OPERATIONAL AND PROJECT MANAGEMENT
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents INTRODUCTION...........................................................................................................................3 Scenario 1: The Airport Transportation System..............................................................................3 Why ATS project manager believed it was not possible to carry out project for less than £16 million..........................................................................................................................................3 Presenting the entire working.....................................................................................................4 Scenario 2: SverigeTech: Air Traffic Control System.....................................................................7 Scenario 3: Terminal Four Refurbishment project- project analysis...............................................8 Progress achieved.........................................................................................................................8 Highlighting the problems that are now arising...........................................................................8 Assigning colour code to each and every task.............................................................................9 Expected completion date for an entire project.........................................................................10 CONCLUSION..............................................................................................................................10 REFERENCES..............................................................................................................................11
INTRODUCTION Operation management is one of the most important function of business, accountable for managing procedure of creation of services and products. It includes organizing, controlling, planning, coordinating and handling all the existing as well as new resources required to manufacture goods. Project management is the activity of executing, initiating and closing work of group of people to achieve business goals & objectives and meet particular success criteria desired time. The current report is based on Snowham international airport expand regional airport in South of England, UK. They cater its services to number of airlines which are continuously using their facilities. This study explain why ATS project manager believed that carrying out the whole project is not possible for less than 16 million. This report justified planning issue using resource histogram to determine any resourcing issues, reschedule plan to eliminate need and to determine start date of testing week. Furthermore, this study clarified progress achieve on stage task and highlight any issues that are now arising. Scenario 1: The Airport Transportation System Why ATS project manager believed it was not possible to carry out project for less than£16 million Airport transportation system is convenient and quick way to get around Snowham international airport. Airport shuttle used bus or other transport services to transport their passengers within airport safely. Due to suffering from their own success with increasing number of consumers, airport decided to planned and implement Airport transportation system that helps to improve their transportation efficiency and affectivity rather than past three years. Snowham Airport authority after varied revisions estimate the cost of project completion is more than £12 million. But project manager of ATS believe that it is impossible to deliver and complete project for less than 16 million, because the major part of airport transportation system required a lot of fund. Procurement manager give updated statement to airport authority about projected and plan costs, which is clearly defined the actual cost required to deliver project effectively. The underground tunnel construction process needed a lot of efforts and money, because it demands skilled labour and the best technologies that is quite expensive. Tunnel construction is the main part of this project, it is underground passenger way used for airport transportation, they will be used for carrying people and their luggages to the terminals within airports. The machines required to create underground terminal goes higher. TBM crew is more expensive resource in
this project, they demand good amount of money to deliver project on time. When the crew members work at night or weekend shift, it increases the cost more than estimated budget (Harrison and Lock, 2017). According to the project manager, when people work in night shift, the extra cost increase more than about 20%, that increase project completion cost which is more than 12 million accordant to the airport authority. Electrical services, test subway systems and other stages in airport transportation system project plan, needed extra efforts and money as well. Therefore, due to increase in the cost and decrease the time, Project manager of ATS believes that it is not easy to carry out the project less than£16 million. Presenting the entire working Project Task ModeTask NameDurationStartFinishPredecessors 1Prepare station sites2 wksWed 2/12/20Tue 2/25/20 2Construct platforms5 wksWed 2/26/20Tue 3/31/201 3Install CCTV systems1 wkWed 4/1/20Tue 4/7/202 4Fit terminal escalators2 wksWed 4/1/20Tue 4/14/202 5Erect information boards1 wkWed 4/1/20Tue 4/7/202 6TBM tunnel work20 wksWed 2/26/20Tue 7/14/201 7Fit electrical services3 wksWed 7/15/20Tue 8/4/206 8Install ventilation2 wksWed 7/15/20Tue 7/28/206 9Lay railway track6 wksWed 8/5/20Tue 9/15/207,8 10Test Subway system1 wkWed 9/16/20Tue 9/22/203,4,5,9
