Running Head: PROJECT MANAGEMENT Project Management Name of the Student Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT Section 3: Major Project Management Activities and Estimates 1. Work Breakdown Structure WBSTask NamePredecessors 0Development of VMS for SMR 1Initial Discussions and Survey 1.1Survey of the Current Requirements of SMR 1.2 Collect Data Regarding the Features of Proposed VMR 2 1.3 Initiation of Board Meeting Regarding the Possible Project 1.3.1Discuss the Required Features of the System3 1.3.2Discuss Possible Budget to be Invested5 1.3.3Discuss Overall Duration of the Project6 1.3.4Discuss Financial Feasibility of the Project7 1.3.5Discuss Business Feasibility of the Project8 1.3.6Discuss How the System will Benefit Business9 1.3.7Reach a Certain Conclusion10
2PROJECT MANAGEMENT 1.4Call Meeting with PMP Consulting 1.4.1Discuss About the System11 1.4.2Propose Project Contract13 1.4.3Discuss Terms of Contract14 1.4.4Discuss Project Requirements15 1.4.5Reach Mutual Agreement16 1.5Prepare an Initial Business Case17 1.6Submit the Business Case to CEO of SMR18 1.7Receive Approval from CEO19 1.8Prepare Contract Paper20 1.9Verify Contract Terms of CEO21 1.10Contract Signing with PMP for the Project22 2Project Planning Phase 2.1Start Second Meeting with PMP Consulting 2.1.1Discuss of the Overall Requirements of the Project23
3PROJECT MANAGEMENT 2.1.2Discuss Whether the Budget is Sufficient26 2.1.3 Discuss whether the proposed duration is sufficient 27 2.2Prepare Detailed Business Case28 2.3Submit Business Case29 2.4Get Evaluation on Business Case30 2.5 Get Final Approval from CEO Regarding the Project 31 3Project Launch 3.1Initiate the Project32 3.2Start Developing Project Charter 3.2.1Determine the Overall Scope of the Project34 3.2.2Determine Project Objectives36 3.2.3 Prepare a Work Breakdown Structure for the Project 37 3.2.4Schedule the Project using Gantt Chart38 3.2.5Determine whether this schedule is feasible39
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT 3.2.6 Allocate resources in each work package in the Gantt Chart 40 3.2.7Determine Budget Using Bottom Up Estimation41 3.2.8Determine Budget Using Top Down Estimation42 3.2.9Compare the Two Estimates43 3.2.10Develop a Suitable Budget Using the Comparison44 3.3Analyze Risks Associated with the Project 3.3.1Prepare Risk Register45 3.3.2Prepare Risk Mitigation Strategy47 3.4Develop Stakeholder Matrix48 3.5Develop Communication Plan49 3.6Develop Quality Management Plan50 3.7Complete the Charter51 3.8Submit the Charter to SMR Authority52 3.9Receive Go Ahead53 3.10Appoint Stakeholders to Respective Roles54 3.11Start Working on the Project55
5PROJECT MANAGEMENT 4Acquire Resources 4.1Analyze System Requirements56 4.2Submit Resource Requirements Documents58 4.3Submit Fund Request to SMR59 4.4Receive the Funds for the Project60 4.5Provide Funds to Procurement Department61 4.6Procure Required Hardware and Software62 4.7Procure Other Necessary Resources63 4.8Check Quality of the Resources64 5Requirements Definition 5.1Analyze Project Charter65 5.2Analyze Project Scope67 5.3Analyze Project Requirements68 5.4Prepare Project Roadmap69 6Detailed Design
