Running Head: PM
PROJ6002: Vehicle Maintenance Case Study
Name of the Student
Name of the University

1PM
Table of Contents
Assessment 1 Part B........................................................................................................................2
1-1) Scope Management Planning...............................................................................................2
Project Scope...............................................................................................................................2
Work Breakdown Structure.........................................................................................................3
1-2) Project Scheduling.............................................................................................................12
Project Schedule and Gantt Chart..............................................................................................12
Critical Path Analysis................................................................................................................16
Bibliography..................................................................................................................................22

2PM
Assessment 1 Part B
1-1) Scope Management Planning
The main goal of this project is to set up the vehicle maintenance facility in the selected
property. The building already exists and the work required includes setting up various
structures, equipments and facilities as well as repair of the existing equipments and facilities
and changing the water and electricity connections. The overall project work will require
considerable amount of time and budget.
The final deliverable of the project is a fully prepared vehicle maintenance facility with
all old (repaired) and new equipments and facilities within the building.
Project Scope
In order to specify the scope of the project, it is also important to discuss in scope and out
scope as well as assumptions and constraints that have been considered for the project. All these
factors are discussed as follows.
In Scope
Modification of the current commercial building
Repair of equipments and other facilities
Change the electricity and water lines that are connected to the building
Possible small scale expansion given permits are available
Out of Scope
Purchase of new property adjacent to the current area

3PM
Installation of new equipments
Changes in the staffing of the building
Assumptions
All relevant permits will be given by the government
The specified time and budget are sufficient for the project
Constraints
In the current property, there is very small space for additional expansion work
Changing water and electricity lines will disrupt work in the building for
considerable amount of time
Work Breakdown Structure
The project is divided into separate phases and then classified under each phase in the
form of work breakdown structure as shown in the following table.
Project Phase 1
ID Name Duration Predecessors
1 Project Management
2 Receive NTP 0 days
3 Set up erosion control 5 days 2(FS)
4 Mobilize General Conditions items 5 days 2(FS)

4PM
5 Bonds and Permits 2 days 2(FS)
6 Initial Site Work
7 Clear & grub site 3 days 3(FS),4(FF+2),5(FS)
8 Rough grade site 5 days 7(FS)
9 Install storm drains 10 days 8(FS)
10 Foundation
11 Excavate for Service Pit 3 days 8(FS)
12 FRPS Service Pit footings 5 days 11(FS)
13 FRPS Service Pit Walls 11 days 12(FS)
14 Backfill around Service Pit 2 days 13(SS+9)
15 Install steel columns in Service Pit 1 day 14(FS)
16 Prep and place SOG in Service Pit 3 days 15(FS)
17 Install work platform in Service Pit 5 days 16(FF-2)
18 Install access stair in Service Pit 4 days 17(FS)
19 Install WF support beams in Service Pit 2 days 18(FS)
20 Lay corrugated steel decking over 2 days 19(FS)

5PM
Service Pit
21 Prep and place concrete topping over 3 days 20(FS)
Service Pit
22 Excavate for footings − Service Bays 2 days 14(FS)
23 FRPS footings – Service Bays 4 days 22(FF+3)
24 FRPS foundation walls – Service Bays 5 days 23(FS)
25 Backfill around foundation walls – 2 days 24(FS)
Service Bays
26 Prep and place SOG – Service Bays 3 & 4 3 days 25(FS)
27 Excavate for footings – Office Area 2 days 14(FS+1)
Project Phase 2
ID Name Duration Predecessors
28 FRPS footings Office Area 5 days 27(FS)
29 FRPS foundation walls – Office Area 6 days 28(SF+7)
30 Install U/G plumbing – Office areas 3 days 28(FS)
31 Install U/G electrical conduit – Office 2 days 28(FS)
Area
32 Prep and place SOG – Office Area 4 days 30(FS),31(FF+5),33(FS)

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management and Information Technology Assignment 2
|22
|2244
|94

Project Management Fundamentals: Building a School
|16
|1531
|406

PM Scope and Time Management Plan
|29
|2072
|10

PROJECT PLANNING AND BUDGETING
|10
|5697
|18

Assignment on Project Planning and Budgeting
|15
|1981
|14

PROJECT PLANNING AND BUDGETING
|11
|2004
|23