Running head: IMPLEMENTATION OF INFORMATION SYSTEM Assessment Component 2 Implementation of Information System for Highland Explore Tours Student name: ID number: Name of the University:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1IMPLEMENTATION OF INFORMATION SYSTEM Assignment 2 Part 1: Initiation The following is considered as project management for Implementation of Highland Explore Tour. Project description:The project has been developed in order to develop strategies to support the process of implementing the activities that can align the information of the factors to support the process of designing the simplification of the activities.In addition, implementing project management plan would be established successfully to ease the flow of information. The project objectives can be described as followed. The subsystem of the Information System (IS) that has been designed specifically for the Highland Explore Tours are a website and a Mobile App. Both of these subsystems are expected to be completed by the system designers within estimated time a budget. The objectives for the development of the Information System in terms of the website and the Mobile App are developed in this assignment. To develop new strategies supporting the process of implementinghighland explore tour project plan and activities To deploy the project tour of highland explore tour supporting development of the factors and enhanced communication To analyze the factors related to developmentof the activities and implement them properly Deliverable of the projects is as followed.
2IMPLEMENTATION OF INFORMATION SYSTEM Strategy for making integration of the aligning the activities Deploying the factors that are able to define the enhanced activities Implementation of highland explore tour would be achieved for completion of the project Project Schedule WBSTask NameDurationStartFinish 0Implementation of highland explore34 daysMon 5/28/18Thu 7/12/18 1Initiation6 daysMon 5/28/18Mon 6/4/18 1.1Analysis of the requirements3 daysMon 5/28/18Wed 5/30/18 1.2Charter Documentation2 daysThu 5/31/18Fri 6/1/18 1.3Risk Management1 dayMon 6/4/18Mon 6/4/18 2Planning11 daysThu 5/31/18Thu 6/14/18 2.1Outline of Plan2 daysThu 5/31/18Fri 6/1/18 2.2Review of Plan3 daysTue 6/5/18Thu 6/7/18 2.3Complete Plan Development5 daysFri 6/8/18Thu 6/14/18 3Execution14 daysThu 5/31/18Tue 6/19/18 3.1The place is selected1 dayThu 5/31/18Thu 5/31/18 3.2The process is Migrated5 daysFri 6/1/18Thu 6/7/18 3.3Operation Alignment8 daysFri 6/8/18Tue 6/19/18 4Controlling11 daysWed 6/20/18Wed 7/4/18 4.1Processes Monitoring4 daysWed 6/20/18Mon 6/25/18 4.2Problem Detection2 daysTue 6/26/18Wed 6/27/18 4.3Modification of the processes5 daysThu 6/28/18Wed 7/4/18 5Closing6 daysThu 7/5/18Thu 7/12/18 5.1Final Documentation3 daysThu 7/5/18Mon 7/9/18
3IMPLEMENTATION OF INFORMATION SYSTEM 5.2Submission of Reports2 daysTue 7/10/18Wed 7/11/18 5.3Sign off1 dayThu 7/12/18Thu 7/12/18 The project plan would comprise the following activities in order to align the activities successfully. The project plan execution would be based on aligning the information as well as developed successfully that help to develop the factors and use of the specific factors. The project plan ofImplementation of highland would be based on the activities and easing the process of completing the enhanced activity development. On the other hand, aligning the activities would be implemented the process and manage the factors. Project budget:The budget for the project isImplementation of highland explore is shown below. Resource NameTypeWorkStandard RateCost Project ManagerWork144 hrsRM100.00/hrRM14,400.00 VendorWork40 hrsRM90.00/hrRM3,600.00 Risk ManagerWork32 hrsRM50.00/hrRM1,600.00 SponsorWork8 hrsRM0.00/hrRM0.00 VP of OperationsWork40 hrsRM110.00/hrRM4,400.00 VP of MarketingWork112 hrsRM80.00/hrRM8,960.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4IMPLEMENTATION OF INFORMATION SYSTEM Monitor ToolsMaterial2RM700.00RM700.00 SystemMaterial3RM1,000.00RM3,000.00 DatabaseMaterial1RM300.00RM300.00 DocumentsMaterial5RM20.00RM40.00 Total BudgetRM 38,000.00 Part 2: Planning The work breakdown structure forImplementation of highland explore can be shown as below. WBSTask NameDurationStartFinishPredecessors 0Implementation of highland explore34 daysMon 5/28/18Thu 7/12/18 1Analysis Phase6 daysMon 5/28/18Mon 6/4/18 1.1Requirements analysis3 daysMon 5/28/18Wed 5/30/18 1.1.1Project Requirements1.5 daysMon 5/28/18Tue 5/29/18 1.1.2System Requirements1.5 daysTue 5/29/18Wed 5/30/183 1.2Risk Management1 dayMon 6/4/18Mon 6/4/18 1.2.1Risk Analysis0.5 daysMon 6/4/18Mon 6/4/1811 1.2.2Risk Mitigation0.5 daysMon 6/4/18Mon 6/4/186 2Documentation Phase28 daysThu 5/31/18Mon 7/9/18 2.1Charter Documentation2 daysThu 5/31/18Fri 6/1/18 2.1.1Initiation document1 dayThu 5/31/18Thu 5/31/184 2.1.2Charter Plan document1 dayFri 6/1/18Fri 6/1/1810
