ProductsLogo
LogoStudy Documents
LogoAI Grader
LogoAI Answer
LogoAI Code Checker
LogoPlagiarism Checker
LogoAI Paraphraser
LogoAI Quiz
LogoAI Detector
PricingBlogAbout Us
logo

Engineering Calculation Review Process

Verified

Added on  2020/06/05

|18
|5204
|134
AI Summary
This assignment outlines a detailed review process for engineering calculations in projects. It emphasizes collaboration between originators, checkers, and project managers to ensure the accuracy, completeness, and adherence to relevant standards. The process involves multiple rounds of review, documentation, and feedback using standardized forms and reference materials.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
QUALITY ASSURANCE
And QUALITY CONTROL
PROCESS GUIDE
For PROJECT MANAGERS
TABLE OF CONTENTS
Discussion..………………………………………………………………………… 2
Scope Verification Meeting..………………………………………………............. 3
Overview…………………………………………………………………… 3
Procedure…………………………………………………………………... 4
Requirements………………………………………………………………. 5
Reference Material………………………………………………………… 5
Base Plan Review (OPTIONAL)………………………………………………….. 6
Overview…………………………………………………………………… 6
Procedure…………………………………………………………………... 7
Requirements………………………………………………………………. 7
Reference Material…………………………………………………………. 8
The Plan Review Meeting………………………………………………………….. 9
Overview…………………………………………………………………… 9
Procedure……………………………………………………………………10

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Requirements………………………………………………………………. 11
Reference Material……………………………………………......………... 11
Errors and Omissions Check (OEC) Meeting……………………………………… 13
Overview…………………………………………………………................ 13
Procedure…………………………………………………………………... 13
Requirements………………………………………………………………. 14
Reference Material....………………………………………………………. 14
Final Package Submittal…………………………………………………………… 15
Overview…………………………………………………………………… 15
Procedure…………………………………………………………………... 15
Requirements………………………………………………………………. 15
Exceptions………………………………………………………………….. 16
Exceptions-Procedure……………………………………………………… 16
Reference Material…………………………………………………………. 16
Quality Control Activities………………………………………………………….. 18
Overview…………………………………………………………………… 18
Procedure…………………………………………………………………... 18
Requirements………………………………………………………………. 18
Reference Material…………………………………………………………. 18
Appendix A: Reference Documents……………………………………………….. 19
MDOT QA/QC PROCESS FOR TRUNKLINE PROJECTS
Discussion
Document Page
The MDOT Quality Assurance/Quality Control (QA/QC) process for trunkline projects is
based on a well-documented plan development procedure. It applies to both in-house and
consultant designed projects, as well as road and bridge projects. The procedure includes
periodic reviews at pre-determined stages during the design of the project. The Quality
Control (QC) includes a plan development process that is described in Chapter 14 of the
Road Design Manual and also in the Program/Project Management System (PPMS) Task
Manual. Both manuals provide a detailed and chronological procedure for the
development of design plans. The procedure ensures all the required elements are
effectively incorporated into the project. The Quality Assurance (QA) consists of 5
distinct stages at which an independent team comprehensively reviews the content and
accuracy of the plans and proposal. The four stages are the Scope Verification Meeting,
the Plan Review Meeting, the Omissions and Errors Check (OEC) Meeting, and the Final
Project Turn-in as shown below. All projects do not require each of the 5 stages. For
instance, a Base Plan Review is not required on any projects. To determine the process
required on a project, reference should be made to the Table titled “QA/QC Review
Process by Template”. In addition, the complete project development network should be
reviewed for a thorough understanding of the entire plan development process.
Scope
Verification
Meeting
The
Plan
Review
Meeting
Omissions
and Errors
Check
Meeting
Final
Package
Submittal
Base
Plan
Review
(Optional)
SCOPE VERIFICATION MEETING
Overview
Once a project is assigned, the Project Manager should request from the office that
scoped the project, a copy of the scoping documents. These documents may include such
items as a completed copy of the Project Scoping Checklist, project concept statement,
pavement coring information, cost estimate, sketch of the proposed typical cross
section(s), and preliminary survey. The initial PPMS Network should also be available.
