Project Management Evaluation Outline
VerifiedAdded on  2021/04/24
|22
|3896
|50
AI Summary
The provided document is an assignment that focuses on evaluating project management strategies. It includes a project management evaluation outline, which assesses the successful implementation of a project in terms of delivering a secured, user-friendly, faster system to clients. The document also references various studies and sources related to project management, including Agile adoption, project success analysis frameworks, and reputation management systems.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Project Management: Globex Project Scenario
Name of the student:
Name of the university:
Project Management: Globex Project Scenario
Name of the student:
Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT
Table of Contents
Part 1: Measurable Organizational Value........................................................................................3
1.1 Identification for desired area of impact................................................................................3
1.2 Identification of type of the values........................................................................................6
1.3 Development for appropriate metrics....................................................................................6
1.4 Timeframe development........................................................................................................7
1.5 Summary for MOV..............................................................................................................11
Part 2: Project scope management.................................................................................................11
2.1 Scope of the project.............................................................................................................11
2.2 Project resource list..............................................................................................................11
2.3 Resource details...................................................................................................................12
Part 3: Project schedule planning..................................................................................................13
3.1 Work breakdown structure for RALS project.....................................................................13
3.2 Project activity set................................................................................................................14
3.3 Project resources..................................................................................................................15
3.4 Cost estimation for the activities.........................................................................................15
3.5 Estimated time for the project..............................................................................................18
Part 4: Risk analysis and planning.................................................................................................19
4.1 Analysis of project risk and planning..................................................................................19
Part 5: Quality management plan..................................................................................................22
5.1 Philosophy of the project team............................................................................................22
5.2 Quality assurance plan for the project.................................................................................22
Part 6: Closure and evaluation.......................................................................................................23
6.1 Annotated Bibliography.......................................................................................................23
6.2 Project closure checklist......................................................................................................24
6.3 Project evaluation outline....................................................................................................25
References......................................................................................................................................26
Table of Contents
Part 1: Measurable Organizational Value........................................................................................3
1.1 Identification for desired area of impact................................................................................3
1.2 Identification of type of the values........................................................................................6
1.3 Development for appropriate metrics....................................................................................6
1.4 Timeframe development........................................................................................................7
1.5 Summary for MOV..............................................................................................................11
Part 2: Project scope management.................................................................................................11
2.1 Scope of the project.............................................................................................................11
2.2 Project resource list..............................................................................................................11
2.3 Resource details...................................................................................................................12
Part 3: Project schedule planning..................................................................................................13
3.1 Work breakdown structure for RALS project.....................................................................13
3.2 Project activity set................................................................................................................14
3.3 Project resources..................................................................................................................15
3.4 Cost estimation for the activities.........................................................................................15
3.5 Estimated time for the project..............................................................................................18
Part 4: Risk analysis and planning.................................................................................................19
4.1 Analysis of project risk and planning..................................................................................19
Part 5: Quality management plan..................................................................................................22
5.1 Philosophy of the project team............................................................................................22
5.2 Quality assurance plan for the project.................................................................................22
Part 6: Closure and evaluation.......................................................................................................23
6.1 Annotated Bibliography.......................................................................................................23
6.2 Project closure checklist......................................................................................................24
6.3 Project evaluation outline....................................................................................................25
References......................................................................................................................................26
2PROJECT MANAGEMENT
Part 1: Measurable Organizational Value
1.1 Identification for desired area of impact
Identified areas Impact Rank
Consumers Consumers are defied as the main asset
to keep a running business successful
commercially. Online registration,
booking and payment system will give
opportunity to the company to grab more
number of consumers. Superior interface
of online booking system can attract
consumers for its user friendly
application and operational features.
1
Strategy This is another valuable feature for
economical business success. The issues
of manual booking and excel or
spreadsheet based data management was
negatively impacting the project of
Globex. Thus, strategies possessed by
Virtucon will exceptionally help it to
grab consumers. As the developers have
identified that online system has the
potential to attract clients.
2
Part 1: Measurable Organizational Value
1.1 Identification for desired area of impact
Identified areas Impact Rank
Consumers Consumers are defied as the main asset
to keep a running business successful
commercially. Online registration,
booking and payment system will give
opportunity to the company to grab more
number of consumers. Superior interface
of online booking system can attract
consumers for its user friendly
application and operational features.
