1PROJECT MANAGEMENT Table of Contents Part One: Measurable Organization Value (MOV).........................................................................2 Part Two: Scope Management Plan.................................................................................................3 Part Three: Work Breakdown Structure..........................................................................................4 Part Four: Project Risk Analysis and Plan.....................................................................................12 Part Five: Quality Management Plan.............................................................................................13 Part Six: Closure and Evaluation...................................................................................................13 Bibliography..................................................................................................................................16
2PROJECT MANAGEMENT Part One: Measurable Organization Value (MOV) Before the start of a project, a standard is set that must be fulfilled at the end of the project. This particular standard is called measurable organization value or MOV. The MOV for a project is generally defined by a number of aspects that are described below focussing on this particular project for the development of online stud farm management system. Desired Area of Impact: Since Globex is focusing to develop the system in order to satisfy the needs of the customer, this project can be called as customer centric and hence, the desired area of impact for the project is customer. Globex wants to exploit the customers’ needs for enhancing the needs of the business for the company. In addition to the desired area of impact, there are also some values that are to be fulfilled by the project. These values are able to define the entire quality of the project are explained as follows. Better: The proposed management system is definitely a better option over the existing systems that are handled manually in the stud farms. Faster: The manual systems at the stud farms are slow and not very efficient. The new proposed management system is thousand times faster and very efficient. Cheaper: The new proposed system will have one time purchase cost and small maintenance costs whereas the manual system requires monthly expenses on wages as well as system maintenance.
3PROJECT MANAGEMENT DoMore: In addition to providing the clients with their business needs, Globex will be able to get a strong hold on the software distribution and development market. After these attributes are defined, the outcome of the project will be judged by some project metrics that are certain sets of values or standards associated with the project. The project metrics are as follows. Quality: The developed system must be of the best quality without any major issues, bugs or interface problems. The user should be able to read the contents and functions of the system easily so that they can use or manage the same. Without the presence of quality, Globex will not be able to develop their business and marketing strategy with the online management system. Service: Another major metric for the project is the service provided by the system. The system must be able to fulfil the requirements of the stud farm managers and additionally, they should be able to use with low maintenance and upgrade costs. The timeframe for achieving the MOV is set at around 10 months within which, the project will be completed and commercialization will be done. The MOV of the project proposed by Globex is a high quality online stud farm management system that will provide the stud farm managers will required services and features without additional maintenance and upgrade costs once the one time cost for the system is paid. Part Two: Scope Management Plan The scope of the project including the out of scope items have been defined as follows.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT Contract with Virtucon for the development of the system is within the scope of the project. Identification of issues faced by the stud farm managers is within the scope of the project. Development of the new online stud farm management system is within the scope of the project. Development of system marketing strategy is out of scope of the project. Plans for future upgrades and mods are out of scope of this project. Part Three: Work Breakdown Structure The work breakdown structure of the project is shown as follows.
5PROJECT MANAGEMENT Figure 1: Work Breakdown Structure of the Project (Source: Created by Author) Based on the work breakdown structure, the schedule for the project is determined and shown in the following table. Task NameDurationStartFinish DevelopmentofOnlineStudFarm Management System 114 daysTue 29-05-18Fri 02-11-18 Project Planning and Preparation25 daysTue 29-05-18Mon 02-07-18 Discussion and Consultation between Globex and Virtucon 4 daysTue 29-05-18Fri 01-06-18 Identification of the Business Solution2 daysMon 04-06-18Tue 05-06-18 Install a Demo Version of Proposed System 5 daysWed 06-06-18Tue 12-06-18 Try on the Demo Version5 daysWed 13-06-18Tue 19-06-18 Approve System Design1 dayWed 20-06-18Wed 20-06-18 Sign Contract for the Development of the Stud Farm Management System 2 daysThu 21-06-18Fri 22-06-18 Develop Project Plan5 daysMon 25-06-18Fri 29-06-18