The Project Manager will then gather the necessary old plans, utility information, traffic
data, and other useful background information, review all scoping documents, and review
cost estimates from the programming of the project and compare it to the programmed
Document Page
cost. If this review of the estimate differs significantly from the programmed cost, the
Project Manager should discuss possible revisions such as increasing the programmed
cost, changing the scope of work and/or reducing the project limits with the System
Manager and/or TSC Manager prior to the Scope Verification Meeting. Attendees of the
Scope Verification Meeting should be informed of any revisions at the meeting to
minimize design time impacts and to avoid a possible delay of the project.
When sufficient information is available, the Project Manager will schedule a Scope
Verification Meeting. In order to ensure that everyone understands and agrees with the
proposed scope of work, it is essential that all the disciplines and work centers that will
be involved in the development of the project be invited to this meeting. This will
minimize possible “scope creep” and reduce the number of redesigns by verifying and
documenting the scope of work as early as possible in the design process.
Prior to this meeting, the Project Manager should establish the role of the Federal
Highway Administration (FHWA) on the project. The oversight responsibility can be
determined by referring to the Agreement between the Michigan Department of
Transportation and the Federal Highway Administration for Administration and
Oversight of Federal-Aid projects. Any uncertainty regarding this determination should
be clarified by discussing the project with the FHWA Area Engineer.
Also, at this stage, the Project Manager should verify that the Pavement Design and
Selection Policy has been followed. Depending on the type of fix and estimated paving
cost, a Life Cycle Cost Analysis (LCCA) may be required. If the procedure has not been
followed, the Project Manager should contact the Pavement Design Engineer or
appropriate Region/TSC Soils Engineer to initiate compliance with the policy.
Items to be discussed at the Scope Verification Meeting may include:
Cost estimate
Project description
Project limits
Environmental impacts and mitigation measures
Hazardous waste coordination
Project schedule
Safety review
Soils information
Pavement information
Geometrics
Right-of-Way
Utilities
Political considerations
Traffic maintenance during construction
Waterway crossings
Railroad crossings
Crash analysis
Affected flood plains
Design exceptions and Crash
Analysis

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Incentive/disincentive clauses
Construction staging/Detour (all routes)
Local agreements
Warranties
Lane Rentals
Night Work
Expedited schedules
Packaging with other projects
Traffic data
Underclearance
Local coordination
Traffic signals
Drainage
FHWA status
Survey
STIP/TIP
MDOT/Consultant design
Context Sensitive Solutions
Multi Modal
Procedure
The Project Manager should:
1. Receive project assignment.
2. Input actual start date (PPMS Task No. 3130) into the appropriate data system.
3. Collect all the available information concerning the project for distribution prior
to, or at, the meeting.
4. Identify meeting attendees and schedules meeting. Attendees may include:
FHWA/MDOT oversight
Design unit
Environmental
Geometrics (Central Traffic and Safety)
Construction
Locals
Central Specialty Units
Region/TSC
Traffic and Safety
Soils/Materials
Utilities/Permits
Delivery/Resident Engineer
Maintenance
Real Estate (if applicable)
Survey (if applicable)
Associate Region Engineer – Development
Businesses
Cost & Scheduling Engineer
TSC Manager
Document Page
TSC Development Engineer
Region/TSC/Central Bridge Design Engineer
5. Distribute the information to verify the scope of work.
6. Conduct meeting.
7. Review scope of work agreed upon at meeting with programmed scope and cost.
8. If significantly different, discuss with TSC Manager and/or System Manager and, if
necessary, submit a Change Request (2604) to revise scope and/or cost.
9. Write and distribute meeting minutes to all those invited to the meeting. The
Region System Manager/Associate Region Engineer-Development and the
Environmental Section in the Bureau of Transportation Planning must always
receive copies of these minutes.