1
Strategy This is another valuable feature for
economical business success. The issues
of manual booking and excel or
spreadsheet based data management was
negatively impacting the project of
Globex. Thus, strategies possessed by
Virtucon will exceptionally help it to
grab consumers. As the developers have
identified that online system has the
potential to attract clients.
2
3PROJECT MANAGEMENT
Finance Financial support is also an important
component to implement any project
successfully. In order to get estimated
financial capital it is necessary for
Globex to contract with supportive
project sponsors.
3
Operation Implementation of a new online system
is not enough to gain business success.
The system should serve adequate
operational and functional activities also.
Thus, operation is an important part for
the system that has to be considered by
the IT project manager.
4
Social In order to promote the online system
developed by the IT project manager of
Globex social support is needed. Thus,
different social media platform are used
to spread the new online system and its
ability throughout.
5
Finance Financial support is also an important
component to implement any project
successfully. In order to get estimated
financial capital it is necessary for
Globex to contract with supportive
project sponsors.
3
Operation Implementation of a new online system
is not enough to gain business success.
The system should serve adequate
operational and functional activities also.
Thus, operation is an important part for
the system that has to be considered by
the IT project manager.
4
Social In order to promote the online system
developed by the IT project manager of
Globex social support is needed. Thus,
different social media platform are used
to spread the new online system and its
ability throughout.
5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT
1.2 Identification of type of the values
Besides the operational factors there are certain values those are equally have to ve
measured. Apart from reliability and flexibility the other values for the online system are as
follows:
Better: The existing manual excel or spreadsheet data management system was raising
error to Globex project thus the new online booking system should serve better delivery
approach with security and user friendly to the consumers.
Faster: The manual booking system was time consuming as it was human controlled
thus, the new booking system is expected to be faster than the existing system.
Cheaper: As the manual booking system caused many errors thus extra budget had to
invest for the maintenance. However, the online booking will cause less error as a result the
system will be cheaper.
1.3 Development for appropriate metrics
In order to implement the online booking system, the total numbers of stakeholders are
segmented in two divisions such as external and internal their expectation from the new system
is as follows:
Name of the stakeholders Roles Expectation
IT project manager Internal To successfully accomplish
the online booking system
within estimated time and
budget.
1.2 Identification of type of the values
Besides the operational factors there are certain values those are equally have to ve
measured. Apart from reliability and flexibility the other values for the online system are as
follows:
Better: The existing manual excel or spreadsheet data management system was raising
error to Globex project thus the new online booking system should serve better delivery
approach with security and user friendly to the consumers.
Faster: The manual booking system was time consuming as it was human controlled
thus, the new booking system is expected to be faster than the existing system.
Cheaper: As the manual booking system caused many errors thus extra budget had to
invest for the maintenance. However, the online booking will cause less error as a result the
system will be cheaper.
1.3 Development for appropriate metrics
In order to implement the online booking system, the total numbers of stakeholders are
segmented in two divisions such as external and internal their expectation from the new system
is as follows:
Name of the stakeholders Roles Expectation
IT project manager Internal To successfully accomplish
the online booking system
within estimated time and
budget.
5PROJECT MANAGEMENT
Finance manager Internal To accomplish the project
within estimated budget and
even for extra resource
requirements also budget
should not exceed the
estimation.
System developers Internal To meet the system
requirements
Project team members Internal To deliver the online system
as per the requirement of the
consumers.
Consumers External Expecting to get a secured,
faster and user friendly system
from the Globex project.
1.4 Timeframe development
Task Name Duratio
n Start Finish Predecessors Resource Names Cost
Schedule
development for
Globex Projects
124 days Fri
3/30/18
Wed
9/19/18 $22,136.00
Project
initiation phase 42 days Fri
3/30/18
Mon
5/28/18 $7,496.00
Project
requirements
10 days Fri Thu operation
manager,project
$2,720.00
Finance manager Internal To accomplish the project
within estimated budget and
even for extra resource
requirements also budget
should not exceed the
estimation.
System developers Internal To meet the system
requirements
Project team members Internal To deliver the online system
as per the requirement of the
consumers.
Consumers External Expecting to get a secured,
faster and user friendly system
from the Globex project.
