Supervising Onsite Medium Rise Building and Construction Work

   

Added on  2023-06-13

21 Pages5445 Words181 Views
Supervise the planning
of onsite medium rise
building and
construction work
Supervising Onsite Medium Rise Building and Construction Work_1
Contents
ASSESSMENT TASK 1.................................................................................................................5
a) List the sequence of operation that will be needed for building the construction...................5
b) Prepare a contingency plan for overcoming the delays in project which can be caused by
bad weather..................................................................................................................................5
c) Create a network diagram and indicate the critical path.........................................................6
d) Review the dates of the schedule and prepare changes...........................................................8
e) Create the procedure for the operation of scheduling system.................................................8
ASSESSMENT TASK 2.................................................................................................................8
a) The requirement which are needed to complete the stage building works..............................8
b) Building the permit application form......................................................................................9
c) Notice for building from the residents of the neighbourhood by notifying them that the work
and the effect on them................................................................................................................10
d) Determine the problems which are associated with the building of work............................11
e) List the item that will be utilised by subcontractors and what stage it will be required........11
ASSESSMENT TASK 3...............................................................................................................12
a) Define the plans for the project, and communicate with them existing structures, vegetation
and neighbouring structures that will get impacted by the build...............................................12
b) Evaluate the location of such site plans for future references...............................................12
c) While consulting foreperson undertake at least 2 protection measures that can be used for
preventing damaging of neighbour properties during the project plan......................................12
d) With the help of meeting, prepare a report that must be issued to owners of neighbour
building including the important details such as protection measures agreed upon in meeting.
...................................................................................................................................................12
ASSESSMENT TASK 4...............................................................................................................13
a) OHS measure.........................................................................................................................13
Supervising Onsite Medium Rise Building and Construction Work_2
b) A process for managing hazardous material found on site...................................................13
c) Methods to be followed when transporting products onto and away from site that includes
payment records as well.............................................................................................................14
d) Guidelines for contract planning personnel to ensure effectiveness.....................................14
e) Explain at least 2 practices for improving efficiency and raising morale of staff.................14
f) Build at least 2 procedures for employees working on multiple projects at same point of
time............................................................................................................................................14
ASSESSMENT TASK 5...............................................................................................................15
a) Explain when and how support staff can get involved in the project....................................15
ASSESSMENT TASK 6...............................................................................................................17
1. Define subcontracting arrangement.......................................................................................17
2. List 6 factors that indicate someone is an independent contractor and not an employee......17
3. What are 4 general principles that apply to tendering?.........................................................17
4. What are 7 pieces of information that should be provided in any invitation to tender?........17
5. What are 2 licenses that are specific to the building and construction industry?..................18
6. There are 4 minimum safety requirements for the construction industry. List two of these
requirements..............................................................................................................................18
7. Employers are required to ensure that they have fall prevention measures on site for high
risk building work. List 6 methods an employer could use to reduce the risk of falling..........18
8. What is the difference between a Domestic Builder Unlimited (DB-U) license, and a
Domestic Builder Manager (DB-M) license?............................................................................18
9. Explain the term ‘payment claim’.........................................................................................19
10. List 2 pieces of information that a payment claim must state.............................................19
11. What are the two focuses in construction planning?...........................................................19
12. What is a work breakdown structure?.................................................................................19
Supervising Onsite Medium Rise Building and Construction Work_3
13. Once a building permit is issued, how long does the builder have to complete the building
works at that site?......................................................................................................................19
14. What is an occupancy permit?.............................................................................................19
REFERENCES..............................................................................................................................20
Supervising Onsite Medium Rise Building and Construction Work_4
ASSESSMENT TASK 1
a) List the sequence of operation that will be needed for building the construction.
Construction of a building is a process which is complete in parts to reach to a final result.
The major of construction are marking, concreting, excavation, brick masonry, flooring,
finishing and laying. Following are the steps used in construction of a building,
Paper work: A layout is prepared before starting the actual construction process.
Marking of Layout: A layout is marked by the engineer on the building is to constructed.
Excavation: It is carried out according to the drawing of the site, it is associated with the
construction of wall.
Foundation work: It is the basic foundation on which the whole building will be built.
Column Casting: It lays a foundation for the of walls and roof, it takes at least 24 hours to
settle.
Construction of walls: It is constructed with the bricks, precast, wooden and others
material as well.
Roofing: Roof slab is imposed on the base constructed in the earlier steps.
Plastering Work: form work is removed after 14 of pouring. After this only plaster work
starts.
Fixing of doors and windows: It has seen over the years that windows and doors are of
wood.
Tiles laying: Firstly, the walls tiles are fixed and then floor tiles are fixed. Material such
as granite, tiles, marble, epoxy are also used.
Painting: At last painting is done, after which it resembles the same picture as of in the
first step it designed.
b) Prepare a contingency plan for overcoming the delays in project which can be caused by bad
weather.
A contingency plan is made for recovering to the prospective problems that may occur during
the completion of the project. It is made to solve or control the high hampered risks that will
disrupt the operation of the project activities. In this, the risk that may occur and the solution
behind that is:
Particular Date
Supervising Onsite Medium Rise Building and Construction Work_5
Start Date 1/1/2021
End Date 9/10/2021
1. Breaking of machines: The probability of risk is high in the condition of bad weather,
components and elements of the machinery failure due to the inventory or maintenance
problems. The production measures need to be taken all around to escalate and solve the
issue faced in the machinery and a maintenance team should be organisation.
2. Outage of power: Mostly in the case of bad weather condition, the electricity fails which
creates a problem of power. So, for this the emergency power backups should be ready
for preventing the safety issues and any kind of casualties on the site.
3. Network outage: The risk probability is high and the network and system designed to
lead to failure in the condition of bad weather. So, the backup top the system and the files
should be made.
c) Create a network diagram and indicate the critical path.
Paper Work 7
Marking of Layout 5
Excavation 15
Foundation Work 70
Construction of walls 90
Lintel 20
Roofing 15
Plastering of work 20
Fixing of doors and windows 15
Electrical and plumbing work 10
Tiles work 10
Miscellaneous work 5
Supervising Onsite Medium Rise Building and Construction Work_6

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Measuring Tendering and Estimating for Construction and the Built Environment
|15
|4032
|271

Evaluate Contract Risk and Specialist Requirements for Tender Documentation Report
|6
|2047
|270

Project Management: Work Breakdown Schedule, Gantt Chart, Precedence Diagram
|11
|2678
|323

Built Environment Professional Practice (SRM750)
|35
|8924
|30

Business Law in Construction: Roles, Licensing, and Regulations Explained
|26
|6639
|497

Construction of a Building for Wesfarmers for Providing Warehouse Facility
|24
|3328
|282