10. Input actual finish date (PPMS Task No. 3130) into the appropriate data system.
Requirements
Old plans and/or a sketch of the proposed typical for the work
Pavement core/soil boring information
Utility information
Traffic data
Project Concept statement
Cost estimate
Environmental Study form
PPMS network
Right-of-Way Plans
Scoping documents
Structure information
Scour information
Other useful background information
Reference Materials
Plan Development Services Website
QA/QC Review Process by Template
Road Design Manual – Section 14.10
Bridge Design Manual – Section 2.02.15
PPMS Task Manual – Task Number 3130
PPMS Global Network
Agreement between the Michigan Department of Transportation and the Federal
Highway Administration for Administration and Oversight of Federal-Aid projects
Design Guidelines
Design Standards
Scope Verification Checklist
Requirements for Preliminary Right-of-Way
BASE PLAN REVIEW MEETING (Optional)
Overview
The purpose of the Base Plan Review Meeting is to ensure the project design is
proceeding according to the scope of work agreed to at the Scope Verification Meeting.
Document Page
Base Plan Review Meetings are not required, but may be scheduled at the discretion of
the Project Manager. These meetings may be held on projects designed in-house or those
designed by consultants. The meeting and corresponding field review should be
conducted by the MDOT Project Manager.
A minimum of four weeks should be allotted from the time of request to the desired date
of the meeting. This allows ample time to schedule the meeting, distribute plans and other
materials and for review of the plans prior to the meeting. Instances when projects require
a compressed schedule or scheduling without plans should be kept to a minimum.
Items to be discussed at the Base Plan Review Meeting may include:
Plan conformance to the MDOT Drafting Standards, that the plans are readable, are
organized properly and that their intent is clearly definable.
Location/limits
Scheduled completion
Project cost
Scope of work
Right-of-Way
-any purchase required
-any grading permits required
-any encroachments
-monument preservation
Utilities
-identify conflicts or problems
-discuss whether a separate meeting will be required
Maintaining traffic/Construction staging
-discuss whether a separate meeting will be required
-discuss basic traffic control scheme
-discuss minimum lanes to remain open during construction
-discuss detour route/agreement signed
-discuss coordination with other projects
Signals/Signing/Pavement Markings
-note locations of signals/loops/ signs that will conflict with construction
-determine if signal work will be is included
-determine if signing work will be included
-determine the need for temporary signals
Soils
-discuss locations of contaminated sites (information obtained from the
Phase 1 evaluation, aka the “Project Area Contamination Survey”-PACS)
-discuss the need for a Phase 2 evaluation (aka the “Project Site Investigation –PSI)
-discuss locations of poor soils with recommendations
Drainage
-discuss erosion problems (>2% grade to ditch)
-discuss culvert work/extensions – permits required
-discuss drainage and vicinity map required
-discuss hydraulic needs
-discuss storm sewer and outlet(s)

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Surveys
-identify problems or additional needs
Geometrics
-superelevations required
-intersection radii/curb type problems
-design exceptions required
-crash analysis
-guardrail and barrier wall
Environmental
-wetland involvement/problems
-environmental clearance
-permits required/impacts
Structures
-coordination
Railroads
-agreements
-coordination
Procedure
The Project Manager should:
1. Verify that all the applicable items on the Requirements for the Base Plan
Review Meeting are included in the plans. Refer to the Consultant Manual
for Consultants – Chapter 24 – PPMS Task 3360 – Part 2 – Section H –
Under Prepare Base Plan Submittal Package.
2. Verify that PPMS Task No. 3380 Start Date is entered.
3. Review cost and schedule of the project and compare with approved
programming documents.
4. Set up meeting and distribute the material for the meeting.
5. Review all the distributed material and prepare for the meeting.
6. Attend the meeting (the Project Manager is to run the meeting)
7. Document all the necessary information
8. Verify PPMS Task No. 3380 Finish Date is entered.
Requirements
plans – including road, bridge, signals, signing, etc.