1.4 Timeframe development
Task Name Duratio
n Start Finish Predecessors Resource Names Cost
Schedule
development for
Globex Projects
124 days Fri
3/30/18
Wed
9/19/18 $22,136.00
Project
initiation phase 42 days Fri
3/30/18
Mon
5/28/18 $7,496.00
Project
requirements
10 days Fri Thu operation
manager,project
$2,720.00
6PROJECT MANAGEMENT
analysis 3/30/18 4/12/18 sponsor
Resource
gathering 5 days Fri
4/13/18
Thu
4/19/18 2 Project manager $720.00
Resource
analysis 6 days Fri
4/20/18 Fri 4/27/18 3 project sponsor $912.00
Cost
estimation 7 days Mon
4/30/18 Tue 5/8/18 4 finance manager $840.00
Time
allotment 8 days Wed
5/9/18 Fri 5/18/18 5 finance manager $960.00
System
requirements
assessment
5 days Wed
5/9/18
Tue
5/15/18 5 team members $480.00
Scope
assessment 6 days Mon
5/21/18
Mon
5/28/18 6,7 Project manager $864.00
Milestone 1:
Completion of
project initiation
phase
0 days Mon
5/28/18
Mon
5/28/18 8
operation
manager,Project
manager
$0.00
Project
planning phase 37 days Tue
5/29/18
Wed
7/18/18 $5,712.00
Scope
management
planning
4 days Tue
5/29/18 Fri 6/1/18 9
Project
manager,system
developer
$1,152.00
Risk
management
planning
9 days Mon
6/4/18
Thu
6/14/18 11 team members $864.00
Quality
management
planning
9 days Fri
6/15/18
Wed
6/27/18 12 team members $864.00
Stakeholde4r 6 days Fri Fri 6/22/18 12 project sponsor $912.00
analysis 3/30/18 4/12/18 sponsor
Resource
gathering 5 days Fri
4/13/18
Thu
4/19/18 2 Project manager $720.00
Resource
analysis 6 days Fri
4/20/18 Fri 4/27/18 3 project sponsor $912.00
Cost
estimation 7 days Mon
4/30/18 Tue 5/8/18 4 finance manager $840.00
Time
allotment 8 days Wed
5/9/18 Fri 5/18/18 5 finance manager $960.00
System
requirements
assessment
5 days Wed
5/9/18
Tue
5/15/18 5 team members $480.00
Scope
assessment 6 days Mon
5/21/18
Mon
5/28/18 6,7 Project manager $864.00
Milestone 1:
Completion of
project initiation
phase
0 days Mon
5/28/18
Mon
5/28/18 8
operation
manager,Project
manager
$0.00
Project
planning phase 37 days Tue
5/29/18
Wed
7/18/18 $5,712.00
Scope
management
planning
4 days Tue
5/29/18 Fri 6/1/18 9
Project
manager,system
developer
$1,152.00
Risk
management
planning
9 days Mon
6/4/18
Thu
6/14/18 11 team members $864.00
Quality
management
planning
9 days Fri
6/15/18
Wed
6/27/18 12 team members $864.00
Stakeholde4r 6 days Fri Fri 6/22/18 12 project sponsor $912.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT MANAGEMENT
management
planning 6/15/18
System
specification 5 days Thu
6/28/18
Wed
7/4/18 13,14 team members $480.00
Payment
gateway system
planning
10 days Thu
7/5/18
Wed
7/18/18 15 system developer $1,440.00
Milestone 2:
Completion of
project planning
phase
0 days Wed
7/18/18
Wed
7/18/18 16 Project manager $0.00
Project
execution phase 25 days Thu
7/19/18
Wed
8/22/18 $4,896.00
Online
booking system
analysis
5 days Thu
7/19/18
Wed
7/25/18 17 system developer $720.00
System
testing 6 days Thu
7/26/18 Thu 8/2/18 19 system developer $864.00
Clients
requirements
checking
8 days Fri 8/3/18 Tue
8/14/18 20 Project manager $1,152.00
Prototype
designing 6 days Wed
8/15/18
Wed
8/22/18 21
system
developer,operation
manager
$1,584.00
Functional
and nonfunctional
requirements
review
6 days Wed
8/15/18
Wed
8/22/18 21 team members $576.00
Milestone 3:
Project
0 days Wed
8/22/18
Wed
8/22/18
21,22 Project manager $0.00
management
planning 6/15/18
System
specification 5 days Thu
