Construction Project Management and BIM

Verified

Added on  2021/04/19

|21
|4559
|445
AI Summary
This assignment provides a comprehensive overview of construction project management and BIM. It includes information on analytical design planning technique (ADePT), IDEF0, column reinforcement, construction management processes, and project management for commercial concrete polishing contractors. The document also explores the future of BIM in the AEC industry and provides insights into project management techniques such as labor, material, and equipment utilization.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
PROJECT MANAGEMENT
SOFTWARE

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Contents
1. INTRODUCTION.............................................................................................................................1
1.1 Project Aim................................................................................................................................1
1.2 Objectives...................................................................................................................................1
1.3 Background of the Project........................................................................................................2
1.4 Project Overview.......................................................................................................................3
2. SPECIALIST TRADE PACKAGE..................................................................................................3
2.1 Purpose.......................................................................................................................................4
2.2 Scope...........................................................................................................................................4
2.3 Information Flow.......................................................................................................................4
2.4 Process Map...............................................................................................................................5
3. IMPLEMENTATIONS.....................................................................................................................6
3.1 Implementation of Microsoft Project Software.......................................................................6
3.1.1 Complete Construction Programme.................................................................................6
3.1.2 Critical Appraisal of Microsoft Project Software..........................................................16
3.2 Implementation of 4D BIM.....................................................................................................17
3.2.1 Advantages for 4D BIM Implementation.......................................................................17
3.2.2 Barriers for 4D BIM Implementation............................................................................17
3.3 Implementation of ADePT......................................................................................................17
3.3.1 Advantages for ADePT Implementation........................................................................17
3.3.2 Barriers for ADePT Implementation.............................................................................18
References................................................................................................................................................19
Abbreviations
ADePT- Analytical Design Planning Technique
BIM- Building Information Modeling
IDEF- Integrated DEFinition
Document Page
1. INTRODUCTION
The management of construction project demands specialized proficiency and knowledge of
handling project management tasks. Construction is an area which requires more experience to
handle teams of diverse nature to meet the required objectives ("Construction Project
Management 101", 2018). In this technology oriented world effective technologies have paved
way for easing the difficulties of construction projects. Similarly, the complexities of
construction management are resolved by various helpful methods and tools, such as Microsoft
project management and so on. The construction management not just focuses on the tasks to
be completed, instead it also gives importance for quality, contract administration and safety
management apart from the other basic factors. Further, communication and effectively
utilizing the available resources by the defined scope, budget and schedule has a significant role
in construction management (Maria Delos Santos, 2017).
Project Management can be defined as an art that effectively directs and helps in coordinating
with diverse people and material resources ("Project Management for Construction:
Construction Planning", 2018). However, to help the project managers the Microsoft project
software is used widely in the construction field. It has features that help in managing the
material resources and human resources effectively ("Project Management for Construction:
Labor, Material and Equipment Utilization", 2018). On the other hand it helps to accomplish the
required project on time and helps to have a track of all the tasks to be completed throughout
the project (Hendrickson & Au, 2008).
1.1 Project Aim
This project aims to provide a clear understanding of the process to be undertaken in the
construction of the building. The relative timing to complete the project, relationship between
the information flows and the specialist trade packages is also the purpose of this aim.
1.2 Objectives
This project’s objectives are listed below:
i. To collect information of the programme.
ii. To design the IDEF0 process map based on the collected information flow.
iii. To determine the required time, for the successful completion of the project.
iv. To assess the effectiveness of Microsoft project software, and
v. To determine the critical appraisals related to the implementation of 4D BIM
tool, Microsoft project software and ADePT methodology.
1
Document Page
1.3 Background of the Project
This project revolves around the construction of a 50-storey tower i.e., built off of a three-
storey podium deck in a city center location. It is basements at two levels. The building’s central
core is a concrete construction. It is to be built in front of the floor slabs. The jump form,
central tower crane, floor slabs all have a significant role in the construction. The complete
construction of the building has reinforced concrete. This is a huge project and required many
people to work on designing and on project management. If the design is not understood
clearly it can create misunderstandings between the contractors and the managers. The
misunderstanding can have negative impact on the management of the work, then on cost and
time of the project ("Project Management 101 for Commercial Concrete Polishing Contractors",
2018).
