ProductsLogo
LogoStudy Documents
LogoAI Grader
LogoAI Answer
LogoAI Code Checker
LogoPlagiarism Checker
LogoAI Paraphraser
LogoAI Quiz
LogoAI Detector
PricingBlogAbout Us
logo

Project Management: New Hybrid Handheld Game Console Project

Verified

Added on  2023/04/21

|28
|4346
|259
AI Summary
The project management tools help the project manager and project team members to manage the project effectively and reduce the risks of project failure. This project study examines the usage of project management tools such as Gantt chart and PERT chart which lead to effective project management. The critical path and project float is also determined in the report. The project manager uses the project float time for scheduling the timing of tasks and timeframes to make best decisions to make sure that the project is on time. The critical path helps to determine important project activities that have impact on the project schedule. The shortest duration for problem 1 is 54 weeks and problem 3 is 84 weeks which is analyzed by using critical path method. Resource leveling is used for resource planning and scheduling the project activities. Resource constraints are caused when staffs are main source of project limitation. Resource leveling has impact on project schedule which causes delay in entire project plan.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
New Hybrid Handheld Game Console Project
Name of the Student:
Name of the University:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Abstract
The project management tools help the project manager and project team members to manage the
project effectively and reduce the risks of project failure. This project study examines the usage
of project management tools such as Gantt chart and PERT chart which lead to effective project
management. The critical path and project float is also determined in the report. The project
manager uses the project float time for scheduling the timing of tasks and timeframes to make
best decisions to make sure that the project is on time. The critical path helps to determine
important project activities that have impact on the project schedule. The shortest duration for
problem 1 is 54 weeks and problem 3 is 84 weeks which is analyzed by using critical path
method. Resource leveling is used for resource planning and scheduling the project activities.
Resource constraints are caused when staffs are main source of project limitation. Resource
leveling has impact on project schedule which causes delay in entire project plan.
Document Page
2PROJECT MANAGEMENT
Table of Contents
Introduction......................................................................................................................................3
Part A- Planning documents for new hybrid handheld game console project.................................3
Problem 1:....................................................................................................................................3
1. Activity-on-node network....................................................................................................3
2. Critical path..........................................................................................................................8
3. Gantt chart............................................................................................................................8
Problem 2:..................................................................................................................................11
Resource Diagram..................................................................................................................11
Problem 3:..................................................................................................................................12
Updated resource diagram......................................................................................................12
Recommendations..........................................................................................................................18
Conclusion.....................................................................................................................................18
Part B:............................................................................................................................................19
1. Network diagram....................................................................................................................19
2. Forward and backward pass calculation................................................................................21
3. Critical path for the project....................................................................................................22
References......................................................................................................................................24
Bibliography..................................................................................................................................25
Document Page
3PROJECT MANAGEMENT
Introduction
The report discusses the activity-on-node, Gantt chart and critical path for the project
plan of new hybrid handheld game console project. The main activities of the project plan are
requirements specification, content specification, design, implementation, integration and
subcontracting. In this report, the project management tool such as Gantt chart is used to
represent the time for each project activities needed to complete the project work. Martinelli and
Milosevic (2016) have stated that it is simple and easier to understand the project progress. The
report also discusses the Precedence network diagrams which is visual representation technique
which can depict the project activities involved into the project.
Part A- Planning documents for new hybrid handheld game console project
Problem 1:
1. Activity-on-node network
The activity-on-node is the term of project management which is referred to precedence
diagramming method that uses boxes to present the schedule activities of entire project plan. The
boxes and nodes are being associated from staring to finish with arrows to present the reasonable
representation of the dependencies among the schedule activities (Too and Weaver 2014). In
terms of project management, float or total slack is sum of time that the project job is delayed
without causing delay to project completion time.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT MANAGEMENT
Document Page
5PROJECT MANAGEMENT
Figure 1: Activity on node
(Source: Created by author)
The project schedule is shown in the table below with starting time, finishing time, floats and other information based on the
activities in the network diagram.