preliminary maintaining traffic concept
latest cost estimate and programmed cost
Reference Materials
Plan Development Services Website
QA/QC Review Process by Template
PPMS Task Manual – Task Number 3380
Requirements for The Base Plan Review Meeting – Road
Document Page
Requirements for The Structure Study Review Meeting – Bridge
Requirements for Final Right-of-Way
THE PLAN REVIEW MEETING
Overview
The purpose of the Plan Review Meeting is to ensure the project design is proceeding
according to the scope of work agreed to at the Scope Verification Meeting. All trunkline
projects with templates requiring a Plan Review as defined in the Table QA/QC Review
Process by Template must have a Plan Review Meeting. This includes projects designed
in-house and those designed by consultants. The meeting and corresponding field review
should be conducted by Quality Assurance and Lettings personnel. However, when
staffing cannot accommodate the project schedule, a Project Manager or System Manager
may arrange to conduct the meeting. In those instances when Quality Assurance and
Lettings personnel cannot hold the meeting or, if the project schedule does not allow
adequate time for a meeting to be held, Quality Assurance and Lettings will complete the
Exception to the Plan Review Meeting/OEC Meeting Process form and forward a copy to
the Project Manager. This form should be placed in the project file. Also, a copy of the
meeting minutes of Plan Review Meetings conducted by a Project Manager of System
Manager must be sent to Quality Assurance and Lettings. A minimum of four weeks
should be allotted from the time of request to the desired date of the meeting. This allows
ample time to schedule the meeting, distribute plans and other materials and for review of
the plans prior to the meeting. Instances when projects require a compressed schedule or
scheduling without plans should be kept to a minimum.
Items to be discussed at the Plan Review Meeting may include:
Location/limits
Scheduled completion
Project cost
Scope of work
Right-of-Way
-any purchase required
-any grading permits required
-any encroachments
-monument preservation
Utilities
-any conflicts or problems
-separate meeting scheduled/required
Maintaining traffic/Construction staging
-separate meeting scheduled
-basic traffic control scheme
-minimum lanes to remain open during construction
-detour route/agreement signed
-coordination with other projects
Signals/Signing/Pavement Markings
-signals/loops that conflict with construction
-signal work included and/or separate contract
Document Page
-signing work included and/or separate contract
-pavement marking included/separate contract
-temporary signals
-rumble strips
Soils
-contaminated sites identified
-additional soil borings needed
-roadside seeding/slope restoration checked by Lansing Roadside
Development
-location of poor soils with recommendations and proposed fixes
-pavement cores
Drainage
-erosion problems (>2% grade to ditch)
-culvert work/extensions – permits required
-drainage and vicinity map required
-hydraulic needs
-storm sewer and outlet(s)
Surveys
-identify problems or additional needs
Geometrics
-superelevations required
-intersection radii/curb type problems
-design exceptions required
-crash analysis
-guardrail and barrier wall
Environmental
-city/county/township noise ordinances
-wetland involvement/problems
-environmental clearance
-permits required/impacts
-erosion control items on plans
Local Agency
-cost participation (100%)
-agreements
-Act 51
Structures
-coordination
Railroads
-agreements
-coordination

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Procedure
The Project Manager should:
1. Refer to the Table QA/QC Review Process by Template to verify the project
must have a Plan Review Meeting.
2. Verify that all the applicable items on the Requirements for the Plan Review
Meeting are included in the plans.
3. Contact Quality Assurance and Lettings to set up an available date for the
meeting. If a Quality Assurance Engineer is not available, identify the person
who will conduct the meeting. Request a completed Exception to the Plan
Review Meeting/OEC Meeting Process form be forwarded for insertion into the
project files.
4. Request to schedule THE Plan Review Meeting through Quality Assurance and
Lettings using form No. 0200 – Plan Review Meeting. Include all items
required for distribution.
5. Verify that PPMS Task No. 3590 Start Date is entered.
6. Review cost and schedule of the project and compare with approved
programming documents.
7. Request all Design Package Evaluations (DPE) be completed prior to the
meeting.
8. Review all the distributed material and prepare for the meeting.
9. Attend the meeting.
10. Coordinate with the Quality Assurance Engineer to ensure all outstanding issues are
resolved.
11. Document all the necessary information in the meeting minutes (if the meeting is
conducted by the Project Manager).
12. Distribute the meeting minutes. If a person other than a Quality Assurance
Engineer conducts the meeting and writes the meeting minutes, a copy of those
minutes must be sent to Quality Assurance and Lettings.