The following are the activities of this project, in a sequence:
1) Lifting the screens.
2) Reinforcing and column formation.
3) Position forming aimed at the band and perimeter beams.
4) Beam formation.
5) Metal deck positioning.
6) Reinforcing and cable stressing process.
7) Concrete floor slab execution.
This project’s construction management contains the following specialty trade packages- Core,
framework, reinforcement, stressing, concrete, screens and crane. The selected specialty trade
package for this project is, “Reinforcement.” The reinforced concrete is a modern material used
in construction of buildings. It has the capacity to be molded into the desired shape ("What is
reinforcement in construction - Basic Civil Engineering", 2018).
It is observed that there exists difficulty in clearly understanding process to be undertaken. This
is resolved by designing an effective process model for the construction of a 50-storey tower or
a building, where the relative timing to complete the project, relationship between the
information flows and the specialist trade packages will be determined. Further, this report also
aims to determine the advantages and barriers of 4D BIM tool, Microsoft project software and
ADePT methodology’s implementation.
For this project, it is recommended to use 4D BIM design tool and ADePT methodology for
successfully completing the project on time. On the other hand, this project also ensures to
concentrate on the quality, contract administration and safety management along with the
other important factors ("Construction Management - Basthatfield", 2018).
2

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1.4 Project Overview
This section of the report emphasizes on the structure of the whole report. The report’s initial
section presents the focal point like aim, objectives and background of the study. This section is
the introductory part of the whole project.
The second section explores the selected specialist trade package and signifies the purpose and
scope in the construction management process. Further, this section is subdivided with the
information of IDEF0 process map, for the project. The process mapping is basically a business
process model and this model is developed in this part for the selected specialty trade package.
The model is designed based on the gathered information as, information flow.
The third section of the report inspects the implementations of Microsoft Project software, 4D
BIM tool and ADePT methodology in the construction project. The Microsoft Project software is
used for investigating the time constraints, cost and resources required for the project. Gantt
chart and the step-by-step tasks required for the project are determined in this specific part.
However, Microsoft project is also used to concentrate on its critical appraisal and scrutinizes
its competencies to help the project managers, in the construction industry. Additionally, in
construction business the advantages and barriers of 4D BIM tool and ADePT methodology’s
implementation is determined. This section also includes the critical appraisals for Microsoft
Project software.
2. SPECIALIST TRADE PACKAGE
The selected specialist trade package is, reinforcement. In construction, reinforcement is held
responsible for the structure of the building, thus it is the foundation of the building which has
to be monitored effectively. If this goes wrong, then it imposes negative impact on the budget
of the project. The following aspects must be taken care ("Concrete and Aggregate Testing",
2018) (Koutsogiannis, 2018):
1) Follow the design ("Construction Project Management | Coursera", 2018).
2) Ensure to check the constructed bar bindings, to manage the risks.
3) Follow the guideline for reinforcement (Landau, 2018).
4) Ensure right amount of materials are used, with right size, weight and quantity.
5) The reinforcement of column, beam and wall has to be carefully monitored by
the project manager ("Column Reinforcement", 2018).
6) The bending stress must be cross-checked.
7) Tension resistance on the beam must be determined.
8) Length of the bar must be checked.
3
Document Page
2.1 Purpose
The purpose is to establish an accurate reinforcement to successfully complete the construction
of the building. This ensures to secure the building and to fulfill the scope of the project.
2.2 Scope
This project’s scope is to enhance the construction management with improved techniques and
tools, which results in effective co-ordination and cooperation between the workers, project
managers and sub-contractors. Further, it ensure the following scopes:
The problem of lifting the screens will be considered and resolved with effective
measures.
The issues of the processes like, striking and collecting the used materials to pass it to
the next above floor will be controlled.
The necessary security measures will be included, for the safety of the people working
on the site.
The risks will be defined.
The staff will be trained to follow the newly proposed process.
The inputs of the project manager, subcontractors and workers will be gathered, to
work on improving the process.
The stressing system will be improved and monitored.
Improved construction management will be presented.
