Running Head: PROJECT MANAGEMENT
Project Management: Renovation of Royale Pizza
Name of the Student
Name of the University

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1PROJECT MANAGEMENT
Table of Contents
1. Project Schedule..........................................................................................................................2
2. Appropriate Budget and Resource Allocations...........................................................................7
3. Risk Management......................................................................................................................16
Bibliography..................................................................................................................................19
Document Page
2PROJECT MANAGEMENT
1. Project Schedule
For developing the project schedule, a work breakdown structure (WBS) has been
developed. In this WBS, the activities are specified and then duration of each activity is set
manually and considering the predecessor links, the total duration of the project is automatically
determined.
WBS Task Name Duration Start Finish
Predecessor
s
0 Renovation for Royale Pizza 4.42 mons
Mon
4/29/19
Thu
8/29/19
1 Design 1 mon
Mon
4/29/19
Fri 5/24/19
1.1 Analysis 0.42 mons
Mon
4/29/19
Thu 5/9/19
1.1.1
Requirement Gathering and
Analysis
0.02 mons
Mon
4/29/19
Mon
4/29/19
1.1.2
Analyzing the Existing Design of
the Store
0.02 mons
Mon
4/29/19
Mon
4/29/19
3
1.1.3 Analyze the Current Floor Plan 0.32 mons
Mon
4/29/19
Wed
5/8/19
4
Document Page
3PROJECT MANAGEMENT
1.1.4
Undertake Discussion Regarding
the Proposed Project
0.01 mons
Wed
5/8/19
Wed
5/8/19
5
1.1.5 Discuss Resources Required 0.05 mons
Wed
5/8/19
Thu 5/9/19 6
1.1.6
Milestone 1: Approach Technical
Manager Regarding the Proposed
Renovation Details
0 mons
Thu
5/9/19
Thu 5/9/19 7
1.2 Planning 0.08 mons
Thu
5/9/19
Fri 5/10/19
1.2.1 Define Scope 0.01 mons
Thu
5/9/19
Thu 5/9/19 8
1.2.2 Estimate Project Schedule 0.01 mons
Thu
5/9/19
Thu 5/9/19 10
1.2.3
Milestone 2: Proper Allocation of
Time to Activities
0 mons
Thu
5/9/19
Thu 5/9/19 11
1.2.4 Estimate Budget 0.02 mons
Thu
5/9/19
Fri 5/10/19 12
1.2.5 Finalise Project Charter 0.04 mons
Fri
5/10/19
Fri 5/10/19 13

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4PROJECT MANAGEMENT
1.3 Renovation Design 0.5 mons
Mon
5/13/19
Fri 5/24/19
1.3.1 Hire Contractor 0.1 mons
Mon
5/13/19
Tue
5/14/19
14
1.3.2
Discuss Requirements of the
Project
0.1 mons
Wed
5/15/19
Thu
5/16/19
16
1.3.3 Prepare New Design of the Store 0.15 mons
Fri
5/17/19
Tue
5/21/19
17
1.3.4
Develop New Floor Plan with
Proposed Layout
0.15 mons
Wed
5/22/19
Fri 5/24/19 18
1.3.5 Milestone 3: Design Complete 0 mons
Fri
5/24/19
Fri 5/24/19 19
2 Procurement and Delivery 2 mons
Thu
5/9/19
Thu 7/4/19
2.1
Handover the List of Requirements
to the Procurement Department
0.5 mons
Thu
5/9/19
Thu
5/23/19
8
2.2
Place Order for the Required
Materials
0.5 mons
Thu
5/23/19
Thu 6/6/19 22
2.3 Delivery of the Materials 1 mon Thu Thu 7/4/19 23
Document Page
5PROJECT MANAGEMENT
6/6/19
2.4
Milestone 4: All Resources
Procured
0 mons
Thu
7/4/19
Thu 7/4/19 24
3 Construction 1 mon
Thu
7/4/19
Thu 8/1/19
3.1
Preparation of the Store for
Construction
0.05 mons
Thu
7/4/19
Fri 7/5/19 20,24
3.2
Packing and Storage of Existing
Equipments
0.05 mons
Fri
7/5/19
Mon
7/8/19
27
3.3
Mark Important Spots like Water
Faucet, Electrical Plug and Circuit
Points
0.05 mons
Mon
7/8/19
Tue 7/9/19 28
3.4 Demolish the Stairs 0.5 mons
Tue
7/9/19
Tue
7/23/19
29
3.5 Set Up New Partitions 0.2 mons
Tue
7/23/19
Mon
7/29/19
30
3.6 Install New Equipments 0.05 mons
Mon
7/29/19
Tue
7/30/19
31
3.7 Install the Previous Equipments that 0.05 mons Tue Wed 32
Document Page
6PROJECT MANAGEMENT
can be Used 7/30/19 7/31/19
3.8 Install Air Conditioning System 0.05 mons
Wed
7/31/19
Thu 8/1/19 33
3.9
Milestone 5: Completion of the
Construction Works
0 mons
Thu
8/1/19
Thu 8/1/19 34
4 Installation and Painting 2 mons
Thu
7/4/19
Thu
8/29/19
4.1
Installation of All Cooking
Equipments
0.2 mons
Thu
7/4/19
Wed
7/10/19
20,24
4.2
Installation of Dining Tables and
Chairs
0.4 mons
Wed
7/10/19
Mon
7/22/19
37
4.3 Interior Painting 0.5 mons
Mon
7/22/19
Mon
8/5/19
38
4.4 Exterior Painting 0.5 mons
Mon
8/5/19
Mon
8/19/19
39
4.5
Milestone 6: Completion of
Painting and Installation Works
0 mons
Mon
8/19/19
Mon
8/19/19
40
4.6 Review of the Project 0.2 mons
Mon
8/19/19
Fri 8/23/19 41

