This article discusses the project management cycle plan for constructing a building, appraising the viability of projects, and explaining the principles behind project management system and procedures with resources required for initiated project. It also includes a case study of Sraymax-London Builder Ltd. project for renovating London School of Science and Technology buildings.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Project Management
1
1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents
Introduction:....................................................................................................................................2
Task 1:.............................................................................................................................................2
1.1 Describing the project management cycle plan for constructing the building......................2
1.2 Appraising the viability of projects, developing success/failure criteria...............................3
1.3 Explaining the principles behind project management system and procedures with
resources required for initiated project........................................................................................4
1.4 Explain the key elements in involved in terminating projects and conducting post project
appraisal.......................................................................................................................................5
Task 2:.............................................................................................................................................6
2.1 Identifying the most appropriate organisational structure, roles and responsibilities of
participants within the project.....................................................................................................6
2.2 Control and co-ordinate a project..........................................................................................8
2.3 Assess project leadership requirements and qualities..........................................................10
2.4 Plan and specify human resources and requirements for a project......................................11
Task 3:...........................................................................................................................................11
3.1 Preparing project plan and establish the project organisation.............................................11
3.2 Apply project scheduling, estimating and cost control techniques......................................13
3.3 Analysis of the methods used to measure project performance..........................................13
3.4 Explain project change control procedures to evaluate the completed project....................16
References......................................................................................................................................18
2
Introduction:....................................................................................................................................2
Task 1:.............................................................................................................................................2
1.1 Describing the project management cycle plan for constructing the building......................2
1.2 Appraising the viability of projects, developing success/failure criteria...............................3
1.3 Explaining the principles behind project management system and procedures with
resources required for initiated project........................................................................................4
1.4 Explain the key elements in involved in terminating projects and conducting post project
appraisal.......................................................................................................................................5
Task 2:.............................................................................................................................................6
2.1 Identifying the most appropriate organisational structure, roles and responsibilities of
participants within the project.....................................................................................................6
2.2 Control and co-ordinate a project..........................................................................................8
2.3 Assess project leadership requirements and qualities..........................................................10
2.4 Plan and specify human resources and requirements for a project......................................11
Task 3:...........................................................................................................................................11
3.1 Preparing project plan and establish the project organisation.............................................11
3.2 Apply project scheduling, estimating and cost control techniques......................................13
3.3 Analysis of the methods used to measure project performance..........................................13
3.4 Explain project change control procedures to evaluate the completed project....................16
References......................................................................................................................................18
2
Introduction:
The study has been based on Sraymax – London Builder Ltd. initiated project as they have
signed a new business venture with London School of Science and Technology in order to
renovate the industrial complex into college buildings. In this approach the project manager have
planned a six months refurbished plan and estimated a total cost of £1,500,000 for the initiated
contract with maintenance duration time for 6 years. The project consist of management cycle
plan so that all task could be completed within estimated period of time. The roles and
responsibilities of each individual within the project team with proper allocation of resources
have been presented. Project scheduling, cost estimation plan, communication plan and risk
management approach have also been discussed and evaluated by the project manager with the
aid of appropriate scheduling tools. The change control procedure in order to complete the
project processes have been presented so that project performance can be easily determined.
Task 1:
1.1 Describing the project management cycle plan for constructing the building
3
The study has been based on Sraymax – London Builder Ltd. initiated project as they have
signed a new business venture with London School of Science and Technology in order to
renovate the industrial complex into college buildings. In this approach the project manager have
planned a six months refurbished plan and estimated a total cost of £1,500,000 for the initiated
contract with maintenance duration time for 6 years. The project consist of management cycle
plan so that all task could be completed within estimated period of time. The roles and
responsibilities of each individual within the project team with proper allocation of resources
have been presented. Project scheduling, cost estimation plan, communication plan and risk
management approach have also been discussed and evaluated by the project manager with the
aid of appropriate scheduling tools. The change control procedure in order to complete the
project processes have been presented so that project performance can be easily determined.
Task 1:
1.1 Describing the project management cycle plan for constructing the building
3
Figure 1: Gantt chart
(Source: Created by Author)
The project management cycle such as Initiation, planning, execution, monitoring & controlling
and closing of the project has been determined with the aid of Gantt chart. Thus, for constructing
the building project, the manager of Sraymax must able to analyse the strategic planning that is
associated with the desired result(Kerzner, 2017).At first the project manager will make overall
plan of the project to measure cost and time of the same. Then the project manager will establish
business case of the project to ensure that the projected outcomes are aligned with the client’s
goal. In the next phase of project cycle the project manager will define all the project scope and
milestones to ensure successful completion of the project. To execute this plan project team will
complete all the project tasks within the projected time and with the expected quality. Success of
a project also depends on monitoring and controlling of the same, so that team leaders of the
4
(Source: Created by Author)
The project management cycle such as Initiation, planning, execution, monitoring & controlling
and closing of the project has been determined with the aid of Gantt chart. Thus, for constructing
the building project, the manager of Sraymax must able to analyse the strategic planning that is
associated with the desired result(Kerzner, 2017).At first the project manager will make overall
plan of the project to measure cost and time of the same. Then the project manager will establish
business case of the project to ensure that the projected outcomes are aligned with the client’s
goal. In the next phase of project cycle the project manager will define all the project scope and
milestones to ensure successful completion of the project. To execute this plan project team will
complete all the project tasks within the projected time and with the expected quality. Success of
a project also depends on monitoring and controlling of the same, so that team leaders of the
4
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
project will measure performance of their team members to monitor all the tasks, and will
provide good working environment and training to control their activities (Nicholas & Steyn,
2017). This process takes four weeks. At last in the closure step, the success of the project is
being analysed and monitored by the manager so that clients demand can easily be met.
Following is the list of the activities those will be carried out for the successful delivery of the
project within the phases stated above:
WBS Task Name Duration Start Finish
1
Syrmaks Project for
Renovating of Industrial
building to college architect
112 days Wed 18-07-18 Thu 20-12-18
1.1 Initiation of Project 41 days Wed 18-07-18 Wed 12-09-18
1.1.1 Project Description 7 days Wed 18-07-18 Thu 26-07-18
1.1.2 Project Benefit 14 days Fri 27-07-18 Wed 15-08-18
1.1.3 Goals of the project 10 days Thu 16-08-18 Wed 29-08-18
1.1.4 Project Vision and aim 10 days Thu 30-08-18 Wed 12-09-18
1.1.5 Analysis of the Project
Requirements 7 days Thu 16-08-18 Fri 24-08-18
1.2 Planning 28 days Mon 27-08-18 Wed 03-10-18
1.2.1 Proper project Planning 14 days Mon 27-08-18 Thu 13-09-18
1.2.2 Preparation of risk register 14 days Fri 14-09-18 Wed 03-10-18
1.2.3 Analysis of the risk
mitigation 14 days Fri 14-09-18 Wed 03-10-18
1.3 Execution 21 days Thu 04-10-18 Thu 01-11-18
1.3.1 Resource Plan 7 days Thu 04-10-18 Fri 12-10-18
5
provide good working environment and training to control their activities (Nicholas & Steyn,
2017). This process takes four weeks. At last in the closure step, the success of the project is
being analysed and monitored by the manager so that clients demand can easily be met.