6PROJECT MANAGEMENT 6.1Start Designing the System70 6.2Install Necessary Hardware72 6.3Install Support Software73 6.4Check System Configuration74 6.5Create Initial System Prototype Framework75 6.6Coding76 6.7Programming77 7Application Development 7.1Start Development on the Prototype Framework78 7.2Run the Program for Checking the Codes80 7.3Add Features to the Prototype81 7.4Run the Prototype Again for Checking the Features82 7.5Start Developing the Full Version83 7.6Design the System84 7.7Add Codes85 7.8Design the Interface86
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT MANAGEMENT 7.9Add Features87 7.10Add Payment Gateway88 7.11Connect Server with Business Portal89 7.12Run the Entire System90 8Data Migration 8.1 Connect the Developed System with the Central Server 91 8.2Migrate Data from Server to Cloud93 8.3Link the Application with the Cloud94 9System Documentation 9.1Create a Log of Activities during the Project95 9.2 Use the Log to Develop System Documentation Report 97 9.3Submit the Report to SMR98 10Testing 10.1Test the Entire System99 10.2Identify Bugs and Errors101
8PROJECT MANAGEMENT 10.3Resolve the Issues102 10.4Go Live103 11Training 11.1Prepare Training Module104 11.2Conduct 15 Days Training of the Staffs of SMR106 12Closing 12.1Stakeholder Sign Off107 12.2Officially Close the Project109 2. Network Diagram Figure 1: Activity on Node Network Diagram
9PROJECT MANAGEMENT (Source: Created by Author) 3. Key Milestones Reach a Certain Conclusion Reach Mutual Agreement Contract Signing with PMP for the Project Get Final Approval from CEO Regarding the Project Submit the Charter to SMR Authority Start Working on the Project Link the Application with the Cloud Submit the Report to SMR Officially Close the Project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT 4. Critical Path Dependencies Figure 2: Critical Path Dependency of the Project (Source: Created by Author)
11PROJECT MANAGEMENT 5. Best Estimation of Time Duration WBSTask NameDurationStartFinish 0Development of VMS for SMR202 days Mon04-06- 18 Tue 12-03-19 1Initial Discussions and Survey25 days Mon04-06- 18 Fri 06-07-18 1.1 Survey of the Current Requirements of SMR 5 days Mon04-06- 18 Fri 08-06-18 1.2 Collect Data Regarding the Features of Proposed VMR 2 days Mon11-06- 18 Tue 12-06-18 1.3 InitiationofBoardMeeting Regarding the Possible Project 2 days Wed13-06- 18 Thu 14-06-18 1.3.1 Discuss the Required Features of the System 0.25 days Wed13-06- 18 Wed 13-06-18 1.3.2 Discuss Possible Budget to be Invested 0.25 days Wed13-06- 18 Wed 13-06-18 1.3.3 Discuss Overall Duration of the Project 0.25 days Wed13-06- 18 Wed 13-06-18 1.3.4Discuss Financial Feasibility of the0.25 daysWed13-06-Wed 13-06-18
12PROJECT MANAGEMENT Project18 1.3.5 Discuss Business Feasibility of the Project 0.5 daysThu 14-06-18Thu 14-06-18 1.3.6 Discuss How the System will Benefit Business 0.5 daysThu 14-06-18Thu 14-06-18 1.3.7Reach a Certain Conclusion0 daysThu 14-06-18Thu 14-06-18 1.4Call Meeting with PMP Consulting4 daysFri 15-06-18Wed 20-06-18 1.4.1Discuss About the System1 dayFri 15-06-18Fri 15-06-18 1.4.2Propose Project Contract1 day Mon18-06- 18 Mon 18-06-18 1.4.3Discuss Terms of Contract1 dayTue 19-06-18Tue 19-06-18 1.4.4Discuss Project Requirements1 day Wed20-06- 18 Wed 20-06-18 1.4.5Reach Mutual Agreement0 days Wed20-06- 18 Wed 20-06-18 1.5Prepare an Initial Business Case5 daysThu 21-06-18Wed 27-06-18 1.6 Submit the Business Case to CEO of SMR 1 dayThu 28-06-18Thu 28-06-18