WB
S Task Name Duratio
n Start Finish Resource Names WBS
Predecessors
Total
Slack
0 New hybrid handheld game
console project_Problem 1 54 wks Mon
12/24/18 Fri 1/3/20 0 wks
1 Requirements specification 13 wks Mon
12/24/18
Fri
3/22/19 0 wks
1 Entire product 3 wks Mon
12/24/18
Fri
1/11/19
Developer, Market Researcher, Project Lead,
Project Manager, Software Engineer, System
Analyst
0 wks
2 Software 5 wks Mon
1/14/19
Fri
2/15/19
Developer, Project Manager, Software
Engineer, System Analyst 1 0 wks
3 Hardware 4 wks Mon
2/18/19
Fri
3/15/19
Developer, Project Manager, Software
Engineer, System Analyst 1,2 0 wks
4 Market research 1 wk Mon
3/18/19
Fri
3/22/19
Market Researcher, Project Lead, Project
Manager 2,3 0 wks
2 Content specification 12.6
wks
Mon
2/18/19
Wed
5/15/19 0 wks
11 Software 6 wks Mon
2/18/19
Wed
5/15/19
Designer, Developer, Project Lead, Project
Manager, Software Engineer, System Analyst 2 0 wks
12 Hardware 5 wks Fri
3/15/19
Thu
5/9/19
Project Lead, Project Manager[0%], Software
Engineer, System Analyst 3 9.8
wks
13 Market research 2 wks Mon
3/25/19 Fri 4/5/19 Project Lead, Project Manager, Market
Researcher, System Analyst 4 0 wks
Document Page
6PROJECT MANAGEMENT
3 Design 18.2
wks
Thu
5/9/19
Fri
9/13/19
0.4
wks
21 User interface 7 wks Thu
5/16/19
Thu
9/5/19
Designer, Developer, Software Engineer,
System Analyst 11 0 wks
22 Functionality 3 wks Mon
7/1/19
Fri
7/19/19
Developer, Project Manager, Software
Engineer, System Analyst, Tester 11,51 0 wks
23 Battery 2 wks Thu
6/20/19
Wed
7/3/19 Project Lead 12 9.8
wks
24 Circuits 8 wks Mon
7/22/19
Fri
9/13/19
Designer, Software Engineer, System Analyst,
Tester 12,22 0 wks
25 Display 3 wks Fri
5/10/19
Tue
6/4/19
Project Manager, Software Engineer, System
Analyst 12 10
wks
26 Outer cover 6 wks Thu
5/9/19
Thu
6/20/19
Market Researcher, Project Lead, Project
Manager, Software Engineer 12 12.6
wks
27 Camera 2 wks Mon
7/22/19 Fri 8/2/19 Developer 11,12,51 4 wks
4 Implementation 21.6
wks
Tue
6/4/19
Fri
11/1/19 3 wks
31 User interface 4 wks Mon
9/16/19
Fri
10/25/19
Designer, Developer, Software Engineer,
System Analyst 21,52 0 wks
32 Functionality 4 wks Fri
7/19/19
Mon
9/16/19 Designer, Developer, Software Engineer 22 5.8
wks
33 Battery 2 wks Thu
7/4/19
Mon
8/26/19 Project Lead, Project Manager 23 9.8
wks
34 Circuits 7 wks Mon
9/16/19
Fri
11/1/19
Designer, Developer, Market Researcher,
Software Engineer, System Analyst 24 0 wks
35 Display 5 wks Tue 6/4/19 Fri
8/23/19
Project Manager, Software Engineer, System
Analyst 25 10
wks
36 Outer cover 5 wks Fri
6/21/19
Tue
8/27/19
Market Researcher, Project Lead, Project
Manager, Software Engineer 26 12.6
wks
5 Integration 10 wks Mon Fri 1/3/20 0 wks

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
7PROJECT MANAGEMENT
10/28/19
41 Software 4 wks Mon
10/28/19
Fri
11/22/19
Designer, Developer, Market Researcher,
Project Manager, Software Engineer, System
Analyst
31,32,53 0 wks
42 Hardware 3 wks Mon
11/4/19
Fri
11/22/19
Developer, Software Engineer, System
Analyst 33,34,35,53 0 wks
43 Entire product 1 wk Mon
11/25/19
Fri
11/29/19
Developer, Market Researcher, Project Lead,
Project Manager, Software Engineer, System
Analyst
36,41,42 0 wks
44 Testing 5 wks Mon
12/2/19 Fri 1/3/20 Software Engineer, System Analyst, Tester 43 0 wks
6 Subcontracting 25 wks Mon
4/8/19
Fri
9/27/19 0 wks
51 Market research
(implementation) 12 wks Mon
4/8/19
Fri
6/28/19 13 0 wks
52 Games (design &
implementation) 5 wks Mon
7/1/19 Fri 8/2/19 11,51 4.8
wks
53 Camera (implementation) 8 wks Mon
8/5/19
Fri
9/27/19 27 4 wks
Document Page
PROJECT MANAGEMENT 8
2. Critical path
The critical path is sequence of the project stages determine minimum time required to
complete the entire project work.