Following is the list of the activities those will be carried out for the successful delivery of the
project within the phases stated above:
WBS Task Name Duration Start Finish
1
Syrmaks Project for
Renovating of Industrial
building to college architect
112 days Wed 18-07-18 Thu 20-12-18
1.1 Initiation of Project 41 days Wed 18-07-18 Wed 12-09-18
1.1.1 Project Description 7 days Wed 18-07-18 Thu 26-07-18
1.1.2 Project Benefit 14 days Fri 27-07-18 Wed 15-08-18
1.1.3 Goals of the project 10 days Thu 16-08-18 Wed 29-08-18
1.1.4 Project Vision and aim 10 days Thu 30-08-18 Wed 12-09-18
1.1.5 Analysis of the Project
Requirements 7 days Thu 16-08-18 Fri 24-08-18
1.2 Planning 28 days Mon 27-08-18 Wed 03-10-18
1.2.1 Proper project Planning 14 days Mon 27-08-18 Thu 13-09-18
1.2.2 Preparation of risk register 14 days Fri 14-09-18 Wed 03-10-18
1.2.3 Analysis of the risk
mitigation 14 days Fri 14-09-18 Wed 03-10-18
1.3 Execution 21 days Thu 04-10-18 Thu 01-11-18
1.3.1 Resource Plan 7 days Thu 04-10-18 Fri 12-10-18
5
1.3.2 Communication plan 7 days Mon 15-10-18 Tue 23-10-18
1.3.3 Time Plan 14 days Mon 15-10-18 Thu 01-11-18
1.4 Monitoring and controlling 21 days Fri 02-11-18 Fri 30-11-18
1.4.1 Recruitment Plan 7 days Fri 02-11-18 Mon 12-11-18
1.4.2 Training Process 7 days Tue 13-11-18 Wed 21-11-18
1.4.3 Testing the machines and
Project Processes 14 days Tue 13-11-18 Fri 30-11-18
1.5 Closing 14 days Mon 03-12-18 Thu 20-12-18
1.5.1 Analyzing the success of
implemented project 14 days Mon 03-12-18 Thu 20-12-18
1.5.2 Determine any issue or
mistake 7 days Mon 03-12-18 Tue 11-12-18
Project Management Cycle
Initiating
Initiation will begin with Sraymax meeting with LSST organisers to talk about the project and if
it is doable. Negotiation will take place with the basic terms of the contract such as costs and
timeframe. After the terms have been achieved, Sraymax will form a project team to carry out
the work. The project will be initiated considering the estimation of the feasibility of the project
that whether the proposed project will be capable of eliminating the existing problems and
leading the project towards the success. The first milestone will be the approval of the draft
prepared considering the goals, objectives, visions, and benefits related to the project.
Planning
6
1.3.3 Time Plan 14 days Mon 15-10-18 Thu 01-11-18
1.4 Monitoring and controlling 21 days Fri 02-11-18 Fri 30-11-18
1.4.1 Recruitment Plan 7 days Fri 02-11-18 Mon 12-11-18
1.4.2 Training Process 7 days Tue 13-11-18 Wed 21-11-18
1.4.3 Testing the machines and
Project Processes 14 days Tue 13-11-18 Fri 30-11-18
1.5 Closing 14 days Mon 03-12-18 Thu 20-12-18
1.5.1 Analyzing the success of
implemented project 14 days Mon 03-12-18 Thu 20-12-18
1.5.2 Determine any issue or
mistake 7 days Mon 03-12-18 Tue 11-12-18
Project Management Cycle
Initiating
Initiation will begin with Sraymax meeting with LSST organisers to talk about the project and if
it is doable. Negotiation will take place with the basic terms of the contract such as costs and
timeframe. After the terms have been achieved, Sraymax will form a project team to carry out
the work. The project will be initiated considering the estimation of the feasibility of the project
that whether the proposed project will be capable of eliminating the existing problems and
leading the project towards the success. The first milestone will be the approval of the draft
prepared considering the goals, objectives, visions, and benefits related to the project.
Planning
6
Careful planning will commence, meeting the aims of the project, and the development of the
mission statement will pursue. Teams will be formed with delegated duties. This will include the
estimation of the budget and schedule planned for the delivery of the project as mentioned in the
above list of activities. The most emphasizing sector in this phase will be the risks and mitigation
of the risks through deploying proper and effective risk mitigation strategies. The impact of the
risks will be minimized to the extent level in manner to assure that the output and production of
the project will be not altered.
Execution
Sraymax will design the project of the college; testing and building of the college will take place.
This process will involve complex team activities. The involvement of the users and clients will
take place as and when deemed necessary according to the progress of the project. This phase
will assure that every stakeholder effectively communicate with each other and progress of the
project can be recorded and amendments can be made for motivating the project towards
success. Other than this, resource management will be emphasizing on the effectively and
efficiently implementation of the resources within every activity.
Controlling and monitoring
Project rollout will take place where Sraymax will expand their business after implementation.
Live testing, feedback and changes to the project will take place. Measuring the project is
important. The managers of Sraymax will measure project performance and progression. This
will be attained through key performance indicators where the managers can determine if the
project is on track. Maintenance for the LSST is five years, and this will be drawn up, and the
closing phase will commence. This will emphasize on assuring that the project is moving
towards the expected objectives and goals and proper measures will be taken such as training and
education program for assuring that the resources being utilized is capable of delivering the
necessary objectives and goals of the project.
Closing
At this stage the project is completed. Contractors hired will be terminated and valuable team
members will be thanked for their hard work. The managers of Sraymax will evaluate what went
well in the project of LSST and the failures they had to endure, as this is a learning process for
7
mission statement will pursue. Teams will be formed with delegated duties. This will include the
estimation of the budget and schedule planned for the delivery of the project as mentioned in the
above list of activities. The most emphasizing sector in this phase will be the risks and mitigation
of the risks through deploying proper and effective risk mitigation strategies. The impact of the
risks will be minimized to the extent level in manner to assure that the output and production of
the project will be not altered.
Execution
Sraymax will design the project of the college; testing and building of the college will take place.
This process will involve complex team activities. The involvement of the users and clients will
take place as and when deemed necessary according to the progress of the project. This phase
will assure that every stakeholder effectively communicate with each other and progress of the
project can be recorded and amendments can be made for motivating the project towards
success. Other than this, resource management will be emphasizing on the effectively and
efficiently implementation of the resources within every activity.
Controlling and monitoring
Project rollout will take place where Sraymax will expand their business after implementation.
Live testing, feedback and changes to the project will take place. Measuring the project is
important. The managers of Sraymax will measure project performance and progression. This
will be attained through key performance indicators where the managers can determine if the
project is on track. Maintenance for the LSST is five years, and this will be drawn up, and the
closing phase will commence. This will emphasize on assuring that the project is moving
towards the expected objectives and goals and proper measures will be taken such as training and
education program for assuring that the resources being utilized is capable of delivering the
necessary objectives and goals of the project.
Closing
At this stage the project is completed. Contractors hired will be terminated and valuable team
members will be thanked for their hard work. The managers of Sraymax will evaluate what went
well in the project of LSST and the failures they had to endure, as this is a learning process for
7
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
future projects. The project lifecycle also includes the closure phase emphasizing on releasing
the human resources and materials from agreements and assuring the documentation of proper
closure. The document prepared after the accomplishment of the project will assure that the
learning and knowledge gathered can be utilized by other manager in manner to proceed with the
project constraints and predicting the consequences of the actions taken for the delivery of the
project.
The project may still have some work still pending. The managers will create a punch-list of
things that did not go as planned and complete them; also, a final project budget and report will
be drawn up. Finally, all project documentation and materials will be taken away from the
project site and stored away in Sraymax.
1.2 Appraising the viability of projects, developing success/failure criteria
Year Cash flow
1 500
2 400
3 450
4 550
5 400
Discount Rate 5%
NPV £1,993.63
The NPV value is £1,993.63,and the project initiated cost is £1,500,000, so in this context, the
NPV value is positive and less than project cost which determines that the project is successful.
Thus, the appraised visibility objectives of the project arebeing determined by the stakeholders
and how the project manager relate the benefits of organisational goals. For the success of the
project, user involvement and executive management support involvement is essential to the
success of the project. On the other hand the project manager will focus on financial sources to
maintain this cost of the project. Decrease of discount rate also can be a cause of project failure.
