Running head: PROJECT MANAGEMENT
Renovation of Royale pizza
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1. Project schedule and different types of tools, techniques and methods......................................2
1.1 Project schedule.....................................................................................................................2
1.3 Critical path reflecting stress point........................................................................................8
1.4 Tools for critical path.............................................................................................................8
2. Project budget and ways for controlling cost of the project........................................................9
2.1 Project budget........................................................................................................................9
2.2 Assumptions that are made..................................................................................................11
2.3 Ways for controlling cost.....................................................................................................11
3. Risk management and identification of tools and techniques...................................................12
3.1 Tools and techniques for identifying risk management.......................................................12
3.3 Risk identification, analysis and mitigation.........................................................................12
Bibliography..................................................................................................................................16
Document Page
2
PROJECT MANAGEMENT
1. Project schedule and different types of tools, techniques and methods
1.1 Project schedule
The prepared schedule reflects duration, resources as well as total budget that is required
for the purpose of renovating the shop of Royale pizza.
WBS
ID
Activity
description
Precedence Duration
estimate
Resource Cost
estimate
0 Pizza shop
renovation
6 mons AU$
40,000.00
1 Design phase 1 mon AU$
5,000.00
1.1 Undertaking
meeting with the
workers of the
store
1 day Project management
consultant
AU$ 500.00
1.2 Researching
the problem
2 4 days Project manager AU$ 500.00
1.3 Identifying
solution
3 5 days Project management
consultant, Project
manager
AU$ 500.00
1.4 Creating
schematic
design
4 10 days Designer AU$
3,500.00
Document Page
3
PROJECT MANAGEMENT
1.5 Milestone 1:
Getting approval
for the design
5 0 days AU$ 0.00
2 Procurement
and delivery
phase
2 mons AU$
18,000.00
2.1 Determining
products and
services
5 5 days Procurement manager AU$ 400.00
2.2 Hiring
suppliers
8 9 days Procurement manager,
Project management
consultant
AU$ 300.00
2.3 Buying
different types
of materials and
equipment
9 10 days Supplier AU$
12,000.00
2.4 Performing
quality
assurance
10 8 days Quality analyst AU$
4,300.00
2.5 Analyzing
the results and
margins
11 8 days Procurement manager,
Project management
consultant
AU$
1,000.00
2.6 Milestone 2: 12 0 days AU$ 0.00
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
PROJECT MANAGEMENT
Completion of
procurement and
delivery phase
3 Construction
phase
1 mon AU$
7,000.00
3.1 Completing
the work of
flooring
12 5 days Civil engineer,
Construction manager
AU$
2,000.00
3.2 Professional
cleaning of
kitchen
15 4 days Construction manager AU$
2,000.00
3.3 Removing
the shop from
rear area for
providing
cooking space
16 6 days Civil engineer,
Construction manager
AU$
1,500.00
3.4 Adding
additional dining
space
17 4 days Construction manager AU$
1,000.00
3.5 Undertaking
inspection
18 1 day Inspection officer AU$ 500.00
3.6 Milestone 3:
Completion of
19 0 days AU$ 0.00
Document Page
5
PROJECT MANAGEMENT
construction
phase
4 Installation
phase
2 mons AU$
10,000.00
4.1 Installation
of air
conditioning
system
20 4 days Installer AU$
2,000.00
4.2 Dust free
painting
22 27 days Painter AU$
5,500.00
4.3 Equipment
installation
23 5 days Installer AU$
1,500.00
4.4 Hardware
and software
installation
24 4 days Installer, Quality
analyst
AU$
1,000.00
4.5 Milestone 4:
Completion of
installation and
painting phase
25 0 days AU$ 0.00
1.2 Utilization of methods, tools and techniques
Method used for the project
Document Page
6
PROJECT MANAGEMENT
While developing a project it becomes essential to prepare a project schedule that will be
able to present all the activities effectively. Thus, in order to present the Gantt chart, the method
used is known as visual description method (Ong, Wang and Zainon, 2016). The main reason
behind using Gantt chart is that it helps in dividing the activities associated with each phase and
are represented with horizontal bar. The main objective behind using Gantt charts is that it helps
in planning the activities successfully and ensures that the project is being executed within the
scheduled duration. Moreover it becomes easy to manage the resources within the project.
