0PROJECT MANAGEMENT
Project Management Principles
Name of the Student
Name of the University

1PROJECT MANAGEMENT
Answer to 1
Figure 1: Network Diagram of the Project
(Source: Created by Author)

2PROJECT MANAGEMENT
Answer to 2
The start and end dates of the project along with the durations of each activity are shown
in the following table.
WBS Task Name Duration Start Finish
Cell Phone Design Project 36 wks Mon 4/15/19 Fri 12/20/19
P Product Specifications (P) 11 wks Mon 4/15/19 Fri 6/28/19
P1
Overall Product
Specifications
4 wks Mon 4/15/19 Fri 5/10/19
P2 Hardware Specifications 5 wks Mon 5/13/19 Fri 6/14/19
P3 Software Specifications 5 wks Mon 5/13/19 Fri 6/14/19
P4 Market Research 2 wks Mon 6/17/19 Fri 6/28/19
S Supplier Specifications (S) 6 wks Mon 6/17/19 Fri 7/26/19
S1 Hardware 5 wks Mon 6/17/19 Fri 7/19/19
S2 Software 6 wks Mon 6/17/19 Fri 7/26/19
S3 Market Research 1 wk Mon 7/1/19 Fri 7/5/19
D Product Design (D) 14 wks Mon 7/8/19 Fri 10/11/19
D1 Circuits 3 wks Mon 9/23/19 Fri 10/11/19

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management
|7
|813
|69

Project Management -Assignment
|11
|1567
|107

PRMG-010 Project Planning and Control Teqniques
|14
|1545
|76

Project Crashing in Project Management
|7
|1752
|60

Project Management Exercises
|6
|1010
|65

Project Management: Tasks, WBS, Activity Durations, Cost Report
|11
|1124
|463