Project Management: WBS, OBS, RAM, Gantt Chart, Risk Register

Develop a Project Execution Plan for the construction of a new Information Technology Centre in the capital city, with a budget of $40 million and additional funds of $25 million for IT support.

11 Pages1372 Words427 Views
   

Added on  2022-11-23

About This Document

This document provides information about Project Management including Work Breakdown Structure (WBS), Organisational Breakdown Structure (OBS), Responsibility Assignment Matrix (RAM), Gantt Chart, Estimated Cost, and Risk Register.

Project Management: WBS, OBS, RAM, Gantt Chart, Risk Register

Develop a Project Execution Plan for the construction of a new Information Technology Centre in the capital city, with a budget of $40 million and additional funds of $25 million for IT support.

   Added on 2022-11-23

ShareRelated Documents
Running Head: PROJECT MANAGEMENT
Assignment Stage 2
Name of the Student
Name of the University
Project Management: WBS, OBS, RAM, Gantt Chart, Risk Register_1
1PROJECT MANAGEMENT
Project Calendar
Holiday Date
New Year’s Eve 1st January
Australia Day 27th January
Labour Day 9th March
Good Friday 10th April
Easter 13th April
Queen’s Birthday 8th June
Final before AFL Grand Final 27th September
Melbourne Cup 5th November
Christmas Day 25th December
Boxing Day 26th December
WBS, OBS, RAM
A WBS or Work Breakdown Structure is a deliverable-oriented breakdown of the entire
project into separate activities and deliverables. The benefit of breaking down the project into
individual activities and deliverables is that they can be treated as individual mini-projects and
can be scheduled separately in order to determine the overall schedule for the project.
Project Management: WBS, OBS, RAM, Gantt Chart, Risk Register_2
2PROJECT MANAGEMENT
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
Project Management: WBS, OBS, RAM, Gantt Chart, Risk Register_3
3PROJECT MANAGEMENT
Project Head Supervisor
WorkersContractor
Technician Tester
Figure 1: OBS of the Project
(Source: Created by Author)
The Organisational Breakdown Structure (OBS) above shows the relationship between
the organisation stakeholders who are involved in the project.
The responsibility assignment matrix is as follows.
Task Name Resource Names
IT Center Design and Development
Construction and Development of IT Center Building
Development of Project Scope, Schedule and Budget Project Head
Selection of Property for the Construction Process Project Head
Purchase Property from Owner Project Head
Select Contractor for the Construction Works Project Head
Develop Architecture Plan Project Head
Hire Workers for the Construction Purposes Project Technical Contractor
Purchase Materials for Construction Project Technical Contractor
Initiate Construction Works Team of Construction Workers
Project Management: WBS, OBS, RAM, Gantt Chart, Risk Register_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Development of a New Information Technology Centre – Stage 2
|10
|1096
|30

Project Management: Tasks, WBS, Activity Durations, Cost Report
|11
|1124
|463

Development of a New Information Technology Centre – Stage 3
|9
|1217
|69

Implementation of Information Technology - Project Charter and Budget
|7
|1491
|458

Development of a New Information Technology Centre
|14
|1733
|34

Project Management and Information Technology Assignment 2
|22
|2244
|94