Running Head: ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS ISYS302 Management of IT Systems and Projects Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS Answer to 1 The overall schedule of the project is shown as follows. Task NameDurationStartFinishPredecessors Cloud Manufacturing522 daysThu 4/4/19Fri 4/2/21 Design Steps122 daysThu 4/4/19Fri 9/20/19 Specification of System Features Needed 10 daysMon 5/6/19Fri 5/17/19 Requirements Gathering10 daysThu 4/4/19Wed 4/17/19 Initiate System Design5 days Mon 5/20/19 Fri 5/24/192,3 Create System Design Diagram5 days Mon 5/27/19 Fri 5/31/194 Finalize System Design15 daysMon 6/3/19Fri 6/21/195 Purchase Cloud Subscription from Vendor 10 daysThu 4/18/19Wed 5/1/193 Develop System Architecture20 days Mon 6/24/19 Fri 7/19/196,7 Develop System Prototype20 daysMonFri 8/16/198
2ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS 7/22/19 Preliminary Testing15 days Mon 8/19/19 Fri 9/6/199 Modifications and Changes10 daysMon 9/9/19Fri 9/20/1910 Complete System Design0 daysFri 9/20/19Fri 9/20/1911 Data Analysis45 days Thu 4/18/19 Wed 6/19/19 Gather System Requirement Data10 daysThu 4/18/19Wed 5/1/193 Prepare Design Usage Data10 daysThu 5/2/19Wed 5/15/1914 Analyze the Data15 daysThu 5/16/19Wed 6/5/1914,15 Document Analysis Results10 daysThu 6/6/19Wed 6/19/1916 Completion of Data Analysis0 days Wed 6/19/19 Wed 6/19/1917 Assembly255 days Mon 9/23/19 Fri 9/11/20 Assemble All System Features90 days Mon 9/23/19 Fri 1/24/2012 Develop Architecture of Final System150 daysMonFri 8/21/2020
3ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS Design1/27/20 Modifications in the System as per Requirements 15 days Mon 8/24/20 Fri 9/11/2021 Complete Final Design0 daysFri 9/11/20Fri 9/11/2022 Testing and Production145 days Mon 9/14/20 Fri 4/2/21 Conduct System Tests30 days Mon 9/14/20 Fri 10/23/2018,23 Identify and Remove Bugs25 days Mon 10/26/20 Fri 11/27/2025 Review System Security15 days Mon 10/26/20 Fri 11/13/2025 Install Security Firewall as Required10 days Mon 11/16/20 Fri 11/27/2027 System Performance Testing25 days Mon 10/26/20 Fri 11/27/2025 Data Management Testing25 days Mon 10/26/20 Fri 11/27/2025 User Interaction Testing30 daysMonFri 12/4/2025
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS 10/26/20 Document Test Results15 days Mon 12/7/20 Fri 12/25/2026,29,30,31 System Launch5 days Mon 12/28/20 Fri 1/1/2132 Initiate Production for Multiple Users15 daysMon 1/4/21Fri 1/22/2133 Develop Client Usable System35 days Mon 1/25/21 Fri 3/12/2134 Documentation of Project15 days Mon 3/15/21 Fri 4/2/2135 Sign Off0 daysFri 4/2/21Fri 4/2/2136 The resource allocation and project budget are shown in the following table. Task NameResource NamesCost Cloud Manufacturing$692,400.00 Design Steps$307,400.00 Specification of System Features NeededSystem Analyst$3,200.00 Requirements GatheringSystem Analyst$3,200.00 Initiate System DesignDeveloper, Software[1]$78,000.00
5ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS Create System Design DiagramDeveloper$3,000.00 Finalize System DesignDeveloper$9,000.00 Purchase Cloud Subscription from Vendor ERPSubscription[1], Network Engineer $154,000.00 Develop System ArchitectureDeveloper$12,000.00 Develop System PrototypeDeveloper$12,000.00 Preliminary Testing SystemTester, Reporting and Analysis System[1] $22,200.00 Modifications and Changes Developer,System Tester $10,800.00 Complete System DesignDeveloper$0.00 Data Analysis$16,400.00 Gather System Requirement DataSystem Analyst$3,200.00 Prepare Design Usage DataSystem Analyst$3,200.00 Analyze the DataSystem Analyst$4,800.00
6ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS Document Analysis Results SystemAnalyst, Content Writer $5,200.00 Completion of Data AnalysisSystem Analyst$0.00 Assembly$205,600.00 Assemble All System Features System Analyst, System Development Tools[1] $53,800.00 Develop Architecture of Final System Design Developer,System Analyst $138,000.00 ModificationsintheSystemasper Requirements Developer,System Analyst $13,800.00 Complete Final DesignDeveloper$0.00 Testing and Production$163,000.00 Conduct System Tests SystemTester, Visulisation Tools[1] $34,400.00 Identify and Remove BugsSystem Tester$12,000.00 Review System Security NetworkEngineer, System Tester $13,200.00 Install Security Firewall as RequiredSystem Tester$4,800.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS System Performance TestingSystem Tester$12,000.00 Data Management TestingSystem Tester$12,000.00 User Interaction TestingSystem Tester$14,400.00 Document Test ResultsSystem Tester$7,200.00 System Launch Developer,Network Engineer $5,000.00 Initiate Production for Multiple Users Developer,Production PlanningandControl System[1] $24,000.00 Develop Client Usable SystemDeveloper$21,000.00 Documentation of ProjectContent Writer$3,000.00 Sign OffDeveloper$0.00 The Gantt chart of the project is shown as follows.
8ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS Figure 1: Gantt Chart of the Project (Source: Created by Author)
9ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS Answer to 2 The project will take a total duration of 500 days. This is the case because the overall critical path will include 500 days and other tasks can be completed within this duration only. The critical path of the project, as determined from the schedule is: 2ï‚®3ï‚®4ï‚®5ï‚®6ï‚® 8ï‚®9ï‚®10ï‚®11ï‚®20ï‚®21ï‚®22ï‚®25ï‚®31ï‚®32ï‚®33ï‚®34ï‚®35ï‚®36ï‚®37. Figure 2: Network Diagram of the Project (Source: Created by Author) Answer to 3 In order to determine the schedule, the work packages have been connected using suitable dependencies and predecessor links (Schwalbe 2015). After linking the activities, estimated durations have been assigned to each work package and the total duration that lies on the critical path of the project forms the total duration of the project itself. After determining the timeframe, staffs were assigned to each work package where their duties are essential (Kerzner and Kerzner 2017). Their payment rates have been specified and the total usage of payment resource has been
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS calculated by multiplying the unit rates with the total working hours of each staff assigned in the project work packages.
11ISYS302 MANAGEMENT OF IT SYSTEMS AND PROJECTS References Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Schwalbe, K., 2015.Information technology project management. Cengage Learning.