5IMPLEMENTATION OF INFORMATION SYSTEM 2.2Final Documentation3 daysThu 7/5/18Mon 7/9/18 2.2.1Test Results are identified2 daysThu 7/5/18Fri 7/6/1828 2.2.2Documented in report1 dayMon 7/9/18Mon 7/9/1813 3Planning Phase11 daysThu 5/31/18Thu 6/14/18 3.1Outline of Plan2 daysThu 5/31/18Fri 6/1/184 3.2Review of Plan3 daysTue 6/5/18Thu 6/7/187 3.3Complete Plan Development5 daysFri 6/8/18Thu 6/14/1817 4Technology Development Phase14 daysThu 5/31/18Tue 6/19/18 4.1Big Data Platform is selected1 dayThu 5/31/18Thu 5/31/184 4.2Data is Migrated5 daysFri 6/1/18Thu 6/7/1820 4.3Operation Alignment8 daysFri 6/8/18Tue 6/19/1821 5Monitoring Phase6 daysWed 6/20/18Wed 6/27/18 5.1Processes Monitoring4 daysWed 6/20/18Mon 6/25/1822 5.2Problem Detection2 daysTue 6/26/18Wed 6/27/1824 6Modification Phase5 daysThu 6/28/18Wed 7/4/18 6.1Processes Change Implementation1 dayThu 6/28/18Thu 6/28/1825 6.2Modification of the processes4 daysFri 6/29/18Wed 7/4/1827 7Closure Phase3 daysTue 7/10/18Thu 7/12/18 7.1Submission of Reports2 daysTue 7/10/18Wed 7/11/1814 7.2Sign off1 dayThu 7/12/18Thu 7/12/1830 The work packages of the project consist of the requirements, risk management, charter documentation and technology formation. The completion of work packages is based on the simplifying the activities regarding the development of the activities regarding the alignment of
6IMPLEMENTATION OF INFORMATION SYSTEM the activities implementing Implementation of highland explore. The duration for the successful implementation of the project including work type and working hours are also illustrated in this section. In addition to this, the power functions, roles, power influence and responsibilities of the project team members are also elaborated in this section. The following table is considered as the usage plan for the project: Resource NameActivity ListedTypeWork VP of Operations TotalWork124 hrs Complete Plan DevelopmentWork30 hrs Processes MonitoringWork12 hrs Problem DetectionWork18 hrs Modification of the processesWork50 hrs Outline of PlanWork26 hrs VP of Marketing TotalWork30 hrs Final DocumentationWork14 hrs Submission of ReportsWork16 hrs Risk ManagerWork24hrs Risk ManagementWork9hrs Plan ReviewerWork16 hrs SponsorWork18 hrs Sign offWork8 hrs Project Manager TotalWork30 hrs Requirements analysisWork24 hrs Charter DocumentationWork26 hrs VendorTotalWork112 hrs
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7IMPLEMENTATION OF INFORMATION SYSTEM The place is selectedWork18 hrs process is MigratedWork30 hrs Operation AlignmentWork54 hrs Project 3: Execution The stakeholder register for Implementation of highland explore can be represented in the following table. NameRoleTypePowerInfluence John SmithVP of OperationsInternalHighHigh Roy Manson VP of MarketingInternalLowLow Rick toyRisk ManagerInternalLowHigh Smith Prone(CFO) Project SponsorInternalLowHigh Jack Susan (CIO)Member of Steering CommitteeInternalLowHigh <<please fill>>Project ManagerInternalLowHigh NameRoleTypePowerInfluenceFunction Roy Manson VP of marketing Interna lHighHigh Managing the activities as well as ensuring the project is completed successfully Rick toyRisk managerInterna l HighLowMaking sure the management of the activities as well as promoting the establishment to a
8IMPLEMENTATION OF INFORMATION SYSTEM wider scale Smith Prone(CFO) Project sponsor Interna lLowLow Managing the risk management procedure as well as ensuring the alignment of effective alignment of the operations for reducing the factors of risk Jack Susan (CIO) Member of Steering Committee Interna lHighHigh Managing the activities for aligning the process of implication of the resources to establish the effective integration of the factors <<please fill>> Project Manager Interna lLowHigh In charge of the management of the activities, it is aligning synthetic development of development The above mentioned two tables clearly depict the stakeholder register to implement of highland explore. In the first table, 6 persons are involved in the project. All of them are of internal type. Only John Smith has a high power and the rest all have low power. The influences of these people are however different. Only Roy Manson has a low influence and all rest of the people have higher influences. This demonstrates that Roy Manson has a lesser impact on this particular project. The second table depicts that 5 persons are involved in this particular project. In this table, Roy Manson has a higher impact on the project with high power and high influence. Only Smith Prone, the Chief Financial Officer, has a lower impact on the project with low power and lower influence. Jack Susan, who is the Chief Information Officer in this project, has similar influence like Ray Manson with higher power and higher influence. He is responsible for managing the several activitiesfor aligning the process of implication of the resources to establish the effective integration of the factors. The project manager of the project has low power and high influence in this project. He is in charge of the activity management.