6/28/18
Wed
7/4/18 13,14 team members $480.00
Payment
gateway system
planning
10 days Thu
7/5/18
Wed
7/18/18 15 system developer $1,440.00
Milestone 2:
Completion of
project planning
phase
0 days Wed
7/18/18
Wed
7/18/18 16 Project manager $0.00
Project
execution phase 25 days Thu
7/19/18
Wed
8/22/18 $4,896.00
Online
booking system
analysis
5 days Thu
7/19/18
Wed
7/25/18 17 system developer $720.00
System
testing 6 days Thu
7/26/18 Thu 8/2/18 19 system developer $864.00
Clients
requirements
checking
8 days Fri 8/3/18 Tue
8/14/18 20 Project manager $1,152.00
Prototype
designing 6 days Wed
8/15/18
Wed
8/22/18 21
system
developer,operation
manager
$1,584.00
Functional
and nonfunctional
requirements
review
6 days Wed
8/15/18
Wed
8/22/18 21 team members $576.00
Milestone 3:
Project
0 days Wed
8/22/18
Wed
8/22/18
21,22 Project manager $0.00
8PROJECT MANAGEMENT
execution phase
completed
Project
monitoring
phase
8 days Thu
8/23/18
Mon
9/3/18 $2,512.00
Status report
presentation 5 days Thu
8/23/18
Wed
8/29/18 23
operation
manager,project
sponsor
$1,360.00
Change
management
planning
8 days Thu
8/23/18
Mon
9/3/18 24 Project manager $1,152.00
Milestone 4:
Completion of
monitoring
phase
0 days Wed
8/29/18
Wed
8/29/18 26 Project manager $0.00
Project closure 12 days Tue
9/4/18
Wed
9/19/18 $1,520.00
Stakeholders
signoff 4 days Tue
9/4/18 Fri 9/7/18 27,28 project sponsor $608.00
Post
maintenance plan 5 days Mon
9/10/18 Fri 9/14/18 30 team members $480.00
Final report
submission and
approval
3 days Mon
9/17/18
Wed
9/19/18 31 Project manager $432.00
Milestone 5:
Completion of
project closure
phase
0 days Wed
9/19/18
Wed
9/19/18 32 Project manager $0.00
execution phase
completed
Project
monitoring
phase
8 days Thu
8/23/18
Mon
9/3/18 $2,512.00
Status report
presentation 5 days Thu
8/23/18
Wed
8/29/18 23
operation
manager,project
sponsor
$1,360.00
Change
management
planning
8 days Thu
8/23/18
Mon
9/3/18 24 Project manager $1,152.00
Milestone 4:
Completion of
monitoring
phase
0 days Wed
8/29/18
Wed
8/29/18 26 Project manager $0.00
Project closure 12 days Tue
9/4/18
Wed
9/19/18 $1,520.00
Stakeholders
signoff 4 days Tue
9/4/18 Fri 9/7/18 27,28 project sponsor $608.00
Post
maintenance plan 5 days Mon
9/10/18 Fri 9/14/18 30 team members $480.00
Final report
submission and
approval
3 days Mon
9/17/18
Wed
9/19/18 31 Project manager $432.00
Milestone 5:
Completion of
project closure
phase
0 days Wed
9/19/18
Wed
9/19/18 32 Project manager $0.00
9PROJECT MANAGEMENT
1.5 Summary for MOV
After managing all the system criteria it can be said that with the successful
accomplishment of the project the consumers will be able to get a much secured, easy to use and
user friendly service from the Globex Project. There will be no intermediate person and due to
online payment after registration with the system users can immediately deliver their payments
accordingly. However, it is necessary for the project manager to utilize all MOV accurately for
correct factors.
Part 2: Project scope management
2.1 Scope of the project
 To replace the current manual booking system with online booking and payment
system
 To deliver an error free system to the consumers for registration and booking
 To develop a sustainable system for selling to existing and prospective clients
2.2 Project resource list
Resource
Name Type Material
Label Initials Group Max.
Units
Std.
Rate
Ovt.
