Running head: PROJECT REPORT
Project Report
Great Northern Highway Upgrades (Upper Swan, Western Australia)
Name of the Student:
Student ID:
Name of the University:
Author’s notes:
Project Report
Great Northern Highway Upgrades (Upper Swan, Western Australia)
Name of the Student:
Student ID:
Name of the University:
Author’s notes:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT REPORT
Executive Summary
The following assignment had covered the information about the project of Great Northern
Highway Upgrades (Upper Swan, Western Australia). The management had been implied with
the consideration of the improved development model. The compilation of the project
construction would be implied with the help of the construction project management. The
management has been implied with the development of the consideration and implication of the
successful management process.
Executive Summary
The following assignment had covered the information about the project of Great Northern
Highway Upgrades (Upper Swan, Western Australia). The management had been implied with
the consideration of the improved development model. The compilation of the project
construction would be implied with the help of the construction project management. The
management has been implied with the development of the consideration and implication of the
successful management process.
2PROJECT REPORT
Table of Contents
Introduction......................................................................................................................................3
Risk Assessment..............................................................................................................................3
Estimates of cost..............................................................................................................................4
Schedule...........................................................................................................................................5
Project Background.........................................................................................................................9
Conclusion.......................................................................................................................................9
Bibliography..................................................................................................................................10
Table of Contents
Introduction......................................................................................................................................3
Risk Assessment..............................................................................................................................3
Estimates of cost..............................................................................................................................4
Schedule...........................................................................................................................................5
Project Background.........................................................................................................................9
Conclusion.......................................................................................................................................9
Bibliography..................................................................................................................................10
3PROJECT REPORT
Introduction
The project management in construction holds an integral role for the development of the
successful compilation and development of the factors for taking care of the completion of the
project. The project management had been playing a considerable role for the development of the
project activities. The following assignment has been developed for the consideration of the risk
assessment, cost estimation, project schedule, and evaluation of the project schedule for the
project of Great Northern Highway Upgrades (Upper Swan, Western Australia).
Risk Assessment
Risk Assessment deals with the implication of the risk identification and the evaluation
for developing the final risk mitigation planning. The construction projects have many flaws and
risk factors that can be evaluated for the modification of the project activities. The following
table can be used for the risk analysis,
Risk Factor Risk Type Probability Impact Risk Mitigation
Disruption in
transportation
Operational Almost Certain Moderate Mitigate
Issues in
Resource
Accumulation
Financial Possible Major Share
Restriction in
Operation
Development
Procurement Likely Major Transfer
Landholders Human Issues Unlikely Minor Exploit
Introduction
The project management in construction holds an integral role for the development of the
successful compilation and development of the factors for taking care of the completion of the
project. The project management had been playing a considerable role for the development of the
project activities. The following assignment has been developed for the consideration of the risk
assessment, cost estimation, project schedule, and evaluation of the project schedule for the
project of Great Northern Highway Upgrades (Upper Swan, Western Australia).
