Project Management - Case Study
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
EXECUTIVE SUMMARY This project consist case study and application of project management techniques for the music festival. Project has four tasks divided into different activities and topics. Task 1 consists of discussion about three methodologies of project management; waterfall, Prince2 and scrum. Task 2 consists PERT/CPM diagram and shortest path to complete the project, it also consists calculation of EST, LST, EFT and LFT. Task 3 consist stakeholder analysis for the music festival and WBS. Task 4 will discuss about how to manage risk to minimize the hurdle in competing the activities.
INTRODUCTION Project management includes the hierarchy of activities, the allocation of people according to competencies, cost and risk management, and especially in reporting.A team that knows how to manage projects becomes experts in solving problems in a personal way and reduces the level of concern of its managers. Work breakdown structure or WBS is nothing more than an extended duration of the project. It should have the complete structure of the project - deliverables, activities and theirs - and assigned a start date and end date for each activity. The correct way to establish a timeline is to go from micro to macro. Begin by determining the hierarchy and duration of each activity. Then look at the full date end date, with each deliverable, start date and end date. Task 1 Project Management Methodologies: These are the tools and techniques help in categories the different activities as planned by supervisor and senior authorities in hierarchal order. It also shows cost and time duration associated with each tasks (Hopkin, 2018). Some of the project management methodologies which can help in arranging planned activities are discussed below: 1.Waterfall:The waterfall method is a sequential model that we use to create different types of software. The project manager divides the work into steps that follow each other's flow (such as a waterfall). The global distribution of development in stages is as follows: 1. Requirements Analysis, 2. Design, 3. Software implementation, 4. Project Verification and Software maintenance. Advantages: This approach is characterized by extensive project planning and insight into dependencies. This approach often leads to precise time and budget. Transferring project knowledge is even simpler, as extensive documentation is created in addition to development.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Disadvantages: It is difficult to record changes in the project once the life cycle of the project has reached the test stage. The model is not suitable for complex and object-oriented projects and should be avoided in long and current projects. 2.PRINCE2:It stands for projects in a controlled environment and is a project management method that is widely used within government. This is a very process-oriented method. PRINCE2 requires that projects be divided into several phases. Each stage has its own strategies and procedures and is heavily documented. Along with Six Sigma and PRSM, PRINCE2 requires accreditation through exams(Glendon, Clarke and McKenna, 2016). Advantages: The extensive documentation required for RINCE2 is useful for: ï‚·Business plan ï‚·Tracking performance ï‚·Limiting risks Disadvantages: A lot of effort goes into creating and maintaining documents and logs at every stage of the process. Therefore implementing project changes is cumbersome. 3.Scrum:Scrum is an agile framework for complex projects that has to do with changing time requirements. Scrum was originally developed for software projects. Over time, however, it was discovered that it worked well in any complex, innovative field. Scream focuses on shorter, faster delivery of projects, so there is quick response and quick response time to changes. This project management method places great emphasis on team dynamics and collaboration. The teams work together on a series of two-week sprints. The Scram master has the task of removing obstacles to progress(Rampini, Viswanathan and Vuillemey, 2019). Advantages:
Scrum is one of those iterations in which new development can be tested quickly and any errors can be resolved immediately. Disadvantages: Scope creep is a major problem in scope projects. Because the project relies on close team collaboration, any member leaving the team can interrupt the entire project. Task 2 The critical path in which music project can be completed with minimum time duration estimated is119 days. The activities of critical path are as follows;1 - Budget Approval→2- Hire Publicity Director→4- Hire Place for Auditions→5 - Advertising to Hire Crew and Cast →9 – Auditions to Hire Cast→10 – Cast Rehearsal→21- Dress Rehearsal→22- Performance. PERT Diagram/ Network Diagram:Shows arrangement of all activities of the music festival to know which activity will start with the end of predecessor event; how much duration it will take. Critical path can identified only after proper diagram of all events drawn(Kerzner, 2017).
