Project Management for Development of Information Technology Centre
VerifiedAdded on 2023/06/10
|30
|3327
|280
AI Summary
This project management report discusses the development of a new information technology centre in Australia. It covers the planning methodology, manual planning, lists of tasks, durations and their logical relationships, execution programme, sub-contractors and required labour schedule.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Project: Development of a new information technology centre
Name of the Student
Name of the University
Author’s Note
Project: Development of a new information technology centre
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
PROJECT MANAGEMENT
Table of Contents
1. Project description..................................................................................................................3
2. List of assumption..................................................................................................................3
3. Planning methodology...........................................................................................................3
4. Manual planning.....................................................................................................................4
4.1 Project calendar................................................................................................................4
4.2 WBS, OBS, and RAM.....................................................................................................4
4.3 Lists of tasks, durations and their logical relationships.................................................10
4.4 Execution programme....................................................................................................13
4.5 Sub-contractors and required labour schedule...............................................................14
4.6 Bill of quantities and cost estimation.............................................................................15
4.7 Risk register...................................................................................................................17
5. Computerized planning........................................................................................................20
5.1 Lists of tasks and WBS..................................................................................................20
5.2 Project calendar..............................................................................................................21
5.3 PDM diagram and Gantt chart.......................................................................................22
5.4 Lists and cost of resources.............................................................................................24
5.5 Cost and detail budget....................................................................................................25
5.6 Resource schedule..........................................................................................................26
5.7 S-curve...........................................................................................................................27
5.8 Histogram for resources.................................................................................................28
5. 9 Relevant report for supporting PEP..............................................................................28
Bibliography.............................................................................................................................29
PROJECT MANAGEMENT
Table of Contents
1. Project description..................................................................................................................3
2. List of assumption..................................................................................................................3
3. Planning methodology...........................................................................................................3
4. Manual planning.....................................................................................................................4
4.1 Project calendar................................................................................................................4
4.2 WBS, OBS, and RAM.....................................................................................................4
4.3 Lists of tasks, durations and their logical relationships.................................................10
4.4 Execution programme....................................................................................................13
4.5 Sub-contractors and required labour schedule...............................................................14
4.6 Bill of quantities and cost estimation.............................................................................15
4.7 Risk register...................................................................................................................17
5. Computerized planning........................................................................................................20
5.1 Lists of tasks and WBS..................................................................................................20
5.2 Project calendar..............................................................................................................21
5.3 PDM diagram and Gantt chart.......................................................................................22
5.4 Lists and cost of resources.............................................................................................24
5.5 Cost and detail budget....................................................................................................25
5.6 Resource schedule..........................................................................................................26
5.7 S-curve...........................................................................................................................27
5.8 Histogram for resources.................................................................................................28
5. 9 Relevant report for supporting PEP..............................................................................28
Bibliography.............................................................................................................................29
2
PROJECT MANAGEMENT
1. Project description
The project reflects on the development in Australia. It is found that for developing
the centre of information technology, the amount of budget that was approved is $25 million
and additionally $15 million was also provided for utilizing latest IT technology within the
data centre. This is generally done so that the data centre can successfully support the IT
requirements of the clients quite effectively.
2. List of assumption
The list of assumptions that are generally made while developing the IT centre in
Australia are listed below:
The IT centre must be developed in such a way that it will support all the IT needs for
the next coming years
The time that will be needed for finishing the development of the IT centre will be
around 182 days
The amount of budget that is approved will be enough for successful completion of
the entire project.
3. Planning methodology
It is identified that in order to develop the information technology centre, agile
project management methodology is mainly utilized within the project. Agile methodology is
used for developing the information technology centre so that the entire development can get
finished within the time that is expected by utilizing the advantage of Automated tools during
the testing phase of the project. Agile project methodology is very much advantageous in
comparison to other methodologies as with the help of agile methodology, the challenges as
well as issues that are mainly related with the project can successfully get reduced. Moreover,
PROJECT MANAGEMENT
1. Project description
The project reflects on the development in Australia. It is found that for developing
the centre of information technology, the amount of budget that was approved is $25 million
and additionally $15 million was also provided for utilizing latest IT technology within the
data centre. This is generally done so that the data centre can successfully support the IT
requirements of the clients quite effectively.
2. List of assumption
The list of assumptions that are generally made while developing the IT centre in
Australia are listed below:
The IT centre must be developed in such a way that it will support all the IT needs for
the next coming years
The time that will be needed for finishing the development of the IT centre will be
around 182 days
The amount of budget that is approved will be enough for successful completion of
the entire project.