2.3 Information Flow
Coordination between the workers, project managers and sub-contractors are essential in the
reinforcement process. Project manager and workers for the following process ("What is
reinforcement in construction - Basic Civil Engineering", 2018) ("Column Reinforcement -
Reinforcement Details In Column", 2018):
a) Binding of bars.
b) Bar Notation
c) Steel bar lapping
d) Length of the crank.
e) Covering
f) Stool in reinforcement.
The reinforcement drawing must be completed and designed correctly, if not it can distort the
diameters of the bar and result in wrong reinforcement.
4
Document Page
Information supplied by Project manager Information supplied by Sub-contractor
Engineering reports Reports of the performed schedule.
Reports of the schedule. Project design
Requirement of health and safety. Cost plan
Information related to risks at the site. Scheduled processes.
Other construction information Safety programme is scheduled
Inputs of the workers and the sub-contractors. Training programme is scheduled
Cost estimation Reports of the performed schedule.
Schedules of all the processes at the site. Inputs of the workers.
Training programme
Security programme
2.4 Process Map
For construction of reinforcement, the easily understood process model is provided in this part
of the report. The IDEF0 mapping method is utilized to denote the activities and functions of
the package ("IDEF0 - Part 1 (understanding it)", 2018). This model delivers clear understanding
of all the necessary processes to be undertaken (Damelio, 2011). The clarity is made possible by
the graphical representation of each process in the model (Introduction to IDEF0/3 for Business
Process Modelling, 2013). The IDEF0 Process Map is depicted in the below figure.
5
Concrete
Floor Cycle
Site clearing
Reinforcing and formation
of columns
Position formation for the
band and perimeter beams
General excavation and
Excavation for utility trenches

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
3. IMPLEMENTATIONS
3.1 Implementation of Microsoft Project Software
This section represents the abilities of Microsoft Project software and defines the complete
structural construction programme for the selected trade package.
3.1.1 Complete Construction Programme
The complete tasks for the construction project are mentioned in the below table.
Task Name
Construction Floor Cycle Project
Gathering the Project Requirements
Analysis the Project Requirements
Pre-construction of Construction Project
Prepare project contract Drawings
Permit Foundation for Project
Permit full building
Site utility relocation
Construction Project Procurement
Subcontractor bid
6
Document Page
Interview period
Recommendation of subcontracts
Approval of subcontracts
Shoring and sheeting procurement
Other material procurement
Construction
Notice to proceed
Drill Dewatering Wells
Install Solider Piles
Excavation
Install Lagging
Install Tiebacks
Concrete Footings
Concrete Walls
Concrete Columns
Concrete Slab
Lift screens
Reinforce and form columns
Position forms for the band and
Perimeter beams
Form beams
Position metal deck
Reinforce including stressing
Cables
Concrete floor slab
Inspections & Close Out
Weather Day Allowance
Commissioning & Training
Final Clean
Punchlist Generation
O&M Manual Submission
Substantial Completion Process
Substantial Completion
Resources
7
Document Page
Project’s resources are listed below.
Resource Name Type Initials Max.
Units
Std. Rate Accru
e At
Base
Calendar
Project Executive Work P 100% $2,500.00/hr Prorat
ed
Standard
Senior Project Manager Work S 100% $3,000.00/hr Prorat
ed
Standard
Project Engineer Work P 100% $2,000.00/hr Prorat
ed
Standard
Project Admin Work P 100% $1,900.00/hr Prorat
ed
Standard
Project Accountant Work P 100% $1,500.00/hr Prorat
ed
Standard
Project Scheduler Work P 100% $1,500.00/hr Prorat
ed
Standard
Senior Superintendent Work S 100% $2,000.00/hr Prorat
ed
Standard
Safety Manager Work S 100% $1,500.00/hr Prorat
ed
Standard
Layout Engineer Work L 100% $1,000.00/hr Prorat
ed
Standard
Unskilled Laborer Work U 100% $1,000.00/hr Prorat
ed
Standard
Equipment and Facilities Work E 100% $2,500.00/hr Prorat
ed
Standard
Contractor Work C 100% $1,000.00/hr Prorat
ed
Standard
Sub-Contractor Work S 100% $1,000.00/hr Prorat
ed
Standard
The overall construction project plan is shown below.
