Running head: PROJECT MANAGEMENT
Bungalow project
Name of the Student
Name of the University
Author’s Note
Bungalow project
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
PROJECT MANAGEMENT
Table of Contents
1. Introduction..................................................................................................................................2
1.1 Background of the case study................................................................................................2
1.2 Project aims and objectives...................................................................................................2
2. Scope management plan..............................................................................................................3
2.1 Scope statement nad project statement document.................................................................3
2.2 WBS.......................................................................................................................................5
2.3 WBS dictionary.....................................................................................................................6
2.4 Scope validation.....................................................................................................................7
2.5 Roles and responsibilities......................................................................................................7
3. Time schedule..............................................................................................................................8
3.1 Network diagram...................................................................................................................8
3.2 Critical path...........................................................................................................................9
Bibliography..................................................................................................................................10
PROJECT MANAGEMENT
Table of Contents
1. Introduction..................................................................................................................................2
1.1 Background of the case study................................................................................................2
1.2 Project aims and objectives...................................................................................................2
2. Scope management plan..............................................................................................................3
2.1 Scope statement nad project statement document.................................................................3
2.2 WBS.......................................................................................................................................5
2.3 WBS dictionary.....................................................................................................................6
2.4 Scope validation.....................................................................................................................7
2.5 Roles and responsibilities......................................................................................................7
3. Time schedule..............................................................................................................................8
3.1 Network diagram...................................................................................................................8
3.2 Critical path...........................................................................................................................9
Bibliography..................................................................................................................................10
2
PROJECT MANAGEMENT
1. Introduction
1.1 Background of the case study
The paper mainly reflects on the construction of strip footings. It is found that the main
aim of the project is to create components of project management plan by utilizing proper
information. It is found that the construction of the bungalow will generally be supported with
the brick piers as well as timber joints whereas the roof is tiled properly. It is found that
bungalow that is constructed mainly includes six different rooms in total, kitchen dining, lounge,
main bedroom, guest bathroom, second bedroom as well as laundry. It is found that the
construction of Bungalow project is quite helpful in providing proper business value to the
construction company.
1.2 Project aims and objectives
The main aim of the project is to properly construct the bungalow on strip footings that
will further include six different rooms in total including main bedroom, second bedroom,
kitchen dining, lounge, guest bathroom as well as laundry.
The objectives of the project mainly include:
To construct the bungalow on strip footing
To include six rooms in the bungalow including bedroom, kitchen, lounge, bathroom as
well as laundry.
To provide proper business value with the construction of the bungalow project
PROJECT MANAGEMENT
1. Introduction
1.1 Background of the case study
The paper mainly reflects on the construction of strip footings. It is found that the main
aim of the project is to create components of project management plan by utilizing proper
information. It is found that the construction of the bungalow will generally be supported with
the brick piers as well as timber joints whereas the roof is tiled properly. It is found that
bungalow that is constructed mainly includes six different rooms in total, kitchen dining, lounge,
main bedroom, guest bathroom, second bedroom as well as laundry. It is found that the
construction of Bungalow project is quite helpful in providing proper business value to the
construction company.
1.2 Project aims and objectives
The main aim of the project is to properly construct the bungalow on strip footings that
will further include six different rooms in total including main bedroom, second bedroom,
kitchen dining, lounge, guest bathroom as well as laundry.
The objectives of the project mainly include:
To construct the bungalow on strip footing
To include six rooms in the bungalow including bedroom, kitchen, lounge, bathroom as
well as laundry.
To provide proper business value with the construction of the bungalow project
3
PROJECT MANAGEMENT
2. Scope management plan
2.1 Scope statement nad project statement document
Project scope description
The scope of the project includes:
Construction of bungalow project
Floor must be supported on brick piers and timber joists
Plastering of internal finish
Weekly payment to the labourers
Proper schedule and cost management
Project deliverables
The deliverables of the project are reflected below:
Project plan
Project status report
Site prepration report
Construction progress report
Inspection of mortage holder
Construction of bungalow project
Project acceptance criteria
The acceptance criteria of the project are elaborated below:
PROJECT MANAGEMENT
2. Scope management plan
2.1 Scope statement nad project statement document
Project scope description
The scope of the project includes:
Construction of bungalow project
Floor must be supported on brick piers and timber joists
Plastering of internal finish
Weekly payment to the labourers
Proper schedule and cost management
Project deliverables
The deliverables of the project are reflected below:
Project plan
Project status report
Site prepration report
Construction progress report
Inspection of mortage holder
Construction of bungalow project
Project acceptance criteria
The acceptance criteria of the project are elaborated below:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4
PROJECT MANAGEMENT
Progress of schedule: If the project can get completed 20% faster than the given
schedule then it will be considered to be successful which means that the client will accept the
project.
Budget: If the entire work of the project gets finished within the time that is provided by
the project manager then the project will be acceptable for the clients as they do not face any
type of financial issues.