13. Verify PPMS Task No. 3590 Finish Date is entered.
Requirements
plans – including road, bridge, signals, signing, etc.
guardrail worksheets
preliminary maintaining traffic scheme
latest cost estimate and programmed cost
preliminary copies of project specific special provisions
design exceptions with Crash Analysis
preliminary construction staging plan/critical path
Reference Materials
Plan Development Services Website
QA/QC Review Process by Template
Exception to the Plan Review Meeting/OEC Meeting Process
Road Design Manual - Section 14.36
Bridge Design Manual – Section 2.02.16
PPMS Task Manual – Task Number 3590
Requirements for THE Plan Review Meeting – Road
Document Page
Requirements for THE Plan Review Meeting – Bridge
Request for Plan Review Meeting
Title Sheet Checklist
Note Sheet Checklist
Existing Typical Cross Section Checklist
Proposed Cross Section Checklist
Removal Sheet Checklist
Construction Sheet Checklist
Profile Sheet Checklist
OMISSIONS and ERRORS CHECK (OEC) MEETING
Overview
The purpose of the Omissions and Errors Check Meeting is to review the final
plan/proposal package to ensure the package is complete. All trunkline projects with
templates requiring an OEC Meeting as defined in the Table QA/QC Review Process by
Template must have an OEC Meeting. . If Quality Assurance and Lettings personnel
cannot review the project, a completed Exception to the Plan Review Meeting/OEC
Meeting Process form will be forwarded to the Project Manager to be placed in the
project files.
The number of participants at this meeting should be kept to a minimum. A large number
of participants results in longer meetings and also promotes requests for additions or
changes to the scope of work. The Project Manager can minimize the number of
participants by coordinating and resolving most outstanding issues directly with others
prior to the meeting. Participants at the meeting should focus only on omissions and
errors in the package. Changes to the scope of work or project limits should not be
considered at this stage except for in the most extreme circumstances.
Note: If the project schedule does not allow for a meeting to be held, the Project
Manager should request a completed Exception to the Plan Review Meeting/OEC
Meeting Process form for insertion into the project file
Procedure
The Project Manager should:
1. Refer to the Table QA/QC Review Process by Template to determine if the project
requires an Omissions and Errors Check (OEC) Meeting.
2. Verify the plan/proposal package is 100% complete (see requirements below).
3. Input actual start date (PPMS Task No. 3870) into the appropriate data system.
4. Identify meeting attendees and schedule meeting. Attendees should include:
Project Manager
Designer (road and/or Bridge)
Quality Assurance Engineer
Resident/Delivery Engineer
Author of Maintaining Traffic Special Provision
Central Geometrics
Central Construction and Technology
FHWA (oversight)
Note: additional people may be invited if an outstanding issue requires
clarification
Document Page
5. Distribute plan/proposal package to all people involved in the project including
those who sign or initialize the Certification Acceptance form (allow for 10 business day
review time for participants)
6. Review cost and schedule of project and compare with approved programming
documents
7. Request all Design Package Evaluations (DPE) be completed
8. Hold Meeting
(a) Sign the Certification Acceptance Form
(b) Project Manager and Resident Engineer sign Title Sheet
9. Ensure all recommendations are incorporated into the plan/proposal package
10. Input actual finish date (PPMS Task No. 3870) into the appropriate data system.
11. Complete and forward a copy of the Submission of Final Plan/Proposal Package to
Quality Assurance and Lettings to verify an OEC Meeting has been held and the project
has been completed (shelf projects only).
Requirements
Plans – 100% Complete
Final quantities
Special details
Title Sheet signed by Project Manager and Delivery Engineer
Title Sheet stamped by Consultant firm(s) if applicable
Proposal – 100% Complete
Maintaining traffic special provision
All coordination clauses
All permits
Transport files complete with bid-based price report
All Frequently Used Special Provisions (FUSP)
All Frequently Used Supplemental Specifications (FUSS)
Notice to Bidders - checklist
All project specific special provisions (with C&T Support Area approval)
All Notices to Bidders – project specific
Right-of-Way certification
Utility relocation status report
Others
Critical path network (if required)
Progress Clause (to be presented at the meeting by the Delivery Engineer)
Approved Design Exceptions
Local agreements
Road Cost Estimating Checklist
Bridge Lump Sum Worksheet
Final QA/QC Checklist
Reference Materials
Plan Development Services Website
QA/QC Review Process by Template
Road Design Manual - Section 14.54
Bridge Design Manual – Section 2.02.18
PPMS Task Manual – Task Number 3870

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Exception to the Plan Review Meeting/OEC Meeting Process
FINAL PACKAGE SUBMITTAL
Overview
The final plan/proposal package should be submitted to the Specifications and Estimates
Unit on or before the date listed under the “turned in to S&E Unit” date in the fiscal
year’s schedule of Letting Dates and Board Dates. Prior to submitting the package to
Specifications and Estimates, the Project Manager should complete a thorough review of
the entire project. At a minimum, the package must include all the items listed on the
Submission of Final Plan/Proposal Package (Form No. 0269). In addition the Project
Manager should ensure the items listed on the Final QA/QC Checklist have been
performed.