3. Planning methodology
It is identified that in order to develop the information technology centre, agile
project management methodology is mainly utilized within the project. Agile methodology is
used for developing the information technology centre so that the entire development can get
finished within the time that is expected by utilizing the advantage of Automated tools during
the testing phase of the project. Agile project methodology is very much advantageous in
comparison to other methodologies as with the help of agile methodology, the challenges as
well as issues that are mainly related with the project can successfully get reduced. Moreover,
3
PROJECT MANAGEMENT
it is found that the use of agile methodology is quite useful in finishing the entire project
faster as compared to the time that is expected earlier.
4. Manual planning
4.1 Project calendar
Project start date: The initial or starting date of the project will be around 18-06-18
Project end date: The end date of the project will be on 01-03-2019.
Weekends: Saturday as well as Sundays are weekends and considered as holiday for all the
employees.
Public holiday list: The list of public holidays is listed in the table that is provided below:
Monday 11th June Queen’s birthday
Monday 1st October Labour day
Tuesday 25th December Christmas Day
Wednesday 26 December Boxing day
4.2 WBS, OBS, and RAM
Work breakdown Structure (WBS)
Work breakdown structure is one of the deliverable related breakdown of project
activities into key deliverables that generally assists in organizing the entire work or activities
of the team that is required to be performed for successful completion of the project into
number of manageable sections. The WBS for the project is provided in the table below:
WBS Task Name
0
Development of new information technology
centre
PROJECT MANAGEMENT
it is found that the use of agile methodology is quite useful in finishing the entire project
faster as compared to the time that is expected earlier.
4. Manual planning
4.1 Project calendar
Project start date: The initial or starting date of the project will be around 18-06-18
Project end date: The end date of the project will be on 01-03-2019.
Weekends: Saturday as well as Sundays are weekends and considered as holiday for all the
employees.
Public holiday list: The list of public holidays is listed in the table that is provided below:
Monday 11th June Queen’s birthday
Monday 1st October Labour day
Tuesday 25th December Christmas Day
Wednesday 26 December Boxing day
4.2 WBS, OBS, and RAM
Work breakdown Structure (WBS)
Work breakdown structure is one of the deliverable related breakdown of project
activities into key deliverables that generally assists in organizing the entire work or activities
of the team that is required to be performed for successful completion of the project into
number of manageable sections. The WBS for the project is provided in the table below:
WBS Task Name
0
Development of new information technology
centre
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4
PROJECT MANAGEMENT
1 Initiation phase
1.1 Project needs analysis
1.2 Project plan development
1.3 Feasibility analysis
1.4
Milestone 1: Completion of initiation
phase
2 Planning phase
2.1 Project task scheduling
2.2 Estimation of project resources
2.3 Allocation of resources
2.4 Communication plan development
2.5 Project team allocation
2.6
Milestone 2: Completion of planning
phase
3 Designing phase
3.1 Blueprint creation
3.2 Assigning IT needs
3.3 Necessary equipment purchase
3.4 Recruitment of development team
3.5
Milestone 3: Completion of designing
phase
4 Development phase
4.1 Assigning new hardware
4.2 Assigning software requirements
PROJECT MANAGEMENT
1 Initiation phase
1.1 Project needs analysis
1.2 Project plan development
1.3 Feasibility analysis
1.4
Milestone 1: Completion of initiation
phase
2 Planning phase
2.1 Project task scheduling
2.2 Estimation of project resources
2.3 Allocation of resources
2.4 Communication plan development
2.5 Project team allocation
2.6
Milestone 2: Completion of planning
phase
3 Designing phase
3.1 Blueprint creation
3.2 Assigning IT needs
3.3 Necessary equipment purchase
3.4 Recruitment of development team
3.5
Milestone 3: Completion of designing
phase
4 Development phase
4.1 Assigning new hardware
4.2 Assigning software requirements
5
PROJECT MANAGEMENT
4.3 Data warehouse development
4.4 Network system development
4.5 Application of security system
4.6 Creating connection between the systems
4.7
Milestone 4: Completion of development
phase
5 Testing phase
5.1 Hardware testing
5.2 Software testing
5.3 Testing of data warehouse
5.4 Milestone 5: Completion of testing phase
6 Closure phase
6.1 Reviewing project
6.2 Sign off
6.3 Data warehouse maintenance
6.4 Milestone 6: Completion of closure phase'
Organizational breakdown structure (OBS)
Organizational breakdown structure is one of the model of hierarchy that assists in
illustrating the entire framework of the organization to plan resources as well as for managing
the time and cost that is associated with the project. The organizational structure for the
project “development of new information technology centre” is provided below:
PROJECT MANAGEMENT
4.3 Data warehouse development
4.4 Network system development
4.5 Application of security system
4.6 Creating connection between the systems
4.7
Milestone 4: Completion of development
phase
5 Testing phase
5.1 Hardware testing
5.2 Software testing
5.3 Testing of data warehouse
5.4 Milestone 5: Completion of testing phase
6 Closure phase
6.1 Reviewing project
6.2 Sign off
6.3 Data warehouse maintenance
6.4 Milestone 6: Completion of closure phase'
Organizational breakdown structure (OBS)
Organizational breakdown structure is one of the model of hierarchy that assists in
illustrating the entire framework of the organization to plan resources as well as for managing
the time and cost that is associated with the project. The organizational structure for the
project “development of new information technology centre” is provided below:
6
PROJECT MANAGEMENT
Figure 1: OBS
(Source: Created by Author)
Responsibility assignment matrix
Responsibility assignment matrix is considered as one of the key component that
assists in finishing the entire project successfully. It assists in identifying the role of each of
the persons who are involved within the project and for what they are accountable within the
project. The RACI stands for responsibility, accountability, consulted and responsible.