9IMPLEMENTATION OF INFORMATION SYSTEM Part 4: Controlling The project has activities that need controlling and monitoring in order to develop the ease of implication for the factors helpful in providing the definition of formation of successful activities of implementation of Information System (IS). The project controlling is dependent mostly on the factors that are specific for the successful implications were the activities have eased the implication process. The factors that have successful alignment would control the project and achieve success in the implication of defining the factors that are aligning by the ease of those factors that are utilized. Project control is the gathering, managing as well as analysis of data that is utilized for the prediction, understanding as well as constructively influencing the cost and time results of any specific project and program. This type of project control is done by the information communication to obtain effective management and proper decision making. The factors for controlling would depend successfully on the process as well as effective communication. The significant implication of controlling and monitoring would be formed by the implication management that is effective to form. Project controlling is done to know about the recent changes in a project. The proper strategy or the undertaking planning methods eventually help the project manager to optimize all the future outcomes. Moreover, this is even helpful in estimating the costs and cost engineering or control. The proper management of risks like the maintenance of risk register or risk analysis and assessment are done by the project control in any typical project. The overall schedule and cost is also checked with the help of this particular project phase. The factors would be simplified that are ease for utilizing the definition of implication that has formation being done successfully. The work packages that each individual have need to be completed and would be assisted for aligning the activities with successive implication. The dependency of the project is completely based on the alignment of
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10IMPLEMENTATION OF INFORMATION SYSTEM the activities. The project is completely dependent on the activities having alignment with successive inclusion which defines the formation of the activities to be improved. Due to this dependency, it is not possible to execute a project without project control. On the other hand, there is a formation of successful implication of the ease that has the model of formation. The project completion would be effectively utilized which could help in formation of activities with ease. The result of project usage could make the modification in the formation of the information. The execution of the project plan is actually based on the alignment which has the development of forming successfully about the factors that are inclusion with the development of utilizing factors. The planning of the project is completely based on the project ofImplementation of Highland explore tourwhich is the actual implementation process. The completion ease would be successfully deployed by the activities that would improve the formation of activities. The deployment of alignment activities would ease the factors that are aligning for the process of formation to be developed. Part 5: Closing The functional alignment is ease which would implied successfully by improving the functional formation. The process of effective management in being utilize with the process of effective implementation. The completion of the project helps the alignment factors that are to be ease. Thus, the project has some lesson to be learnt that are discussed below: Prepared by: <Please fill>Date: <5/28/2018-7/12/2018> Project Name: Implementation ofinformation system (subsystem websites
11IMPLEMENTATION OF INFORMATION SYSTEM and mobile app) for Highland Explore Tours Project Sponsor: <Please fill> Project Manager: <Please fill> Project Dates: <8/13/2018-4/19/2019> Final Budget:Total budget for the project is$51,000 1.Did the project meet scope, time, and cost goals? From the detail learning of the case project of development of Information System in terms of website and mobile app I have realized that, scope time and goals the most important project constraints to be considered for the successful implementation of the project. At the early project development phase components are required to be estimated by the system designer and project manager. 2.What was the success criteria listed in the project scope statement? Proper decision making to implement required changes in the project An achievable date of project delivery with the design of project schedule Less scope creep Internal coordination between the contractor and the suppliers Less range of project scope creep Availability for the project resources 3.Reflect on whether or not you met the project success criteria. I think that the project success criterion for the information system development project has been met within estimated time and budget. This is the role of the project managertocompletetheprojectwithinestimatedtimeandbudget.ProperKey