Tools used within the project
The main aim behind using an effective technique is to ensure that the project can be
carried out successfully. In this project the selected method is critical path method that has
helped in scheduling the project for renovation. With the help of critical path it becomes easy to
determine the longest possible path for carrying out the project. Apart from this critical path
method also supports in identifying the tasks that are critical within the project (Mehlawat and
Gupta, 2016). This also discovers the activities within the project that may float. Beside this the
critical path method ensures that proper visualization is being provided for maintaining a proper
flow within the project. This helps in calculating the duration effectively when all dependencies
are defined from early stages.
Comparing all the tools, methods and techniques available for project management
The project management offers a wide range of tools for organizing the task within a
project. However this project has used Gantt chart for the purpose of scheduling method. The
other type of scheduling method that are offered towards the project is known as resources
oriented scheduling. The main reason behind using Gantt chart is to provide an effective idea
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
about the way project can be planned and scheduled based on the resources that are available. On
the other hand resource oriented scheduling is performed when there is competition between
different components (Hwang et al. 2015). In addition to this resources-oriented scheduling
offers knowledge related to the tasks only. Project management software tool helps in managing
the projects effectively and ensures that all components are explained with the use of MS project
software tool. The main reason behind using MS project tool is that it helps in analyzing the
activities effectively whereas in MS excel it becomes difficult to manage complex processes like
renovation project. With the help of MS project tools it becomes easy to manage the activities for
Royale Pizza shop renovation effectively and ensure that the project is being carried out
successfully within the given time period. Beside this it has been observed that the project
managers use critical path technique for determining the path (Iyer and Banerjee 2016).
However, one more technique is offered towards project managers that is known as PERT
technique. The main reason behind selecting CPM is that it helps in discovering the longest
possible route for the project managers whereas PERT helps in providing visualization towards
the task flow only. Thus, CPM is considered as the best method for this project.
Document Page
8
PROJECT MANAGEMENT
1.3 Critical path reflecting stress point
The figure that is provided below helps in reflecting the stress point on the critical path of
the project.
Figure 1: Critical path
(Source: Created by Author)
1.4 Tools for critical path
CPM analysis method is mainly used in order to showcase the critical path of the project.
It is found that the CPM analysis method helps in planning all the work activities that is required
to be completed and helps in determining the minimum length of time that is required for
accomplishing the project successfully.
Document Page
9
PROJECT MANAGEMENT
2. Project budget and ways for controlling cost of the project
2.1 Project budget
The table that is provided below helps in depicting the total budget by including
information about direct cost, indirect cost as well as method that is utilized for estimation
WBS
description
Resource Direct
costs
Indirect
costs
Total
estimate
Method Additional
informatio
n
Pizza shop
renovation
AU$
27,500.0
0
AU$
12,500.0
0
AU$
40,000.0
0
Bottom -
up
estimatio
n
N/A
Design
phase
AU$
5,000.00
AU$
000.00
AU$
5,000.00
Bottom -
up
estimatio
n
N/A
Undertaking
meeting with
the workers of
the store
Project
management
consultant
AU$
500.00
AU$
000.00
AU$
500.00
Bottom -
up
estimatio
n
N/A
Researching
the problem
Project
manager
AU$
500.00
AU$
000.00
AU$
500.00
Bottom -
up
estimatio
n
N/A
Identifying
solution
Project
management
consultant,
Project
manager
AU$
500.00
AU$