Risk Assessment
Risk Assessment deals with the implication of the risk identification and the evaluation
for developing the final risk mitigation planning. The construction projects have many flaws and
risk factors that can be evaluated for the modification of the project activities. The following
table can be used for the risk analysis,
Risk Factor Risk Type Probability Impact Risk Mitigation
Disruption in
transportation
Operational Almost Certain Moderate Mitigate
Issues in
Resource
Accumulation
Financial Possible Major Share
Restriction in
Operation
Development
Procurement Likely Major Transfer
Landholders Human Issues Unlikely Minor Exploit
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT REPORT
disagreement
Estimates of cost
The project has been estimated to cost up to 41million dollars considering the work
required to be done in the project including the reconstruction and Widening of Highway,
construction of high strength pavements including HCTCRB, installation of stormwater pipe
network, installation of street lighting and traffic signals at West Swan Road, construction of
medians, traffic islands, dual use paths and cycle paths, and construction of two special spill
capture units at either end of Swan River Bridge. The cost estimation for the project would be
done using the bottom up estimation for the resources used in the construction. The following
table would show the project estimates for the cost,
Resource Name Type Work Standard Rate Cost
Documenter Work 304 $5,600 $1,702,400
Planner Work 160 $6,400 $1,024,000
Risk Analyst Work 80 $8,000 $640,000
Project Manager Work 312 $6,000 $1,872,000
Contractor Work 800 $5,400 $4,320,000
Vendor Work 96 $5,000 $480,000
Workers Work 2,480 $4,400 $10,912,000
Civil Engineer Work 840 $5,600 $4,704,000
Client Work 0 $0 $0
Documents Material 3 $1,000 $3,000
Machineries Material 4 $1,140,000 $4,560,000
Safety Tools Material 1 $1,635,000 $1,635,000
disagreement
Estimates of cost
The project has been estimated to cost up to 41million dollars considering the work
required to be done in the project including the reconstruction and Widening of Highway,
construction of high strength pavements including HCTCRB, installation of stormwater pipe
network, installation of street lighting and traffic signals at West Swan Road, construction of
medians, traffic islands, dual use paths and cycle paths, and construction of two special spill
capture units at either end of Swan River Bridge. The cost estimation for the project would be
done using the bottom up estimation for the resources used in the construction. The following
table would show the project estimates for the cost,
Resource Name Type Work Standard Rate Cost
Documenter Work 304 $5,600 $1,702,400
Planner Work 160 $6,400 $1,024,000
Risk Analyst Work 80 $8,000 $640,000
Project Manager Work 312 $6,000 $1,872,000
Contractor Work 800 $5,400 $4,320,000
Vendor Work 96 $5,000 $480,000
Workers Work 2,480 $4,400 $10,912,000
Civil Engineer Work 840 $5,600 $4,704,000
Client Work 0 $0 $0
Documents Material 3 $1,000 $3,000
Machineries Material 4 $1,140,000 $4,560,000
Safety Tools Material 1 $1,635,000 $1,635,000
5PROJECT REPORT
Construction
Materials Material 1 $1,758,000 $1,758,000
Road Materials Material 1 $1,740,000 $1,740,000
Intersection
Materials Material 1 $1,850,000 $1,850,000
Underpass Materials Material 1 $2,175,000 $2,175,000
Checking Tools Material 1 $1,624,600 $1,624,600
Total Budget $41,000,000
Schedule
The project has been running for 3 years of time due to its vast work requirements like
reconstruction and Widening of Highway, construction of high strength pavements including
HCTCRB, installation of stormwater pipe network, installation of street lighting and traffic
signals at West Swan Road, construction of medians, traffic islands, dual use paths and cycle
paths, and construction of two special spill capture units at either end of Swan River Bridge. The