12IMPLEMENTATION OF INFORMATION SYSTEM Performance Indicators for this project are also considered. Aligned quantitative methods are also measured and stated for this project. The business objectives are also aligned towards the project goal. During the project testing phase, it is defined that this project will successfully deliver an error free and user friendly online official website and mobile app for the consumers. All the project success factors are considered to meet the expectation of the consumers. 4.In terms of managing the project, what were the main lessons your team learned? For successful implementation of the Information System (IS) the leading must be played by the project manager and the operation manager of the project. They must play their allocated job roles within estimated time boundary. 5.Describe one example of what went right on this project. According to project details the thing that went right for this particular project includes support and coordination from the project team members. Due to both internal and external support the project is expected to be completed within time and budget. 6.Describe one example of what went wrong on this project. I think that the only thing that went wrong in this project is improper project budget design. 7.What will you do differently on the next project based on your experience working on this project? I think that the set of knowledge and skills obtained from the project are extremely valuable for me and if I will apply those ideas in future then the project will definitely meet the expectation of the consumers. I think that at the project initiation
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13IMPLEMENTATION OF INFORMATION SYSTEM phase the project goal set and scope should be designed. The one negative experience that I have faced is associated to lack of action plan. I think that if proper action plans are undertaken then the project will definitely meet the objectives. The activities are handle successfully for deploying the factors of the project for effective implication The activities of marketing management is ensure effectively for the factors that are implied the successful integration The factors having successful integration have effectively implied the progress of the project for marketing The risk factors are reduce for the activities having effective alignment and ensure the alignment and the process of risk management The management of risk is eased by formation of priority matrix of the risk and planning of the risk mitigation The implication alignment activities has management of resources that could develop the factors for effective integration The easing of the alignment need to be formed by using the resource alignment formation for the development of improved activities The utilization factors is the in charge of alignment of the processes that needs to be take care for the formation of effective formation
14IMPLEMENTATION OF INFORMATION SYSTEM References Besteiro,E.N.C.,Pinto,J.D.,&Novaski,O.(2015).Successfactorsinproject management.Business Management Dynamics,4(9), 19-34. Brioso, X. (2015). Integrating ISO 21500 guidance on project management, lean construction and PMBOK.Procedia Engineering,123, 76-84. Browning,T.R.,& Ramasesh,R.V. (2015).Reducingunwelcomesurprisesin project management.MIT Sloan Management Review,56(3), 53. Carvalho, M. M., & Rabechini, R. (2017). Can project sustainability management impact project success? An empirical study applying a contingent approach.International Journal of Project Management,35(6), 1120-1132. Colin, J., & Vanhoucke, M. (2015). Developing a framework for statistical process control approaches in project management.International Journal of Project Management,33(6), 1289-1300. Dyba, T., Dingsøyr, T., & Moe, N. B. (2014). Agile project management. InSoftware project management in a changing world(pp. 277-300). Springer, Berlin, Heidelberg. Elbanna,S.(2015).Intuitioninprojectmanagementandmissinglinks:Analyzingthe predicating effects of environment and the mediating role of reflexivity.International Journal of Project Management,33(6), 1236-1248. Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.
15IMPLEMENTATION OF INFORMATION SYSTEM Floricel, S., Bonneau, C., Aubry, M., & Sergi, V. (2014). Extending project management research:Insightsfromsocialtheories.InternationalJournalofProject Management,32(7), 1091-1107. Guo, F., Chang-Richards, Y., Wilkinson, S., & Li, T. C. (2014). Effects of project governance structures on the management of risks in major infrastructure projects: A comparative analysis.International Journal of Project Management,32(5), 815-826. Hu, X., Cui, N., & Demeulemeester, E. (2015). Effective expediting to improve project due date and cost performance through buffer management.International Journal of Production Research,53(5), 1460-1471. Kerzner, H. (2015).Project management 2.0: leveraging tools, distributed collaboration, and metrics for project success. John Wiley & Sons. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kopmann, J., Kock, A., Killen, C. P., & Gemünden, H. G. (2017). The role of project portfolio management in fostering both deliberate and emergent strategy.International Journal of Project Management,35(4), 557-570. Machado, T. C. S., Pinheiro, P. R., & Tamanini, I. (2015). Project management aided by verbal decisionanalysisapproaches:a casestudy for the selectionof the bestSCRUM practices.International Transactions in Operational Research,22(2), 287-312. Marchewka, J. T. (2014).Information technology project management. John Wiley & Sons.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16IMPLEMENTATION OF INFORMATION SYSTEM McClory, S., Read, M., & Labib, A. (2017). Conceptualising the lessons-learned process in project management: Towards a triple-loop learning framework.International Journal of Project Management,35(7), 1322-1335. Paquin, J. P., Gauthier, C., & Morin, P. P. (2016). The downside risk of project portfolios: The impact of capital investment projects and the value of project efficiency and project risk management programmes.International Journal of Project Management,34(8), 1460- 1470. Sage, D., Dainty, A., & Brookes, N. (2014). A critical argument in favor of theoretical pluralism: Project failure and the many and varied limitations of project management.International journal of project management,32(4), 544-555. Silvius, A. G., Kampinga, M., Paniagua, S., & Mooi, H. (2017). Considering sustainability in projectmanagementdecisionmaking;AninvestigationusingQ- methodology.International Journal of Project Management,35(6), 1133-1150.