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
The next step consist calculations of Earliest start time, Earliest finish time, Latest start time and Latest finish time (EST, EFT, LST and LFT). N rMain Activities with Predecessors Earliest TimeLatest Time Name of the Task Star t Finis h Star t Finis h 1Budget Approval0101 2Hire Publicity Director115115 3Hire Set Designer115115 4Hire Place For Auditions7221522 5Advertising To Hire Crew and Cast7221522 6Hire Production & Publicity Crew22502250 7Set Designed and Built15925092 8Train Production Crew15175062 9Auditions To Hire Cast22242224 1Cast Rehearsal2410824108
0 1 1Hire Orchestra1818 1 2Music815885 1 3 Photograph Cast And Crew & Collect Biographies843886 1 4Enter Information Into Computer43448593 1 5Printing51518657 1 6Develop an Advertising Plan50575078 1 7Advertising Media57785778 1 8Orchestra rehearsal15191519 1 9Order Costumes24312431 2 0Costume Parade And Alterations31369297 2 1Dress Rehearsal1920108109 2 2Performance2030109119 Hence,critical path for above project are 1 – 2 – 4, 5 – 9 – 10 – 21 – 22 which is 119 days. Project will take maximum time of 119days to finish; it is the minimum time taken by project; because no other path shows minimum time with maximum coverage of all essential activities. Task 3 Stakeholder analysis Stakeholder means a strategic public and describes a person or group who has an interest in a company, business or industry and may not have invested in them. There are two types of stakeholders; external and internal. Where external stakeholders are those individuals or groups
who staying outside the company; on the other hand; internal stakeholders have interest within firm (Meredith, Mantel. and Shafer, 2017).. Steps in analyses: 1.Identification of stakeholder:The music festival project has following stakeholders; college students, participants, project managers, sponsors, investors, project owner, project mentor, designer, competitor, workers, suppliers, landowner and many more. 2.Classification of major stakeholders:These stakeholders have been categorized based on their impact on project externally and internally InternalExternal ï‚·College students ï‚·Project managers ï‚·Project owner ï‚·Project mentor ï‚·Designer ï‚·Workers ï‚·Participants ï‚·Sponsors ï‚·Investors ï‚·Competitor ï‚·Suppliers ï‚·Landowners . 3.Assessment of stakeholders in different circumstances: It is clear that both stakeholders external and internal want growth and profit from the project. But still there are some situations where both react in different manner. For instance; internal stakeholders only interested in successful launching of project and growth in popularity. Their main objective is to entertain public and give opportunities to new talents. But on the other hand; external stake holders indirectly interested in popularity of project. Their main focus is on how much cash is collected from project, what the return on investment is and how long this project will sustain (Turner, 2016.). Work Breakdown structure: Activity description InitialGeneration of idea to organize music festival. Planning Making budget within which project has to finish. Budget approval by senior management and owner. Develop an advertising plan. Implementatio n Hire publicity director, set designer, production and publicity crew. Select place for auditions, printing, enter information into computer. Advertisement to hire staff and auditions invitation. `Hire orchestra, order costumes, advertising media, Arrange music and sound system. MonitorandDesigningset,trainproductioncrew,castrehearsal,orchestra
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
controlrehearsal,dressrehearsal,costumeparadeandalterations, photograph cast and crew and collect biographies. CloserPerformance
Task 4 Project risk management:It is an initiative adopt by every project manager to minimize the chances of occurrence of any unexpected event and obstacles in completion of project. Below are the risk analyses of different types of risks: Type of risksAffect on projectRisk management strategy CostWithlesscontrolover activitiesandtaskscould increase the cost of overall projects. It is major risk, which can affect whole project and profit. External stakeholders have eye on this.Itcanbeminimizedthroughproper controlling and mentor all activities. Avoiding wastage of resources; adopting cost controlling techniques at initial level. TimeInsteadofcriticalpath; sometimeriskslikenon availabilityofemployee, government permission, non agreementwithlandfor rent, etc. could raise the risk of time. It is also major risk associated with completion of project. Risk cost can also be minimized through reducing the risk of delay in project. This risk could be minimized through adopting strictness to complete particular activity within set time period. ScheduleAvoidanceofstrictnessin following up schedule could raise schedule risk. Schedule risk is moderate; because it can be reduced through proper explaining about what to do and when. PerformanceMentors might not perform well for which they known for;duetoincomplete information,less supervision over employees etc. It is high risk and requires lots of concentration and controlling to minimize the affect of risk. It can be avoid if all above three types of risk; schedule,costandtimedealtproperly (Heagney, 2016). QualityLack of rehearsal has a risk ofbadqualityin performance. This risk has low compatibility but has major affect; hence it can be controlled from day 1; if there isenough timeleftwith proper time management then it could be avoided.
REFERENCES Books and Journals Glendon, A.I., Clarke, S. and McKenna, E., 2016.Human safety and risk management. Crc Press. Heagney, J., 2016.Fundamentals of project management. Amacom. Hopkin,P.,2018.Fundamentalsofriskmanagement:understanding,evaluatingand implementing effective risk management. Kogan Page Publishers. Hubbard, D.W., 2020.The failure of risk management: Why it's broken and how to fix it. John Wiley & Sons. Kerzner, H., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017.Project management: a managerial approach. John Wiley & Sons. Rampini, A.A., Viswanathan, S. and Vuillemey, G., 2019. Risk management in financial institutions.The Journal of Finance. Turner, R., 2016.Gower handbook of project management. Routledge.