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13PROJECT MANAGEMENT 1.7Receive Approval from CEO2 daysFri 29-06-18Mon 02-07-18 1.8Prepare Contract Paper2 daysTue 03-07-18Wed 04-07-18 1.9Verify Contract Terms of CEO2 daysThu 05-07-18Fri 06-07-18 1.10 Contract Signing with PMP for the Project 0 daysFri 06-07-18Fri 06-07-18 2Project Planning Phase9 days Mon09-07- 18 Thu 19-07-18 2.1 Start Second Meeting with PMP Consulting 1 day Mon09-07- 18 Mon 09-07-18 2.1.1 DiscussoftheOverall Requirements of the Project 0.5 days Mon09-07- 18 Mon 09-07-18 2.1.2 Discuss Whether the Budget is Sufficient 0.25 days Mon09-07- 18 Mon 09-07-18 2.1.3 Discuss whether the proposed duration is sufficient 0.25 days Mon09-07- 18 Mon 09-07-18 2.2Prepare Detailed Business Case5 daysTue 10-07-18Mon 16-07-18 2.3Submit Business Case1 dayTue 17-07-18Tue 17-07-18 2.4Get Evaluation on Business Case2 daysWed18-07-Thu 19-07-18
14PROJECT MANAGEMENT 18 2.5 Get Final Approval from CEO Regarding the Project 0 daysThu 19-07-18Thu 19-07-18 3Project Launch16 daysFri 20-07-18Fri 10-08-18 3.1Initiate the Project2 daysFri 20-07-18Mon 23-07-18 3.2Start Developing Project Charter3 daysTue 24-07-18Thu 26-07-18 3.2.1 Determine the Overall Scope of the Project 0.5 daysTue 24-07-18Tue 24-07-18 3.2.2Determine Project Objectives0.5 daysTue 24-07-18Tue 24-07-18 3.2.3 Prepare a Work Breakdown Structure for the Project 0.25 days Wed25-07- 18 Wed 25-07-18 3.2.4 Schedule the Project using Gantt Chart 0.25 days Wed25-07- 18 Wed 25-07-18 3.2.5 Determine whether this schedule is feasible 0.25 days Wed25-07- 18 Wed 25-07-18 3.2.6 Allocate resources in each work package in the Gantt Chart 0.25 days Wed25-07- 18 Wed 25-07-18 3.2.7Determine Budget Using Bottom0.25 daysThu 26-07-18Thu 26-07-18
15PROJECT MANAGEMENT Up Estimation 3.2.8 Determine Budget Using Top Down Estimation 0.25 daysThu 26-07-18Thu 26-07-18 3.2.9Compare the Two Estimates0.25 daysThu 26-07-18Thu 26-07-18 3.2.10 Develop a Suitable Budget Using the Comparison 0.25 daysThu 26-07-18Thu 26-07-18 3.3 Analyze Risks Associated with the Project 2 daysFri 27-07-18Mon 30-07-18 3.3.1Prepare Risk Register1 dayFri 27-07-18Fri 27-07-18 3.3.2Prepare Risk Mitigation Strategy1 day Mon30-07- 18 Mon 30-07-18 3.4Develop Stakeholder Matrix0.5 daysTue 31-07-18Tue 31-07-18 3.5Develop Communication Plan0.5 daysTue 31-07-18Tue 31-07-18 3.6Develop Quality Management Plan3 days Wed01-08- 18 Fri 03-08-18 3.7Complete the Charter1 day Mon06-08- 18 Mon 06-08-18 3.8Submit the Charter to SMR Authority0 daysMon06-08-Mon 06-08-18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
19PROJECT MANAGEMENT 7.11Connect Server with Business Portal2 daysTue 15-01-19Wed 16-01-19 7.12Run the Entire System2 daysThu 17-01-19Fri 18-01-19 8Data Migration7 days Mon21-01- 19 Tue 29-01-19 8.1 Connect the Developed System with the Central Server 2 days Mon21-01- 19 Tue 22-01-19 8.2Migrate Data from Server to Cloud5 days Wed23-01- 19 Tue 29-01-19 8.3Link the Application with the Cloud0 daysTue 29-01-19Tue 29-01-19 9System Documentation7 days Wed30-01- 19 Thu 07-02-19 9.1 Create a Log of Activities during the Project 2 days Wed30-01- 19 Thu 31-01-19 9.2 Use the Log to Develop System Documentation Report 5 daysFri 01-02-19Thu 07-02-19 9.3Submit the Report to SMR0 daysThu 07-02-19Thu 07-02-19 10Testing5 daysFri 08-02-19Thu 14-02-19 10.1Test the Entire System4 daysFri 08-02-19Wed 13-02-19