Task
Mode
Task Name Duration Start Finis
h
Prede
cessor
s
Resource Names
Auto Construction 266 days Fri Fri
8

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Sched
uled
Floor Cycle
Project
3/16
/18
3/22
/19
Auto
Sched
uled
Gathering
the Project
Requirements
1 day Fri
3/16/
18
Fri
3/16/
18
Project Engineer, Project
Scheduler, Senior Project
Manager
Auto
Sched
uled
Analysis the
Project
Requirements
2 days Fri
3/16/
18
Mon
3/19/
18
Project Engineer, Senior
Project Manager
Auto
Sched
uled
Pre
construction
of
Construction
Project
10 days Fri
3/16/
18
Thu
3/29/
18
Layout Engineer, Project
Engineer, Senior Project
Manager
Auto
Sched
uled
Prepare
project
contract
Drawings
2 days Fri
3/30/
18
Mon
4/2/1
8
4 Equipment and Facilities,
Layout Engineer, Project
Engineer
Auto
Sched
uled
Permit
Foundation
for Project
1 day Tue
4/3/1
8
Tue
4/3/1
8
5 Equipment and Facilities,
Senior Project Manager, Senior
Superintendent
Auto
Sched
uled
Permit full
building
3 days Wed
4/4/1
8
Fri
4/6/1
8
6 Equipment and Facilities,
Project Engineer, Senior
Project Manager
Auto
Sched
uled
Site utility
relocation
5 days Mon
4/9/1
8
Fri
4/13/
18
7 Layout Engineer, Senior
Project Manager, Senior
Superintendent
Auto
Sched
uled
Construction
Project
Procurement
14 days Mon
4/16
/18
Thu
5/3/
18
8
Auto
Sched
uled
Subcontractor
bid
3 days Mon
4/16/
18
Wed
4/18/
18
Project Engineer, Senior
Project Manager, Sub-
Contractor
Auto
Sched
uled
Interview
period
2 days Mon
4/16/
18
Tue
4/17/
18
Project Engineer, Senior
Project Manager
Auto
Sched Recommenda
6 days Thu
4/19/
Thu
4/26/
10 Contractor, Project Admin,
Project Executive, Senior
9
Document Page
uled tion of
subcontracts
18 18 Project Manager
Auto
Sched
uled
Approval
of
subcontracts
1 day Mon
4/16/
18
Mon
4/16/
18
Project Engineer[50%],Project
Scheduler[50%],Senior Project
Manager[50%]
Auto
Sched
uled
Shoring
and sheeting
procurement
2 days Fri
4/27/
18
Mon
4/30/
18
12 Equipment and Facilities,
Layout Engineer, Senior
Project Manager, Senior
Superintendent
Auto
Sched
uled
Other
material
procurement
3 days Tue
5/1/1
8
Thu
5/3/1
8
14 Project Admin, Project
Engineer, Senior Project
Manager
Auto
Sched
uled
Construction
199 days Fri
5/4/
18
Wed
2/6/
19
9
Auto
Sched
uled
Notice to
proceed
1 day Fri
5/4/1
8
Fri
5/4/1
8
Contractor, Equipment and
Facilities, Layout Engineer,
Senior Project Manager, Senior
Superintendent
Auto
Sched
uled
Drill
Dewatering
Wells
30 days Mon
5/7/1
8
Fri
6/15/
18
17 Contractor, Equipment and
Facilities, Project Executive,
Sub-Contractor, Unskilled
Laborer
Auto
Sched
uled
Install
Solider Piles
20 days Mon
6/18/
18
Fri
7/13/
18
18 Contractor, Equipment and
Facilities, Project Executive,
Sub-Contractor, Unskilled
Laborer
Auto
Sched
uled
Excavation 10 days Mon
7/16/
18
Fri
7/27/
18
19 Equipment and Facilities,
Project Executive, Sub-
Contractor, Unskilled Laborer
Auto
Sched
uled
Install
Lagging
5 days Mon
7/30/
18
Fri
8/3/1
8
20 Equipment and Facilities,
Layout Engineer, Project
Engineer, Project Executive,
Safety Manager
Auto
Sched
uled
Install
Tiebacks
5 days Mon
8/6/1
8
Fri
8/10/
18
21 Contractor, Equipment and
Facilities, Project Engineer,
Project Executive, Unskilled
Laborer
10
Document Page
Auto
Sched
uled
Concrete
Footings
6 days Mon
8/13/
18
Mon
8/20/
18
22 Equipment and Facilities,
