitymanagement report Successfulremoval of level crossing Removaloflevel crossingwillbe completedbyearly 2019. YearlyYearlyquality management report
27 PROJECT MANAGEMMENT PLAN Bibliography Buckley Street, Essendon. (2018).Your Level Crossing. Retrieved 3 April 2018, from https://your.levelcrossings.vic.gov.au/buckley-street-essendon De Carvalho, M. M., Patah, L. A., & de Souza Bido, D. (2015). Project management and its effects on project success: Cross-country and cross-industry comparisons.International Journal of Project Management,33(7), 1509-1522. Fitzpatrick, B. J. (2016).Determining the Optimal Work Breakdown Structure for Defense Acquisition Contracts. Air Force Institute of Technology WPAFB United States. Heldman, K. (2018).PMP: project management professional exam study guide. John Wiley & Sons. Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. Joslin, R., & Müller, R. (2015). Relationships between a project management methodology and project success in different project governance contexts.International Journal of Project Management,33(6), 1377-1392. Kerzner, H. (2017).Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons. Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success.International journal of project management,32(2), 202-217.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
28 PROJECT MANAGEMMENT PLAN Połoński, M. (2015). Application of the work breakdown structure in determining cost buffers in construction schedules.Archives of Civil Engineering,61(1), 147-161. Sequeira, S., & Lopes, E. (2015). Simple Method Proposal for Cost Estimation from Work Breakdown Structure.Procedia Computer Science,64, 537-544. Sharon, A., & Dori, D. (2015). A Project–product model–based approach to planning work breakdown structures of complex system projects.IEEE Systems Journal,9(2), 366-376. Snyder, C. S. (2014). A guide to the project management body of knowledge: PMBOK (®) guide.Project Management Institute: Newtown Square, PA, USA. Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world.International Journal of Project Management,33(2), 278-290 Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual framework for project governance.International Journal of Project Management,32(8), 1382-1394.