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
4.7 Documentation 0.2 mons
Fri
8/23/19
Thu
8/29/19
42
4.8 Milestone 7: Sign Off 0 mons
Thu
8/29/19
Thu
8/29/19
43
2. Appropriate Budget and Resource Allocations
WBS Task Name Duration Resource Names Cost
0
Renovation for Royale
Pizza
4.42 mons $40,000
1 Design 1 mon $5,000
1.1 Analysis 0.42 mons $0
1.1.1
Requirement Gathering
and Analysis
0.02 mons Project Manager $0
1.1.2
Analyzing the Existing
Design of the Store
0.02 mons Project Manager $0
1.1.3
Analyze the Current
Floor Plan
0.32 mons Project Manager $0
1.1.4 Undertake Discussion 0.01 mons Project Manager $0
Document Page
8PROJECT MANAGEMENT
Regarding the Proposed
Project
1.1.5
Discuss Resources
Required
0.05 mons Project Manager $0
1.1.6
Milestone 1: Approach
Technical Manager
Regarding the Proposed
Renovation Details
0 mons $0
1.2 Planning 0.08 mons $500
1.2.1 Define Scope 0.01 mons Project Manager $0
1.2.2
Estimate Project
Schedule
0.01 mons Project Manager $0
1.2.3
Milestone 2: Proper
Allocation of Time to
Activities
0 mons $0
1.2.4 Estimate Budget 0.02 mons Finance Manager $0
1.2.5 Finalise Project Charter 0.04 mons Finance Manager $500
1.3 Renovation Design 0.5 mons $4,500
1.3.1 Hire Contractor 0.1 mons Project Manager $2,500
Document Page
9PROJECT MANAGEMENT
1.3.2
Discuss Requirements
of the Project
0.1 mons Project Manager $500
1.3.3
Prepare New Design of
the Store
0.15 mons Technical Manager $500
1.3.4
Develop New Floor
Plan with Proposed Layout
0.15 mons Technical Manager $1,000
1.3.5
Milestone 3: Design
Complete
0 mons $0
2
Procurement and
Delivery
2 mons $18,000
2.1
Handover the List of
Requirements to the
Procurement Department
0.5 mons Technical Manager $0
2.2
Place Order for the
Required Materials
0.5 mons Technical Manager $0
2.3 Delivery of the Materials 1 mon
Procurement Manager,
Installable Equipments[1]
$18,000
2.4 Milestone 4: All 0 mons $0