20PROJECT MANAGEMENT 10.2Identify Bugs and Errors0.5 daysThu 14-02-19Thu 14-02-19 10.3Resolve the Issues0.5 daysThu 14-02-19Thu 14-02-19 10.4Go Live0 daysThu 14-02-19Thu 14-02-19 11Training17 daysFri 15-02-19Mon 11-03-19 11.1Prepare Training Module2 daysFri 15-02-19Mon 18-02-19 11.2 Conduct 15 Days Training of the Staffs of SMR 15 daysTue 19-02-19Mon 11-03-19 12Closing1 dayTue 12-03-19Tue 12-03-19 12.1Stakeholder Sign Off1 dayTue 12-03-19Tue 12-03-19 12.2Officially Close the Project0 daysTue 12-03-19Tue 12-03-19 6. Budget Estimation Bottom Up: Task NameCost Development of VMS for SMR$1,230,680.00 Initial Discussions and Survey$129,280.00 Survey of the Current Requirements of SMR $18,000.00
21PROJECT MANAGEMENT Collect Data Regarding the Features of Proposed VMR $7,200.00 Initiation of Board Meeting Regarding the Possible Project $43,680.00 Discuss the Required Features of the System $5,460.00 Discuss Possible Budget to be Invested$5,460.00 Discuss Overall Duration of the Project$5,460.00 Discuss Financial Feasibility of the Project $5,460.00 Discuss Business Feasibility of the Project $10,920.00 Discuss How the System will Benefit Business $10,920.00 Reach a Certain Conclusion$0.00 Call Meeting with PMP Consulting$21,200.00 Discuss About the System$8,000.00 Propose Project Contract$4,400.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
22PROJECT MANAGEMENT Discuss Terms of Contract$4,400.00 Discuss Project Requirements$4,400.00 Reach Mutual Agreement$0.00 Prepare an Initial Business Case$9,000.00 Submit the Business Case to CEO of SMR$1,800.00 Receive Approval from CEO$8,800.00 Prepare Contract Paper$7,200.00 Verify Contract Terms of CEO$12,400.00 Contract Signing with PMP for the Project$0.00 Project Planning Phase$88,200.00 Start Second Meeting with PMP Consulting $9,800.00 Discuss of the Overall Requirements of the Project $4,900.00 Discuss Whether the Budget is Sufficient $2,450.00
23PROJECT MANAGEMENT Discuss whether the proposed duration is sufficient $2,450.00 Prepare Detailed Business Case$49,000.00 Submit Business Case$9,800.00 Get Evaluation on Business Case$19,600.00 Get Final Approval from CEO Regarding the Project $0.00 Project Launch$66,000.00 Initiate the Project$3,600.00 Start Developing Project Charter$16,200.00 Determine the Overall Scope of the Project $2,700.00 Determine Project Objectives$2,700.00 Prepare a Work Breakdown Structure for the Project $1,350.00 Schedule the Project using Gantt Chart$1,350.00
24PROJECT MANAGEMENT Determine whether this schedule is feasible $1,350.00 Allocate resources in each work package in the Gantt Chart $1,350.00 Determine Budget Using Bottom Up Estimation $1,350.00 Determine Budget Using Top Down Estimation $1,350.00 Compare the Two Estimates$1,350.00 Develop a Suitable Budget Using the Comparison $1,350.00 Analyze Risks Associated with the Project $10,800.00 Prepare Risk Register$5,400.00 Prepare Risk Mitigation Strategy$5,400.00 Develop Stakeholder Matrix$2,200.00 Develop Communication Plan$2,200.00 Develop Quality Management Plan$13,200.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
25PROJECT MANAGEMENT Complete the Charter$1,800.00 Submit the Charter to SMR Authority$0.00 Receive Go Ahead$8,800.00 Appoint Stakeholders to Respective Roles$7,200.00 Start Working on the Project$0.00 Acquire Resources$41,760.00 Analyze System Requirements$3,600.00 SubmitResourceRequirements Documents $1,800.00 Submit Fund Request to SMR$1,800.00 Receive the Funds for the Project$5,400.00 Provide Funds to Procurement Department$1,800.00 Procure Required Hardware and Software$15,200.00 Procure Other Necessary Resources$6,080.00 Check Quality of the Resources$6,080.00 Requirements Definition$54,000.00 Analyze Project Charter$18,000.00
