logo

Project Status and Control Report for Implementing 3 Tier Structure for Storage in Barwon Health

   

Added on  2023-06-13

16 Pages4455 Words254 Views
 | 
 | 
 | 
PROJECT STATUS AND CONTROL REPORT
NAME OF PROJECT
PPMP20010- Assignment 1
Part A
Project Status Report
1 PROJECT INFORMATION
Project name: Implementing 3 Tier Structure for Storage in Barwon Health
Organization
Date: 7th April, 2018
Project ownership: IT Project Management
Prepared by: <<name of the student>>
Distribution list: Chris Jones, CEO (Barwon Health Organization)
Jessica Keith, CFO (Barwon Health Organization)
Laurence Heath, Head of Project Steering Committee
(Barwon Health Organization)
ENTER YOUR NAME WITH STUDENT ID PAGE 1
Project Status and Control Report for Implementing 3 Tier Structure for Storage in Barwon Health_1

PROJECT STATUS AND CONTROL REPORT
NAME OF PROJECT
2 GANTT CHART
WB
S #
Task &
Subtask
Mon
3/19/1
8
Fri
3/23/1
8
Mon
3/26/1
8
Thu
3/29/1
8
Fri
3/30/1
8
Mon
4/2/1
8
Tue
4/10/18
Thu
4/12/1
8
Fri
4/13/18
Mon
4/16/18
1 Initiation
Phase
——————
1.1 Initial
Documen
ts are
made

1.2 Project
Kick off
Meeting

1.3 Plan is
Develope
d

2 Design of
new
structure
is made
————
2.1 Outline of
design is
made
___
2.2 Design
Review
___
2.3 Complete
Design is
made
___
3 Existing
Data is
Backed
up
————————
3.1 Backup
database
is created
_____
3.2 Migration
of data
_____
3.3 Integrate
d
Database
is
develope
d
_____
4 3-Tier
Structure
Develop
ment
————————————
4.1 Develop
ment of
HCI, VDI,
and
Microsoft
SQL
—————
4.2 Integratio ——————
ENTER YOUR NAME WITH STUDENT ID PAGE 2
Project Status and Control Report for Implementing 3 Tier Structure for Storage in Barwon Health_2

PROJECT STATUS AND CONTROL REPORT
NAME OF PROJECT
n of the
technolog
ies
5 Testing of
the 3 Tier
Structure
—————
5.1 Test Plan
is
develope
d
_____
5.2 Testing of
the
structure
_____
6 Implemen
tation of
the new
structure
——
6.1 Implemen
tation
Plan
__
6.2 Implemen
ting the
structure
__
7 Deploym
ent of the
new
hybrid
structure

7.1 Deploym
ent Plan
_
7.2 Deployin
g the
hybrid
structure
_
8 Final
Documen
tation and
Closure

3 VARIANCE ANALYSIS (COST IN THOUSANDS)
Schedule Variance (SV) = EV-PV
Schedule Variance%= SV*100/PV
Cost Variance (CV) = EV-AC
Cost Variance% = CV*100/AC
Task &
Subtask
Milestone
Status PV EV AC
Variance %
Schedule Cost
Initiation
Phase
Completed 100 100 100 0 0
Initial
Documents
are made
Completed 25 25 25 0 0
Project Kick
off Meeting
Completed 50 50 50 0 0
Plan is Completed 25 25 25 0 0
ENTER YOUR NAME WITH STUDENT ID PAGE 3
Project Status and Control Report for Implementing 3 Tier Structure for Storage in Barwon Health_3

PROJECT STATUS AND CONTROL REPORT
NAME OF PROJECT
Developed
Design of
new
structure is
made
Completed 50 50 55 0 -9.1%
Existing
Data is
Backed up
Completed 50 50 40 0 -25%
3-Tier
Structure
Developmen
t
In progress 70 40 110 -42% -63.63%
Developmen
t of HCI,
VDI, and
Microsoft
SQL
Completed 30 30 50 0 -40%
Integration
of the
technologies
In progress 40 10 60 -75% -83.33%
Testing of
the 3 Tier
Structure
Not started 90 0 0 0 0
Implementati
on of the
new
structure
Not started 40 0 0 0 0
Deployment
of the new
hybrid
structure
Not started 50 0 0 0 0
Final
Documentati
on and
Closure
Not started 5 0 0 0 0
Task Totals 455 240 305
4 ESTIMATE AT COMPLETION (EAC)
EAC = BAC/CPI
(where BAC= budget at completion and CPI= cost performance index)
CPI= EV/AC and BAC is the final budget of the project
EAC= (40000/240)*305
= $50,833.33
5 COST SUMMARY
The speculation of the costs of the project can be done considering the resources of the
project and the alignment of the activities and utilization of the integration of the
operations. The costs analysis for the resources would allow the utilization for the
resources of both human and materials for the alignment of the cost operations. The
following table would show the utilization of the costs in the project,
Resource
Name Work Standard Rate Cost
Documenter 24
hrs $65.00/hr $1,560.00
ENTER YOUR NAME WITH STUDENT ID PAGE 4
Project Status and Control Report for Implementing 3 Tier Structure for Storage in Barwon Health_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Status and Control Report for Barwon Health Project Tender
|13
|3565
|165

Project Status and Control Report: Barwon Health Integration with SWARH Project
|7
|1928
|239

PPMP20010 - Assignment 1: Barwon Storage and Computer Infrastructure Project Status and Control Report
|7
|1579
|345

PPMP20010- Executing and Closing Projects Assignment
|9
|2023
|68

PPMP20010 - Assignment 1: Project Status and Control Report
|9
|1888
|291

PPMP20010 - Assignment 1: Project Status and Control Report
|10
|1949
|385