Thus, if there is no proper planning, then there is a chance of project failure so the manager must
maintain an appropriate cash flow so that all clients requirement can be fulfilledpositively. By
8
the human resources and materials from agreements and assuring the documentation of proper
closure. The document prepared after the accomplishment of the project will assure that the
learning and knowledge gathered can be utilized by other manager in manner to proceed with the
project constraints and predicting the consequences of the actions taken for the delivery of the
project.
The project may still have some work still pending. The managers will create a punch-list of
things that did not go as planned and complete them; also, a final project budget and report will
be drawn up. Finally, all project documentation and materials will be taken away from the
project site and stored away in Sraymax.
1.2 Appraising the viability of projects, developing success/failure criteria
Year Cash flow
1 500
2 400
3 450
4 550
5 400
Discount Rate 5%
NPV £1,993.63
The NPV value is £1,993.63,and the project initiated cost is £1,500,000, so in this context, the
NPV value is positive and less than project cost which determines that the project is successful.
Thus, the appraised visibility objectives of the project arebeing determined by the stakeholders
and how the project manager relate the benefits of organisational goals. For the success of the
project, user involvement and executive management support involvement is essential to the
success of the project. On the other hand the project manager will focus on financial sources to
maintain this cost of the project. Decrease of discount rate also can be a cause of project failure.
Thus, if there is no proper planning, then there is a chance of project failure so the manager must
maintain an appropriate cash flow so that all clients requirement can be fulfilledpositively. By
8
determining the NPV positive value, it can be evaluated that Sraymax initiated project for
renovating London School of Science and Technology buildings is successful.
1.3 Explaining the principles behind project management system and procedures with
resources required for initiated project
Resource management is defined as the approach which is essential for managing the project in
an effective manner. Resource allocation ensures that all deliverables are met within the
stipulated periodto maintain the quality of the Sraymax project.
Types of resource that can be used for the construction of buildings are:
A human resource such as labour, staffs etc.
Raw materials such as cement, stones, sand dust, concrete etc.
Technical equipment’s
Proper Budget plan
Project plan
The procedure and principles adopted for an effective project management is dependent on the
Board of Directors and employees of Sraymax – London Builder Ltd. which is being presented
below:
The commitment principle: To accomplish the task there should be a proper understanding and
commitment between project team and stakeholders so that all requirements could be fulfilled
within desired period of time without any delay.
The success principles: The success principles of Sraymax project for innovating the classroom
facilities of London School of Science and Technology building is dependent on the quality
attribute of desired result(Tao, et al., 2014). In this approach the project manager must be able to
meet all the clients’ requirement of making highly equipped classrooms, art library and faculty
offices within stipulated budget of project.
The process principle: This process defines the roles and responsibilities of the employees or
staffs within Sraymax project. It also provides specific designation and powers to the member
within the project according to their desired skills and experience in project management sector.
9
renovating London School of Science and Technology buildings is successful.
1.3 Explaining the principles behind project management system and procedures with
resources required for initiated project
Resource management is defined as the approach which is essential for managing the project in
an effective manner. Resource allocation ensures that all deliverables are met within the
stipulated periodto maintain the quality of the Sraymax project.
Types of resource that can be used for the construction of buildings are:
A human resource such as labour, staffs etc.
Raw materials such as cement, stones, sand dust, concrete etc.
Technical equipment’s
Proper Budget plan
Project plan
The procedure and principles adopted for an effective project management is dependent on the
Board of Directors and employees of Sraymax – London Builder Ltd. which is being presented
below:
The commitment principle: To accomplish the task there should be a proper understanding and
commitment between project team and stakeholders so that all requirements could be fulfilled
within desired period of time without any delay.
The success principles: The success principles of Sraymax project for innovating the classroom
facilities of London School of Science and Technology building is dependent on the quality
attribute of desired result(Tao, et al., 2014). In this approach the project manager must be able to
meet all the clients’ requirement of making highly equipped classrooms, art library and faculty
offices within stipulated budget of project.
The process principle: This process defines the roles and responsibilities of the employees or
staffs within Sraymax project. It also provides specific designation and powers to the member
within the project according to their desired skills and experience in project management sector.
9
The Unity of Command principle: The significant advantage of this principle is that it allows
the project team members to create an effective communication channel with the stakeholders to
avoid any confusion or miscommunication. It also ensuresthat project necessity such as raw
materials, skilled staffs and provided training can easily be estimated.
Sl. No Human Resources Cost / hr ($)
1 Project manager 50
2 Business Analyst 45
3 Market Analyst 40
4 Facility Manager 40
5 Staffs 25
6 HR Manager 30
7 Resource Manager 30
8 Contractors 20
9 Head of the project 0
Materials
Sl no. Material Cost / hr ($)
1 Civil engineering tools 5
2 Interior designing materials 9
3 Transporting 7
4 Miscellaneous objects 5
The estimated budget, returns, and NPV values have been stated in the above report as per the
rate mentioned in the above table.
10
the project team members to create an effective communication channel with the stakeholders to
avoid any confusion or miscommunication. It also ensuresthat project necessity such as raw
materials, skilled staffs and provided training can easily be estimated.
Sl. No Human Resources Cost / hr ($)
1 Project manager 50
2 Business Analyst 45
3 Market Analyst 40
4 Facility Manager 40
5 Staffs 25
6 HR Manager 30
7 Resource Manager 30
8 Contractors 20
9 Head of the project 0
Materials
Sl no. Material Cost / hr ($)
1 Civil engineering tools 5
2 Interior designing materials 9
3 Transporting 7
4 Miscellaneous objects 5
The estimated budget, returns, and NPV values have been stated in the above report as per the
rate mentioned in the above table.
10
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
1.4 Explain the key elements in involved in terminating projects and conducting post-
project appraisal
A project needs to follow project closer procedure to complete it successfully. The project
manager of this project will develop closing procedure according to consent of the client. At first
they will close the contract and verify all the project scopes to gain formal acceptance from all
the key stakeholders. The next element of project closer is proper documentation of the project
after that they will conduct phase-end review. To go through the process of post-project appraisal
the manager will submit the final report about overall performance of project members. In order
to make proper appraisal according to performance the project manager also will test and verify
the final product against estimated project deliverables. Project closer checklist also one of the
important element of this process.
Checklist for Sraymax project closure:
Attributes Completed or
fulfilled
Yes No
Project objectives fulfilled
Cost input design process Completed
Renovation of building Completed
Enhancing class facilities Completed
Colouring the walls fulfilled
Maintained the quality of raw materials for
construction
Completed
Resource about the project is informed to the
associated people after project closure
fulfilled
Risk management approach for enhancing safety
of staffs
Completed
Stakeholders analysis who are involved with
Sraymax project
fulfilled
Documentation related to project management
successful implementation
Completed
The roles and responsibilities of project manager fulfilled
11
project appraisal
A project needs to follow project closer procedure to complete it successfully. The project
manager of this project will develop closing procedure according to consent of the client. At first
they will close the contract and verify all the project scopes to gain formal acceptance from all
the key stakeholders. The next element of project closer is proper documentation of the project
after that they will conduct phase-end review. To go through the process of post-project appraisal
the manager will submit the final report about overall performance of project members. In order
to make proper appraisal according to performance the project manager also will test and verify
the final product against estimated project deliverables. Project closer checklist also one of the
important element of this process.
Checklist for Sraymax project closure:
Attributes Completed or
fulfilled
Yes No
Project objectives fulfilled
Cost input design process Completed
Renovation of building Completed
Enhancing class facilities Completed
Colouring the walls fulfilled
Maintained the quality of raw materials for
construction
Completed
Resource about the project is informed to the
associated people after project closure
fulfilled
Risk management approach for enhancing safety
of staffs
Completed
Stakeholders analysis who are involved with
Sraymax project
fulfilled
Documentation related to project management
successful implementation
Completed
The roles and responsibilities of project manager fulfilled
11
is deployed after project closure
Clients requirement are fulfilled within planned
budget
fulfilled
Task 2:
2.1 Identifying the most appropriate organisational structure, roles and responsibilities of
participants within the project
Organisational structure plays a vital role in developing and systematically monitoring all the
task. There are different organisation structure that could be adopted by the project management
to accomplish the task within deadline period by controlling all the project attribute in an
effective manner(Teller & Gemünden, 2014).The organisational structure is matrix based
structure, programmatic based structure, hierarchical based structure, project-based structure etc.