Rate Cost/Use Accrue
At
Base
Calendar
Project
manager Work P 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
finance
manager Work f 100% $15.00/hr $0.00/hr $0.00 Prorated Standard
operation
manager Work o 100% $15.00/hr $0.00/hr $0.00 Prorated Standard
team Work t 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
1.5 Summary for MOV
After managing all the system criteria it can be said that with the successful
accomplishment of the project the consumers will be able to get a much secured, easy to use and
user friendly service from the Globex Project. There will be no intermediate person and due to
online payment after registration with the system users can immediately deliver their payments
accordingly. However, it is necessary for the project manager to utilize all MOV accurately for
correct factors.
Part 2: Project scope management
2.1 Scope of the project
 To replace the current manual booking system with online booking and payment
system
 To deliver an error free system to the consumers for registration and booking
 To develop a sustainable system for selling to existing and prospective clients
2.2 Project resource list
Resource
Name Type Material
Label Initials Group Max.
Units
Std.
Rate
Ovt.
Rate Cost/Use Accrue
At
Base
Calendar
Project
manager Work P 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
finance
manager Work f 100% $15.00/hr $0.00/hr $0.00 Prorated Standard
operation
manager Work o 100% $15.00/hr $0.00/hr $0.00 Prorated Standard
team Work t 100% $12.00/hr $0.00/hr $0.00 Prorated Standard
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT
members
system
developer Work s 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
project
sponsor Work p 100% $19.00/hr $0.00/hr $0.00 Prorated Standard
2.3 Resource details
In order to successfully implement any project different resources (in terms of human,
technical, financial, facility) are required. For this particular Project of Globex the resource
details are detailed below:
Human resource: The IT project manager is responsible to monitor and control the
project from the starting up to its successful completion. In addition to this, IT project manager
should track the progress rate or flow of the project also. The finance manager’s responsibility is
to estimate the budget for the project and make sure with a feasibility study that the project will
be completed within the estimation only. The other stakeholders such as system developers,
application programming manager, project team members and operation manager to develop an
user friendly, faster and secure system for their consumers with a lower cost.
Technologies: For this online booking system, software license, hardware support and
internet connection are required.
Facilities: During the development of online booking system, the team member’s
involvement is very important and accordingly planning and execution should be implemented.
members
system
developer Work s 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
project
sponsor Work p 100% $19.00/hr $0.00/hr $0.00 Prorated Standard
2.3 Resource details
In order to successfully implement any project different resources (in terms of human,
technical, financial, facility) are required. For this particular Project of Globex the resource
details are detailed below:
Human resource: The IT project manager is responsible to monitor and control the
project from the starting up to its successful completion. In addition to this, IT project manager
should track the progress rate or flow of the project also. The finance manager’s responsibility is
to estimate the budget for the project and make sure with a feasibility study that the project will
be completed within the estimation only. The other stakeholders such as system developers,
application programming manager, project team members and operation manager to develop an
user friendly, faster and secure system for their consumers with a lower cost.
Technologies: For this online booking system, software license, hardware support and
internet connection are required.
Facilities: During the development of online booking system, the team member’s
involvement is very important and accordingly planning and execution should be implemented.
