Running head:PROJECT REPORT Project Report Great Northern Highway Upgrades (Upper Swan, Western Australia) Name of the Student: Student ID: Name of the University: Author’s notes:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT REPORT Executive Summary The following assignment had covered the information about the project of Great Northern Highway Upgrades (Upper Swan, Western Australia). The management had been implied with theconsiderationoftheimproveddevelopmentmodel.Thecompilationoftheproject construction would be implied with the help of the construction project management. The management has been implied with the development of the consideration and implication of the successful management process.
2PROJECT REPORT Table of Contents Introduction......................................................................................................................................3 Risk Assessment..............................................................................................................................3 Estimates of cost..............................................................................................................................4 Schedule...........................................................................................................................................5 Project Background.........................................................................................................................9 Conclusion.......................................................................................................................................9 Bibliography..................................................................................................................................10
3PROJECT REPORT Introduction The project management in construction holds an integral role for the development of the successful compilation and development of the factors for taking care of the completion of the project. The project management had been playing a considerable role for the development of the project activities. The following assignment has been developed for the consideration of the risk assessment, cost estimation, project schedule, and evaluation of the project schedule for the project of Great Northern Highway Upgrades (Upper Swan, Western Australia). Risk Assessment Risk Assessment deals with the implication of the risk identification and the evaluation for developing the final risk mitigation planning. The construction projects have many flaws and risk factors that can be evaluated for the modificationof the project activities. The following table can be used for the risk analysis, Risk FactorRisk TypeProbabilityImpactRisk Mitigation Disruptionin transportation OperationalAlmost CertainModerateMitigate Issuesin Resource Accumulation FinancialPossibleMajorShare Restrictionin Operation Development ProcurementLikelyMajorTransfer LandholdersHuman IssuesUnlikelyMinorExploit
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT REPORT disagreement Estimates of cost The project has been estimated to cost up to 41million dollars considering the work required to be done in the project including the reconstruction and Widening of Highway, construction of high strength pavements including HCTCRB, installation of stormwater pipe network, installation of street lighting and traffic signals at West Swan Road, construction of medians, traffic islands, dual use paths and cycle paths, and construction of two special spill capture units at either end of Swan River Bridge. The cost estimation for the project would be done using the bottom up estimation for the resources used in the construction. The following table would show the project estimates for the cost, Resource NameTypeWorkStandard RateCost DocumenterWork304$5,600$1,702,400 PlannerWork160$6,400$1,024,000 Risk AnalystWork80$8,000$640,000 Project ManagerWork312$6,000$1,872,000 ContractorWork800$5,400$4,320,000 VendorWork96$5,000$480,000 WorkersWork2,480$4,400$10,912,000 Civil EngineerWork840$5,600$4,704,000 ClientWork0$0$0 DocumentsMaterial3$1,000$3,000 MachineriesMaterial4$1,140,000$4,560,000 Safety ToolsMaterial1$1,635,000$1,635,000
5PROJECT REPORT Construction MaterialsMaterial1$1,758,000$1,758,000 Road MaterialsMaterial1$1,740,000$1,740,000 Intersection MaterialsMaterial1$1,850,000$1,850,000 Underpass MaterialsMaterial1$2,175,000$2,175,000 Checking ToolsMaterial1$1,624,600$1,624,600 Total Budget$41,000,000 Schedule The project has been running for 3 years of time due to its vast work requirements like reconstruction and Widening of Highway, construction of high strength pavements including HCTCRB, installation of stormwater pipe network, installation of street lighting and traffic signals at West Swan Road, construction of medians, traffic islands, dual use paths and cycle paths, and construction of two special spill capture units at either end of Swan River Bridge. The project has followed the traditional waterfall method and the following tables and diagrams would be helpful for identifying the project schedule and critical path of the project, WBSTask NameDurationStartFinish 0Great Northern Highway Upgrades (Upper Swan, Western Australia) 749 days Mon 1/28/08 Thu 12/9/10 1Initiation Phase41 daysMon 1/28/08 Mon 3/24/08 1.1Resource Identification15 daysMon 1/28/08Fri 2/15/08 1.2Charter Documentation10 daysMon 2/18/08Fri 2/29/08 1.3Tender Development12 daysMon 3/3/08Tue 3/18/08
6PROJECT REPORT 1.4Submission of Tender4 daysWed 3/19/08 Mon 3/24/08 1.5Initiation Phase Completed0 daysMon 3/24/08 Mon 3/24/08 2Plan Phase40 daysTue 3/25/08 Mon 5/19/08 2.1Activities are sorted8 daysTue 3/25/08Thu 4/3/08 2.2Scheduling the activities12 daysFri 4/4/08Mon 4/21/08 2.3Risk Management Plan10 daysTue 4/22/08Mon 5/5/08 2.4Scope Management Plan10 daysTue 5/6/08Mon 5/19/08 2.5Plan Phase Completed0 daysMon 5/19/08 Mon 5/19/08 3Execution Phase627 days Tue 5/20/08 Wed 10/13/10 3.1Site acquisition5 daysTue 5/20/08 Mon 5/26/08 3.2Site clearing20 daysTue 5/27/08 Mon 6/23/08 3.3Safety Tools were installed12 daysTue 6/24/08Wed 7/9/08 3.4Reconstruction and Widening of Highway120 daysThu 7/10/08 Wed 12/24/08 3.5Construction of high strength pavements including HCTCRB100 daysThu 12/25/08 Wed 5/13/09 3.6Installation of stormwater pipe network90 daysThu 5/14/09 Wed 9/16/09 3.7Installation of street lighting and traffic signals at West Swan Road70 daysThu 9/17/09 Wed 12/23/09 3.8Construction of medians, traffic islands, dual use paths and cycle paths110 daysThu 12/24/09 Wed 5/26/10