Thus, the most appropriate organisational structure that can be followed by Sraymax – London
Builder Ltd. is a hierarchical business structure in which the flow of information is done from
top to down management. The responsibilities and roles of the team members within the project
is defined by the Board of directors or senior manager as they have the authority to command all
the subordinated in a structured manner. Under the selected organisational structure the
responsibilities and roles of individuals can be classified by the below given structure:
Figure 2: Organisational structure
12
Clients requirement are fulfilled within planned
budget
fulfilled
Task 2:
2.1 Identifying the most appropriate organisational structure, roles and responsibilities of
participants within the project
Organisational structure plays a vital role in developing and systematically monitoring all the
task. There are different organisation structure that could be adopted by the project management
to accomplish the task within deadline period by controlling all the project attribute in an
effective manner(Teller & Gemünden, 2014).The organisational structure is matrix based
structure, programmatic based structure, hierarchical based structure, project-based structure etc.
Thus, the most appropriate organisational structure that can be followed by Sraymax – London
Builder Ltd. is a hierarchical business structure in which the flow of information is done from
top to down management. The responsibilities and roles of the team members within the project
is defined by the Board of directors or senior manager as they have the authority to command all
the subordinated in a structured manner. Under the selected organisational structure the
responsibilities and roles of individuals can be classified by the below given structure:
Figure 2: Organisational structure
12
Source: (Tao, et al., 2014)
The roles and responsibilities of participants working under the Sraymax – London Builder Ltd.
initiated project can be determined and examined by Belbin team role.
Project Manager:
Responsible for recruiting and selecting project staffs
Develop an appropriate project plan
Lead the team in order to complete the project according to time plan
Inform the upper management of Sraymax about current status of London School of
Science and Technology building renovation.
Make a project schedule to assign the task in a systematic manner
Manage and provide deliverables linked to project plan
Project Team Members:
Responsible for doing the task according to their provided job roles by the project
manager
Complete all deliverables to accomplish the project objectives and goals
Work according to the client’s requirement
Document the initiated processes within Sraymax
Executive sponsor:
They are responsible for approving the changes to meet the project scope of Sraymax
They have the major responsibility to maintain the quality aspect of project in all steps
Agree on project deliverables
Responsible for maintaining a healthy relationship with internal and external stakeholders
They provide additional funds to the project so that project scope could be accomplished
in an effective manner
Project Sponsor:
They are responsible for communicating the project goals with the managers so that an
effective budget plan can be made
13
The roles and responsibilities of participants working under the Sraymax – London Builder Ltd.
initiated project can be determined and examined by Belbin team role.
Project Manager:
Responsible for recruiting and selecting project staffs
Develop an appropriate project plan
Lead the team in order to complete the project according to time plan
Inform the upper management of Sraymax about current status of London School of
Science and Technology building renovation.
Make a project schedule to assign the task in a systematic manner
Manage and provide deliverables linked to project plan
Project Team Members:
Responsible for doing the task according to their provided job roles by the project
manager
Complete all deliverables to accomplish the project objectives and goals
Work according to the client’s requirement
Document the initiated processes within Sraymax
Executive sponsor:
They are responsible for approving the changes to meet the project scope of Sraymax
They have the major responsibility to maintain the quality aspect of project in all steps
Agree on project deliverables
Responsible for maintaining a healthy relationship with internal and external stakeholders
They provide additional funds to the project so that project scope could be accomplished
in an effective manner
Project Sponsor:
They are responsible for communicating the project goals with the managers so that an
effective budget plan can be made
13
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
They ensure and analyses the availability of resources to maintain the quality of the
initiated project by timely providing all deliverables.
They also approve and assign the budget of the project for London School of Science and
Technology building construction process
Project Sponsor takes part in all the decision-making process and accordingly analyses
the appropriate fund for project accomplishment
2.2 Control and coordinate a project
Project co-ordination reflects the monitoring, planning and controlling of all the attributes related
to the project deliverables. The key elements related to the project coordinationare projected
plan, communication plan, risk management plan, HR plan, budget plan, project manager and
regular meetings with the team members of Sraymax. According to Belbin team, there must be a
project coordinator who is responsible for making an effective communication channel with all
the project members to discuss bout the current project status and plan to accomplish business
goals(Ning, 2017). The controlling is also done by them and are responsible for distrusting the
task to all the staffs associated with the project according to their skill, experience and working
efficiency. To mitigate the risk, project coordinator always supports the subordinates and provide
the appropriate training and grooming session to enhance their proficiency skills. To control the
initiated project, the venture manager of Sraymax follow hierarchical organisation structure so
that all information can be transmitted to the staffs in a structured manner.
The coordination of the project is also maintained by making a communication plan where the
project managers and Board of members are responsible for coordinating with the project team to
get all current status of project deliverables(Boyle, 2017).
Communication plan
No. Project
current
information
that is to be
discussed
Spectators Timing at
which the
information is
communicated
Communicatio
n medium
With whom the
communication
is done
1 Conferring London Initial stage of F2F Project
14
initiated project by timely providing all deliverables.
They also approve and assign the budget of the project for London School of Science and
Technology building construction process
Project Sponsor takes part in all the decision-making process and accordingly analyses
the appropriate fund for project accomplishment
2.2 Control and coordinate a project
Project co-ordination reflects the monitoring, planning and controlling of all the attributes related
to the project deliverables. The key elements related to the project coordinationare projected
plan, communication plan, risk management plan, HR plan, budget plan, project manager and
regular meetings with the team members of Sraymax. According to Belbin team, there must be a
project coordinator who is responsible for making an effective communication channel with all
the project members to discuss bout the current project status and plan to accomplish business
goals(Ning, 2017). The controlling is also done by them and are responsible for distrusting the
task to all the staffs associated with the project according to their skill, experience and working
efficiency. To mitigate the risk, project coordinator always supports the subordinates and provide
the appropriate training and grooming session to enhance their proficiency skills. To control the
initiated project, the venture manager of Sraymax follow hierarchical organisation structure so
that all information can be transmitted to the staffs in a structured manner.
The coordination of the project is also maintained by making a communication plan where the
project managers and Board of members are responsible for coordinating with the project team to
get all current status of project deliverables(Boyle, 2017).
Communication plan
No. Project
current
information
that is to be
discussed
Spectators Timing at
which the
information is
communicated
Communicatio
n medium
With whom the
communication
is done
1 Conferring London Initial stage of F2F Project
14
the
clientrequests
and
requirements
School of
Science and
Technology
project
starting
communication management
2 Inspecting
the
requirement
Team
members
and Board of
members
Planning
phase of
project
management
cycle
Face to face
meeting
Project
manager
3 Task
allotment to
all the
members of a
team(Teller
&
Gemünden,
2014)
Board of
members
Preparation
phase
F2F meeting Project
manager
4 Changes or
alternation
that takes
place within
the initiated
project
Team
members
and Board of
members
During project
development
and execution
stage
On telephone
or messaging
through emails
Board of
members and
project
managers
5 Reporting of
project status
Board of
members
During the
closure and
middle of
execution
stage
Face to face
meeting
Board of
members,
management
and Team
members
15
clientrequests
and
requirements
School of
Science and
Technology
project
starting
communication management
2 Inspecting
the
requirement
Team
members
and Board of
members
Planning
phase of
project
management
cycle
Face to face
meeting
Project
manager
3 Task
allotment to
all the
members of a
team(Teller
&
Gemünden,
2014)
Board of
members
Preparation
phase
F2F meeting Project
manager
4 Changes or
alternation
that takes
place within
the initiated
project
Team
members
and Board of
members
During project
development
and execution
stage
On telephone
or messaging
through emails
Board of
members and
project
managers
5 Reporting of
project status
Board of
members
During the
closure and
middle of
execution
stage
Face to face
meeting
Board of
members,
management
and Team
members
15
2.3 Assess project leadership requirements and qualities
Sraymax – London Builder Ltd. is a construction company which has done a contract to renovate
the industrial complex and building to make it a part of London School of Science and
Technology campus. Thus, the project manager related to this project must follow contemporary
leadership style to maintain and fulfil the project objectives within a stipulated period. To
accomplish the project work with the improved quality, the manager should have a project
management degree and have valuable experienced construction industry field. The qualities that
the leaders within the project should have are as follows:
Communication skills: The project manager or leader of the Sraymax project must have a good
communication skills so that they could convey their message and command to the team
members in an effective manner.
