Running head:IT Project Management1 IT Project Management [Author Name(s), First M. Last, Omit Titles and Degrees] [Institutional Affiliation(s)] Author Note [Include any grant/funding information and a complete correspondence address.]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Running head:IT Project Management2 EXECUTIVESUMMARY The project plan under critique is for the application development if Sovereign Hill App, which shall be the main focus of this report. Typically, the plan has a detailed approach that shall be used to plan and execute the development of the Sovereign app which is envisioned to be a cutting edge application that shall run on both Android and Ios making visitor plan for their trip in prior before embarking on the journey. The initial phase involves the plan on how the project shall be executed. A critical analysis of the plan of the project management has been detailed in this report with the key recommendation given focused on addressing the key issues raised by this critique. It is typical of the project manager to use the various modern software project management toolkits to give some high-level simulations before a commitment of resources for the project is committed.
Running head:IT Project Management3 TABLEOFCONTENTS Executive summary.....................................................................................................................................2 1Introduction.........................................................................................................................................4 2CRITICAL ANALYSIS OF PMP.................................................................................................................4 2.1Introduction.................................................................................................................................4 2.2Organization................................................................................................................................4 2.2.1Name...................................................................................................................................4 2.2.2Description...........................................................................................................................5 2.2.3Sponsor’s Details..................................................................................................................6 2.2.4Project manager and details of team...................................................................................7 2.3Management and Technical Approach........................................................................................7 2.3.1Deliverables.........................................................................................................................7 2.3.2Documentation....................................................................................................................7 2.3.3Details of References...........................................................................................................8 2.3.4Definitions............................................................................................................................8 2.3.5Project responsibilities.........................................................................................................8 2.3.6Management and the technical processes..........................................................................9 2.3.7Management objectives......................................................................................................9 2.3.8Project controls..................................................................................................................10 2.3.9Risk management..............................................................................................................11 2.4Work To Perform.......................................................................................................................11 2.4.1Work breakdown structure................................................................................................11 2.5Schedule....................................................................................................................................14 2.6Budget.......................................................................................................................................15 3Conclusion.........................................................................................................................................15 4Recommendation..............................................................................................................................16 References.................................................................................................................................................16
Running head:IT Project Management4 1INTRODUCTION Any project requires a comprehensive project management plan to ensure the project start and ends within the stipulated time and within the budget. The current PMP to be critiqued shall be focused on the areas of project scope, the project sponsors and any other key PMP components that the analysts deemed important to dig deep into. The documents are structured into sections with the first sections describes the project whose PMP is under criticism. The second section is the actual criticism where key components of the PMP is looked deeply for flaws which are highlighted. The last section details some of the key recommendations to the project manager based on the issues highlighted by the critique. These recommendations are critical for the correction of the issues raised by the critique 2CRITICAL ANALYSIS OF PMP 2.1INTRODUCTION The following components detailed in the subsequent sections details the various components that formed part of the critique 2.2ORGANIZATION 2.2.1Name Every project starts with a good name hence it is very critical to come up with a name that users can instantly relate to and gives the descriptive information of the whole project. After a thorough evaluation of the project name “Sovereign Hill App”, the critique has finds the name no to reflect on any of the actual designations of the project. One is left to wonder what the Hill App is all about since the name is somehow confusing and has nothing to do with travel.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Running head:IT Project Management5 A more interesting title could have been “Crossing Sovereignties App’, this title not only provides information that actually relates to traveling across different sovereignty but also provides critical information about the project under development and to some extent provides a purpose for which the project is to be done(Furlong & Al-Karaghouli, 2010). 2.2.2Description The description of the project answerers the “why” and the “how” the project shall be implemented. The PMP has failed the benchmark for a complete project description as it has not covered the way the project timeline and key milestones which are somehow specific for each PMP documentation. The project management plan has not provided any estimation of the budgets. The only part the project description has scored is the clear and simple language the project management plan has used in describing the project. A sample project charter is as shown below