Project
manager
Sponsor Contractor Designer Tester Financial
managers
Supervisor
Project needs
analysis
A, R I C
PROJECT MANAGEMENT
Figure 1: OBS
(Source: Created by Author)
Responsibility assignment matrix
Responsibility assignment matrix is considered as one of the key component that
assists in finishing the entire project successfully. It assists in identifying the role of each of
the persons who are involved within the project and for what they are accountable within the
project. The RACI stands for responsibility, accountability, consulted and responsible.
Project
manager
Sponsor Contractor Designer Tester Financial
managers
Supervisor
Project needs
analysis
A, R I C
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7
PROJECT MANAGEMENT
Project plan
development
A, R I C
Feasibility
analysis
I C A, R
Project task
scheduling
A, R I C
Estimation of
project resources
I C A, R
Allocation of
resources
I C A, R
Communicati
on plan
development
A, R I C
Project team
allocation
A, R I C
Blueprint
creation
C I R, A
Assigning IT
needs
Necessary
equipment
purchase
C I R, A
Recruitment
of development
team
C I R, A
PROJECT MANAGEMENT
Project plan
development
A, R I C
Feasibility
analysis
I C A, R
Project task
scheduling
A, R I C
Estimation of
project resources
I C A, R
Allocation of
resources
I C A, R
Communicati
on plan
development
A, R I C
Project team
allocation
A, R I C
Blueprint
creation
C I R, A
Assigning IT
needs
Necessary
equipment
purchase
C I R, A
Recruitment
of development
team
C I R, A
8
PROJECT MANAGEMENT
Assigning
new hardware
C I R, A
Assigning
software
requirements
C I R, A
Data
warehouse
development
C I R, A
Network
system
development
C I R, A
Application
of security
system
C I R, A
Creating
connection
between the
systems
C I R, A
Hardware
testing
I A, R C
Software
testing
I A, R C
Testing of
data warehouse
I A, R C
Reviewing
project
A, R I C
PROJECT MANAGEMENT
Assigning
new hardware
C I R, A
Assigning
software
requirements
C I R, A
Data
warehouse
development
C I R, A
Network
system
development
C I R, A
Application
of security
system
C I R, A
Creating
connection
between the
systems
C I R, A
Hardware
testing
I A, R C
Software
testing
I A, R C
Testing of
data warehouse
I A, R C
Reviewing
project
A, R I C
9
PROJECT MANAGEMENT
Sign off A, R I C
Data
warehouse
maintenance
A, R I C
4.3 Lists of tasks, durations and their logical relationships
The tasks, durations as well as their logical relationships is reflected in the table that is
provided below:
Task Name Duration Start Finish Predecessors
Development of new information
technology centre
182 days Mon 18-06-18
Fri 01-
03-19
Initiation phase 10 days Mon 18-06-18
Fri 29-
06-18
Project needs analysis 7 days Mon 18-06-18
Tue 26-
06-18
Project plan development 5 days Tue 19-06-18
Wed 27-
06-18
2
Feasibility analysis 4 days Mon 25-06-18
Thu 28-
06-18
3
Milestone 1: Completion of
initiation phase
0 days Fri 29-06-18
Fri 29-06-
18
4
Planning phase 38 days Mon 02-07-18
Wed 22-
08-18
Project task scheduling 3 days Mon 02-07-18
Wed 04-
07-18
4
PROJECT MANAGEMENT
Sign off A, R I C
Data
warehouse
maintenance
A, R I C
4.3 Lists of tasks, durations and their logical relationships
The tasks, durations as well as their logical relationships is reflected in the table that is
provided below:
Task Name Duration Start Finish Predecessors
Development of new information