000.00
AU$
500.00
Bottom -
up
estimatio
n
N/A
Creating
schematic
design
Designer AU$
3,500.00
AU$
000.00
AU$
3,500.00
Bottom -
up
estimatio
n
N/A
Procurement
and delivery
phase
AU$
6,000.00
AU$
12,000.0
0
AU$
18,000.0
0
Bottom -
up
estimatio
n
N/A
Determining
products and
services
Procurement
manager
AU$
400.00
AU$
000.00
AU$
400.00
Bottom -
up
estimatio
n
N/A
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10
PROJECT MANAGEMENT
Hiring
suppliers
Procurement
manager,
Project
management
consultant
AU$
300.00
AU$
000.00
AU$
300.00
Bottom -
up
estimatio
n
N/A
Buying
different types
of materials
and equipment
Supplier AU$
000.00
AU$
12,000.0
0
AU$
12,000.0
0
Bottom -
up
estimatio
n
N/A
Performing
quality
assurance
Quality
analyst
AU$
4,300.00
AU$
4,300.00
Bottom -
up
estimatio
n
N/A
Analyzing
the results and
margins
Procurement
manager,
Project
management
consultant
AU$
1,000.00
AU$
1,000.00
Bottom -
up
estimatio
n
N/A
Construction
phase
AU$
6,500.00
AU$
500.00
AU$
7,000.00
Bottom -
up
estimatio
n
N/A
Completing
the work of
flooring
Civil
engineer,
Constructio
n manager
AU$
2,000.00
AU$
000.00
AU$
2,000.00
Bottom -
up
estimatio
n
N/A
Professional
cleaning of
kitchen
Constructio
n manager
AU$
2,000.00
AU$
000.00
AU$
2,000.00
Bottom -
up
estimatio
n
N/A
Removing
the shop from
rear area for
providing
cooking space
Civil
engineer,
Constructio
n manager
AU$
1,500.00
AU$
000.00
AU$
1,500.00
Bottom -
up
estimatio
n
N/A
Adding
additional
dining space
Constructio
n manager
AU$
1,000.00
AU$
1,000.00
Bottom -
up
estimatio
n
N/A
Undertaking
inspection
Inspection
officer
AU$
000.00
AU$
500.00
AU$
500.00
Bottom -
up
estimatio
n
N/A
Installation
phase
AU$
10,000.0
0
AU$
000.00
AU$
10,000.0
0
Bottom -
up
estimatio
N/A
Document Page
11
PROJECT MANAGEMENT
n
Installation of
air
conditioning
system
Installer AU$
2,000.00
AU$
000.00
AU$
2,000.00
Bottom -
up
estimatio
n
N/A
Dust free
painting
Painter AU$
5,500.00
AU$
000.00
AU$
5,500.00
Bottom -
up
estimatio
n
N/A
Equipment
installation
Installer AU$
1,500.00
AU$
000.00
AU$
1,500.00
Bottom -
up
estimatio
n
N/A
Hardware
and software
installation
Installer,
Quality
analyst
AU$
1,000.00
AU$
000.00
AU$
1,000.00
Bottom -
up
estimatio
n
N/A
2.2 Assumptions that are made
The various types of assumptions which are made with the help of the project manager
during the preparation of the budget are listed below:
The money that is required for buying different types of equipment’s including exhaust
system, dough roller and more within the budget of around AU$12,000
The entire work of renovation is assumed to be completed within the budget of
AU$40,000 and the financial manager further assumes that the problem of budget
overshoot will not occur.
2.3 Ways for controlling cost
The strategies or methods which are used within the project in order to control the cost of
the project for avoiding budget overshoot are listed below:
Document Page
12
PROJECT MANAGEMENT
The budget expenditure should be tracked on a regular basis for avoiding the issue of
over expenditure while executing the project activities.
The estimation during the initial plan should be done effectively so that the problem of
over budget will not be faced by the project managers.
3. Risk management and identification of tools and techniques
3.1 Tools and techniques for identifying risk management
The different types of tools, techniques which are used for determining the risks that can
occur during the renovation work are listed below:
Root cause analysis: This is one of the methods that identifies the various types of
challenges which occur during the renovation of the pizza shop so that they can be mitigated
effectively (Carvalho and Rabechini Junior 2015).
Risk register: This is one of the significant tools that is used for updating risks with
proper mitigation strategies so that the problems that occur within the project can be mitigated
properly without creating any type of negative impact.
Probability and impact matrix: This particular matrix is generally used for categorizing
the risk as per their impact and likelihood of occurrence and this can further be customized as per
the required for mitigating the risks (Kaiser et al. 2015).