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT REPORT 3.9Construction of two special Spill Capture Units at either end of Swan River Bridge80 daysThu 5/27/10 Wed 9/15/10 3.10Review of Construction20 daysThu 9/16/10 Wed 10/13/10 3.11Execution Phase Completed0 daysWed 10/13/10 Wed 10/13/10 4Monitor Phase23 daysThu 10/14/10 Mon 11/15/10 4.1Review of safety consideration15 daysThu 10/14/10 Wed 11/3/10 4.2Checking the constructed infrastructure5 daysThu 11/4/10 Wed 11/10/10 4.3Evaluation in terms of WHO safety guidelines3 daysThu 11/11/10 Mon 11/15/10 4.4Monitor Phase Completed0 daysMon 11/15/10 Mon 11/15/10 5Close Phase18 daysTue 11/16/10 Thu 12/9/10 5.1Final Documentation10 daysTue 11/16/10 Mon 11/29/10 5.2Review of documents5 daysTue 11/30/10 Mon 12/6/10 5.3Submission of documents2 daysTue 12/7/10 Wed 12/8/10 5.4Sign off1 dayThu 12/9/10 Thu 12/9/10 5.5Close Phase Completed0 daysThu 12/9/10 Thu 12/9/10
8PROJECT REPORT IDTask Mode WBSTask NameDuration 00Great Northern Highway Upgrades (Upper Swan, Western Australia) 749 days 11Initiation Phase41 days 21.1Resource Identification15 days 31.2Charter Documentation10 days 41.3Tender Development12 days 51.4Submission of Tender4 days 61.5Initiation Phase Completed0 days 72Plan Phase40 days 82.1Activities are sorted8 days 92.2Scheduling the activities12 days 102.3Risk Management Plan10 days 112.4Scope Management Plan10 days 122.5Plan Phase Completed0 days 133Execution Phase627 days 143.1Site acquisition5 days 153.2Site clearing20 days 163.3Safety Tools were installed 12 days 173.4Reconstruction and Widening of Highway 120 days 183.5Construction of high strength pavements including HCTCRB 100 days 193.6Installation of stormwater pipe network 90 days 203.7Installation of street lighting and traffi c signals at West Swan Road 70 days 213.8Construction of medians, traffi c islands, dual use paths and cycle paths 110 days 223.9Construction of two special Spill Capture Units at either end of Swan River Bridge 80 days 233.10Review of Construction20 days 243.11Execution Phase Completed0 days 254Monitor Phase23 days 264.1Review of safety consideration 15 days 274.2Checking the constructed infrastructure 5 days 284.3Evaluation in terms of WHO safety guidelines 3 days 294.4Monitor Phase Completed0 days 305Close Phase18 days 315.1Final Documentation10 days 325.2Review of documents5 days 335.3Submission of documents2 days 345.4Sign off1 day 355.5Close Phase Completed0 days Project Manager Documenter,Documents[1] Documenter,Documents[1] Documenter 3/24 Planner Planner Risk Analyst Project Manager 5/19 Contractor Contractor,Machineries[1] Vendor,Civil Engineer,Safety Tools[1] Workers,Construction Materials[1],Machineries[1] Workers,Machineries[1],Road Materials[1],Intersection Materials[1] Workers,Machineries[1],Underpass Materials[1] Contractor,Civil Engineer 10/13 Civil Engineer Civil Engineer,Project Manager,Contractor,Check Civil Engineer,Project Manager 11/15 Documenter,Documents[1] Project Manager Documenter Project Manager 12/9 12/162/245/47/139/2111/302/84/196/289/611/151/244/46/138/2210/311/93/205/298/7 September 21February 11July 1November 21April 11September 1January 21June 11November 1March 21 Figure 1: Project Gantt chart 384 52 912141718 20 2122 6101115161923 26 24 27 2829 3132 3334 35 Figure 2: Project Network Diagram
9PROJECT REPORT Project Background The project is developed for implementing the plan for executing the management of the successful and effective management of the construction management for the project of Great Northern Highway Upgrades. The implication management had been successive for taking care of the factors and implication would be implied with the consideration of the consideration for the management of the successful project completion. The project would include the construction works like reconstruction and Widening of Highway, construction of high strength pavements including HCTCRB, installation of stormwater pipe network, installation of street lighting and traffic signals at West Swan Road, construction of medians, traffic islands, dual use paths and cycle paths, and construction of two special spill capture units at either end of Swan River Bridge. Conclusion Itcanbeconcludedfromtheassignmentthattheimplicationofthesuccessful management of the implied processes. The overall budget for the project had been listed and estimated with the help of the bottom up estimation and the complete budget estimate has come up to be $ 41 million. The project had commenced on Monday 1/28/08 and ended on Thursday 12/9/10 stretching for 749 working days. The completion of the project had been helpful for developing the widened highway and the west Swan Road.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT REPORT Bibliography Burtonshaw-Gunn, S.A., 2017.Risk and financial management in construction. Routledge. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Kuchta, D. and Ptaszyńska, E., 2017, July. Fuzzy based risk register for construction project risk assessment. InAIP Conference Proceedings(Vol. 1863, No. 1, p. 230006). AIP Publishing. Lock, D., 2016.Project management in construction. Routledge. Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming psychologicalsafetyclimateinconstructionprojectmanagement.Internationaljournalof project management,33(1), pp.223-235. Walker, D.H., 2016. Reflecting on 10 years of focus on innovation, organisational learning and knowledge management literature in a construction project management context.Construction Innovation,16(2), pp.114-126.