technology centre
182 days Mon 18-06-18
Fri 01-
03-19
Initiation phase 10 days Mon 18-06-18
Fri 29-
06-18
Project needs analysis 7 days Mon 18-06-18
Tue 26-
06-18
Project plan development 5 days Tue 19-06-18
Wed 27-
06-18
2
Feasibility analysis 4 days Mon 25-06-18
Thu 28-
06-18
3
Milestone 1: Completion of
initiation phase
0 days Fri 29-06-18
Fri 29-06-
18
4
Planning phase 38 days Mon 02-07-18
Wed 22-
08-18
Project task scheduling 3 days Mon 02-07-18
Wed 04-
07-18
4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10
PROJECT MANAGEMENT
Estimation of project resources 5 days Fri 06-07-18
Thu 12-
07-18
7
Allocation of resources 8 days Mon 16-07-18
Wed 25-
07-18
8
Communication plan development 9 days Fri 27-07-18
Wed 08-
08-18
9
Project team allocation 10 days Thu 09-08-18
Wed 22-
08-18
10
Milestone 2: Completion of
planning phase
0 days Tue 21-08-18
Tue 21-
08-18
11
Designing phase 40 days Wed 22-08-18
Wed 17-
10-18
Blueprint creation 8 days Wed 22-08-18
Fri 31-08-
18
11
Assigning IT needs 7 days Fri 31-08-18
Mon 10-
09-18
14
Necessary equipment purchase 7 days Mon 10-09-18
Tue 18-
09-18
15
Recruitment of development team 20 days Wed 19-09-18
Wed 17-
10-18
16
Milestone 3: Completion of
designing phase
0 days Wed 17-10-18
Wed 17-
10-18
17
Development phase 62 days Thu 18-10-18
Tue 15-
01-19
PROJECT MANAGEMENT
Estimation of project resources 5 days Fri 06-07-18
Thu 12-
07-18
7
Allocation of resources 8 days Mon 16-07-18
Wed 25-
07-18
8
Communication plan development 9 days Fri 27-07-18
Wed 08-
08-18
9
Project team allocation 10 days Thu 09-08-18
Wed 22-
08-18
10
Milestone 2: Completion of
planning phase
0 days Tue 21-08-18
Tue 21-
08-18
11
Designing phase 40 days Wed 22-08-18
Wed 17-
10-18
Blueprint creation 8 days Wed 22-08-18
Fri 31-08-
18
11
Assigning IT needs 7 days Fri 31-08-18
Mon 10-
09-18
14
Necessary equipment purchase 7 days Mon 10-09-18
Tue 18-
09-18
15
Recruitment of development team 20 days Wed 19-09-18
Wed 17-
10-18
16
Milestone 3: Completion of
designing phase
0 days Wed 17-10-18
Wed 17-
10-18
17
Development phase 62 days Thu 18-10-18
Tue 15-
01-19
11
PROJECT MANAGEMENT
Assigning new hardware 7 days Thu 18-10-18
Fri 26-10-
18
17
Assigning software requirements 8 days Mon 29-10-18
Wed 07-
11-18
20
Data warehouse development 22 days Thu 08-11-18
Fri 07-12-
18
21
Network system development 9 days Thu 06-12-18
Tue 18-
12-18
22
Application of security system 9 days Thu 20-12-18
Thu 03-
01-19
23
Creating connection between the
systems
8 days Fri 04-01-19
Tue 15-
01-19
24
Milestone 4: Completion of
development phase
0 days Tue 15-01-19
Tue 15-
01-19
25
Testing phase 23 days Wed 16-01-19
Fri 15-
02-19
Hardware testing 8 days Wed 16-01-19
Fri 25-01-
19
25
Software testing 8 days Mon 28-01-19
Wed 06-
02-19
28
Testing of data warehouse 7 days Thu 07-02-19
Fri 15-02-
19
29
Milestone 5: Completion of
testing phase
0 days Fri 15-02-19
Fri 15-02-
19
30
PROJECT MANAGEMENT
Assigning new hardware 7 days Thu 18-10-18
Fri 26-10-
18
17
Assigning software requirements 8 days Mon 29-10-18
Wed 07-
11-18
20
Data warehouse development 22 days Thu 08-11-18
Fri 07-12-
18
21
Network system development 9 days Thu 06-12-18
Tue 18-
12-18
22
Application of security system 9 days Thu 20-12-18
Thu 03-
01-19
23
Creating connection between the
systems
8 days Fri 04-01-19
Tue 15-
01-19
24
Milestone 4: Completion of
development phase
0 days Tue 15-01-19