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13
PROJECT MANAGEMENT
3.3 Risk identification, analysis and mitigation
Document Page
14
PROJECT MANAGEMENT
Risk
ID Risk Statement Probability Impact Score Response
plan/Strategy
1 Schedule
slippage: The
project schedule
that is created for
the renovation
project gets slipped
because of
improper
management then it
generally can cause
delay within the
project that further
increases the
budget for
completing the
work in the
extended schedule.
High High 4 In order to mitigate
this challenge, one of
the most important
steps is to keep track
on the current status of
the project so that the
renovation work gets
finished on time and
the project does not
face any type of issue.
2 Budget overshoot:
If the budget that
that is needed for
managing the
project is not
sufficient then a lot
of financial
obstruction occurs
which the project
due to which the
High High 5 The problem of budget
overshoot can be
resolved if proper
track on the
expenditure is kept. In
addition to this, the
project managers must
adopt proper strategies
which are beneficial in
controlling the budget
Document Page
15
PROJECT MANAGEMENT
Bibliography
Batselier, J. and Vanhoucke, M., 2015. Construction and evaluation framework for a real-life
project database. International Journal of Project Management, 33(3), pp.697-710.
Cagliano, A.C., Grimaldi, S. and Rafele, C., 2015. Choosing project risk management
techniques. A theoretical framework. Journal of Risk Research, 18(2), pp.232-248.
Carvalho, M.M.D. and Rabechini Junior, R., 2015. Impact of risk management on project
performance: the importance of soft skills. International Journal of Production Research, 53(2),
pp.321-340.
Cheng, J.Y., Shu, L.Y. and Liu, Q., 2017. Design and Implementation of Fine Monitoring and
Management System of Traditional Chinese Medicine Project Budget. Journal of Medical
Informatics, 38(8), pp.35-39.
de Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its effects
on project success: Cross-country and cross-industry comparisons. International Journal of
Project Management, 33(7), pp.1509-1522.
Hopkin, P., 2018. Fundamentals of risk management: understanding, evaluating and
implementing effective risk management. Kogan Page Publishers.
Hwang, B.G., Zhao, X. and Tan, L.L.G., 2015. Green building projects: Schedule performance,
influential factors and solutions. Engineering, Construction and Architectural
Management, 22(3), pp.327-346.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16
PROJECT MANAGEMENT
Iyer, K.C. and Banerjee, P.S., 2016. Measuring and benchmarking managerial efficiency of
project execution schedule performance. International Journal of Project Management, 34(2),
pp.219-236.
Kaiser, M.G., El Arbi, F. and Ahlemann, F., 2015. Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), pp.126-139.
Kerzner, H., 2019. Using the project management maturity model: strategic planning for project
management. Wiley.
Lu, F., Hu, Y., Bi, H., Huang, M. and Zhao, M., 2018. An Auction Approach for Cost and
Schedule Management of IT Outsourcing Project. Asia-Pacific Journal of Operational
Research, 35(05), p.1850034.
Mehlawat, M.K. and Gupta, P., 2016. A new fuzzy group multi-criteria decision making method
with an application to the critical path selection. The International Journal of Advanced
Manufacturing Technology, 83(5-8), pp.1281-1296.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Routledge.
Ong, H.Y., Wang, C. and Zainon, N., 2016. Integrated earned value Gantt chart (EV-Gantt) tool
for project portfolio planning and monitoring optimization. Engineering Management
Journal, 28(1), pp.39-53.
Serrador, P. and Turner, R., 2015. The relationship between project success and project
efficiency. Project Management Journal, 46(1), pp.30-39.
Document Page
17
PROJECT MANAGEMENT
Serrador, P. and Pinto, J.K., 2015. Does Agile work?—A quantitative analysis of agile project
success. International Journal of Project Management, 33(5), pp.1040-1051.
Thomas, H.R. and Ellis Jr, R.D., 2017. Construction Site Management and Labor Productivity
Improvement: How to Improve the Bottom Line and Shorten the Project Schedule.
chevron_up_icon
1 out of 18
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]