11PROJECT MANAGEMENT
Part 3: Project schedule planning
Figure 1: Schedule development for Globex Project
(Source: created by author)
Part 3: Project schedule planning
Figure 1: Schedule development for Globex Project
(Source: created by author)
12PROJECT MANAGEMENT
3.1 Work breakdown structure for RALS project
Figure 2: WBS for Globex Project
(Source: created by author)
3.2 Project activity set
Task Name Duration
Schedule development for Globex Projects 124 days
Project initiation phase 42 days
Project requirements analysis 10 days
Resource gathering 5 days
Resource analysis 6 days
Cost estimation 7 days
Time allotment 8 days
3.1 Work breakdown structure for RALS project
Figure 2: WBS for Globex Project
(Source: created by author)
3.2 Project activity set
Task Name Duration
Schedule development for Globex Projects 124 days
Project initiation phase 42 days
Project requirements analysis 10 days
Resource gathering 5 days
Resource analysis 6 days
Cost estimation 7 days
Time allotment 8 days
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13PROJECT MANAGEMENT
System requirements assessment 5 days
Scope assessment 6 days
Milestone 1: Completion of project initiation phase 0 days
Project planning phase 37 days
Scope management planning 4 days
Risk management planning 9 days
Quality management planning 9 days
Stakeholde4r management planning 6 days
System specification 5 days
Payment gateway system planning 10 days
Milestone 2: Completion of project planning phase 0 days
Project execution phase 25 days
Online booking system analysis 5 days
System testing 6 days
Clients requirements checking 8 days
Prototype designing 6 days
Functional and nonfunctional requirements review 6 days
Milestone 3: Project execution phase completed 0 days
Project monitoring phase 8 days
Status report presentation 5 days
Change management planning 8 days
Milestone 4: Completion of monitoring phase 0 days
Project closure 12 days
Stakeholders signoff 4 days
Post maintenance plan 5 days
Final report submission and approval 3 days
Milestone 5: Completion of project closure phase 0 days
System requirements assessment 5 days
Scope assessment 6 days
Milestone 1: Completion of project initiation phase 0 days
Project planning phase 37 days
Scope management planning 4 days
Risk management planning 9 days
Quality management planning 9 days
Stakeholde4r management planning 6 days
System specification 5 days
Payment gateway system planning 10 days
Milestone 2: Completion of project planning phase 0 days
Project execution phase 25 days
Online booking system analysis 5 days
System testing 6 days
Clients requirements checking 8 days
Prototype designing 6 days
Functional and nonfunctional requirements review 6 days
Milestone 3: Project execution phase completed 0 days
Project monitoring phase 8 days
Status report presentation 5 days
Change management planning 8 days
Milestone 4: Completion of monitoring phase 0 days
Project closure 12 days
Stakeholders signoff 4 days
Post maintenance plan 5 days
Final report submission and approval 3 days
Milestone 5: Completion of project closure phase 0 days
14PROJECT MANAGEMENT
3.3 Project resources
Resource Name
Project manager
finance manager
operation manager
team members
system developer
project sponsor
3.4 Cost estimation for the activities
WBS Task Name Duration Cost
0 Schedule development for Globex
Projects 124 days $22,136.00
1 Project initiation phase 42 days $7,496.00
1.1 Project requirements analysis 10 days $2,720.00
1.2 Resource gathering 5 days $720.00
1.3 Resource analysis 6 days $912.00
1.4 Cost estimation 7 days $840.00
1.5 Time allotment 8 days $960.00
1.6 System requirements assessment 5 days $480.00
1.7 Scope assessment 6 days $864.00
2 Milestone 1: Completion of project
initiation phase 0 days $0.00
3 Project planning phase 37 days $5,712.00
3.1 Scope management planning 4 days $1,152.00
3.2 Risk management planning 9 days $864.00
3.3 Quality management planning 9 days $864.00
3.4 Stakeholde4r management
planning 6 days $912.00
3.5 System specification 5 days $480.00
3.3 Project resources
Resource Name
Project manager
finance manager
operation manager
team members
system developer
project sponsor
3.4 Cost estimation for the activities
WBS Task Name Duration Cost
0 Schedule development for Globex
Projects 124 days $22,136.00
1 Project initiation phase 42 days $7,496.00
1.1 Project requirements analysis 10 days $2,720.00
1.2 Resource gathering 5 days $720.00
1.3 Resource analysis 6 days $912.00
1.4 Cost estimation 7 days $840.00
1.5 Time allotment 8 days $960.00
1.6 System requirements assessment 5 days $480.00
1.7 Scope assessment 6 days $864.00
2 Milestone 1: Completion of project
initiation phase 0 days $0.00
3 Project planning phase 37 days $5,712.00