Tue 15-
01-19
25
Testing phase 23 days Wed 16-01-19
Fri 15-
02-19
Hardware testing 8 days Wed 16-01-19
Fri 25-01-
19
25
Software testing 8 days Mon 28-01-19
Wed 06-
02-19
28
Testing of data warehouse 7 days Thu 07-02-19
Fri 15-02-
19
29
Milestone 5: Completion of
testing phase
0 days Fri 15-02-19
Fri 15-02-
19
30
12
PROJECT MANAGEMENT
Closure phase 10 days Mon 18-02-19
Fri 01-
03-19
Reviewing project 3 days Mon 18-02-19
Wed 20-
02-19
30
Sign off 3 days Thu 21-02-19
Mon 25-
02-19
33
Data warehouse maintenance 4 days Tue 26-02-19
Fri 01-03-
19
34
Milestone 6: Completion of
closure phase'
0 days Fri 01-03-19
Fri 01-03-
19
35
4.4 Execution programme
The entire execution programme for the development of the IT centre is provided in
the table that is provided below:
WBS Task Name Duration
3 Designing phase 40 days
3.1 Blueprint creation 8 days
3.2 Assigning IT needs 7 days
3.3 Necessary equipment’s purchase 7 days
3.4 Recruitment of development team 20 days
3.5
Milestone 3: Completion of
designing phase
0 days
4 Development phase 62 days
4.1 Assigning new hardware 7 days
PROJECT MANAGEMENT
Closure phase 10 days Mon 18-02-19
Fri 01-
03-19
Reviewing project 3 days Mon 18-02-19
Wed 20-
02-19
30
Sign off 3 days Thu 21-02-19
Mon 25-
02-19
33
Data warehouse maintenance 4 days Tue 26-02-19
Fri 01-03-
19
34
Milestone 6: Completion of
closure phase'
0 days Fri 01-03-19
Fri 01-03-
19
35
4.4 Execution programme
The entire execution programme for the development of the IT centre is provided in
the table that is provided below:
WBS Task Name Duration
3 Designing phase 40 days
3.1 Blueprint creation 8 days
3.2 Assigning IT needs 7 days
3.3 Necessary equipment’s purchase 7 days
3.4 Recruitment of development team 20 days
3.5
Milestone 3: Completion of
designing phase
0 days
4 Development phase 62 days
4.1 Assigning new hardware 7 days
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13
PROJECT MANAGEMENT
4.2 Assigning software requirements 8 days
4.3 Data warehouse development 22 days
4.4 Network system development 9 days
4.5 Application of security system 9 days
4.6
Creating connection between the
systems
8 days
4.7
Milestone 4: Completion of
development phase
0 days
5 Testing phase 23 days
5.1 Hardware testing 8 days
5.2 Software testing 8 days
5.3 Testing of data warehouse 7 days
5.4
Milestone 5: Completion of
testing phase
0 days
4.5 Sub-contractors and required labour schedule
The sub-contractors as well as needed schedule of the labours are provided in the
table below:
Name Start Finish Remaining Work
Project Manager Mon 18-06-18 Fri 01-03-19 152 hrs.
Project Sponsor Mon 18-02-19 Wed 20-02-19 24 hrs.
Contractor Mon 02-07-18 Fri 07-12-18 16 hrs.
PROJECT MANAGEMENT
4.2 Assigning software requirements 8 days
4.3 Data warehouse development 22 days
4.4 Network system development 9 days
4.5 Application of security system 9 days
4.6
Creating connection between the
systems
8 days
4.7
Milestone 4: Completion of
development phase
0 days
5 Testing phase 23 days
5.1 Hardware testing 8 days
5.2 Software testing 8 days
5.3 Testing of data warehouse 7 days
5.4
Milestone 5: Completion of
testing phase
0 days
4.5 Sub-contractors and required labour schedule
The sub-contractors as well as needed schedule of the labours are provided in the
table below:
Name Start Finish Remaining Work
Project Manager Mon 18-06-18 Fri 01-03-19 152 hrs.