ID Task
Mode
WBS Task Name
2 1 Entire product
3 2 Software
4 3 Hardware
5 4 Market research
7 11 Software
9 13 Market research
11 21 User interface
12 22 Functionality
14 24 Circuits
19 31 User interface
22 34 Circuits
26 41 Software
27 42 Hardware
28 43 Entire product
29 44 Testing
31 51 Market research (implementation)
Developer,Market Researcher,Project Lead,Project Manager,Software Engineer,System Analyst
Developer,Project Manager,Software Engineer,System Analyst
Developer,Project Manager,Software Engineer,System Analyst
Market Researcher,Project Lead,Project Manager
Designer,Developer,Project Lead,Project Manager,Software Engineer,System Analyst
Project Lead,Project Manager,Market Researcher,System Analyst
Designer,Developer,Software Engineer,System Analyst
Developer,Project Manager,Software Engineer,System Analyst,Tester
Designer,Software Engineer,System Analyst,Tester
Designer,Developer,Software Engineer,System Analyst
Designer,Developer,Market Researcher,Software Engineer,System Analyst
Designer,Developer,Market Researcher,Project Manager,Software Engineer,System An
Developer,Software Engineer,System Analyst
Developer,Market Researcher,Project Lead,Project Manager,Software Engineer,System
Software Engineer,System Analyst,Tester
S M T W T F S S M T W T F S S M T W T F S S M T W T F
Nov 18, '18 Jan 6, '19 Feb 24, '19 Apr 14, '19 Jun 2, '19 Jul 21, '19 Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
Figure 2: Critical path
From the above diagram, it is identified that the critical path is the shortest possible
duration for the project which is highlighted in red.
Critical path activities = 1-2-3-4-13-22-24-34-42-43-44-51
= (3+5+4+1+2+3+8+7+3+1+5+12) weeks
= 54 weeks
Therefore, 54 weeks is the shortest possible duration for the project.
3. Gantt chart
Gantt chart is the graphical method to demonstrate the development of the project work
(Fuller et al. 2017). The tasks of the project plan are complex and it is dependent on each other
Document Page
PROJECT MANAGEMENT 9
which are shown in the diagram. With the project management tool such as Gantt chart, the sub-
tasks of each project activities are viewed graphically.