3.1 Scope management planning 4 days $1,152.00
3.2 Risk management planning 9 days $864.00
3.3 Quality management planning 9 days $864.00
3.4 Stakeholde4r management
planning 6 days $912.00
3.5 System specification 5 days $480.00
15PROJECT MANAGEMENT
3.6 Payment gateway system planning 10 days $1,440.00
4 Milestone 2: Completion of project
planning phase 0 days $0.00
5 Project execution phase 25 days $4,896.00
5.1 Online booking system analysis 5 days $720.00
5.2 System testing 6 days $864.00
5.3 Clients requirements checking 8 days $1,152.00
5.4 Prototype designing 6 days $1,584.00
5.5 Functional and nonfunctional
requirements review 6 days $576.00
6 Milestone 3: Project execution
phase completed 0 days $0.00
7 Project monitoring phase 8 days $2,512.00
7.1 Status report presentation 5 days $1,360.00
7.2 Change management planning 8 days $1,152.00
8 Milestone 4: Completion of
monitoring phase 0 days $0.00
9 Project closure 12 days $1,520.00
9.1 Stakeholders signoff 4 days $608.00
9.2 Post maintenance plan 5 days $480.00
9.3 Final report submission and
approval 3 days $432.00
10 Milestone 5: Completion of project
closure phase 0 days $0.00
3.6 Payment gateway system planning 10 days $1,440.00
4 Milestone 2: Completion of project
planning phase 0 days $0.00
5 Project execution phase 25 days $4,896.00
5.1 Online booking system analysis 5 days $720.00
5.2 System testing 6 days $864.00
5.3 Clients requirements checking 8 days $1,152.00
5.4 Prototype designing 6 days $1,584.00
5.5 Functional and nonfunctional
requirements review 6 days $576.00
6 Milestone 3: Project execution
phase completed 0 days $0.00
7 Project monitoring phase 8 days $2,512.00
7.1 Status report presentation 5 days $1,360.00
7.2 Change management planning 8 days $1,152.00
8 Milestone 4: Completion of
monitoring phase 0 days $0.00
9 Project closure 12 days $1,520.00
9.1 Stakeholders signoff 4 days $608.00
9.2 Post maintenance plan 5 days $480.00
9.3 Final report submission and
approval 3 days $432.00
10 Milestone 5: Completion of project
closure phase 0 days $0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16PROJECT MANAGEMENT
Figure 3: Estimated cost for Globex Project
(Source: created by author)
3.5 Estimated time for the project
WBS Task Name Duration
0 Schedule development for Globex Projects 124 days
1 Project initiation phase 42 days
1.1 Project requirements analysis 10 days
1.2 Resource gathering 5 days
1.3 Resource analysis 6 days
1.4 Cost estimation 7 days
Figure 3: Estimated cost for Globex Project
(Source: created by author)
3.5 Estimated time for the project
WBS Task Name Duration
0 Schedule development for Globex Projects 124 days
1 Project initiation phase 42 days
1.1 Project requirements analysis 10 days
1.2 Resource gathering 5 days
1.3 Resource analysis 6 days
1.4 Cost estimation 7 days
17PROJECT MANAGEMENT
1.5 Time allotment 8 days
1.6 System requirements assessment 5 days
1.7 Scope assessment 6 days
2 Milestone 1: Completion of project
initiation phase 0 days
3 Project planning phase 37 days
3.1 Scope management planning 4 days
3.2 Risk management planning 9 days
3.3 Quality management planning 9 days
3.4 Stakeholde4r management planning 6 days
3.5 System specification 5 days
3.6 Payment gateway system planning 10 days
4 Milestone 2: Completion of project
planning phase 0 days
5 Project execution phase 25 days
5.1 Online booking system analysis 5 days
5.2 System testing 6 days
5.3 Clients requirements checking 8 days
5.4 Prototype designing 6 days
5.5 Functional and nonfunctional
requirements review 6 days
6 Milestone 3: Project execution phase
completed 0 days
7 Project monitoring phase 8 days
7.1 Status report presentation 5 days
1.5 Time allotment 8 days
1.6 System requirements assessment 5 days
1.7 Scope assessment 6 days
2 Milestone 1: Completion of project
initiation phase 0 days
3 Project planning phase 37 days
3.1 Scope management planning 4 days
3.2 Risk management planning 9 days
3.3 Quality management planning 9 days
3.4 Stakeholde4r management planning 6 days
3.5 System specification 5 days
3.6 Payment gateway system planning 10 days
4 Milestone 2: Completion of project
planning phase 0 days
5 Project execution phase 25 days
5.1 Online booking system analysis 5 days
5.2 System testing 6 days
5.3 Clients requirements checking 8 days
5.4 Prototype designing 6 days
5.5 Functional and nonfunctional
requirements review 6 days
6 Milestone 3: Project execution phase
completed 0 days
7 Project monitoring phase 8 days
7.1 Status report presentation 5 days
18PROJECT MANAGEMENT
7.2 Change management planning 8 days
8 Milestone 4: Completion of monitoring
phase 0 days
9 Project closure 12 days
9.1 Stakeholders signoff 4 days
9.2 Post maintenance plan 5 days
