Running head: PROJECT MANAGEMENT
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:

1PROJECT MANAGEMENT
Table of Contents
Part 1................................................................................................................................................3
a. Explanation of the following terms..........................................................................................3
b. Draw a Work Breakdown Schedule........................................................................................4
c. Activity schedule and allocate reasonable estimates...............................................................4
d. Manually produce a precedence diagram................................................................................5
Task 2...............................................................................................................................................5
a. Produce a Gantt chart...............................................................................................................5
b. Produce a detailed precedence diagram...................................................................................7
c. Renewed Project Plan..............................................................................................................7
d. Suggestion for timely project completion................................................................................9
Bibliography..................................................................................................................................10

2PROJECT MANAGEMENT
Part 1
a. Explanation of the following terms
Work Breakdown Structure (WBS): Work Breakdown Structure can be defined as the key
product deliverable that can be developed by classifying the project in a stratified way. The WBS
visually forms the definition of the scope of the project in manageable chunks for making it easy
for the team to understand.
Precedence Diagram Method: Precedence diagram is a figuratively representation of the
project activities in a network form so that each of the box is termed as node and the line
connecting them acts a dependencies.
Critical Path: Critical Path is a sequence of the activities that consists of network packages in a
form that would involve the least possible slack. The path is a sequence of activities developed
for ensuring that the project is completed in the least possible time consumption.

3PROJECT MANAGEMENT
b. Draw a Work Breakdown Schedule
Sheerness Dock Wall
New Road
Project Intialization
Analysis of the
requirements
Development of
Tender Documents
Submission of
tender
documentation
Approval of tender
by the Government
Project Planning
Selecting a plan
methodology
Developing plan
outline
Reviewing the plan
made
Complete plan
development
Plan Approval
Design Phase
Outline of the
design of harbour
sea wall
Designing the new
road by the harbour
Design of crane rails
is made
Design is approved
Construction Phase
Site Offices Development
Construction of
Welfare Facilities
Office building
development
Resource
Accumulation and
Materials are bought
Implementation of
services, storage,
and utilities
Site boundary
development
Wall Development
Installation of Sheet
piles
Concrete infillment
Application of tie-rod
anchors
Welding of the plate
Casting of concrete
anchor block
Construction of
concrete capping
beam
Development of full
expansion joint
Removal of old
crash barrier
Development of Crane
Construction of
crane foundation
Placement of
Engineering Fill
Removal of old
voids
Construction of new
bollards
Laying of new road
Fenders are fixed
Finishing the
construction
Removal of the site set
up
Removing the Site
compound and
structure
Safety Fencing is
removed
Project is closed
c. Activity schedule and allocate reasonable estimates
WBS Task Name Duration Start Finish Predecessors Resource Names
0 Sheerness Dock Wall New Road 97 days Thu 10/5/17 Fri 3/2/18
1 Project Intialization 11 days Thu 10/5/17 Thu 10/19/17
1.1 Analysis of the requirements 3 days Thu 10/5/17 Mon 10/9/17 Analyst
1.2 Development of Tender Documents 4 days Tue 10/10/17 Fri 10/13/17 2 Documenter
1.3 Submission of tender documentation 3 days Mon 10/16/17 Wed 10/18/17 3 Documenter
1.4 Approval of tender by the Government 1 day Thu 10/19/17 Thu 10/19/17 4 Project Manager
2 Project Planning 14 days Fri 10/20/17 Wed 11/8/17
2.1 Selecting a plan methodology 3 days Fri 10/20/17 Tue 10/24/17 5 Planner
2.2 Developing plan outline 3 days Wed 10/25/17 Fri 10/27/17 7 Planner
2.3 Reviewing the plan made 3 days Mon 10/30/17 Wed 11/1/17 8 Planner
2.4 Complete plan development 4 days Thu 11/2/17 Tue 11/7/17 9 Planner
2.5 Plan Approval 1 day Wed 11/8/17 Wed 11/8/17 10 Project Manager
3 Design Phase 15 days Fri 10/20/17 Thu 11/9/17
3.1 Outline of the design of harbour sea wall 4 days Fri 10/20/17 Wed 10/25/17 5 Designer
3.2 Designing the new road by the harbour 4 days Thu 10/26/17 Tue 10/31/17 13 Designer
3.3 Design of crane rails is made 4 days Wed 11/1/17 Mon 11/6/17 14 Designer
3.4 Design is approved 3 days Tue 11/7/17 Thu 11/9/17 15 Client
4 Construction Phase 71 days Fri 11/10/17 Fri 3/2/18
4.1 Site Offices Development 10 days Fri 11/10/17 Thu 11/23/17
4.1.1 Construction of Welfare Facilities 4 days Fri 11/10/17 Wed 11/15/17 16 Contractor
4.1.2 Office building development 4 days Thu 11/16/17 Tue 11/21/17 19 Engineer
4.1.3 Resource Accumulation and Materials are bought 3 days Fri 11/10/17 Tue 11/14/17 16 Equipments[1],Other Costs[1],Raw Materials[1]
4.1.4 Implementation of services, storage, and utilities 2 days Wed 11/22/17 Thu 11/23/17 20 Engineer
4.1.5 Site boundary development 5 days Fri 11/10/17 Thu 11/16/17 16 Worker
4.2 Wall Development 33 days Fri 11/17/17 Tue 1/16/18
4.2.1 Installation of Sheet piles 4 days Fri 11/17/17 Wed 11/22/17 23 Contractor
4.2.2 Concrete infillment 4 days Thu 11/23/17 Tue 11/28/17 25 Contractor
4.2.3 Application of tie-rod anchors 4 days Wed 11/29/17 Mon 12/4/17 26 Worker

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Scope Statement PDF
|12
|1107
|23

Project Scope Statement for Construction of Museo Atlantico
|14
|1165
|375

Project Budget, Schedule and Resources
|22
|2559
|400

Project Planning and Budgeting
|12
|1234
|341

CSM80006 | Engineering Project Management | Swinburne University
|13
|1558
|62

Project Final Report
|20
|3971
|484