Question 1
Linear programming for DEA (Sherman & Zhu, 2006) (Wang & Yang, 2007):
From the table below:
DMU A B C D E
INPUT X1 4 12 30 21 40
X2 8 6 5 6 24
OUTPUT Y 2 3 5 3 8
The following can be deducted:
LP for DMU-A
4 A +12 B+30 C+ 21 D+ 40E-4 s 08 A+6 B+5 C+ 6 D+ 24E-8 s 0 2 A +3 B+ 5C +3 D+8 E 2
LP for DMU-B
4 A +12 B+30 C+ 21 D+ 40E-12 s 08 A+6 B+5 C+ 6 D+ 24E-6 s 02 A +3 B+ 5C +3 D+8 E 3
LP for DMU-C
4 A +12 B+30 C+ 21 D+ 40E-30 s 08 A+6 B+5 C+ 6 D+ 24E-5 s 0 2 A +3 B+ 5C +3 D+8 E 5
LP for DMU-D
4 A +12 B+30 C+ 21 D+ 40E-21 s 08 A+6 B+5 C+ 6 D+ 24E-6 s 02 A +3 B+ 5C +3 D+8 E 3
LP for DMU-E
4 A +12 B+30 C+ 21 D+ 40E-40 s 0 8 A+6 B+5 C+ 6 D+ 24E-24 s 0 2 A +3 B+ 5C +3 D+8 E 8
Efficient levels of Inputs:
0.425 [12
6 ]+0.575 [40
24 ]=[ 28.1
16.35 ]
Efficient levels of Inputs
0.425 [ 3 ] +0.575 [ 8 ] =5.875
Linear Programming for DEA Assignment_1
Efficient of port A: 0.625
Efficient of port B: =0.625
Question 2: (Smartnote, 2012) (Usmani, 2014)
Possible path and Critical path (highlighted is the critical path)
Start ABEFinish=10 daysStart ACEFinish=8 days
Start ADFinish=10 days
Float time of all paths are:
Linear Programming for DEA Assignment_2

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
BNV6047 Project Management Assignment
|6
|1309
|304