Project Engineer, Project
Executive, Sub-Contractor,
Unskilled Laborer
Auto
Sched
uled
Concrete
Walls
7 days Tue
8/21/
18
Wed
8/29/
18
23 Contractor, Equipment and
Facilities, Project Accountant,
Project Admin, Project
Executive, Unskilled Laborer
Auto
Sched
uled
Concrete
Columns
9 days Thu
8/30/
18
Tue
9/11/
18
24 Contractor, Equipment and
Facilities, Project Engineer,
Project Executive, Sub-
Contractor
Auto
Sched
uled
Concrete
Slab
20 days Wed
9/12/
18
Tue
10/9/
18
25 Contractor, Project Engineer,
Project Executive, Sub-
Contractor, Unskilled Laborer
Auto
Sched
uled
Lift
screens
12 days Wed
10/1
0/18
Thu
10/2
5/18
26 Equipment and Facilities,
Project Engineer, Project
Executive, Sub-Contractor,
Unskilled Laborer
Auto
Sched
uled
Reinforce
and form
columns
5 days Fri
10/2
6/18
Thu
11/1/
18
27 Contractor, Equipment and
Facilities, Project Engineer,
Sub-Contractor, Unskilled
Laborer
Auto
Sched
uled
Position
forms for the
band and
7 days Fri
11/2/
18
Mon
11/1
2/18
28 Contractor, Equipment and
Facilities, Project Engineer,
Project Executive, Safety
Manager
Auto
Sched
uled
Perimeter
beams
8 days Tue
11/1
3/18
Thu
11/2
2/18
29 Equipment and Facilities,
Project Executive, Sub-
Contractor, Unskilled Laborer
Auto
Sched
uled
Form
beams
9 days Fri
11/2
3/18
Wed
12/5/
18
30 Project Executive, Project
Scheduler, Sub-Contractor
Auto
Sched
uled
Position
metal deck
12 days Thu
12/6/
18
Fri
12/2
1/18
31 Equipment and Facilities,
Layout Engineer, Project
Admin, Sub-Contractor
Auto
Sched
Reinforce
including
8 days Mon
12/2
Wed
1/2/1
32 Project Engineer, Project
Executive, Sub-Contractor
11

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
uled stressing 4/18 9
Auto
Sched
uled
Cables 10 days Thu
1/3/1
9
Wed
1/16/
19
33 Equipment and Facilities,
Layout Engineer, Project
Accountant, Project Engineer
Auto
Sched
uled
Concrete
floor slab
15 days Thu
1/17/
19
Wed
2/6/1
9
34 Contractor, Layout Engineer,
Project Executive, Project
Scheduler, Safety Manager,
Sub-Contractor, Unskilled
Laborer
Auto
Sched
uled
Inspections
& Close Out
32 days Thu
2/7/
19
Fri
3/22
/19
35
Auto
Sched
uled
Weather
Day
Allowance
4 days Thu
2/7/1
9
Tue
2/12/
19
10 Project Admin, Project
Engineer, Project Executive,
Project Scheduler, Senior
Superintendent
Auto
Sched
uled
Commissionin
g & Training
7 days Wed
2/13/
19
Thu
2/21/
19
37 Equipment and Facilities,
Project Engineer, Senior
Project Manager
Auto
Sched
uled
Final Clean 9 days Fri
2/22/
19
Wed
3/6/1
9
38 Contractor, Equipment and
Facilities, Project Admin,
Unskilled Laborer
Auto
Sched
uled
Punchlist
Generation
4 days Thu
3/7/1
9
Tue
3/12/
19
39 Contractor, Layout Engineer,
Project Engineer, Project
Executive, Sub-Contractor
Auto
Sched
uled
O&M
Manual
Submission
6 days Wed
3/13/
19
Wed
3/20/
19
40 Layout Engineer, Senior
Project Manager, Senior
Superintendent, Project Admin
Auto
Sched
uled
Substantial
Completion
Process
1 day Thu
3/21/
19
Thu
3/21/
19
41 Project Accountant, Project
Admin, Senior Project
Manager, Senior
Superintendent
Auto
Sched
uled
Substantial
Completion
1 day Fri
3/22/
19
Fri
3/22/
19
42 Project Admin, Project
Executive, Project Scheduler,
Senior Project Manager, Senior
Superintendent
Work Breakdown Structure
12
Document Page
Work breakdown structure represented as shown below.