Project exclusions
The exclusions of the project are elaborated below:
Information regarding the project suppliers are not provided within the project
Training manuals or guides are not provided to the project manager as help as the
project managers who are involved with the bungalow project are highly experienced.
Project constraints
The constraints of the project are mainly listed below:
Budget: If the entire project does not gets completed within the assumed budget then the
chnaces of occurring financial issues are quite high that can further obstruct the progress of the
project.
Time: If the project duration that is needed to be completed is generally increased by
50% then it can obstruct the progress of the project.
Project assumptions
The assumptions that are made within the project are listed below:
PROJECT MANAGEMENT
Progress of schedule: If the project can get completed 20% faster than the given
schedule then it will be considered to be successful which means that the client will accept the
project.
Budget: If the entire work of the project gets finished within the time that is provided by
the project manager then the project will be acceptable for the clients as they do not face any
type of financial issues.
Project exclusions
The exclusions of the project are elaborated below:
Information regarding the project suppliers are not provided within the project
Training manuals or guides are not provided to the project manager as help as the
project managers who are involved with the bungalow project are highly experienced.
Project constraints
The constraints of the project are mainly listed below:
Budget: If the entire project does not gets completed within the assumed budget then the
chnaces of occurring financial issues are quite high that can further obstruct the progress of the
project.
Time: If the project duration that is needed to be completed is generally increased by
50% then it can obstruct the progress of the project.
Project assumptions
The assumptions that are made within the project are listed below:
5
PROJECT MANAGEMENT
It is assumed that the work week of the project will be mainly based on 50 hr week
It is assumed by the finacial manager that the budget that is needed for the project
will be finanaced with the help of bank loan.
PROJECT MANAGEMENT
It is assumed that the work week of the project will be mainly based on 50 hr week
It is assumed by the finacial manager that the budget that is needed for the project
will be finanaced with the help of bank loan.
6
PROJECT MANAGEMENT
2.2 WBS
0 Bungalow project
1 Design
1.1
Design structure,
meeting client
requirements
1.2 Appoint project manager
1.3 Modify till acceptance has
been achieved
1.4 Conduct soil test
1.5 Receiving design
approval from client
1.6 Drawing plans and
schedules
1.7 Attain enginerring
certificate
1.8 Submit plans to local
council
1.9 Prepare and submit
application to QBCC
1.10 Select Insurance package
1.11 Engage project
management team
2 Site preparation
2.1 Erecting temporary safety
fencing
2.2 Installing portable WC
facilities
2.3 Installing temporary
power hole
2.4 installing water point
2.5 Fund site power and
water costs
2.6 Clearing the site
2.7 Setting out the dwelling
2.8 Dig foundations
2.9 Foundation inspection
2.10 Installing trench mesh
2.11 Pour footings
3 Building (to Lock up)
3.1 Erecting double brick
external wall system
3.2 Install windows and doors
3.3 install glazing
3.4 Install floor joists
3.5 Exrect internal timber
frame, floor and walls
3.6 Erecting the roof trusses
and battens
3.7 Install roof railing
3.8 Fit ceiling joists
3.9 Fit T & G strip flooring
3.10 Install guttering
3.11 Fit roof tiles
3.12 Rough in electrical
3.13 Rough in plumbing
4 Building (Hand Over)
4.1 Install insulation
4.2 Fit plasterboard to
ceilings
4.3 Fit plasterboard to walls
4.4 Crane lift pool shell into
place
4.5
Install & connect
swimming pool shell
pump
4.6 Conduct second fix
4.7 Tiles
4.8 Paint walls and ceilings
4.9 Fit off electrical points
and appliances
4.10 Fit off plumbing & heating
points
4.11 Installing downpipes and
connect to storm water
4.12 Landscapping
4.13 Connection to server
4.14 Connection to water
supply
4.15 Connection to power
supply
4.16 Clean up site
4.17 Client handover
4.18 Mortage holder
inspection
Figure 1: Work breakdown structure
(Source: Created by Author)
PROJECT MANAGEMENT
2.2 WBS
0 Bungalow project
1 Design
1.1
Design structure,
meeting client
requirements
1.2 Appoint project manager
1.3 Modify till acceptance has
been achieved
1.4 Conduct soil test
1.5 Receiving design
approval from client
1.6 Drawing plans and
schedules
1.7 Attain enginerring
certificate
1.8 Submit plans to local
council
1.9 Prepare and submit
application to QBCC
1.10 Select Insurance package
1.11 Engage project
management team
2 Site preparation
2.1 Erecting temporary safety
fencing
2.2 Installing portable WC
facilities
2.3 Installing temporary
power hole
2.4 installing water point
2.5 Fund site power and
water costs
2.6 Clearing the site
2.7 Setting out the dwelling
2.8 Dig foundations
2.9 Foundation inspection
2.10 Installing trench mesh
2.11 Pour footings
3 Building (to Lock up)
3.1 Erecting double brick
external wall system
3.2 Install windows and doors
3.3 install glazing
3.4 Install floor joists
3.5 Exrect internal timber
frame, floor and walls
3.6 Erecting the roof trusses
and battens
3.7 Install roof railing