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PROJECT MANAGEMENT 10
ID Task
Mode
WBS Task Name Duration
0 0 New hybrid handheld game
console project_Problem 1
54 wks
1 1 Requirements specification 13 wks
2 1 Entire product 3 wks
3 2 Software 5 wks
4 3 Hardware 4 wks
5 4 Market research 1 wk
6 2 Content specification 12.6 wks
7 11 Software 6 wks
8 12 Hardware 5 wks
9 13 Market research 2 wks
10 3 Design 18.2 wks
11 21 User interface 7 wks
12 22 Functionality 3 wks
13 23 Battery 2 wks
14 24 Circuits 8 wks
15 25 Display 3 wks
16 26 Outer cover 6 wks
17 27 Camera 2 wks
18 4 Implementation 21.6 wks
19 31 User interface 4 wks
20 32 Functionality 4 wks
21 33 Battery 2 wks
22 34 Circuits 7 wks
23 35 Display 5 wks
24 36 Outer cover 5 wks
25 5 Integration 10 wks
26 41 Software 4 wks
27 42 Hardware 3 wks
28 43 Entire product 1 wk
29 44 Testing 5 wks
30 6 Subcontracting 25 wks
31 51 Market research (implementation)12 wks
32 52 Games (design & implementation)5 wks
33 53 Camera (implementation) 8 wks
Developer,Market Researcher,Project Lead,Project Manager,Software Engineer,System Analyst
Developer,Project Manager,Software Engineer,System Analyst
Developer,Project Manager,Software Engineer,System Analyst
Market Researcher,Project Lead,Project Manager
Designer,Developer,Project Lead,Project Manager,Software Engineer,System Analyst
Project Lead,Project Manager[0%],Software Engineer,System Analyst
Project Lead,Project Manager,Market Researcher,System Analyst
Designer,Developer,Software Engineer,System Analyst
Developer,Project Manager,Software Engineer,System Analyst,Tester
Project Lead
Designer,Software Engineer,System Analyst,Tester
Project Manager,Software Engineer,System Analyst
Market Researcher,Project Lead,Project Manager,Software Engineer
Developer
Designer,Developer,Software Engineer,System Analyst
Designer,Developer,Software Engineer
Project Lead,Project Manager
Designer,Developer,Market Researcher,Software Engineer,System Analyst
Project Manager,Software Engineer,System Analyst
Market Researcher,Project Lead,Project Manager,Software Engineer
Designer,Developer,Market Researcher,Project Manager,Software Engineer,System Analyst
Developer,Software Engineer,System Analyst
Developer,Market Researcher,Project Lead,Project Manager,Software Engineer,System An
Software Engineer,System Analyst,Tester
S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Nov 18, '18 Jan 6, '19 Feb 24, '19 Apr 14, '19 Jun 2, '19 Jul 21, '19 Sep 8, '19 Oct 27, '19 Dec 15, '19 Feb 2, '20 Mar 22, '20 May 10, '20 Jun 28, '20
Figure 3: Gantt chart
Document Page
PROJECT MANAGEMENT 11
Problem 2:
Resource Diagram
The remaining work is the amount of work in terms of the time unit that is left for
completed on the project tasks.
Figure 4:
Resource Histogram
Name Start Finish Remaining Work
Project Manager Mon 12/24/18 Fri 12/6/19 1,400 hrs
Developer Mon 12/24/18 Fri 12/6/19 1,760 hrs
Software Engineer Mon 12/24/18 Fri 1/10/20 2,120 hrs
Market Researcher Mon 12/24/18 Fri 12/6/19 1,040 hrs
Tester Mon 7/1/19 Fri 1/10/20 640 hrs
System Analyst Mon 12/24/18 Fri 1/10/20 2,200 hrs
Designer Mon 2/18/19 Fri 11/8/19 1,160 hrs
Project Manager
Developer
Software Engineer
Market Researcher
Tester
System Analyst
Designer
Project Lead
0 hrs 500 hrs 1,000 hrs 1,500 hrs 2,000 hrs 2,500 hrs
1,400 hrs
1,760 hrs
2,120 hrs
1,040 hrs
640 hrs
2,200 hrs
1,160 hrs
1,040 hrs
Remaining Work Work
Document Page
PROJECT MANAGEMENT 12
Project Lead Mon 12/24/18 Fri 12/6/19 1,040 hrs
Problem 3:
Updated resource diagram
According to the study of Harrison and Lock (2017), in order to estimate the human
resources for the project plan, it is estimated that there are total of 10 staffs selected at any one
time to work into the project. The resources are level as per the limitation into the project work.