Project Sponsor Mon 18-02-19 Wed 20-02-19 24 hrs.
Contractor Mon 02-07-18 Fri 07-12-18 16 hrs.
14
PROJECT MANAGEMENT
Risk Manager Mon 28-01-19 Fri 15-02-19 120 hrs.
Designer Mon 25-06-18 Fri 15-02-19 192 hrs.
Tester Mon 25-06-18 Fri 15-02-19 176 hrs.
Business Consultant Thu 20-12-18 Mon 25-02-19 80 hrs.
Financial Manager Fri 06-07-18 Fri 07-12-18 16 hrs.
Team Leaders Mon 16-07-18 Mon 10-09-18 16 hrs.
Supervisor Mon 16-07-18 Wed 25-07-18 0 hrs.
4.6 Bill of quantities and cost estimation
The bill of quantities and cost estimation as per the WBS is provided in the table
below:
WBS Task Name Duration Cost
0
Development of new information
technology centre
182 days $39,395,200.00
1 Initiation phase 10 days $36,800.00
1.1 Project needs analysis 7 days $14,000.00
1.2 Project plan development 5 days $10,000.00
1.3 Feasibility analysis 4 days $12,800.00
1.4
Milestone 1: Completion of
initiation phase
0 days $0.00
2 Planning phase 38 days $73,360.00
2.1 Project task scheduling 3 days $5,040.00
PROJECT MANAGEMENT
Risk Manager Mon 28-01-19 Fri 15-02-19 120 hrs.
Designer Mon 25-06-18 Fri 15-02-19 192 hrs.
Tester Mon 25-06-18 Fri 15-02-19 176 hrs.
Business Consultant Thu 20-12-18 Mon 25-02-19 80 hrs.
Financial Manager Fri 06-07-18 Fri 07-12-18 16 hrs.
Team Leaders Mon 16-07-18 Mon 10-09-18 16 hrs.
Supervisor Mon 16-07-18 Wed 25-07-18 0 hrs.
4.6 Bill of quantities and cost estimation
The bill of quantities and cost estimation as per the WBS is provided in the table
below:
WBS Task Name Duration Cost
0
Development of new information
technology centre
182 days $39,395,200.00
1 Initiation phase 10 days $36,800.00
1.1 Project needs analysis 7 days $14,000.00
1.2 Project plan development 5 days $10,000.00
1.3 Feasibility analysis 4 days $12,800.00
1.4
Milestone 1: Completion of
initiation phase
0 days $0.00
2 Planning phase 38 days $73,360.00
2.1 Project task scheduling 3 days $5,040.00
15
PROJECT MANAGEMENT
2.2 Estimation of project resources 5 days $6,800.00
2.3 Allocation of resources 8 days $19,200.00
2.4
Communication plan
development
9 days $29,520.00
2.5 Project team allocation 10 days $12,800.00
2.6
Milestone 2: Completion of
planning phase
0 days $0.00
3 Designing phase 40 days $58,480.00
3.1 Blueprint creation 8 days $12,800.00
3.2 Assigning IT needs 7 days $8,960.00
3.3
Necessary equipment’s
purchase
7 days $9,520.00
3.4
Recruitment of development
team
20 days $27,200.00
3.5
Milestone 3: Completion of
designing phase
0 days $0.00
4 Development phase 62 days $27,110,240.00
4.1 Assigning new hardware 7 days $8,000,000.00
4.2
Assigning software
requirements
8 days $7,000,000.00
4.3 Data warehouse development 22 days $66,880.00
4.4 Network system development 9 days $12,000,000.00
4.5 Application of security system 9 days $27,360.00
PROJECT MANAGEMENT
2.2 Estimation of project resources 5 days $6,800.00
2.3 Allocation of resources 8 days $19,200.00
2.4
Communication plan
development
9 days $29,520.00
2.5 Project team allocation 10 days $12,800.00
2.6
Milestone 2: Completion of
planning phase
0 days $0.00
3 Designing phase 40 days $58,480.00
3.1 Blueprint creation 8 days $12,800.00
3.2 Assigning IT needs 7 days $8,960.00
3.3
Necessary equipment’s
purchase
7 days $9,520.00
3.4
Recruitment of development
team
20 days $27,200.00
3.5
Milestone 3: Completion of
designing phase
0 days $0.00
4 Development phase 62 days $27,110,240.00
4.1 Assigning new hardware 7 days $8,000,000.00
4.2
Assigning software
requirements
8 days $7,000,000.00
4.3 Data warehouse development 22 days $66,880.00
4.4 Network system development 9 days $12,000,000.00
4.5 Application of security system 9 days $27,360.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16
PROJECT MANAGEMENT
4.6
Creating connection between
the systems
