Table of Contents INTRODUCTION.........................................................................................................................3 STAGE 3......................................................................................................................................3 1.Lists of activities and work breakdown structure for project..............................................3 2. Project calendar.....................................................................................................................6 ...................................................................................................................................................8 3. PDM diagram and A Gantt chart...........................................................................................9 4. Weekly Gantt Chart of all activities..................................................................................10 5. A list and costs of all resources..........................................................................................11 6. Final costs and detail budget reports..................................................................................11 7. Different resources schedule in form of Gantt chart..........................................................11 8. A budget and cost forecast.................................................................................................12 9. Other relevant reports to support the PEP...........................................................................12 CONCLUSION...........................................................................................................................13 REFERENCES.............................................................................................................................14
INTRODUCTION Project managementis basically a procedure which include initiation, development of plan, execution and closure activitiesafter completion ofparticular objectives. IT project management can be referred to as procedure of managing plan.Proper administration of undertaking is essential for ensuring successful (Griffiths, Kovaleva and Hepburn, 2015 ). It is the procedure which includes planning as well as organisation offirm resourcesfor accomplishing desired project related targets. The project planning management plan assist project manager in addressing the risksrelated to implementation of the specific project. It assist project manager in identifying the factors which might influence on project. The project management report will have focus on identification of the costs as well as resources required for implementation of project related toestablishment of information technology centre in capital city. STAGE 3. 1. Lists of activities and work breakdown structure Lists of tasks : It is considered to be as one of the crucial activity in project management. Lists of tasks prepared by project manager assist them in making an accurate determination related to the time required for performing the different tasks. Proper allocation and distribution of resources are very much essential in order to eliminate the barriers during the project. Listing of resources also assist project manager in developing the milestones (Hasnine, Chayon and Rahman, 2015.). It is required by the project manager to involves stakeholders in preparing the list of tasks for the project, as the information provided them can be valuable in context of maintaining or managing the different activities during the tasks. Project lists Project task list 1.Preparation of lists of tasks 2.Deter mining the needs of performing specific activity.
3.Creation of charter for project 4.Permission from management 5.Construction of building 6.Combining the requirements 7.Consolidation of beliefs 8.Designing of final system 9.Again taking permission from management 10.Preparation of model 11.Combining necessitate 12.Construction procedure 13.Combination of Hardware 14.Testing of system 15.Testing the applications 16.Identification of problems 17.Trouble shooting procedure 18.Live construction and development of system 19.Integrating hard-wares and soft wares 20.Arranging and managing resources 21.Management of problems using different techniques 22.Up gradation of System 23.Rejection 24.Closing of project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Name of activities Establishment of new information centre at capital city Analysis of requirements Preparation of lists Determination of need of resources in project Creation of the charter for project Seeking permission from management Designing of system Creation or establishment ofinfrastructure and framework for system Integrating the applicable necessity Integrating hypothesis Designing ofterminal Permission from management Execution Preparation ofparadigm Integrating necessitate building procedure Integrating of hardware Testing Testing of system elucidation of problems Development Integrating of hardware and software tool Resource governance Maintenance of instrumentation Maintenance of problems Updation of system
Rejection Closure of project waterfall methodology ha been utilised by project manager in this project for showing the differentstages of the project which are required to be completed. Every stage or big tasks in the procedure are breakdown into small parts in order to make easier for employees to perform specific activity. Above work breakdown structure indicates the activities which are required to be performed for completing the project related to development of new IT centre in capital city in systematic manner (Heagney, 2016.).All themain as well as sub activities will be performed according to the schedule date. The work breakdown structure has been prepared by the project manager in order to manage the work distribution procedure. It is the work break down structure which has assisted project manager in doing a proper allocation of time within with specific activity is required to be completed. 2. Project calendar In context of implementation of undertakingrelated to theestablishment of information technology centre calendar consists of list of public holidays in Australia.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
In context of present project related to establishment of Information technological centre in capital city, it is the calendar has assist project manager in managing the time (Heldman, 2018. ).Through the calendar only, project manager has been able to gather the information related to the holidays. Project has been schedule considering the week off which are required
to be provided to workers. Calender also indicates length of different tasks which are required to be performed during the project. 3. PDM diagram and A Gantt chart