Running head:IT Project Management6 2.2.3Sponsor’s Details The project sponsor forms key project stakeholder as it is the sponsor who commits most of the resources for the given project. It is therefore vital for the details of the project sponsor to more detailed in the project management document. A thorough analysis of the project management plan has revealed it has the sponsor’s telephone contacts, the sponsor’s email address contacts, and the complete name of the sponsor. It is however noted that the project management plan has not provided secondary emergency contact that can be used to reach out to the project sponsor in
Running head:IT Project Management7 an event the primary contacts faile and the sponsor is critically required to be contacted especially in an emergency(Talley Jared L., Schneider Jen, & Lindquist Eric, 2016). 2.2.4Project manager and details of team A good project team set up should have a reflection on the hierarchy of the associated roles and responsibilities of each of the members of the project team. The project management plan under critique does not provide such a hierarchy of team members in terms of roles and responsibilities. The project management plan has only provided the contact details of the team members with no mechanism to know the roles and responsibilities that each member of the team shall do with relation to their skillset. 2.3MANAGEMENTANDTECHNICALAPPROACH 2.3.1Deliverables The project management plan under scrutiny has provided a means to classify deliverables based on the milestones achieved in the implementation strategies of the project. Each of the phrases that are successfully completed is what forms the deliverables. It is, however, important to note that, although keenness has been done in trying to identify and provide documentation of the deliverables, there is no proper framework in place to have the deliverables in terms of resources requires to achieve such deliverables. 2.3.2Documentation Documentation is a critical project management plan component. After thorough scrutiny of the project management plan, the document, contrary to the expectation has indicated rather a
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Running head:IT Project Management8 deficiency in the details on how the project configurations and the complete source code are not protected by necessary copyright laws and any special permissions under which the code can be altered based on business or legal requirements. Protection of the source code is critical in any project management plan hence no loose ends should be left out in the vendor-client relationships 2.3.3Details of References It is always a best practice to have a reference section that details the project management plan. The details in the references section should be accompanied by details of the project section or deliverable which can be used by the team for accurate implementation of the project and future maintenance practices. The project management plan under scrutiny has failed to provide technical references section for the team member making errors prone in the execution of the project. 2.3.4Definitions The definitions indicate the detailed meaning or the implied name. The project management plan under review clearly lacks any section set up for the definition of terms and should be urgently updated to meet the requirement. 2.3.5Project responsibilities A good project management plan should have a detailed portion of the roles and the responsibilities that are assigned to the team members. The best mechanisms to outline these roles and responsibilities is through the use of RAM(Responsibility Assignment Matrix). The standard procedure is having some tool to check the effects of the various reviews on the general progress of the project.
Running head:IT Project Management9 The document under scrutiny has a lot of confusion shall be experienced in the execution of the plan since there is no clear mechanism that the management can audit the progress of the work against any benchmarks established. Besides this, there is generally inefficient resource allocation which has the potential to affect the execution of the project deliverables. A more efficient means is to first have s detailed framework which details the assigned roles and responsibilities. 2.3.6Management and the technical processes The technical details of the various processes that are to be implemented by the project are key. Such details will form the basis of hiring the correct personnel for a given deliverable. Critical analysis of the project management plan shows rather shows that the project manager has not taken into account the key technical details of the various processes, This will raise issues with the implementation as risks related to software procurements, hardware procurement and any other technical components needed to deliver a given project deliverable may arise. The management of quality and the scope are critical components of the technical processes that must be taken keen of. 2.3.7Management objectives Most successful projects teams are always constituted under a good project leader and supportive management who are keen on the overall project objectives. The set objectives act as the guiding light during the whole life of the project. The objectives can be used by the team members to self evaluate their activities, track their project progress. Any deviations realized from the objectives shall be corrected earlier to make sure the project is always on track.
