Project Management Plan: Combustible Cladding in High Rise Construction

   

Added on  2023-01-10

11 Pages1262 Words33 Views
Running Head: PROJECT MANAGEMENT PLAN
Project Management Plan: Combustible Cladding in High Rise
Construction
Name of the Student
Name of the University

1PROJECT MANAGEMENT PLAN
3. Milestones and Major Deliverables
The milestones of the project are specified in the following table.
Milestones Estimated Completion Timeframe
Approval of the Proposal 25 days after requirement specification for the
project
Finalise the Project 21 days after project is planned
Project Successfully Initiated 23 days after project is initiated
Construction Complete 260 days after start of construction
Sign Off and Closing of the Project 349 days after the start of the project
4. Work Breakdown Structure
Work breakdown structure of a project is defined as the break down of the entire project
into a number of deliverables that are in turn broken down into different work packages. The
work breakdown structure for the project is shown in the following table.
WBS Task Name Duration
0
Design and Deployment of Combustible Cladding in High Rise
Construction
349 days
1 Requirement Specification and Analysis 25 days
1.1 Gathering of Requirements for the Project 4 days

2PROJECT MANAGEMENT PLAN
1.2 Analysis of the Requirements 3 days
1.3 Specify Building Plan 4 days
1.4 Analysis of the Proposed Plan of the Building 4 days
1.5 Determine Cladding Requirements 3 days
1.6 Design Cladding Plan along with the Building Infrastructure 2 days
1.7 Submit Proposal 5 days
1.8 Approval of the Proposal 0 days
2 Project Planning and Preparations 21 days
2.1 Define Scope and Requirements of the Project 4 days
2.2 Define Project Objectives 2 days
2.3 Determine Suitable Budget As Per Project Requirements 2 days
2.4 Risk Assessment and Analysis 5 days
2.5 Determine Suitable Risk Management Plan 4 days
2.6 Develop Quality Management Plan 4 days
2.7 Finalise the Project 0 days

3PROJECT MANAGEMENT PLAN
3 Project Initiation 23 days
3.1 Hire Contractor for Construction Management 4 days
3.2 Discuss All Relevant Requirements for the Project 2 days
3.3 Finalise the Plan and Design of the Building 3 days
3.4 Create List of Resource Requirements 2 days
3.5 Place Order for the Resource Requirements 2 days
3.6 Procure Construction Materials 5 days
3.7 Procure Cladding Materials 5 days
3.8 Project Successfully Initiated 0 days
4 Project Execution 260 days
4.1 Foundation 22 days
4.1.1 Conduct Site Excavation 5 days
4.1.2 Build Building Foundation 10 days
4.1.3 Complete Foundation Works 5 days
4.1.4 Fill the Remaining Areas with Soil and Landfill 2 days
4.2 Structural Works 138 days

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Combustible Cladding in High Rise Construction
|8
|1334
|96

Project Management Fundamentals: Building a School
|16
|1531
|406

Project Management Community Energy Scheme Report 2022
|20
|5087
|20

Project Management Fundamentals and Practices
|14
|3208
|83

Vehicle Maintenance Case Study
|29
|2434
|39

Construction Planning: Construction of Boarding Houses in NSW
|18
|2123
|63