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Critical Path ParticularsAmount Fixed cost20000002000000 Project team2000004000000 TBM and equipment300000*206000000 TBM Crew100000*202000000 Total14000000 From the above table, it is critically analysed that project manager require 14m euro in order to complete the work within 301 days. Moreover, it is also determining from critical path that by using task 1,6,7,9,10 the entire project will be completed on time. That means project manager require 224 days. Revised Plan Gantt chart Task ModeTask NameDurationStartFinishPredecessors 1Prepare station sites2 wksWed 2/12/20Tue 2/25/20 2Construct platforms5 wksWed 2/26/20Tue 3/31/201 3Install CCTV systems1 wkWed 4/1/20Tue 4/7/202 4Fit terminal escalators2 wksWed 4/1/20Tue 4/14/202 5Erect information boards1 wkWed 4/1/20Tue 4/7/202 6TBM tunnel work8 wksWed 2/26/20Tue 4/21/201 7Fit electrical services3 wksWed 4/22/20Tue 5/12/206 8Install ventilation2 wksWed 4/22/20Tue 5/5/206 9Lay railway track6 wksWed 5/13/20Tue 6/23/207,8 10Test Subway system1 wkWed 6/24/20Tue 6/30/203,4,5,9
Critical Path ParticularsAmount Fixed cost20000002000000 Project team2600000 TBM and equipment325000*82600000 TBM Crew325000*82600000 Total7200000 From the above table, it is analysed that project manager require 7200000 euro only when it increase cost and minimize time. Thus, as compared to planned project schedule, project manager requires only 217 days which means less than 84 days from project. Moreover, critical path of both plan is same, but it is analysed that by using revised plan schedule, project manager may easily complete the project in specified time by taking shortest path i.e. Task 1,6,7,9,10 i.e in 140 days.
By comparing revised plan with project 1, it is analysed that project manager chooses revised plan as compared to first one because project manager mainly focused upon those project which require low cost and less time. In the same way, choosing revised plan of TBM and equipment which are used for 8 weeks are beneficial as compared to other. Hence, selecting 2nd project which require 7200000 within 140 days. Scenario 2: SverigeTech: Air Traffic Control System As per the case study it is analysed that project managers faces an issue of resources location and that is why, it is analysed due to not having sufficient resources the project planning got affected and also leads to delay the entire project too. Further, this also leads to cause bottlenecks and therefore, affect the entire project and generate the need of re-scheduling as well. Further, after resigning of Akesson, new project manager requires extra engineer but qualify only five engineer which is low number and it is not possible to deliver the project on time. Further, it is also recommended to the Sverige Tech to get the best performance and results from the resources, project manager should also make sure that manage the workloads in order to avoid over and under allocations. Such that they may use Professional services automation software which in turn assist to see the effect of changes in order to allocation of resources from their overall schedule (Fewings and Henjewele, 2019). On the other side, it also leads to increase the overall performance of employees and improve the ability to meet the project goals as well. In order to reschedule the plan which also eliminate the need of additional engineer. For that, it is recommended to the project to start taking extra work from the existing engineer in which project manager have to pay extra. Moreover, in order to rescheduling the overall project, air control module is done by 2 engineer only from week 1 to week 9, further, for ground control module, 2 engineer assigned but make sure that its must be completed within week 2 only. As it is analysed that these work is depended upon each other and that is why, they should consider and also complete the same. On the other side, flight clearance module and for terminal control module, 2 engineer simultaneously used for the two system (Kerzner, 2018). On the other side, for Integration, 3 engineers may also used instead of 4 so that it will not affect the overall project. Lastly. Fro testing, only single engineer is assigned who can test the project and take action which is required. Therefore, for rescheduling the plan, the estimated date for this project is 15 may which assist to meet the define aim and objectives.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Scenario 3: Terminal Four Refurbishment project- project analysis Progress achieved ParticularsPlannedActualVariance Check- in facilities1007030 BaggageHandling Services 1004060 Building Services 1001585 Circulation areas 1006040 Work on Concessions units 100Not started I.e. 0100 Thus, it is clearly reflected that project manager planning to complete the project within 6 months. Such that Check in facilities will be completed within 3 months from January to March but on March, the actual progress of this task is only 70%. While on the other side, Baggage Handling Services was estimated to complete up to April but deviation shows that 60% of the total work is still pending on March. In addition to this on March 1st, It is analyzed by project manager that building service is 85% pending which clearly reflect that it took lot of time for completion. Moreover, the current status of circulation areas is 60% completed that reflect it needs 40% more for the completion of the project. Thus, it shows that project require some additional months in order to complete the project. Hence, there is a wide difference between planned and actual task therefore, majority of the task is fall under the category of Red i.e. Task in progress which falling more than 5% behind the plan. Highlighting the problems that are now arising In order to refurbishment of terminal, project manager may face different issues such that:
Lack of Time management:It is consider one of the major issue that affect the project because it is analysed that Terminal Four structure needs to be completed within the six months, and the current status shows that entire project is completed up to 70% only. Time and communication is also proving to be a challenge for project manager and as a result, it cause delay the refurbishment of terminal (Kerzner, 2017). Human Resource:Another challenge which project manager faces because it is not easy to manage people and team because of good scale and size. Thus, project manager needs to make effective planning that assist to manage entire team as well as minimize the issue of delaying the project. Structural challenge:Another important challenge that may also cause negative impact upon entire refurbishment of terminal. It is so because, every time, the planning is change which may cause negative impact. Such that the work scope of this project is divided into six stages such that Check-in facilities, Circulation areas, Baggage handling services, concession units, building services and Terminal support services. Thus, due to sudden change in the overall facility takes lots of time and as a result, project manager did not meet the defined time (Meredith, Mantel Jr and Shafer, 2017). Communication issue:It is another issue which Project manager face while delegating roles and responsibilities to their team members. Further, this problem rises more, when project manager have any inexperienced team members who have lack of skill in order to handle any task. This challenge is also slows down the progress of entire work and sometimes it also lead to termination of the project as well. Thus, it is quite important for the project manager to make sure that they provide effective training to their employees and this will assist to make proper coordination with the team members. Assigning colour code to each and every task RedTask falling more than 5% behind plan AmberTask which is not yet started GreenTask completed or else, 5% ahead of plan Check-in facilities Baggage Handling services
Circulation areas Building services Work on concession units From the above, it is analysed that majority of the work is not completed because most of the work is falling more than 5% behind the plan, and these task is Check-in facilities, Baggage Handling services, Circulation areas and Building services, that is why, it fall under red colour While on the other side, Work on concession units is that task which is not yet started and therefore, it fall under Amber colour. None of these mention five task will fall under green colour because there is no task which is completed ahead from March onward. Expected completion date for an entire project After analysing the project progress, it is analysed that most of of work is not completed as per the defined deadlines and that is why, the expected date of completion of the project is 30th September. It is so because, Check in facilities is proceeding well and as per the progress analysis, it is now completed only 70%. Further, Baggage handling services is also 40% completed and Building services at early stages is also 15% completed. Thus, it is clearly reflected that project is delayed from its actual deadline such that with the effective planning, project needs only 6 month i.e. up to June, but actually it will be completed up to September due to Work on concession is not yet started. Hence, this is also evaluated that due to having high variance from planned and actual estimation, the project got delayed and also takes 3 months more in order to refurbishment the entire project of Four Terminals (Heagney, 2016). CONCLUSION By summing up above report it has been concluded that for case scenario 1, project manager chooses revised plan because the total amount spent for completion of project is 720000, while on contrary, actual project requires 14000000 which is quite high. Thus, it is reflect that project manager always select that project whose cost is low and require low time as compared to other. From case scenario 3, it is analysed from progress analysis that majority of the work is not completed up to March and thus, there is a wide difference between planned and actual working performance. Moreover, at the time of refurbishment, project manager also faces differentproblemssuchthatStructuralchallenge,lackofhumanresource,lackoftime management which may delay the entire project as well.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
REFERENCES Book and Journals Fewings,P.andHenjewele,C.,2019.Constructionprojectmanagement:anintegrated approach. Routledge. Harrison, F. and Lock, D., 2017.Advanced projectmanagement: a structured approach. Routledge. Heagney, J., 2016.Fundamentals of project management. Amacom. Kerzner, H., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kerzner, H., 2018.Project management best practices: Achieving global excellence. John Wiley & Sons. Meredith, J. R., Mantel Jr, S. J. and Shafer, S. M., 2017.Project management: a managerial approach. John Wiley & Sons.