Timing required for the Project Completion
The time required to finish this construction project is 266 days.
Project Cost
The overall project cost is as shown below.
Name Actual
Cost
Remain
ing
Cost
Baseline
Cost
Cost Cost
Variance
Constructio
n Floor
Cycle
Project
$0.00 $16,71
4,800.0
0
$0.00 $16,
714,
800.
00
$16,714,800.
00
13
Document Page
The above graph depicts the cost of the whole project.
Cost of the Resources
The total cost of the resources cost are presented in the following table.
Name Start Finish Remaining
Work
Project Executive Thu
4/19/18
Fri
3/22/19
1,488 hrs
Senior Project
Manager
Fri
3/16/18
Fri
3/22/19
436 hrs
Project Engineer Fri
3/16/18
Tue
3/12/19
1,028 hrs
Project Admin Thu
4/19/18
Fri
3/22/19
392 hrs
Project Accountant Tue
8/21/18
Thu
3/21/19
144 hrs
Project Scheduler Fri
3/16/18
Fri
3/22/19
244 hrs
Senior Superintendent Tue
4/3/18
Fri
3/22/19
168 hrs
Safety Manager Mon
7/30/18
Wed
2/6/19
216 hrs
Layout Engineer Fri
3/16/18
Wed
3/20/19
576 hrs
Unskilled Laborer Mon
5/7/18
Wed
3/6/19
1,176 hrs
14

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Equipment and
Facilities
Fri
3/30/18
Wed
3/6/19
1,368 hrs
Contractor Thu
4/19/18
Tue
3/12/19
1,104 hrs
Sub-Contractor Mon
4/16/18
Tue
3/12/19
1,368 hrs
The above graph depicts the cost of the whole project.
3.1.2 Programme Information Required
The following are the programme information required for the selected package:
Schedule for lifting the screens.
Striking process
Information of collected used materials.
Cleaning process
Stressing system
Risks
Scheduled working staff
Information from the subcontractors and workers, to improve the process.
15
Document Page
3.1.3 Critical Appraisal of Microsoft Project Software
The highly used software for project management is, “Microsoft Project Software”, because it
provides satisfied results. It has smart features to help scheduling. It ensures to work parallel
with the tasks and gives effective communication. It tracks the progress and highlights the
encountered issues.
The Microsoft project software helps in resolving the following issues.
Lifting of screens is scheduled based on the available manpower, to avoid any delay of
the work.
The striking process is scheduled.
Collection of used material is monitored, and the same is sent to the above floor next.
Cleaning process is scheduled, to avoid any mishaps in the site.
The stressing system is monitored and scheduled.
The risks are defined.
The staff are scheduled to provide the required training, to get accustomed to the newly
proposed process.
The inputs of the project manager, subcontractors and workers have helped in
improving the process.
Improved construction management is presented.
3.2 Implementation of 4D BIM
3.2.1 Advantages for 4D BIM Implementation
The advantages of implementing the 4D BIM are as follows:
4D BIM ensures to benefit the users with four dimensional graphical
representation of the building that is designed for construction (Ahmed, Emam &
Farrell, 2014).
It is an effective design tool which helps the development phase of the plans
along with its schedule.
It has significant design features which helps to combine the design and
construction.
It benefits with consistent scheduling and intelligent features.
It helps to save costs related to rework and scheduling.
3.2.2 Barriers for 4D BIM Implementation
The barriers for the effective implementation of the 4D BIM design tool are listed below:
The construction project managers lack enough skills to work on the 4D BIM tool.
The users are not provided with sufficient training.
Availability of the required software and matching the standards of the industry.
16
Document Page
Cost for upgrading the hardware and software at the initial stage can be barrier
too (Hardin & McCool, 2015).
3.3 Implementation of ADePT
3.3.1 Advantages for ADePT Implementation
The advantages of implementing the ADePT are as follows:
ADePT is mainly is useful before planning stage (Austin, Baldwin, Li & Waskett,
2000).