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
In context of project on implementation of the IT centre in the capital city,the Gantt chart indicates the different tasks . It also represents the start and finish date of each activities which will be performed during the project (Krimpmann, 2015 ).The Gantt chart has provided project manager an ease inanalysing the present status of the project. It has provided them in managing the project in systematic manner. Gantt chart consists of time in terms of monthly basis according to which different activities will be performed . Gantt chart has been prepared by project manager by utilising the technical software. 5. A list and costs of all resources In order to open the new IT centre for Versus. IT resources must have managed by the application of subcontractor and by owned. By the help of all such resources the project manager required to manage all resources with the help of effective management task. All such requirement of the project helps to set the scheduling procedure (Harrison and Lock, 2017). . No.Assets name Namesof the equipments needed RootTimingNecessityUsed by 1HR teamEmployees required withinthe organizatio n. Sub- contractor: HR Services First step in the project plan. HRor workforce resources requiredto accomplish thewhole project task. Program coordina tor 2Technical supporters Technical person requiredto managethe system growth. Contractor requiredthe best required mannerof thingwhich makesthe more effective learning goals. Developme nt and managing the work opportunity goals and make the best developing source. It is necessary to understand thetechnical requirements. Project director 3Cloud services Grouping functionalit y Dealers, investors, stakeholders. Deploymen t phase of project Administratio nproject related work. Board 4ArrangeConcreteRequiredDevelopEnhanceCommis
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
theraw material andalso managing thework accordingly andgrowth intobest manner. resources for construction s. the project further for the implementa tion. overall scenarioof the project sion 5Access funding through different mediums. Arrange funds makesthe good thing. Customers, stakeholders, dealers. Etc. Arms of shift Takesteps forwardto accomplish overall task. Project manager 6. Final costs and detail budget reports Project cost estimation is one of the most leading tool that generally adopted for setting the budgeting of the project (Fleming and Koppelman, 2016). This process has been done on the basis of the set activities which required throughout the activities or set resources such as Human Resource, Machinery, and Technical resources. However, the more authenticated and working leading target helps to determine the long lasting work opportunity and goals. This overall project cost estimation also helpful for project manager to set the cost of the overall project. Overall it helps to estimate the budget which is needful to accomplish the outcomes (Ishii, Takano and Muraki, 2016) Project Cost Estimation Task nameDescriptionCost Development of listOfficeequipmentand employees resources. 1000 Starts or initiate the building and followed the systematic procedure Designercost,system technologicalcosttopull offtheoverallsystem opportunity. 10000 Group actionSystem developer cost5000 Design the final steps system Accepting cots.2500 System testingTestercostandtaking feedbackthroughdifferent methods and ways. 10000 Application of the UAT testing Testers software’s2000 Discuss issues and systemStudy improvement2000 Problem solving processDeveloper cost and resource25000 Update the live event andAll theresourcesrequired10 million AUD
develop the all required system forconstructionproject which is required to manage the all assigned work such as land, resources Collaboration of software and hardware skills. All system developing cost.2 million system UpdateWorkforceresources,or some computer hardware’s or software resources. 10000AUD 7. Different resources schedule in form of Gantt chart In context of present project related to the establishment of Information centre in Capital city, the different resources required are :
8. A budget and cost forecast Estimation of costs Task nameDescriptionCost 1.Preparation of listsCosts of human resource, purchase of stationery 1200 AUD 2.Construction of buildingSalary of designer,costs of installation of hardware and software 130145 AUD 3.Integrating of premisesSalary of System developer4950 AUD 4.Designing of final systemSalaryandwagesof employees 1450 AUD 5.Testing of systemTester cost, testing tool cost15159 AUD 6.ApplicationoftheUAT testing Testers software’s3149 AUD 7.Trouble shooting procedureDevelopercostand purchase of resource 22143. AUD 8.Liveconstructionand development of system Constructionmaterial, softwareandhardware material 12 million AUD 9. Other applicable reports to support the PEP. In context of present project related to the establishment ofinformation technology centre in capital city, the Gantt chart has assisted the project manager in development of project implementation plan (Kuchta and Skowron, 2016. ).All the activities are represented in form of water fall like framework. It is the Gantt chart which indicate the present status of the project. It also assist an individual in determining the next procedures which will be performed in order top reach desired project goals.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
SeptemberOctoberNovemberDecemberJanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovember Developmentofne winformationcentrefor Ve rsus IT Requirement analysis Development of list Assumption of requirement Development of the project charter Approval from management System design Development of building and system prototype Integration of all the relevant requirement Integration of assumption Final system design Approval from management Implementation Deployment of prototype Integration of requirements construction process Integration of hardware Testing System testing application of the UAT testing clarification of issues Trouble shooting process Development Live construction and system development Integration of hardware and software tool management of resource System Maintenance Maintenance of issues system Update Avoidance Project closure CONCLUSION Ithasbeenconcludedfromtheabovestudythatselectionofanappropriate methodology is very much crucial forcompleting the specific project in systematic manner.
From the above report, it has been summarised thatwaterfall hypothesis can be helpful in completionifprojectinpropermanner.Ithasalsobeenconcludedthatpropertime management is very much essential in order to accomplish desired outcomes. It has been suggested that project manager should develop the Gantt chart as it will provide them an ease in managing the project.