Procedure
The Project Manager should:
1. Refer to the Table QA/QC Review Process by Template to determine if the project
requires a Project Review by QA prior to turn in.
2. Determine the date, depending on the allowable advertising period, required for turn in
by referencing the fiscal year’s Letting Dates and Board Dates.
3. Review the package to insure all the required items are included
4. Complete and sign the Final QA/QC Checklist
5. Verify STIP/TIP/Environmental Clearance status
6. Verify the cost in Transport is ≤ the approved programmed cost
7. Submit the package to the Specifications and Estimates unit.
Requirements
One print of the Title Sheet
Bid Based Price Report (Transport) with any cost changes noted
Submission of Final Plan/Proposal Package
Advertising Data
Proposal level cost summary (Transport)
Unique Special Provisions (approved)
Maintaining Traffic Special Provision
Frequently Used Special Provisions (FUSP)
Frequently Used Supplemental Specifications (FUSS)
All required permits
Utility Relocation Status Report
Utility Charge Estimate
Right-of-Way Certification for Advertising
Coordination Clauses
Certification and Acceptance Forms
Notices to Bidder (insurance, warranties, contact person, projects in area, etc)
Progress Clause
Road Estimating Checklist
Bridge Lump Sum Worksheet
Design Exceptions (if applicable)
Exception with Risk Analysis (if applicable)
Notice to Bidders checklist
Document Page
Railroad Agreement
Local Agreements
STIP/TIP
Environmental Clearance
Final QA/QC checklist
Exceptions
There are some allowable exceptions to the minimum requirements for submittal of
plan/proposal packages to the Specifications and Estimates Unit. Exceptions are
permitted on the following items
Permits
Right-of-Way Certification on non-federally funded projects
Local Agency agreements
**Unique Special Provisions
**Although unique Special Provisions are one of the allowable exceptions, it is
rarely enforced. However, Project Managers should make every attempt to get
approvals prior to project submittal. Special Provisions pertaining to lane
rentals, ramp rentals, A+B, and changes to the Schedule of Liquidated
Damages in the Standard Specifications for Construction do require approval
from Construction and Technology Support Area prior to advertisement.
Procedure - Exceptions
The Project Manager should:
1. Identify an item will not be available for inclusion in the plan/proposal
package at the time of submittal.
2. Verify the item is eligible for the Exception process.
3. Investigate the status of the item to ascertain the expected date of receipt
of the item.
4. Perform a risk analysis to determine the probability of the receipt of the
item within the anticipated time frame, and the impact to the project both
in terms of cost and schedule.
5. Send the information to the Region Engineer with a request for a signed
memorandum accepting the risk and approving the project to go forward
without the item.
6. Insert the signed memorandum with an attached Risk Analysis into the
plan/proposal package.
7. If the exception is for a permit or ROW, include a Notice to Bidders that
includes the projected date of approval and any restrictive conditions.
Reference Materials
Plan Development Services Website
QA/QC Review Process by Template
Road Design Manual – Section 14.60
PPMS Task Manual – Task Number 3910
Utility Relocation Status Report - CPM
Utility Charge Estimate
Certification and Acceptance – Type 2
Advertising Data
Certification and Acceptance – Type 1
Document Page
Road Design Cost Estimating Checklist
Submission of Final Plan/Proposal Package
Certification and Acceptance – Type 3
Right-of-Way Certification for Advertisement (Improvements)
Right-of-Way Certification for Advertisement (No Improvement)
Environmental Clearance
Utility Relocation Status Report
Design Exception
Structure Lump Sum Item Worksheet
Agreement between the Michigan Department of Transportation and the Federal
Highway Administration for Administration and Oversight of Federal-Aid projects
FY Letting Dates and Board Dates
FY Letting Dates and Board Dates – Capital Preventive Maintenance Projects Only
FY Letting Dates and Board Dates – Maintenance Funded Projects Only
FY 6 Week Advertisements
Final QA/QC checklist
Risk Analysis – Local Agency Agreement
Risk Analysis – Permits
Risk Analysis – M Funded Right-of-Way
Risk Analysis – Special Provisions
18
QUALITY CONTROL ACTIVITIES
Overview
Quality control activities should be conducted throughout the course of the project.