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10PROJECT MANAGEMENT
Resources Procured
3 Construction 1 mon $7,000
3.1
Preparation of the Store
for Construction
0.05 mons Labour (Unskilled) $1,000
3.2
Packing and Storage of
Existing Equipments
0.05 mons Labour (Unskilled) $1,000
3.3
Mark Important Spots
like Water Faucet, Electrical
Plug and Circuit Points
0.05 mons Labour (Unskilled) $1,000
3.4 Demolish the Stairs 0.5 mons Labour (Skilled) $1,000
3.5 Set Up New Partitions 0.2 mons Labour (Skilled) $1,000
3.6 Install New Equipments 0.05 mons Labour (Skilled) $1,000
3.7
Install the Previous
Equipments that can be Used
0.05 mons Labour (Unskilled) $500
3.8
Install Air Conditioning
System
0.05 mons Labour (Skilled) $500
3.9
Milestone 5: Completion
of the Construction Works
0 mons $0
Document Page
11PROJECT MANAGEMENT
4 Installation and Painting 2 mons $10,000
4.1
Installation of All
Cooking Equipments
0.2 mons Labour (Unskilled) $2,500
4.2
Installation of Dining
Tables and Chairs
0.4 mons Labour (Unskilled) $2,500
4.3 Interior Painting 0.5 mons Labour (Unskilled) $2,500
4.4 Exterior Painting 0.5 mons Labour (Skilled) $2,500
4.5
Milestone 6: Completion
of Painting and Installation
Works
0 mons $0
4.6 Review of the Project 0.2 mons Project Manager $0
4.7 Documentation 0.2 mons Technical Manager $0
4.8 Milestone 7: Sign Off 0 mons $0
The detailed analysis in the specific cost elements of the project is shown in the following
table.
WBS
Resource
Names
Direct Costs Indirect Costs Total
Estimate
Method Constraints /
Assumptions
1.2.5 Finance
Manager
$500 $0 $500 Bottom Up All elements
of the charter
Document Page
12PROJECT MANAGEMENT
addressed
1.3.1
Project
Manager
$2500 $0 $2,500
Bottom Up The fee is
sufficient for
hiring the
contractor
1.3.2
Project
Manager
$500 $0 $500
Bottom Up There are no
indirect costs
1.3.3
Technical
Manager
$500 $0 $500
Bottom Up There are no
indirect costs
1.3.4
Technical
Manager
$1000 $0 $1,000
Bottom Up There are no
indirect costs
2.3
Procuremen
t Manager,
Installable
Equipments
$15,000 $3000 $18,000
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
3.1 Labour
(Unskilled)
$800 $200 $1,000 Bottom Up There are
some indirect
costs that are
required for

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13PROJECT MANAGEMENT
maintaining
project quality
3.2
Labour
(Unskilled)
$800 $200 $1,000
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
3.3
Labour
(Unskilled)
$800 $200 $1,000
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
3.4
Labour
(Skilled)
$800 $200 $1,000
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
3.5 Labour
(Skilled)
$800 $200 $1,000 Bottom Up There are
some indirect
Document Page
14PROJECT MANAGEMENT
costs that are
required for
maintaining
project quality
3.6
Labour
(Skilled)
$800 $200 $1,000
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
3.7
Labour
(Unskilled)
$400 $100 $500
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
3.8 Labour
(Skilled)
$400 $100 $500 Bottom Up There are
some indirect
costs that are
required for
maintaining
Document Page
15PROJECT MANAGEMENT
project quality
4.1
Labour
(Unskilled)
$2000 $500 $2,500
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
4.2
Labour
(Unskilled)
$2000 $500 $2,500
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
4.3
Labour
(Unskilled)
$2000 $500 $2,500
Bottom Up There are
some indirect
costs that are
required for
maintaining
project quality
4.4 Labour
(Skilled)
$2000 $500 $2,500 Bottom Up There are
some indirect
costs that are

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16PROJECT MANAGEMENT
required for
maintaining
project quality
Document Page
17PROJECT MANAGEMENT
3. Risk Management
Document Page
18PROJECT MANAGEMENT
Risk
ID
Risk Statement
Probabilit
y
Impact Score
Response
plan/Strategy
1 Due to inaccurate
project schedule,
condition may arise in
which the project
exceeds the deadline
and results penalty.
This is not desired in
this project as its scope
is limited and the
amount of penalty will
be a significant loss
for the project
management team.
2 4 8 During the planning
phase of the project, it is
important to prepare
accurate schedule using
suitable techniques. One
such recommended
technique is the Gantt
chart.
2 Due to over-expenses
and spending in
unnecessary tasks,
budget overshoot may
occur that may result
in significant financial
problems for the
project team.
3 4 12 Prepare accurate
budgeting plan and
allocate budget to the
tasks as per the
specifications only. Keep
10% contingency budget
that may be useful
during budget overshoot.
3 Due to some accidents
or working without
protective gears,
injuries may occur to
the workers in the
project.
3 5 15 Before starting to work
on the project, protective
gears and equipments
must be rented and
provided to the workers.
In case the injuries still
occur, immediate first
aid kits must be provided

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19PROJECT MANAGEMENT
Document Page
20PROJECT MANAGEMENT
Bibliography
Archibald, R. D., & Archibald, S. (2016). Leading and Managing Innovation: What Every
Executive Team Must Know about Project, Program, and Portfolio Management.
Auerbach Publications.
Clark, T. A. (2018). Project management for planners. Routledge.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley &
Sons.
Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Ruggles, W. S., & Harrington, H. J. (2018). Project Management for Performance Improvement
Teams. Productivity Press.
Tonchia, S. (2018). The International Standards of Project Management. In Industrial Project
Management (pp. 7-20). Springer, Berlin, Heidelberg.