6PROJECT MANAGEMENT Approve Project Plan1 dayMon 02-07-18Mon 02-07-18 Project Initiation7 daysTue 03-07-18Wed 11-07-18 Allocation Funds for the Project1 dayTue 03-07-18Tue 03-07-18 Create a List of Requirements3 daysWed 04-07-18Fri 06-07-18 Final Review Management System Design2 daysMon 09-07-18Tue 10-07-18 Estimate an Overall Schedule for Project1 dayWed 11-07-18Wed 11-07-18 Project Execution63 daysThu 12-07-18Mon 08-10-18 Procure System Softwares and Software Platform 2 daysThu 12-07-18Fri 13-07-18 Procure Hardware Upgrades2 daysThu 12-07-18Fri 13-07-18 Upgrade Current Hardware10 daysMon 16-07-18Fri 27-07-18 Start Development of Online Stud Farm Management System 1 dayMon 16-07-18Mon 16-07-18 Develop the System Architecture25 daysTue 17-07-18Mon 20-08-18 Develop Proposed Features15 daysTue 21-08-18Mon 10-09-18 Add GUI10 daysTue 11-09-18Mon 24-09-18 Test System for Bugs and Errors6 daysTue 25-09-18Tue 02-10-18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT MANAGEMENT Complete the Development of the System4 daysWed 03-10-18Mon 08-10-18 Training10 daysTue 09-10-18Mon 22-10-18 Train Current Employees at Globex5 daysTue 09-10-18Mon 15-10-18 DevelopMarketingPlanforthe Management System 2 daysTue 16-10-18Wed 17-10-18 Provide Future Upgrade Information2 daysThu 18-10-18Fri 19-10-18 System Handover1 dayMon 22-10-18Mon 22-10-18 Project Closing9 daysTue 23-10-18Fri 02-11-18 Post Project Review2 daysTue 23-10-18Wed 24-10-18 Project Documentation5 daysThu 25-10-18Wed 31-10-18 Stakeholder Sign Off1 dayThu 01-11-18Thu 01-11-18 Closing of the Project1 dayFri 02-11-18Fri 02-11-18 For the development of the budget plan for the project, the following resources are considered along with their standard usage rates. Resource NameTypeInitialsMax. UnitsStd. Rate
8PROJECT MANAGEMENT Project ManagerWorkP100%$175.00/hr ManagerofMarketingand Finance WorkM100%$125.00/hr IT Technical ManagerWorkI100%$125.00/hr TrainerWorkT100%$50.00/hr System Integration ExpertWorkS100%$75.00/hr System DeveloperWorkS100%$75.00/hr Chief IT OfficerWorkC100%$125.00/hr DataManagementand Control Officer WorkD100%$125.00/hr Project SupervisorWorkP100%$125.00/hr Hardware UpgradesMaterialH$30,000.00 Development SoftwareMaterialD$15,000.00 These resources are allocated within the project and the overall budget for the project is determined using bottom up estimation method as follows. Task NameResource NamesCost
9PROJECT MANAGEMENT Development of Online Stud Farm Management System $125,000.00[TOTAL BUDGET] ProjectPlanningand Preparation $38,000.00 Discussion and Consultation between Globex and Virtucon Project Manager$5,600.00 Identification of the Business Solution ProjectManager,ITTechnical Manager $4,800.00 Install a Demo Version of Proposed System ChiefITOfficer,ITTechnical Manager $10,000.00 Try on the Demo VersionChief IT Officer$5,000.00 Approve System DesignProject Manager$1,400.00 SignContractforthe DevelopmentoftheStudFarm Management System ProjectSupervisor,Project Manager $4,800.00 Develop Project PlanIT Technical Manager$5,000.00 Approve Project PlanProject Manager$1,400.00 Project Initiation$7,000.00 Allocation Funds for the ProjectProject Supervisor$1,000.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT Create a List of Requirements ManagerofMarketingand Finance $3,000.00 Final Review Management System Design ManagerofMarketingand Finance $2,000.00 Estimate an Overall Schedule for Project IT Technical Manager$1,000.00 Project Execution$59,000.00 Procure System Softwares and Software Platform Chief IT Officer$2,000.00 Procure Hardware UpgradesChief IT Officer$2,000.00 Upgrade Current HardwareSystem Integration Expert$6,000.00 Start Development of Online Stud Farm Management System System Integration Expert$600.00 DeveloptheSystem Architecture System Integration Expert$15,000.00 Develop Proposed Features DataManagementandControl Officer $15,000.00 Add GUISystem Developer$6,000.00
11PROJECT MANAGEMENT Test System for Bugs and ErrorsSystem Developer$3,600.00 Complete the Development of the System SystemDeveloper,System IntegrationExpert,ChiefIT Officer $8,800.00 Training$4,000.00 Train Current Employees at Globex Trainer$2,000.00 Develop Marketing Plan for the Management System Trainer$800.00 ProvideFutureUpgrade Information Trainer$800.00 System HandoverTrainer$400.00 Project Closing$17,000.00 Post Project ReviewChief IT Officer$2,000.00 Project DocumentationProject Manager$7,000.00 Stakeholder Sign OffProjectSupervisor,Managerof MarketingandFinance,Data $6,600.00
12PROJECT MANAGEMENT Management and Control Officer, SystemDeveloper,System IntegrationExpert,ChiefIT Officer,ITTechnicalManager, Trainer Closing of the ProjectProject Manager$1,400.00 Part Four: Project Risk Analysis and Plan Before analysing the project risks, the assumptions made during execution of the project are described as follows. The proposed system will be accepted by stud farm managers. The development costs and investments can be recovered within 6 to 10 months through the profits. The project will be completed within 5 months time frame. The risks of the project are identified using risk register matrix as follows. RiskChance of OccurrenceEffect on ProjectManagement Strategy Financial riskVery HighHighEstimateappropriate budget,donot overspend Scope riskHighVery HighDefineprojectscope
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13PROJECT MANAGEMENT andexcludeoutof scope items No technical supportHighHighThe hardware should be upgradedandupdated softwareplatform should be used Bugs and glitches in the system HighVery HighDebugandsystem testing Lack of businessMediumHighPromotetheusesand featuresofthe developed system Part Five: Quality Management Plan The project team follows one philosophy: team work. The entire team believes if the team members coordinate with each other, they will be able to overcome any challenges and complete all their project duties successfully. The project quality will be determined based on the pre set measurable organization value (MOV) and the project metrics that have also been defined earlier. To analyse the quality of the project, the project supervisor must ensure all the requirements and standards for the project have been made.