Vision skills: They should have the ability to set an achievable goal and could predict the future
outcome related to the project situation and task description.
Conflict is resolving skills: They must poses capability to mitigate any conflict within Sraymax
project by maintaining and controlling all attributes efficiently(Popaitoon & Siengthai., 2016).
They must motivate and influence the staffs to think beyond by providing technical and
grooming session to enhance their skills.
Enhanced knowledge of project management tools and technologies: The project manager
should have modernised knowledge about project management to complete the task in a cost-
efficient knowledge. Software knowledge of MSProject, Excel and command prompt should be
known to them so that they could make a reliable and appropriate project or budget plan
according to client requirement.
Leadership qualities: Project manager of Sraymax should have the ability to command and
motivate the employees so that they could all achieve the project goals in an efficient manner.
2.4 Plan and specify human resources and requirements for a project
Human resource management is defined as a practice which helps to manage and control
different attribute within workplace of the initiated project. Influential Human Resource
Management involves specialists in serving profitably to the general association and the
achievement of the affiliation's goals. The human resource management is responsible for
16
Sraymax – London Builder Ltd. is a construction company which has done a contract to renovate
the industrial complex and building to make it a part of London School of Science and
Technology campus. Thus, the project manager related to this project must follow contemporary
leadership style to maintain and fulfil the project objectives within a stipulated period. To
accomplish the project work with the improved quality, the manager should have a project
management degree and have valuable experienced construction industry field. The qualities that
the leaders within the project should have are as follows:
Communication skills: The project manager or leader of the Sraymax project must have a good
communication skills so that they could convey their message and command to the team
members in an effective manner.
Vision skills: They should have the ability to set an achievable goal and could predict the future
outcome related to the project situation and task description.
Conflict is resolving skills: They must poses capability to mitigate any conflict within Sraymax
project by maintaining and controlling all attributes efficiently(Popaitoon & Siengthai., 2016).
They must motivate and influence the staffs to think beyond by providing technical and
grooming session to enhance their skills.
Enhanced knowledge of project management tools and technologies: The project manager
should have modernised knowledge about project management to complete the task in a cost-
efficient knowledge. Software knowledge of MSProject, Excel and command prompt should be
known to them so that they could make a reliable and appropriate project or budget plan
according to client requirement.
Leadership qualities: Project manager of Sraymax should have the ability to command and
motivate the employees so that they could all achieve the project goals in an efficient manner.
2.4 Plan and specify human resources and requirements for a project
Human resource management is defined as a practice which helps to manage and control
different attribute within workplace of the initiated project. Influential Human Resource
Management involves specialists in serving profitably to the general association and the
achievement of the affiliation's goals. The human resource management is responsible for
16
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
recruiting, staffing and development of team members so that the initiated project can be
completed within particular time framework(Brewster & Hegewisch, 2017). The roles and
responsibilities of Human resource within the project are to determine and allocate the resources
which are required for building construction process of Sraymax – London Builder Ltd. Human
resources are also associated with the project job description and manage the attribute so that
minimal resource allocation can be used by the managerto accomplish the task within initiated
budget. They provide training and grooming session to the team members according to their
skills and make sure that all members can get valuable benefits according to employee
performance within the workplace. The role of HR manager is to organise a meeting with all the
project associated and stakeholders so that specified client need could be evaluated.
Sl. No, Human
Resources
Roles Responsibilities
1
Project manager
Manage the project
constraints and
stakeholders
Assure that the project delivered
within the expected constraints
2
Business Analyst
Analyse the investment,
business, and profit that
can be gained through this
project
Effectively analyse the business and
provide strategies that can lead the
project towards success
3
Market Analyst
Analyse the market and
competitors to allow
better output and
sustainability in the
market
Provide strategies those could be
helpful in long run of the project
output (new renovation)
4 Facility Manager Manage the facilities for
the staffs
The working ebvironment is
suitable for the staffs
5 Staffs Contribute in the daily
operational activities
Meeting the objectives and goals of
the project individually
6 HR Manager Manage the human
resources
Assure that every staff is getting
their rights and benifits
7 Resource Manager Manage the resources Assure that enough resources are
17
completed within particular time framework(Brewster & Hegewisch, 2017). The roles and
responsibilities of Human resource within the project are to determine and allocate the resources
which are required for building construction process of Sraymax – London Builder Ltd. Human
resources are also associated with the project job description and manage the attribute so that
minimal resource allocation can be used by the managerto accomplish the task within initiated
budget. They provide training and grooming session to the team members according to their
skills and make sure that all members can get valuable benefits according to employee
performance within the workplace. The role of HR manager is to organise a meeting with all the
project associated and stakeholders so that specified client need could be evaluated.
Sl. No, Human
Resources
Roles Responsibilities
1
Project manager
Manage the project
constraints and
stakeholders
Assure that the project delivered
within the expected constraints
2
Business Analyst
Analyse the investment,
business, and profit that
can be gained through this
project
Effectively analyse the business and
provide strategies that can lead the
project towards success
3
Market Analyst
Analyse the market and
competitors to allow
better output and
sustainability in the
market
Provide strategies those could be
helpful in long run of the project
output (new renovation)
4 Facility Manager Manage the facilities for
the staffs
The working ebvironment is
suitable for the staffs
5 Staffs Contribute in the daily
operational activities
Meeting the objectives and goals of
the project individually
6 HR Manager Manage the human
resources
Assure that every staff is getting
their rights and benifits
7 Resource Manager Manage the resources Assure that enough resources are
17
necessary for the delivery
of the project
available throughout the project life
cycle
8
Contractors
Manage the outsourcing
and resources those are
necessary for the project
Provide all the necessary
requirements of the project
9 Head of the project Decision-making Take better decision making
considering every stakeholder
Task 3:
3.1 Preparing project plan and establish the project organisation
Sraymax project must keep this mind that to carry out the project plan they must maintain strong
plan backed up by contingency plan, so that when Sraymax project face problem they can
implement those ideas to stabilise their business structures. The projects plans are described as
follows such as chalking down the primary planning that regulates the business process(Driskell,
2017). Making the involvement of expertise from each department of project process, assignment
or dividing the task according to the departments to minimise the threats that may occur. And
avoid the conflict among employees regarding job roles assigned to them. This process involves
setting up key target such as capital, employees, analysing the risk, testing the programme in
ground reality before executing it on project task. Analysing the risk factors for Sraymax project
and drawing out conclusion for eliminating the threat from the project task. Documentation of all
work-related documents such as report, planning chart, blueprint and task action plan(Kerzner,
2017). The project management requires all this steps and procedures so that if anything happens
then Sraymax project must be ready with backup plan to control the situation and maintain the
smooth flow of operations. Hence it is essential for Sraymax project to maintain the timeframe
properly and monitor the situations to take corrective measure when needed.