project has followed the traditional waterfall method and the following tables and diagrams
would be helpful for identifying the project schedule and critical path of the project,
WBS Task Name Duration Start Finish
0 Great Northern Highway Upgrades (Upper Swan,
Western Australia)
749
days
Mon
1/28/08
Thu
12/9/10
1 Initiation Phase 41 days Mon
1/28/08
Mon
3/24/08
1.1 Resource Identification 15 days Mon
1/28/08 Fri 2/15/08
1.2 Charter Documentation 10 days Mon
2/18/08 Fri 2/29/08
1.3 Tender Development 12 days Mon 3/3/08 Tue 3/18/08
Construction
Materials Material 1 $1,758,000 $1,758,000
Road Materials Material 1 $1,740,000 $1,740,000
Intersection
Materials Material 1 $1,850,000 $1,850,000
Underpass Materials Material 1 $2,175,000 $2,175,000
Checking Tools Material 1 $1,624,600 $1,624,600
Total Budget $41,000,000
Schedule
The project has been running for 3 years of time due to its vast work requirements like
reconstruction and Widening of Highway, construction of high strength pavements including
HCTCRB, installation of stormwater pipe network, installation of street lighting and traffic
signals at West Swan Road, construction of medians, traffic islands, dual use paths and cycle
paths, and construction of two special spill capture units at either end of Swan River Bridge. The
project has followed the traditional waterfall method and the following tables and diagrams
would be helpful for identifying the project schedule and critical path of the project,
WBS Task Name Duration Start Finish
0 Great Northern Highway Upgrades (Upper Swan,
Western Australia)
749
days
Mon
1/28/08
Thu
12/9/10
1 Initiation Phase 41 days Mon
1/28/08
Mon
3/24/08
1.1 Resource Identification 15 days Mon
1/28/08 Fri 2/15/08
1.2 Charter Documentation 10 days Mon
2/18/08 Fri 2/29/08
1.3 Tender Development 12 days Mon 3/3/08 Tue 3/18/08
6PROJECT REPORT
1.4 Submission of Tender 4 days Wed
3/19/08
Mon
3/24/08
1.5 Initiation Phase Completed 0 days Mon
3/24/08
Mon
3/24/08
2 Plan Phase 40 days Tue
3/25/08
Mon
5/19/08
2.1 Activities are sorted 8 days Tue
3/25/08 Thu 4/3/08
2.2 Scheduling the activities 12 days Fri 4/4/08 Mon
4/21/08
2.3 Risk Management Plan 10 days Tue
4/22/08 Mon 5/5/08
2.4 Scope Management Plan 10 days Tue 5/6/08 Mon
5/19/08
2.5 Plan Phase Completed 0 days Mon
5/19/08
Mon
5/19/08
3 Execution Phase 627
days
Tue
5/20/08
Wed
10/13/10
3.1 Site acquisition 5 days Tue
5/20/08
Mon
5/26/08
3.2 Site clearing 20 days Tue
5/27/08
Mon
6/23/08
3.3 Safety Tools were installed 12 days Tue
6/24/08 Wed 7/9/08
3.4 Reconstruction and Widening of Highway 120 days Thu
7/10/08
Wed
12/24/08
3.5 Construction of high strength pavements including
HCTCRB 100 days Thu
12/25/08
Wed
5/13/09
3.6 Installation of stormwater pipe network 90 days Thu
5/14/09
Wed
9/16/09
3.7 Installation of street lighting and traffic signals at
West Swan Road 70 days Thu
9/17/09
Wed
12/23/09
3.8 Construction of medians, traffic islands, dual use
paths and cycle paths 110 days Thu
12/24/09
Wed
5/26/10
1.4 Submission of Tender 4 days Wed
3/19/08
Mon
3/24/08
1.5 Initiation Phase Completed 0 days Mon
3/24/08
Mon
3/24/08
2 Plan Phase 40 days Tue
3/25/08
Mon
5/19/08
2.1 Activities are sorted 8 days Tue
3/25/08 Thu 4/3/08
2.2 Scheduling the activities 12 days Fri 4/4/08 Mon
4/21/08
2.3 Risk Management Plan 10 days Tue
4/22/08 Mon 5/5/08
2.4 Scope Management Plan 10 days Tue 5/6/08 Mon
5/19/08
2.5 Plan Phase Completed 0 days Mon
5/19/08
Mon
5/19/08
3 Execution Phase 627
days
Tue
5/20/08
Wed
10/13/10
3.1 Site acquisition 5 days Tue
5/20/08
Mon
5/26/08
3.2 Site clearing 20 days Tue
5/27/08
Mon
6/23/08
3.3 Safety Tools were installed 12 days Tue
6/24/08 Wed 7/9/08
3.4 Reconstruction and Widening of Highway 120 days Thu
7/10/08
Wed
12/24/08
3.5 Construction of high strength pavements including
HCTCRB 100 days Thu
12/25/08
Wed
5/13/09
3.6 Installation of stormwater pipe network 90 days Thu