3.8 Fit ceiling joists
3.9 Fit T & G strip flooring
3.10 Install guttering
3.11 Fit roof tiles
3.12 Rough in electrical
3.13 Rough in plumbing
4 Building (Hand Over)
4.1 Install insulation
4.2 Fit plasterboard to
ceilings
4.3 Fit plasterboard to walls
4.4 Crane lift pool shell into
place
4.5
Install & connect
swimming pool shell
pump
4.6 Conduct second fix
4.7 Tiles
4.8 Paint walls and ceilings
4.9 Fit off electrical points
and appliances
4.10 Fit off plumbing & heating
points
4.11 Installing downpipes and
connect to storm water
4.12 Landscapping
4.13 Connection to server
4.14 Connection to water
supply
4.15 Connection to power
supply
4.16 Clean up site
4.17 Client handover
4.18 Mortage holder
inspection
Figure 1: Work breakdown structure
(Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7
PROJECT MANAGEMENT
2.3 WBS dictionary
Figure 2: WBS dictionary
(Source: Created by Author)
PROJECT MANAGEMENT
2.3 WBS dictionary
Figure 2: WBS dictionary
(Source: Created by Author)
8
PROJECT MANAGEMENT
2.4 Scope validation
Scope validation is mainly defined as one of the procedure that is helpful in formalizing
the acceptance of the completed deliverables of the project. The main benefit of the entire
process is that it generally helps in bringing objectivity for the acceptance process that further
helps in increasing the chances of the final service or result acceptance by proper validation of
each of the project deliverable.
2.5 Roles and responsibilities
The roles and responsibilities of the stakeholder who are involved in the project are
reflected in the table below:
Project roles Responsibilities
Project manager The project manager is responsible of
managing the activities starting from the
initiation phase for constructing the
bungalow.
Construction manager The construction manager is mainly
responsible of managing the constriction work
including the construction of 6 rooms, tiled
roof, external gutters and more.
Labourers The labourers are mainly responsible of
completing the construction work in the
project so that the bungalow can be
effectively constructed.
Suppliers A supplier is the person or the person who
PROJECT MANAGEMENT
2.4 Scope validation
Scope validation is mainly defined as one of the procedure that is helpful in formalizing
the acceptance of the completed deliverables of the project. The main benefit of the entire
process is that it generally helps in bringing objectivity for the acceptance process that further
helps in increasing the chances of the final service or result acceptance by proper validation of
each of the project deliverable.
2.5 Roles and responsibilities
The roles and responsibilities of the stakeholder who are involved in the project are
reflected in the table below:
Project roles Responsibilities
Project manager The project manager is responsible of
managing the activities starting from the
initiation phase for constructing the
bungalow.
Construction manager The construction manager is mainly
responsible of managing the constriction work
including the construction of 6 rooms, tiled
roof, external gutters and more.
Labourers The labourers are mainly responsible of
completing the construction work in the
project so that the bungalow can be
effectively constructed.
Suppliers A supplier is the person or the person who
9
PROJECT MANAGEMENT
helps in providing business product or
service. They generally provide high quality
of materials for the purpose of bungalow
construction.
Contractor The contractor is mainly responsible of
providing all the materials, labour as well as
equipment for the construction of bungalow.
3. Time schedule
3.1 Network diagram
Figure 3: Network Diagram
(Source: Created by Author)
PROJECT MANAGEMENT
helps in providing business product or
service. They generally provide high quality
of materials for the purpose of bungalow
construction.
Contractor The contractor is mainly responsible of
providing all the materials, labour as well as
equipment for the construction of bungalow.
3. Time schedule
3.1 Network diagram
Figure 3: Network Diagram
(Source: Created by Author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10
PROJECT MANAGEMENT
3.2 Critical path
Figure 4: Critical path
(Source: Created by Author)
PROJECT MANAGEMENT
3.2 Critical path
Figure 4: Critical path
(Source: Created by Author)
11
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics applied to
project management. International Journal of Project Management, 35(2), pp.169-179.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on project
success and on the execution of business strategies. International Journal of Project
Management, 33(1), pp.53-66.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), pp.772-783.
PROJECT MANAGEMENT
Bibliography
Badewi, A., 2016. The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), pp.761-778.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Papke-Shields, K.E. and Boyer-Wright, K.M., 2017. Strategic planning characteristics applied to
project management. International Journal of Project Management, 35(2), pp.169-179.
Serra, C.E.M. and Kunc, M., 2015. Benefits realisation management and its influence on project
success and on the execution of business strategies. International Journal of Project
Management, 33(1), pp.53-66.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), pp.772-783.
1 out of 12
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.