26PROJECT MANAGEMENT Analyze Project Scope$9,000.00 Analyze Project Requirements$9,000.00 Prepare Project Roadmap$18,000.00 Detailed Design$367,800.00 Start Designing the System$7,200.00 Install Necessary Hardware$168,000.00 Install Support Software$145,800.00 Check System Configuration$3,600.00 CreateInitialSystemPrototype Framework $18,000.00 Coding$18,000.00 Programming$7,200.00 Application Development$248,400.00 Start Development on the Prototype Framework $7,200.00 Run the Program for Checking the Codes$18,000.00
27PROJECT MANAGEMENT Add Features to the Prototype$36,000.00 Run the Prototype Again for Checking the Features $18,000.00 Start Developing the Full Version$3,600.00 Design the System$54,000.00 Add Codes$36,000.00 Design the Interface$36,000.00 Add Features$18,000.00 Add Payment Gateway$7,200.00 Connect Server with Business Portal$7,200.00 Run the Entire System$7,200.00 Data Migration$37,800.00 Connect the Developed System with the Central Server $10,800.00 Migrate Data from Server to Cloud$27,000.00 Link the Application with the Cloud$0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
28PROJECT MANAGEMENT System Documentation$75,600.00 Create a Log of Activities during the Project $21,600.00 UsetheLogtoDevelopSystem Documentation Report $54,000.00 Submit the Report to SMR$0.00 Testing$9,000.00 Test the Entire System$7,200.00 Identify Bugs and Errors$900.00 Resolve the Issues$900.00 Go Live$0.00 Training$91,800.00 Prepare Training Module$10,800.00 Conduct 15 Days Training of the Staffs of SMR $81,000.00 Closing$21,040.00
29PROJECT MANAGEMENT Stakeholder Sign Off$21,040.00 Officially Close the Project$0.00 Top Down Estimation: Resource / RequirementsBudget Total Budget$1,200,000 Budget for Wages$300,000 Budget for Material Resources$500,000 Development Costs$400,000 Contingency Budget20% It is seen that using bottom up and top down estimation, the overall budget is almost the same but in bottom up, the value is slightly higher. Hence, it is important to keep some additional budget to compensate for the extra. Based on the top down estimation, the initial budget is too low and must be increased. Hence, a formal request must be placed for increasing the budget considering the additional value found in bottom up. 7. Human Resource Estimate The estimate is shown in the following table. Resource NameTypeMax. UnitsStd. RateOvt. Rate Project ManagerWork100%$550.00/hr$0.00/hr
30PROJECT MANAGEMENT Project SupervisorWork100%$450.00/hr$0.00/hr IT Technical AnalystWork100%$450.00/hr$0.00/hr Finance ManagerWork100%$450.00/hr$0.00/hr Procurement ManagerWork100%$380.00/hr$0.00/hr HR ManagerWork100%$450.00/hr$0.00/hr DeveloperWork100%$225.00/hr$0.00/hr System Analyst and TesterWork100%$225.00/hr$0.00/hr
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
31PROJECT MANAGEMENT Bibliography Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Harrison, F. andLock,D., 2017.Advancedprojectmanagement:astructuredapproach. Routledge. Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Schwalbe, K., 2015.Information technology project management. Cengage Learning.