5/14/09
Wed
9/16/09
3.7 Installation of street lighting and traffic signals at
West Swan Road 70 days Thu
9/17/09
Wed
12/23/09
3.8 Construction of medians, traffic islands, dual use
paths and cycle paths 110 days Thu
12/24/09
Wed
5/26/10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT REPORT
3.9 Construction of two special Spill Capture Units at
either end of Swan River Bridge 80 days Thu
5/27/10
Wed
9/15/10
3.10 Review of Construction 20 days Thu
9/16/10
Wed
10/13/10
3.11 Execution Phase Completed 0 days Wed
10/13/10
Wed
10/13/10
4 Monitor Phase 23 days Thu
10/14/10
Mon
11/15/10
4.1 Review of safety consideration 15 days Thu
10/14/10
Wed
11/3/10
4.2 Checking the constructed infrastructure 5 days Thu
11/4/10
Wed
11/10/10
4.3 Evaluation in terms of WHO safety guidelines 3 days Thu
11/11/10
Mon
11/15/10
4.4 Monitor Phase Completed 0 days Mon
11/15/10
Mon
11/15/10
5 Close Phase 18 days Tue
11/16/10
Thu
12/9/10
5.1 Final Documentation 10 days Tue
11/16/10
Mon
11/29/10
5.2 Review of documents 5 days Tue
11/30/10
Mon
12/6/10
5.3 Submission of documents 2 days Tue
12/7/10
Wed
12/8/10
5.4 Sign off 1 day Thu
12/9/10
Thu
12/9/10
5.5 Close Phase Completed 0 days Thu
12/9/10
Thu
12/9/10
3.9 Construction of two special Spill Capture Units at
either end of Swan River Bridge 80 days Thu
5/27/10
Wed
9/15/10
3.10 Review of Construction 20 days Thu
9/16/10
Wed
10/13/10
3.11 Execution Phase Completed 0 days Wed
10/13/10
Wed
10/13/10
4 Monitor Phase 23 days Thu
10/14/10
Mon
11/15/10
4.1 Review of safety consideration 15 days Thu
10/14/10
Wed
11/3/10
4.2 Checking the constructed infrastructure 5 days Thu
11/4/10
Wed
11/10/10
4.3 Evaluation in terms of WHO safety guidelines 3 days Thu
11/11/10
Mon
11/15/10
4.4 Monitor Phase Completed 0 days Mon
11/15/10
Mon
11/15/10
5 Close Phase 18 days Tue
11/16/10
Thu
12/9/10
5.1 Final Documentation 10 days Tue
11/16/10
Mon
11/29/10
5.2 Review of documents 5 days Tue
11/30/10
Mon
12/6/10
5.3 Submission of documents 2 days Tue
12/7/10
Wed
12/8/10
5.4 Sign off 1 day Thu
12/9/10
Thu
12/9/10
5.5 Close Phase Completed 0 days Thu
12/9/10
Thu
12/9/10
8PROJECT REPORT
ID Task
Mode
WBS Task Name Duration
0 0 Great Northern Highway
Upgrades (Upper Swan,
Western Australia)
749 days
1 1 Initiation Phase 41 days
2 1.1 Resource Identification15 days
3 1.2 Charter Documentation10 days
4 1.3 Tender Development 12 days
5 1.4 Submission of Tender 4 days
6 1.5 Initiation Phase Completed0 days
7 2 Plan Phase 40 days
8 2.1 Activities are sorted 8 days
9 2.2 Scheduling the activities12 days
10 2.3 Risk Management Plan 10 days
11 2.4 Scope Management Plan10 days
12 2.5 Plan Phase Completed 0 days
13 3 Execution Phase 627 days
14 3.1 Site acquisition 5 days
15 3.2 Site clearing 20 days
16 3.3 Safety Tools were
installed
12 days
17 3.4 Reconstruction and
Widening of Highway
120 days
18 3.5 Construction of high
strength pavements
including HCTCRB
100 days
19 3.6 Installation of
stormwater pipe
network
90 days
20 3.7 Installation of street
lighting and traffi c
signals at West Swan
Road
70 days
21 3.8 Construction of
medians, traffi c
islands, dual use paths
and cycle paths
110 days
22 3.9 Construction of two
special Spill Capture
Units at either end of
Swan River Bridge
80 days
23 3.10 Review of Construction 20 days
24 3.11 Execution Phase Completed0 days
25 4 Monitor Phase 23 days
26 4.1 Review of safety
consideration
15 days
27 4.2 Checking the
constructed
infrastructure
5 days
28 4.3 Evaluation in terms of
WHO safety guidelines
3 days
29 4.4 Monitor Phase Completed0 days
30 5 Close Phase 18 days
31 5.1 Final Documentation 10 days
32 5.2 Review of documents 5 days
33 5.3 Submission of documents2 days
34 5.4 Sign off 1 day
35 5.5 Close Phase Completed0 days
Project Manager
Documenter,Documents[1]
Documenter,Documents[1]
Documenter
3/24
Planner
Planner
Risk Analyst
Project Manager
5/19
Contractor