Calculations, estimates, etc. must be checked immediately so that errors are not
perpetuated. The checker must have a similar or greater level of experience as the
originator, should be a member of the project team familiar with the details of the project,
and must be familiar with the type of work proposed for the project.
Procedure
The originator should:
1. Label every sheet with the control section, job number, if known, or project
location, personal initials, and date.
2. List all assumptions and provide reference materials. Enough descriptions and
reference materials are given such that the calculations can be checked without
asking the originator any questions.
The checker should:
1. Note items that are correct with yellow.
2. Show corrections that need to be made in red.
3. Return the calculations to the originator.
The originator should then:
1. Make corrections.
2. Provide the checker with revised calculations and the original comments from the
checker.
The checker should then:
1. Ensure that all comments have been addressed.
2. Provide personal initials and date on every sheet that has been checked.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
If checker and originator cannot resolve a disagreement, the project manager makes the
final decision.
Requirements
List all assumptions
Provide appropriate reference materials
Show all work
Provide stationing limits where possible
Back up calculations in spreadsheets must be provided
Reference Materials
Road Design Manual
Bridge Design Manual
Drainage Manual
Design Reference Site
APPENDIX A: Reference Documents
Copies of the following documents are included. Documents followed by a number in
parenthesis are official forms. When completing these forms, Project Managers should
access the Plan Development Services website to get the latest version. Most of the other
documents are available on the Plan development Services website. Many are in the
process of being converted to official forms.
Advertising Data (#0256)
Agreement between the Michigan Department of Transportation and the Federal
Highway Administration for Administration & Oversight of Federal-Aid projects
Alignment (Information required on Plan Sheets) Checklist
Capital Preventive Maintenance Project/M-Funded Project Checklist
Certification and Acceptance – Type 1 (#0265)
Certification and Acceptance – Type 2 (#0253)
Certification and Acceptance – Type 3 (#0301)
Construction Sheet Checklist
Design Exceptions (#FC26)
Environmental Clearance (#1775)
Exception to the Plan Review/OEC Meeting Process
Existing Typical Cross Section Checklist
Final QA/QC Checklist
FY Letting Dates and Board Dates
FY Letting Dates and Board Dates–Capital Preventive Maintenance Projects Only
FY Letting Dates and Board Dates – Maintenance Funded Projects Only
FY 6 Week Advertisements
Note Sheet Checklist
Plan Completion Checklist
Profile Sheet Checklist
Project Scoping Checklist
Proposed Cross Section Checklist
QA/QC Review Process by Template
Removal Sheet Checklist
Request for Plan Review Meeting (#0200)
Document Page
Requirements for Preliminary Right-of-Way Plans
Requirements for Final Right-of-Way Plans
Requirements for THE Plan Review Meeting – Road
Requirements for THE Plan Review Meeting – Bridge
Right-of-Way Certification for Advertising (Improvements) (725I)
Right-of-Way Certification for Advertising (No Improvements) (725N)
Risk Analysis – Local Agency Agreement
Risk Analysis – Permits
Risk Analysis – M Funded Right-of-Way
Risk Analysis – Special Provision 20
Road Design Cost Estimating Checklist (#0268)
Structure Lump Sum Item Worksheet (#2911)
Submission of Final Plan/Proposal Package (#0269)
Title Sheet Checklist
Utility Charge Estimate(#0223)
Utility Relocation Status Report(#2286)
Utility Relocation Status Report - Capital Preventive Maintenance Projects Only
Utility Relocation Status Report – Pavement Marking Projects Only
1 out of 18
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]