18
of the project
available throughout the project life
cycle
8
Contractors
Manage the outsourcing
and resources those are
necessary for the project
Provide all the necessary
requirements of the project
9 Head of the project Decision-making Take better decision making
considering every stakeholder
Task 3:
3.1 Preparing project plan and establish the project organisation
Sraymax project must keep this mind that to carry out the project plan they must maintain strong
plan backed up by contingency plan, so that when Sraymax project face problem they can
implement those ideas to stabilise their business structures. The projects plans are described as
follows such as chalking down the primary planning that regulates the business process(Driskell,
2017). Making the involvement of expertise from each department of project process, assignment
or dividing the task according to the departments to minimise the threats that may occur. And
avoid the conflict among employees regarding job roles assigned to them. This process involves
setting up key target such as capital, employees, analysing the risk, testing the programme in
ground reality before executing it on project task. Analysing the risk factors for Sraymax project
and drawing out conclusion for eliminating the threat from the project task. Documentation of all
work-related documents such as report, planning chart, blueprint and task action plan(Kerzner,
2017). The project management requires all this steps and procedures so that if anything happens
then Sraymax project must be ready with backup plan to control the situation and maintain the
smooth flow of operations. Hence it is essential for Sraymax project to maintain the timeframe
properly and monitor the situations to take corrective measure when needed.
18
Figure 3: Project plan
Source:(Brewster & Hegewisch, 2017)
The project management follows some patterns in their organisations such as project
management, portfolio management, programme management, project context and project office.
To carry out the project plan in a systematic and effective way the project follows certain plans
such as technical information system, software and hardware purchase, installation of hardware
and wiring, software development and training to minimise the time frame and gain the desired
output within limited time period and cut down the cost of company such as operating cost and
other expenses.
Scope: the project scope is to renovate the existing industrial buildings into the college buildings in manner to
allow the college students to have better and enhanced education services.
Resources: For the successful deployment of this project we will need human resources as well as the
materials those are considerable for renovating the industrial buildings into college buildings
Human resources:
Project manager
Business Analyst
Market Analyst
Facility Manager
Staffs
HR Manager
Resource Manager
Contractors
Head of the project
Industry owners
College Owners
Students
19
Source:(Brewster & Hegewisch, 2017)
The project management follows some patterns in their organisations such as project
management, portfolio management, programme management, project context and project office.
To carry out the project plan in a systematic and effective way the project follows certain plans
such as technical information system, software and hardware purchase, installation of hardware
and wiring, software development and training to minimise the time frame and gain the desired
output within limited time period and cut down the cost of company such as operating cost and
other expenses.
Scope: the project scope is to renovate the existing industrial buildings into the college buildings in manner to
allow the college students to have better and enhanced education services.
Resources: For the successful deployment of this project we will need human resources as well as the
materials those are considerable for renovating the industrial buildings into college buildings
Human resources:
Project manager
Business Analyst
Market Analyst
Facility Manager
Staffs
HR Manager
Resource Manager
Contractors
Head of the project
Industry owners
College Owners
Students
19
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Interior Designer
Engineers
Materials:
Civil engineering tools
Interior designing materials
Transporting
Miscellaneous objects
Cost:
Sl. No Human Resources Cost / hr ($)
1 Project manager 50
2 Business Analyst 45
3 Market Analyst 40
4 Facility Manager 40
5 Staffs 25
6 HR Manager 30
7 Resource Manager 30
8 Contractors 20
9 Head of the project 0
Communication: Since, the project will be lasting for a long period once it gets started and
hence, monthly meeting will be best suited for every stakeholder to gather at a single venue and
raise the issues, problems, and other concerns related to the project. Every stakeholder will
supposed to bring their project growth and development report in manner to tally them with
others to identify what are the lagging and leading factors of the project and what amendments
are necessary for the project to be accomplished within the expected schedule and budget
Risks:
Big projects are always vulnerable to uncertainties and hence, the probability of the risk
occurrence is higher those can be listed as follows:
Timeline escalation
Cost escalation
Resource lagging
Ineffective management
Improper communication
Zero output or project failure
Accidents
Dust
Natural calamities
Transportation facilities
20
Engineers
Materials:
Civil engineering tools
Interior designing materials
Transporting
Miscellaneous objects
Cost:
Sl. No Human Resources Cost / hr ($)
1 Project manager 50
2 Business Analyst 45
3 Market Analyst 40
4 Facility Manager 40
5 Staffs 25
6 HR Manager 30
7 Resource Manager 30
8 Contractors 20
9 Head of the project 0
Communication: Since, the project will be lasting for a long period once it gets started and
hence, monthly meeting will be best suited for every stakeholder to gather at a single venue and
raise the issues, problems, and other concerns related to the project. Every stakeholder will
supposed to bring their project growth and development report in manner to tally them with
others to identify what are the lagging and leading factors of the project and what amendments
are necessary for the project to be accomplished within the expected schedule and budget
Risks:
Big projects are always vulnerable to uncertainties and hence, the probability of the risk
occurrence is higher those can be listed as follows:
Timeline escalation
Cost escalation
Resource lagging
Ineffective management
Improper communication
Zero output or project failure
Accidents
Dust
Natural calamities
Transportation facilities
20
3.2 Apply project scheduling, estimating and cost control techniques
Before stepping into project Sraymax project needs to schedule properly the monetary prospect
with calculating the estimated time frame that may be required to carry out the project
management task for Sraymax project. The capital factor in the project will decide the numbers
of employees required, machinery required and supplier’s role in the business
operations(Martens & Vanhoucke, 2017). Perceive the future goals by setting out the present
objectives and fixed their targets weekly or monthly basis. Separating the targets according to
their size such as small, medium, and large and focusing on each and every targets specifically to
achieve their set targets within limited timeframe such as maintaining records, growth rate data,
improving precision, and identifying alternative solutions. Discussing all the decisions with its
stakeholders, shareholders and its business partners and understanding their needs and modifying
the project if it is needed. And finally analysing each and every process and coming out with a
solution to modify the project and generate profits for long-term(Tereso, et al., 2017). Time is
the most important factor in project management for Sraymax project if they fail to identify each
task according to their impact on the organisations and fail to utilise their financial part then the
project might collapse or it may extend for longer period of time. In both of the cases the
management of Sraymax project has suffer the worst.
Gantt chart with critical path demonstration
21
Before stepping into project Sraymax project needs to schedule properly the monetary prospect
with calculating the estimated time frame that may be required to carry out the project
management task for Sraymax project. The capital factor in the project will decide the numbers
of employees required, machinery required and supplier’s role in the business
operations(Martens & Vanhoucke, 2017). Perceive the future goals by setting out the present
objectives and fixed their targets weekly or monthly basis. Separating the targets according to
their size such as small, medium, and large and focusing on each and every targets specifically to
achieve their set targets within limited timeframe such as maintaining records, growth rate data,
improving precision, and identifying alternative solutions. Discussing all the decisions with its
stakeholders, shareholders and its business partners and understanding their needs and modifying
the project if it is needed. And finally analysing each and every process and coming out with a
solution to modify the project and generate profits for long-term(Tereso, et al., 2017). Time is
the most important factor in project management for Sraymax project if they fail to identify each
task according to their impact on the organisations and fail to utilise their financial part then the
project might collapse or it may extend for longer period of time. In both of the cases the
management of Sraymax project has suffer the worst.