Contractor,Machineries[1]
Vendor,Civil Engineer,Safety Tools[1]
Workers,Construction Materials[1],Machineries[1]
Workers,Machineries[1],Road Materials[1],Intersection Materials[1]
Workers,Machineries[1],Underpass Materials[1]
Contractor,Civil Engineer
10/13
Civil Engineer
Civil Engineer,Project Manager,Contractor,Check
Civil Engineer,Project Manager
11/15
Documenter,Documents[1]
Project Manager
Documenter
Project Manager
12/9
12/16 2/24 5/4 7/13 9/21 11/30 2/8 4/19 6/28 9/6 11/15 1/24 4/4 6/13 8/22 10/31 1/9 3/20 5/29 8/7
September 21 February 11 July 1 November 21 April 11 September 1 January 21 June 11 November 1 March 21
Figure 1: Project Gantt chart
3 84
52
9 12 14 17 18
20
21 22
6 10 11 15 16 19 23
26
24
27
28 29
31 32
33 34
35
Figure 2: Project Network Diagram
ID Task
Mode
WBS Task Name Duration
0 0 Great Northern Highway
Upgrades (Upper Swan,
Western Australia)
749 days
1 1 Initiation Phase 41 days
2 1.1 Resource Identification15 days
3 1.2 Charter Documentation10 days
4 1.3 Tender Development 12 days
5 1.4 Submission of Tender 4 days
6 1.5 Initiation Phase Completed0 days
7 2 Plan Phase 40 days
8 2.1 Activities are sorted 8 days
9 2.2 Scheduling the activities12 days
10 2.3 Risk Management Plan 10 days
11 2.4 Scope Management Plan10 days
12 2.5 Plan Phase Completed 0 days
13 3 Execution Phase 627 days
14 3.1 Site acquisition 5 days
15 3.2 Site clearing 20 days
16 3.3 Safety Tools were
installed
12 days
17 3.4 Reconstruction and
Widening of Highway
120 days
18 3.5 Construction of high
strength pavements
including HCTCRB
100 days
19 3.6 Installation of
stormwater pipe
network
90 days
20 3.7 Installation of street
lighting and traffi c
signals at West Swan
Road
70 days
21 3.8 Construction of
medians, traffi c
islands, dual use paths
and cycle paths
110 days
22 3.9 Construction of two
special Spill Capture
Units at either end of
Swan River Bridge
80 days
23 3.10 Review of Construction 20 days
24 3.11 Execution Phase Completed0 days
25 4 Monitor Phase 23 days
26 4.1 Review of safety
consideration
15 days
27 4.2 Checking the
constructed
infrastructure
5 days
28 4.3 Evaluation in terms of
WHO safety guidelines
3 days
29 4.4 Monitor Phase Completed0 days
30 5 Close Phase 18 days
31 5.1 Final Documentation 10 days
32 5.2 Review of documents 5 days
33 5.3 Submission of documents2 days
34 5.4 Sign off 1 day
35 5.5 Close Phase Completed0 days
Project Manager
Documenter,Documents[1]
Documenter,Documents[1]
Documenter
3/24
Planner
Planner
Risk Analyst
Project Manager
5/19
Contractor
Contractor,Machineries[1]
Vendor,Civil Engineer,Safety Tools[1]
Workers,Construction Materials[1],Machineries[1]
Workers,Machineries[1],Road Materials[1],Intersection Materials[1]
Workers,Machineries[1],Underpass Materials[1]
Contractor,Civil Engineer
10/13
Civil Engineer
Civil Engineer,Project Manager,Contractor,Check
Civil Engineer,Project Manager
11/15
Documenter,Documents[1]
Project Manager
Documenter
Project Manager
12/9
12/16 2/24 5/4 7/13 9/21 11/30 2/8 4/19 6/28 9/6 11/15 1/24 4/4 6/13 8/22 10/31 1/9 3/20 5/29 8/7
September 21 February 11 July 1 November 21 April 11 September 1 January 21 June 11 November 1 March 21
Figure 1: Project Gantt chart
3 84
52
9 12 14 17 18
20
21 22
6 10 11 15 16 19 23
26
24
27
28 29
31 32
33 34
35
Figure 2: Project Network Diagram
9PROJECT REPORT
Project Background
The project is developed for implementing the plan for executing the management of the
successful and effective management of the construction management for the project of Great
Northern Highway Upgrades. The implication management had been successive for taking care
of the factors and implication would be implied with the consideration of the consideration for
the management of the successful project completion. The project would include the construction
works like reconstruction and Widening of Highway, construction of high strength pavements