8 days $16,000.00
4.7
Milestone 4: Completion of
development phase
0 days $0.00
5 Testing phase 23 days $12,087,200.00
5.1 Hardware testing 8 days $12,012,800.00
5.2 Software testing 8 days $39,680.00
5.3 Testing of data warehouse 7 days $34,720.00
5.4
Milestone 5: Completion of
testing phase
0 days $0.00
6 Closure phase 10 days $29,120.00
6.1 Reviewing project 3 days $10,800.00
6.2 Sign off 3 days $10,320.00
6.3 Data warehouse maintenance 4 days $8,000.00
6.4
Milestone 6: Completion of
closure phase'
0 days $0.00
4.7 Risk register
Risk Description Impact Probability Mitigation
measures
Inappropriate
estimation of
budget
It is identified
that due to
inappropriate
High High It is very much
necessary to
utilized earned
PROJECT MANAGEMENT
4.6
Creating connection between
the systems
8 days $16,000.00
4.7
Milestone 4: Completion of
development phase
0 days $0.00
5 Testing phase 23 days $12,087,200.00
5.1 Hardware testing 8 days $12,012,800.00
5.2 Software testing 8 days $39,680.00
5.3 Testing of data warehouse 7 days $34,720.00
5.4
Milestone 5: Completion of
testing phase
0 days $0.00
6 Closure phase 10 days $29,120.00
6.1 Reviewing project 3 days $10,800.00
6.2 Sign off 3 days $10,320.00
6.3 Data warehouse maintenance 4 days $8,000.00
6.4
Milestone 6: Completion of
closure phase'
0 days $0.00
4.7 Risk register
Risk Description Impact Probability Mitigation
measures
Inappropriate
estimation of
budget
It is identified
that due to
inappropriate
High High It is very much
necessary to
utilized earned
17
PROJECT MANAGEMENT
budget estimate
it is very much
difficult to
finish the entire
project
successfully.
value analysis
in order to track
the budget
successfully.
Lack of proper
resources
Due to
inappropriate
resources within
the project, it is
very much
difficult to
complete the
development of
the IT centre
within the
expected time
and budget.
High Medium It is very much
necessary to
analyze the
resources
properly for the
project.
Inappropriate
management
Due to
inappropriate
management of
project it is
quite tough to
finish the entire
project within
Medium Medium It is very much
necessary to
utilize proper
management
strategies for
managing the
project
PROJECT MANAGEMENT
budget estimate
it is very much
difficult to
finish the entire
project
successfully.
value analysis
in order to track
the budget
successfully.
Lack of proper
resources
Due to
inappropriate
resources within
the project, it is
very much
difficult to
complete the
development of
the IT centre
within the
expected time
and budget.
High Medium It is very much
necessary to
analyze the
resources
properly for the
project.
Inappropriate
management
Due to
inappropriate
management of
project it is
quite tough to
finish the entire
project within
Medium Medium It is very much
necessary to
utilize proper
management
strategies for
managing the
project
18
PROJECT MANAGEMENT
the expected
budget and time
effectively.
Technical
issues
The technical
problem that
occurs due to
inappropriate
connection as
well as
problems in
data warehouse
causes lot of
challenges for
the project
manager.
High High It is necessary
to undertake
testing after the
development
phase of the
project.
Lack of
experience
Due to lack of
proper
experience, it is
very much
difficult for the
project manager
to properly
finish the
project
Medium Medium It is quite
necessary to
hire workers for
the project who
are very much
experienced for
avoiding such
issues.
PROJECT MANAGEMENT
the expected
budget and time
effectively.
Technical
issues
The technical
problem that
occurs due to
inappropriate
connection as
well as
problems in
data warehouse
causes lot of
challenges for
the project
manager.
High High It is necessary
to undertake
testing after the
development
phase of the
project.