Running head:IT Project Management10 The project management plan under criticism has not set project progress objectives clearly enumerated to act as the guide for the team. Therefore, high chances of confusion during the execution of project deliverables are bound to happen with possible loss of track. It is therefore critical that the project manager addresses these important issues by ensuring the business requirements plans are set up and enumerates the key areas that the team needs to address immediately. 2.3.8Project controls It is critical for a project to have some level of controls, monitoring and evaluation since the project without controls tends to lose progress track, the resources get poorly allocated, deadlines are mostly missed and key milestones are severely missed which may result in the overall poor implementation of the project, worst case failure of the whole project. The project management plan under scrutiny has no mechanism to carefully track the project. There is a missing component of roles and responsibilities, a delegation of duties hierarchy which is key in driving the project to implementation. The plan lacks any strategic approach that the project manager can implement to address issues of quality assurance and quality control, quality management and how to review interactive processes periodically. Another rather key issues are the lack of a clear plan of how the complete project is to be handed over to the clients, the various benefits of the application, both short term and long terms. The project plan should at least document the various benefits that are accrued to the implementation of the project for the client.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Running head:IT Project Management11 2.3.9Risk management Every project has some level of uncertainties before, during and even after the implementation of the project. Nearly all the phrases of the project have some risks associated with it. It is, therefore, critical for the project manager to have some mechanisms in place to address project risks during the project lifecycle. A good project management plan should, therefore, include some mechanism to identify, assess, plan and make implementation and strategies to mitigate some of the risks envisioned. The project management plan under scrutiny lacks an essentials documentations on how the various risks are to be managed and the mechanisms to share the risks among the various project stakeholders. A good risks management plan should again detail of how the exit of a key stakeholder can affect the project execution. Contingency plans are therefore necessary to be in place to address this risk. Moreover, the document seems to lack the details of the various risks that the project is likely to phrase during the application development lifecycle. Some of the essential risks that the project manager should focus on includes, technical, financial, skills in a situation where the skilled project team leader dessert the project team or they falls sick, system functionality risks in case the developed software does not meet the various operational performance matrix 2.4WORKTOPERFORM 2.4.1Work breakdown structure The work breakdown structure details the various tasks and its related activities for each of the employees is one of the project management tools that a project manager can use to track the progress, allocate resources and demands, track project milestones. The document under review clearly lacks a means that the project manager can deploy to identify project milestones.
Running head:IT Project Management12 It is vital to ensure details about the work in incorporated into the work breakdown structure to indicate the various assigned tasks and key deliverables which is important for tracking to be done more effectively and efficiently. In conjunction with the work breakdown structures, the project plan should include some graphical tools that indicate the various approach taken in detailing the project activities. The various project dependencies should be included in these graphical tools to ensure task dependencies can be easily noted A sample workbreakdown structure is as shown below,
Running head:IT Project Management13
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Running head:IT Project Management14 2.5SCHEDULE The PMP being investigated doesn’t have a detailed approach used to assign the various project resources, there is no mention of the number of the available resources, no dependency between tasks details or even how the various activities shall be organized and ran. The responsibilities assigned for each individual is vague as no one is explicitly assigned roles. Moreover, the PMP does not provide a mechanism to show the overlap in activities and any critical activity that needs to be addressed in the entire lifetime of the project. It is recommended that the manager used software tools such as the Gantt chart which eases the process of accurately scheduling the various resources and assignment of tasks. Sample Gantt chart is as shown below
Running head:IT Project Management15 2.6BUDGET The PMP has failed to link between the various resource allocation to the various project costs and tasks. It is, however, important to note that the project has done well in detailing the allocation of resources including the employees salaries, software and hardware tools and the compensation schedule for each employee. It is, however, critical to note that the PMP has not established an ROI(Return on investment) on the completion of the Sovereign Hill App. It is recommended that the project manager establish using modern software tools in the general management of the planning to simulate the project success before the project is initiated 3CONCLUSION The criticism report of the project titles “Sovereign Hill App” initializes with the analysis of the product title and has made suggestion that the app should be renamed to “Crossing Sovereignties”. Typically, the project management plan under scrutiny clearly lacks some of the various critical elements of a successful project management plan. The highlights issues are of paramount importance in ensuring the project succeeds effectively. Key among them includes the lack of well-defined project charter that should be used to show the project roles and responsibilities for the various team members. The available work breakdown structure lacks mechanisms to clearly indicate what roles, duties, and responsibilities each of the team members are assigned to
Running head:IT Project Management16 4RECOMMENDATION It is vital for the project manager to come up with a more informative title for the project that relates to the project under development. The manager should utilize various tools to come up with better work breakdown structures, project risks management, and personnel management to effectively and efficiently manage the project. Last but not least, the project manager should beforehand identity and thorough plan laid out how to allocate these resources in the most prudent way to ensure project success. REFERENCES Furlong, S., & Al-Karaghouli, W. (2010). Delivering professional projectsThe effectiveness of project management in transformational e-government initiatives.Transforming Government,4(1), 73. Talley Jared L., Schneider Jen, & Lindquist Eric. (2016). A simplified approach to stakeholder engagement in natural resource management : the Five-Feature Framework.Ecology and Society,21(4).