including HCTCRB, installation of stormwater pipe network, installation of street lighting and
traffic signals at West Swan Road, construction of medians, traffic islands, dual use paths and
cycle paths, and construction of two special spill capture units at either end of Swan River
Bridge.
Conclusion
It can be concluded from the assignment that the implication of the successful
management of the implied processes. The overall budget for the project had been listed and
estimated with the help of the bottom up estimation and the complete budget estimate has come
up to be $ 41 million. The project had commenced on Monday 1/28/08 and ended on Thursday
12/9/10 stretching for 749 working days. The completion of the project had been helpful for
developing the widened highway and the west Swan Road.
Project Background
The project is developed for implementing the plan for executing the management of the
successful and effective management of the construction management for the project of Great
Northern Highway Upgrades. The implication management had been successive for taking care
of the factors and implication would be implied with the consideration of the consideration for
the management of the successful project completion. The project would include the construction
works like reconstruction and Widening of Highway, construction of high strength pavements
including HCTCRB, installation of stormwater pipe network, installation of street lighting and
traffic signals at West Swan Road, construction of medians, traffic islands, dual use paths and
cycle paths, and construction of two special spill capture units at either end of Swan River
Bridge.
Conclusion
It can be concluded from the assignment that the implication of the successful
management of the implied processes. The overall budget for the project had been listed and
estimated with the help of the bottom up estimation and the complete budget estimate has come
up to be $ 41 million. The project had commenced on Monday 1/28/08 and ended on Thursday
12/9/10 stretching for 749 working days. The completion of the project had been helpful for
developing the widened highway and the west Swan Road.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT REPORT
Bibliography
Burtonshaw-Gunn, S.A., 2017. Risk and financial management in construction. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Kuchta, D. and Ptaszyńska, E., 2017, July. Fuzzy based risk register for construction project risk
assessment. In AIP Conference Proceedings (Vol. 1863, No. 1, p. 230006). AIP Publishing.
Lock, D., 2016. Project management in construction. Routledge.
Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming
psychological safety climate in construction project management. International journal of
project management, 33(1), pp.223-235.
Walker, D.H., 2016. Reflecting on 10 years of focus on innovation, organisational learning and
knowledge management literature in a construction project management context. Construction
Innovation, 16(2), pp.114-126.
Bibliography
Burtonshaw-Gunn, S.A., 2017. Risk and financial management in construction. Routledge.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Kuchta, D. and Ptaszyńska, E., 2017, July. Fuzzy based risk register for construction project risk
assessment. In AIP Conference Proceedings (Vol. 1863, No. 1, p. 230006). AIP Publishing.
Lock, D., 2016. Project management in construction. Routledge.
Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming
psychological safety climate in construction project management. International journal of
project management, 33(1), pp.223-235.
Walker, D.H., 2016. Reflecting on 10 years of focus on innovation, organisational learning and
knowledge management literature in a construction project management context. Construction
Innovation, 16(2), pp.114-126.
1 out of 11
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.