Lack of
experience
Due to lack of
proper
experience, it is
very much
difficult for the
project manager
to properly
finish the
project
Medium Medium It is quite
necessary to
hire workers for
the project who
are very much
experienced for
avoiding such
issues.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19
PROJECT MANAGEMENT
5. Computerized planning
5.1 Lists of tasks and WBS
Figure 2: Lists of tasks and schedule
(Source: Created by Author)
PROJECT MANAGEMENT
5. Computerized planning
5.1 Lists of tasks and WBS
Figure 2: Lists of tasks and schedule
(Source: Created by Author)
20
PROJECT MANAGEMENT
5.2 Project calendar
Figure 3: Project calendar
(Source: Created by Author)
PROJECT MANAGEMENT
5.2 Project calendar
Figure 3: Project calendar
(Source: Created by Author)
21
PROJECT MANAGEMENT
5.3 PDM diagram and Gantt chart
PDM diagram
PROJECT MANAGEMENT
5.3 PDM diagram and Gantt chart
PDM diagram
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
22
PROJECT MANAGEMENT
Gantt chart
Figure 5: Gantt chart
(Source: Created by Author)
PROJECT MANAGEMENT
Gantt chart
Figure 5: Gantt chart
(Source: Created by Author)
23
PROJECT MANAGEMENT
5.4 Lists and cost of resources
Figure 6: Resource cost
(Source: Created by Author)
PROJECT MANAGEMENT
5.4 Lists and cost of resources
Figure 6: Resource cost
(Source: Created by Author)
24
PROJECT MANAGEMENT
5.5 Cost and detail budget
Figure 6: Detailed budget
(Source: Created by Author)
PROJECT MANAGEMENT
5.5 Cost and detail budget
Figure 6: Detailed budget
(Source: Created by Author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
25
PROJECT MANAGEMENT
5.6 Resource schedule
Figure 6: Resource schedule
(Source: Created by Author)
PROJECT MANAGEMENT
5.6 Resource schedule
Figure 6: Resource schedule
(Source: Created by Author)
26
PROJECT MANAGEMENT
5.7 S-curve
2016 2017 2018 2019
Development of new information technology centre
0
200
400
600
800
1000
1200
1400
S-CURVE
Cumulative Actual Work
Work
Figure 7: S curve
(Source: Created by Author)
PROJECT MANAGEMENT
5.7 S-curve
2016 2017 2018 2019
Development of new information technology centre
0
200
400
600
800
1000
1200
1400
S-CURVE
Cumulative Actual Work
Work
Figure 7: S curve
(Source: Created by Author)
27
PROJECT MANAGEMENT
5.8 Histogram for resources
Project Manager
Project Sponsor
Contractor
Risk Manager
Designer
Tester
Business Consultant
Finacial Manager
Team Leaders
Supervisor
0%
20%
40%
60%
80%
100%
120%
% Work Complete
Figure 8: Resource Histogram
(Source: Created by Author)
5. 9 Relevant report for supporting PEP
Project Manager
Project Sponsor
Contractor
Risk Manager
Designer
Tester
Business Consultant
Finacial Manager
Team Leaders
Supervisor
0 hrs
100 hrs
200 hrs
300 hrs
400 hrs
500 hrs
Actual Work Remaining Work
Baseline Work
Figure 8: Resource cost overview
(Source: Created by Author)
PROJECT MANAGEMENT
5.8 Histogram for resources
Project Manager
Project Sponsor
Contractor
Risk Manager
Designer
Tester
Business Consultant
Finacial Manager
Team Leaders
Supervisor
0%
20%
40%
60%
80%
100%
120%
% Work Complete
Figure 8: Resource Histogram
(Source: Created by Author)
5. 9 Relevant report for supporting PEP
Project Manager
Project Sponsor
Contractor
Risk Manager
Designer
Tester
Business Consultant
Finacial Manager
Team Leaders
Supervisor
0 hrs
100 hrs
200 hrs
300 hrs
400 hrs
500 hrs
Actual Work Remaining Work
Baseline Work
Figure 8: Resource cost overview
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
28
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Conforto, E.C., Salum, F., Amaral, D.C., da Silva, S.L. and de Almeida, L.F.M., 2014. Can
agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), pp.21-34.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology
and project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Kucharska, W. and Kowalczyk, R., 2016. Trust, Collaborative Culture and Tacit Knowledge
Sharing in Project Management–a Relationship Model.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Conforto, E.C., Salum, F., Amaral, D.C., da Silva, S.L. and de Almeida, L.F.M., 2014. Can
agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), pp.21-34.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology
and project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Kucharska, W. and Kowalczyk, R., 2016. Trust, Collaborative Culture and Tacit Knowledge
Sharing in Project Management–a Relationship Model.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
29
PROJECT MANAGEMENT
Sánchez, M.A., 2015. Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, pp.319-330.roject Management, 33(4), pp.772-783.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of P
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
PROJECT MANAGEMENT
Sánchez, M.A., 2015. Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, pp.319-330.roject Management, 33(4), pp.772-783.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of P
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
1 out of 30
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.