9.3 Final report submission and approval 3 days
10 Milestone 5: Completion of project
closure phase 0 days
Part 4: Risk analysis and planning
4.1 Analysis of project risk and planning
Phases Risk Person who is
responsible
Frequency Impact Mitigation
strategy
Project
initiation phase
Incorrect
estimation of
budget
Finance
manager
Low High Before
initiating the
project a
feasibility
study should
make and
accordingly
should be
7.2 Change management planning 8 days
8 Milestone 4: Completion of monitoring
phase 0 days
9 Project closure 12 days
9.1 Stakeholders signoff 4 days
9.2 Post maintenance plan 5 days
9.3 Final report submission and approval 3 days
10 Milestone 5: Completion of project
closure phase 0 days
Part 4: Risk analysis and planning
4.1 Analysis of project risk and planning
Phases Risk Person who is
responsible
Frequency Impact Mitigation
strategy
Project
initiation phase
Incorrect
estimation of
budget
Finance
manager
Low High Before
initiating the
project a
feasibility
study should
make and
accordingly
should be
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19PROJECT MANAGEMENT
approved by
the sponsors
and project
manager
Planning phase Wrong
system
component
identification
Project team
members
Low Medium Besides the
team
members,
other
stakeholders
should ensure
the needs
based on the
client
requirements.
Development
phase
Improper risk
assessment
Project
manager
Medium High A risk register
should be
prepared by
the project
manager at
the planning
phase to
prioritize the
risks and risk
approved by
the sponsors
and project
manager
Planning phase Wrong
system
component
identification
Project team
members
Low Medium Besides the
team
members,
other
stakeholders
should ensure
the needs
based on the
client
requirements.
Development
phase
Improper risk
assessment
Project
manager
Medium High A risk register
should be
prepared by
the project
manager at
the planning
phase to
prioritize the
risks and risk
20PROJECT MANAGEMENT
priority
matrix
Implementation
phase
System
testing
failure
System
developer
High High After system
development
two phases to
be considered
in terms of
unit testing
and integrated
testing for
getting the
test result
properly
Closure phase Improper
checklist
Operational
manager
Medium Medium The closure
checklist
should be
approved by
the project
manager and
sponsor to
ensure that its
results are
positive and
priority
matrix
Implementation
phase
System
testing
failure
System
developer
High High After system
development
two phases to
be considered
in terms of
unit testing
and integrated
testing for
getting the
test result
properly
Closure phase Improper
checklist
Operational
manager
Medium Medium The closure
checklist
should be
approved by
the project
manager and
sponsor to
ensure that its
results are
positive and
21PROJECT MANAGEMENT
beneficial
Part 5: Quality management plan
5.1 Philosophy of the project team
Based on the project and clients requirements it can be said that philosophy of the team is
to deliver a cheaper, user friendly, secure, affordable online booking system to the clients of
Globex Project. It is expected that this efficient system will successfully garb huge number of
consumer and also retain the existing clients. Again the other activities ought to be considered
include leadership, motivation and support from the project sponsors while additional resource
will be required.
5.2 Quality assurance plan for the project
Phases Activities
verification Data gathering
Analysis of data
Prototype design of the online system
Developing service level agreement
Unit testing and integrated testing
Control on the system activities
Validation Final implementation of the online ticket
booking system
Post maintenance plan for the online booking
beneficial
Part 5: Quality management plan
5.1 Philosophy of the project team
Based on the project and clients requirements it can be said that philosophy of the team is
to deliver a cheaper, user friendly, secure, affordable online booking system to the clients of
Globex Project. It is expected that this efficient system will successfully garb huge number of
consumer and also retain the existing clients. Again the other activities ought to be considered
include leadership, motivation and support from the project sponsors while additional resource
will be required.
5.2 Quality assurance plan for the project
Phases Activities
verification Data gathering
Analysis of data
Prototype design of the online system
Developing service level agreement
Unit testing and integrated testing
Control on the system activities
Validation Final implementation of the online ticket
booking system
Post maintenance plan for the online booking
1 out of 22
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.