ADePT has better change management handling.
It seizes any limitations related to building’s drawing (Schultz, 2002).
ADePT supports to manage the building design, helps in decision making, and in
defining the roles.
It improves project management and helps in prioritizing the work.
3.3.2 Barriers for ADePT Implementation
The barriers for the effective implementation of the ADePT are listed below:
Complexity to clearly understand the design.
Delayed construction.
Highly expensive
References
Ahmed, S., Emam, H., & Farrell, P. (2014). Barriers to BIM/4D Implementation in Qatar .1 St
International Conference On Smart, Sustainable And Healthy Cities [CIB-MENA], At Abu
Dhabi, UAE. http://dx.doi.org/10.13140/RG.2.1.4990.4164
Austin, S., Baldwin, A., Li, B., & Waskett, P. (2000). Analytical design planning technique
(ADePT): a dependency structure matrix tool to schedule the building design
process. Construction Management And Economics, 18(2), 173-182.
http://dx.doi.org/10.1080/014461900370807
BIM and the future of AEC. (2018). Autodesk.com. Retrieved 17 March 2018, from
https://www.autodesk.com/solutions/bim
Column Reinforcement - Reinforcement Details In Column. (2018). Daily Civil. Retrieved 20
March 2018, from http://www.dailycivil.com/column-reinforcement-details/
17

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Column Reinforcement. (2018). Constructionmanuals.tpub.com. Retrieved 20 March 2018, from
http://constructionmanuals.tpub.com/14045/css/Column-Reinforcement-119.htm
Construction Management - Basthatfield. (2018). Basthatfield. Retrieved 19 March 2018,
from http://www.basthatfield.com/services/construction-management/
Construction Project Management | Coursera. (2018). Coursera. Retrieved 19 March 2018,
from https://www.coursera.org/learn/construction-project-management
Construction Project Management 101. (2018). Smartsheet. Retrieved 20 March 2018, from
https://www.smartsheet.com/construction-project-management-101-full
Hardin, B., & McCool, D. (2015). BIM and construction management (2nd ed.).
Hendrickson, C., & Au, T. (2008). Project management for construction. Pittsburgh, Penn.:
Carnegie Mellon University.
IDEF0 - Part 1 (understanding it). (2018). Syque.com. Retrieved 19 March 2018, from
http://syque.com/quality_tools/tools/Tools19.htm
Introduction to IDEF0/3 for Business Process Modelling. (2013).
Koutsogiannis, A. (2018). Construction Project Management Processes: Everything You Need to
Know - GenieBelt. GenieBelt. Retrieved 19 March 2018,
from https://geniebelt.com/blog/construction-project-management-processes
Landau, P. (2018). Construction Project Management - A Quick Guide. ProjectManager.com.
Retrieved 19 March 2018, from https://www.projectmanager.com/blog/construction-
project-management
Maria Delos Santos, J. (2017). What Is Construction Project Management?. project-
management.com. Retrieved 20 March 2018, from
https://project-management.com/what-is-construction-project-management/
Project Management 101 for Commercial Concrete Polishing Contractors. (2018). For
Construction Pros. Retrieved 19 March 2018,
18
Document Page
from https://www.forconstructionpros.com/business/business-services/article/
12281263/project-management-101-for-commercial-concrete-polishing-contractors
Project Management for Construction: Construction Planning. (2018). Cmu.edu. Retrieved 19
March 2018,
from https://www.cmu.edu/cee/projects/PMbook/09_Construction_Planning.html
Project Management for Construction: Labor, Material and Equipment Utilization.
(2018). Cmu.edu. Retrieved 19 March 2018,
from https://www.cmu.edu/cee/projects/PMbook/04_Labor,_Material,_And_Equipment_
Utilization.html
Schultz, T. (2002). ADEPT-The Advanced Database Environment for Planning and Tracking. Bell
Labs Technical Journal, 3(3), 3-9. http://dx.doi.org/10.1002/bltj.2111
What is reinforcement in construction - Basic Civil Engineering. (2018). Basic Civil Engineering.
Retrieved 20 March 2018, from http://www.basiccivilengineering.com/2015/05/what-is-
reinforcement-in-construction.html
19
1 out of 21
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]