It is also noticed that the tasks are not broken into pieces and not conducted for long period of
time. The new Gantt chart for the project is shown along with the resource usage which is
described in new resource diagram, then it will describe the shortest possible duration for the
project plan as:
WBS Task Name Duration Start Finish
0
New hybrid handheld
game console project
55 wks Mon 12/24/18 Fri 1/10/20
1
Requirements
specification
13 wks Mon 12/24/18 Fri 3/22/19
1 Entire product 3 wks Mon 12/24/18 Fri 1/11/19
2 Software 5 wks Mon 1/14/19 Fri 2/15/19
3 Hardware 4 wks Mon 2/18/19 Fri 3/15/19
4 Market research 1 wk Mon 3/18/19 Fri 3/22/19

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PROJECT MANAGEMENT 13
2 Content specification 11 wks Fri 2/15/19 Fri 5/3/19
11 Software 6 wks Fri 2/15/19 Fri 3/29/19
12 Hardware 5 wks Mon 4/1/19 Fri 5/3/19
13 Market research 2 wks Mon 3/25/19 Fri 4/5/19
3 Design 24 wks Mon 4/1/19 Fri 9/13/19
21 User interface 7 wks Mon 4/1/19 Fri 5/17/19
22 Functionality 3 wks Mon 7/1/19 Fri 7/19/19
23 Battery 2 wks Mon 6/3/19 Fri 6/14/19
24 Circuits 8 wks Mon 7/22/19 Fri 9/13/19
25 Display 3 wks Mon 5/6/19 Fri 5/24/19
26 Outer cover 6 wks Mon 5/6/19 Fri 6/14/19
27 Camera 2 wks Mon 7/22/19 Fri 8/2/19
4 Implementation 24 wks Mon 5/27/19 Fri 11/8/19
31 User interface 4 wks Mon 9/2/19 Fri 9/27/19
32 Functionality 4 wks Fri 7/19/19 Fri 8/30/19
Document Page
PROJECT MANAGEMENT 14
33 Battery 2 wks Mon 6/17/19 Fri 6/28/19
34 Circuits 7 wks Mon 9/16/19 Fri 11/8/19
35 Display 5 wks Mon 5/27/19 Fri 6/28/19
36 Outer cover 5 wks Fri 6/14/19 Fri 7/19/19
5 Integration 15 wks Mon 9/30/19 Fri 1/10/20
41 Software 4 wks Mon 9/30/19 Fri 10/25/19
42 Hardware 3 wks Mon 11/11/19 Fri 11/29/19
43 Entire product 1 wk Mon 12/2/19 Fri 12/6/19
44 Testing 5 wks Mon 12/9/19 Fri 1/10/20
6 Subcontracting 25 wks Mon 4/8/19 Fri 9/27/19
51
Market research
(implementation)
12 wks Mon 4/8/19 Fri 6/28/19
52
Games (design &
implementation)
5 wks Mon 7/1/19 Fri 8/2/19
53
Camera
(implementation)
8 wks Mon 8/5/19 Fri 9/27/19
Document Page
PROJECT MANAGEMENT 15

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PROJECT MANAGEMENT 16
Updated Gantt chart
Figure 5: Gantt chart
Document Page
PROJECT MANAGEMENT 17
Updated Resource diagram
Figure 6: Updated resource diagram
The critical path of the new project plan is:
= 1-2-3-4-13-22-24-34-42-43-44-51
= (3+5+4+1+2+3+8+7+3+1+5+12) weeks
= 54 weeks, possible shortest duration of the project.
Therefore, it is seen that the duration of entire project is increased due to resource
constraints.
Yes, the resource constraints can change perception of the critically of the project
activities in new Gantt chart. Delay in the critical path activities will cause delay in the entire
Project Manager
Developer
Software Engineer
Market Researcher
Tester
System Analyst
Designer
Project Lead
0 hrs 500 hrs 1,000 hrs 1,500 hrs 2,000 hrs 2,500 hrs
1,400 hrs
1,760 hrs
2,120 hrs
1,040 hrs
640 hrs
2,200 hrs
1,160 hrs
1,040 hrs
Document Page
PROJECT MANAGEMENT 18
project work. Perceptions present way people become aware of other people’s concerns (Kerzner
2017). Therefore, the critical projects are crucial perception for the project manager.
Recommendations
In order to overcome with the resource constraints in the project, following
recommendations are suggested to the project manager as:
Resource planning: A proper resource planning is required in the project before the
activity is required to have resources assigned to the project activities as per their availability.
Therefore, proper resource estimation is done to assign the resources to each project activities in
activity list.
Hire of more resources: As per division of the project activities for conducting the
project work, the HR manager should hire resources as per the tasks. The resources are selected
based on their skills and expertise.