Gantt chart with critical path demonstration
21
Figure 4: Gantt chart with critical path
(Source: Created by Author)
Critical path analysis
Task Name Duration Start Finish Early Start Early Finish Late Start Late Finish
Syramax
Project for
Renovating
of Industrial
building to
college
architect
112 days Wed 18-07-
18
Thu 20-12-
18
Wed 18-07-
18
Thu 20-12-
18
Wed 18-07-
18
Thu 20-12-
18
22
(Source: Created by Author)
Critical path analysis
Task Name Duration Start Finish Early Start Early Finish Late Start Late Finish
Syramax
Project for
Renovating
of Industrial
building to
college
architect
112 days Wed 18-07-
18
Thu 20-12-
18
Wed 18-07-
18
Thu 20-12-
18
Wed 18-07-
18
Thu 20-12-
18
22
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Initiation
of Project 41 days Wed 18-07-
18
Wed 12-09-
18
Wed 18-07-
18
Wed 12-09-
18
Wed 18-07-
18
Thu 20-12-
18
Project
Description 7 days Wed 18-07-
18 Thu 26-07-18 Wed 18-07-
18
Thu 26-07-
18
Wed 18-07-
18 Thu 26-07-18
Project
Benefit 14 days Fri 27-07-18 Wed 15-08-
18
Fri 27-07-
18
Wed 15-08-
18
Fri 27-07-
18
Wed 15-08-
18
Goals of
th project 10 days Thu 16-08-
18
Wed 29-08-
18
Thu 16-08-
18
Wed 29-08-
18
Fri 23-11-
18 Thu 06-12-18
Project
Vision and
aim
10 days Thu 30-08-
18
Wed 12-09-
18
Thu 30-08-
18
Wed 12-09-
18
Fri 07-12-
18 Thu 20-12-18
Analysis
of the Project
Requirement
s
7 days Thu 16-08-
18 Fri 24-08-18 Thu 16-08-
18
Fri 24-08-
18
Thu 16-08-
18 Fri 24-08-18
Planning 28 days Mon 27-08-
18
Wed 03-10-
18
Mon 27-08-
18
Wed 03-10-
18
Mon 27-08-
18
Thu 20-12-
18
Proper
project
Planning
14 days Mon 27-08-
18 Thu 13-09-18 Mon 27-08-
18
Thu 13-09-
18
Mon 27-08-
18 Thu 13-09-18
Preparati
on of risk
rgister
14 days Fri 14-09-18 Wed 03-10-
18
Fri 14-09-
18
Wed 03-10-
18
Mon 03-12-
18 Thu 20-12-18
Analysis
of the risk
mitigation
14 days Fri 14-09-18 Wed 03-10-
18
Fri 14-09-
18
Wed 03-10-
18
Fri 14-09-
18
Wed 03-10-
18
Execution 21 days Thu 04-10-
18
Thu 01-11-
18
Thu 04-10-
18
Thu 01-11-
18
Thu 04-10-
18
Thu 20-12-
18
Resource
Plan 7 days Thu 04-10-
18 Fri 12-10-18 Thu 04-10-
18
Fri 12-10-
18
Thu 04-10-
18 Fri 12-10-18
Communi
cation plan 7 days Mon 15-10-
18 Tue 23-10-18 Mon 15-10-
18
Tue 23-10-
18
Wed 12-12-
18 Thu 20-12-18
Time
Plan 14 days Mon 15-10-
18 Thu 01-11-18 Mon 15-10-
18
Thu 01-11-
18
Mon 15-10-
18 Thu 01-11-18
23
of Project 41 days Wed 18-07-
18
Wed 12-09-
18
Wed 18-07-
18
Wed 12-09-
18
Wed 18-07-
18
Thu 20-12-
18
Project
Description 7 days Wed 18-07-
18 Thu 26-07-18 Wed 18-07-
18
Thu 26-07-
18
Wed 18-07-
18 Thu 26-07-18
Project
Benefit 14 days Fri 27-07-18 Wed 15-08-
18
Fri 27-07-
18
Wed 15-08-
18
Fri 27-07-
18
Wed 15-08-
18
Goals of
th project 10 days Thu 16-08-
18
Wed 29-08-
18
Thu 16-08-
18
Wed 29-08-
18
Fri 23-11-
18 Thu 06-12-18
Project
Vision and
aim
10 days Thu 30-08-
18
Wed 12-09-
18
Thu 30-08-
18
Wed 12-09-
18
Fri 07-12-
18 Thu 20-12-18
Analysis
of the Project
Requirement
s
7 days Thu 16-08-
18 Fri 24-08-18 Thu 16-08-
18
Fri 24-08-
18
Thu 16-08-
18 Fri 24-08-18
Planning 28 days Mon 27-08-
18
Wed 03-10-
18
Mon 27-08-
18
Wed 03-10-
18
Mon 27-08-
18
Thu 20-12-
18
Proper
project
Planning
14 days Mon 27-08-
18 Thu 13-09-18 Mon 27-08-
18
Thu 13-09-
18
Mon 27-08-
18 Thu 13-09-18
Preparati
on of risk
rgister
14 days Fri 14-09-18 Wed 03-10-
18
Fri 14-09-
18
Wed 03-10-
18
Mon 03-12-
18 Thu 20-12-18
Analysis
of the risk
mitigation
14 days Fri 14-09-18 Wed 03-10-
18
Fri 14-09-
18
Wed 03-10-
18
Fri 14-09-
18
Wed 03-10-
18
Execution 21 days Thu 04-10-
18
Thu 01-11-
18
Thu 04-10-
18
Thu 01-11-
18
Thu 04-10-
18
Thu 20-12-
18
Resource
Plan 7 days Thu 04-10-
18 Fri 12-10-18 Thu 04-10-
18
Fri 12-10-
18
Thu 04-10-
18 Fri 12-10-18
Communi
cation plan 7 days Mon 15-10-
18 Tue 23-10-18 Mon 15-10-
18
Tue 23-10-
18
Wed 12-12-
18 Thu 20-12-18
Time
Plan 14 days Mon 15-10-
18 Thu 01-11-18 Mon 15-10-
18
Thu 01-11-
18
Mon 15-10-
18 Thu 01-11-18
23
Monitorin
g and
controlling
21 days Fri 02-11-18 Fri 30-11-18 Fri 02-11-
18
Fri 30-11-
18
Fri 02-11-
18
Thu 20-12-
18
Recruitm
ent Plan 7 days Fri 02-11-18 Mon 12-11-
18
Fri 02-11-
18
Mon 12-11-
18
Fri 02-11-
18
Mon 12-11-
18
Training
Proces 7 days Tue 13-11-
18
Wed 21-11-
18
Tue 13-11-
18
Wed 21-11-
18
Wed 12-12-
18 Thu 20-12-18
Testing
the machines
and Project
Processes
14 days Tue 13-11-
18 Fri 30-11-18 Tue 13-11-
18
Fri 30-11-
18
Tue 13-11-
18 Fri 30-11-18
Closing 14 days Mon 03-12-
18
Thu 20-12-
18
Mon 03-12-
18
Thu 20-12-
18
Mon 03-12-
18
Thu 20-12-
18
Analyzin
g the success
of
implemented
project
14 days Mon 03-12-
18 Thu 20-12-18 Mon 03-12-
18
Thu 20-12-
18
Mon 03-12-
18 Thu 20-12-18
Determin
e any issue or
mistake
7 days Mon 03-12-
18 Tue 11-12-18 Mon 03-12-
18
Tue 11-12-
18
Wed 12-12-
18 Thu 20-12-18
Network diagram as per the above calculation
24
g and
controlling
21 days Fri 02-11-18 Fri 30-11-18 Fri 02-11-
18
Fri 30-11-
18
Fri 02-11-
18
Thu 20-12-
18
Recruitm
ent Plan 7 days Fri 02-11-18 Mon 12-11-
18
Fri 02-11-
18
Mon 12-11-
18
Fri 02-11-
18
Mon 12-11-
18
Training
Proces 7 days Tue 13-11-
18
Wed 21-11-
18
Tue 13-11-
18
Wed 21-11-
18
Wed 12-12-
18 Thu 20-12-18
Testing
the machines
and Project
Processes
14 days Tue 13-11-
18 Fri 30-11-18 Tue 13-11-
18
Fri 30-11-
18
Tue 13-11-
18 Fri 30-11-18
Closing 14 days Mon 03-12-
18
Thu 20-12-
18
Mon 03-12-
18
Thu 20-12-
18
Mon 03-12-
18
Thu 20-12-
18
Analyzin
g the success
of
implemented
project
14 days Mon 03-12-
18 Thu 20-12-18 Mon 03-12-
18
Thu 20-12-
18
Mon 03-12-
18 Thu 20-12-18
Determin
e any issue or
mistake
7 days Mon 03-12-
18 Tue 11-12-18 Mon 03-12-
18
Tue 11-12-
18
Wed 12-12-
18 Thu 20-12-18
Network diagram as per the above calculation
24
Figure 5: Network Diagram (CPM)
(Source: Created by Author)
3.3 Analysis of the methods used to measure project performance
To measure the project performance work breakdown structure has been made with an
appropriate network diagram.
WBS
WBS Task Name
1 Syrmaks Project for Renovating of Industrial building to college architect
1.1 Initiation of Project
1.1.1 Project Description
1.1.2 Project Benefit
1.1.3 Goals of the project
1.1.4 Project Vision and aim
25
(Source: Created by Author)
3.3 Analysis of the methods used to measure project performance
To measure the project performance work breakdown structure has been made with an
appropriate network diagram.
WBS
WBS Task Name
1 Syrmaks Project for Renovating of Industrial building to college architect
1.1 Initiation of Project
1.1.1 Project Description
1.1.2 Project Benefit
1.1.3 Goals of the project
1.1.4 Project Vision and aim
25
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1.1.5 Analysis of the Project Requirements
1.2 Planning
1.2.1 Proper project Planning
1.2.2 Preparation of risk register
1.2.3 Analysis of the risk mitigation
1.3 Execution
1.3.1 Resource Plan
1.3.2 Communication plan
1.3.3 Time Plan
1.4 Monitoring and controlling
1.4.1 Recruitment Plan
1.4.2 Training Process
1.4.3 Testing the machines and Project Processes
1.5 Closing
1.5.1 Analyzing the success of implemented project
1.5.2 Determine any issue or mistake
3.4 Explain project change control procedures to evaluate the completed project
In order to follow the proposed changes of the project the project manager will make individual
proposal for all the required changes. After that the manager will establish the summary of
impact of the change on project deliverables. In next stage of change procedure the project
manager will take decision about change with the consent of key stakeholders to implement all
the changes effectively. In last stage of change control the manager will close the change
procedure by making proper documentation about changes.
26
1.2 Planning
1.2.1 Proper project Planning
1.2.2 Preparation of risk register
1.2.3 Analysis of the risk mitigation
1.3 Execution
1.3.1 Resource Plan
1.3.2 Communication plan
1.3.3 Time Plan
1.4 Monitoring and controlling
1.4.1 Recruitment Plan
1.4.2 Training Process
1.4.3 Testing the machines and Project Processes
1.5 Closing
1.5.1 Analyzing the success of implemented project
1.5.2 Determine any issue or mistake
3.4 Explain project change control procedures to evaluate the completed project
In order to follow the proposed changes of the project the project manager will make individual
proposal for all the required changes. After that the manager will establish the summary of
impact of the change on project deliverables. In next stage of change procedure the project
manager will take decision about change with the consent of key stakeholders to implement all
the changes effectively. In last stage of change control the manager will close the change
procedure by making proper documentation about changes.
26
No. Changes related
to project
Purpose Change
procedure
Result
1 Project Budgets The client
changes their
constraint and
want more
renovation
within
classroom and
offices of
London School
of Science and
Technology
As guided by
project manager
Hike in budget
plan changes in
project time plan
2 Scope Certain
functionality is
being added by
the client
Directed by
Board of
members and
Project team
Low or moderate
change occurs to
project plan
3 Timing Requirement
change with
evaluation of
time
Manager and
Board of
members
Effect the WBS
of project
4 Project resource Client
requirement
changes
As initiated by
Directed by
Board of
members and
Project team
Influence is low
as some
resources are to
be added more
27
to project
Purpose Change
procedure
Result
1 Project Budgets The client
changes their
constraint and
want more
renovation
within
classroom and
offices of
London School
of Science and
Technology
As guided by
project manager
Hike in budget
plan changes in
project time plan
2 Scope Certain
functionality is
being added by
the client
Directed by
Board of
members and
Project team
Low or moderate
change occurs to
project plan
3 Timing Requirement
change with
evaluation of
time
Manager and
Board of
members
Effect the WBS
of project
4 Project resource Client
requirement
changes
As initiated by
Directed by
Board of
members and
Project team
Influence is low
as some
resources are to
be added more
27
5 Critical path It is developed
if there is
alternation in
project
schedule
Management and
project manager
High impact
takes place on
critical path
28
if there is
alternation in
project
schedule
Management and
project manager
High impact
takes place on
critical path
28
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
References
Boyle, G., 2017. Design project management. London: Routledge.
Brewster, C. & Hegewisch, A. e., 2017. Policy and Practice in European Human Resource
Management: The Price Waterhouse Cranfield Survey. London: Taylor & Francis.
Driskell, D., 2017. Creating better cities with children and youth: A manual for
participation.London: Routledge.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. London: John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. London: John Wiley & Sons.
Martens, A. & Vanhoucke, M., 2017. A buffer control method for top-down project control.
European Journal of Operational Research, 262(1), pp. 274-286.
Nicholas, J. & Steyn, H., 2017. Project management for engineering, business and technology.
London: Taylor & Francis.
Ning, Y., 2017. Selecting client's project control strategies in person-to-organization
transactions.International Journal of Project Management, 35(2), pp. 212-220.
Popaitoon, S. & Siengthai., S., 2016. "The moderating effect of human resource management
practices on the relationship between knowledge absorptive capacity and project performance in
project-oriented companies.". International Journal of Project Mannagement , 32(6), pp. 908-
920.
Tao, F. et al., 2014. CCIoT-CMfg: cloud computing and internet of things-based cloud
manufacturing service system.. IEEE Transactions on Industrial Informatics, 10(2), pp. 1435-
1442..
Teller, J. K. A. & Gemünden, H., 2014. Risk management in project portfolios is more than
managing project risks: A contingency perspective on risk management.. Project Management
Journal, 45(4), pp. 67-80.
29
Boyle, G., 2017. Design project management. London: Routledge.
Brewster, C. & Hegewisch, A. e., 2017. Policy and Practice in European Human Resource
Management: The Price Waterhouse Cranfield Survey. London: Taylor & Francis.
Driskell, D., 2017. Creating better cities with children and youth: A manual for
participation.London: Routledge.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. London: John Wiley & Sons.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to measuring
and monitoring project performance. London: John Wiley & Sons.
Martens, A. & Vanhoucke, M., 2017. A buffer control method for top-down project control.
European Journal of Operational Research, 262(1), pp. 274-286.
Nicholas, J. & Steyn, H., 2017. Project management for engineering, business and technology.
London: Taylor & Francis.
Ning, Y., 2017. Selecting client's project control strategies in person-to-organization
transactions.International Journal of Project Management, 35(2), pp. 212-220.
Popaitoon, S. & Siengthai., S., 2016. "The moderating effect of human resource management
practices on the relationship between knowledge absorptive capacity and project performance in
project-oriented companies.". International Journal of Project Mannagement , 32(6), pp. 908-
920.
Tao, F. et al., 2014. CCIoT-CMfg: cloud computing and internet of things-based cloud
manufacturing service system.. IEEE Transactions on Industrial Informatics, 10(2), pp. 1435-
1442..
Teller, J. K. A. & Gemünden, H., 2014. Risk management in project portfolios is more than
managing project risks: A contingency perspective on risk management.. Project Management
Journal, 45(4), pp. 67-80.
29
Tereso, A., Ribeiro, P. & Cardoso, M., 2017. Integration Between EVM and Risk Management:
Proposal of an Automated Framework. In World Conference on Information Systems and
Technologies , pp. 31-40.
30
Proposal of an Automated Framework. In World Conference on Information Systems and
Technologies , pp. 31-40.
30
1 out of 30
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.