Conclusion
It is concluded that the report is relevant to the project management bodies of knowledge
which is an evaluation tool used to focus as well as measure management of change within
project domains. The project manager ensures that all terms of project are being addressed. The
project management tool is used to handle change dynamics will add towards supporting as well
as leveraging individual capital of organization in awareness with familiar goals as well as
improved the development deliverables.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PROJECT MANAGEMENT 19
From this report, it is learnt that monitoring and controlling of project plan is required to
keep track of the project. The project management team can understand reasons for the project
and the factors which can influence the project activities. There is also support plus participation
of the project stakeholders to ensure controlled development of project plan. This report
addresses development of activity on node diagram and analyzes corrective actions to determine
the project schedule. We have leant about the critical path method which measures the longest
path of the developed project activities to complete the project work. When any of the project
activity is delayed, then it impacts the considered project completion time. Understanding of the
critical path permits the project manager to decide which project schedule activities are flexible
and those are the activities which are not on critical path. By observing the network diagram, the
project manager can decide the float or slack. It is sum of time that the calendar activities can
stoppage without reasoning any delay to the starting date of the tasks or project completion time.
By addition of resource limits, the result leads that the critical path is longer. Resource forced
critical path is termed as critical chain.
Part B:
1. Network diagram
The network diagram is schematic displays of the project schedule tasks along with
interdependencies among the project activities. The graphical view of the project related
activities will convey vital schedule needed to examine as well as adjust the project schedule
(Larson and Gray 2015). The network diagram visually expresses the critical path which allows
the project manager to give priority to the project tasks moreover get proper actions to meet with
scheduled project deadlines.
Document Page
20PROJECT MANAGEMENT
Document Page
21PROJECT MANAGEMENT

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
22PROJECT MANAGEMENT
Figure 5: Network Diagram
(Source: Created by author)
2. Forward and backward pass calculation
Forward pass calculation
Activity Time EST EFT
A 5 0 5
B 7 5 12
C 2 5 7
D 12 12 24
E 20 12 32
F 4 7 11
G 11 7 18
H 8 24 32
I 6 32 38
J 3 32 35
K 9 11 20
L 1 32 33
M 14 35 49
N 19 49 68
Backward pass calculation
Activity Time EST EFT LST LFT
A 5 0 5 0 5
B 7 5 12 5 12
C 2 5 7 34 36
Document Page
23PROJECT MANAGEMENT
D 12 12 24 28 40
E 20 12 32 12 32
F 4 7 11 36 40
G 11 7 18 38 49
H 8 24 32 40 48
I 6 32 38 43 49
J 3 32 35 32 35
K 9 11 20 40 49
L 1 32 33 48 49
M 14 35 49 35 49
N 19 49 68 49 68
3. Critical path for the project
Activity Time EST EFT LST LFT Slack Criticality
A 5 0 5 0 5 0 **
B 7 5 12 5 12 0 **
C 2 5 7 34 36 29
D 12 12 24 28 40 16
E 20 12 32 12 32 0 **
F 4 7 11 36 40 29
G 11 7 18 38 49 31
H 8 24 32 40 48 16
I 6 32 38 43 49 11
J 3 32 35 32 35 0 **
K 9 11 20 40 49 29
L 1 32 33 48 49 16
M 14 35 49 35 49 0 **
Document Page
24PROJECT MANAGEMENT
N 19 49 68 49 68 0 **
From the above table, it is seen that the critical path of the project is:
= A-B-E-J-M-N
= (5+7+20+3+14+19) weeks
= 68 weeks.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
25PROJECT MANAGEMENT
References
Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project
Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. John Wiley & Sons.
Larson, E.W. and Gray, C.F., 2015. A Guide to the Project Management Body of Knowledge:
PMBOK (®) Guide. Project Management Institute.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and techniques
for the practicing project manager. John Wiley & Sons.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
Document Page
26PROJECT MANAGEMENT
Bibliography
Heldman, K., 2018. PMP: project management professional exam study guide. John Wiley &
Sons.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology and
project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management:
The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Lientz, B. and Rea, K., 2016. Breakthrough technology project management. Routledge.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Ramazani, J. and Jergeas, G., 2015. Project managers and the journey from good to great: The
benefits of investment in project management training and education. International Journal of
Project Management, 33(1), pp.41-52.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Document Page
27PROJECT MANAGEMENT
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), pp.772-783.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
1 out of 28
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]