This assignment involves developing a comprehensive project management plan. The student analyzes the time requirements for various tasks, identifies critical activities, and addresses potential resource constraints. A presentation on project management blogs is also included in the plan. The document showcases the understanding of project management principles and their practical application.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Project Management: Victoria Construction Pty Ltd.
Name of the student:
Name of the university:
Project Management: Victoria Construction Pty Ltd.
Name of the student:
Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT MANAGEMENT
Table of Contents
Task A..................................................................................................................................2
Development of project schedule (ProjectSchedulePartA1.mpp)...................................2
Task B................................................................................................................................12
Development of project schedule (ProjectSchedulePartA2.mpp).................................12
Task C- Presenting Project Management Blogs................................................................22
Bibliography......................................................................................................................23
Table of Contents
Task A..................................................................................................................................2
Development of project schedule (ProjectSchedulePartA1.mpp)...................................2
Task B................................................................................................................................12
Development of project schedule (ProjectSchedulePartA2.mpp).................................12
Task C- Presenting Project Management Blogs................................................................22
Bibliography......................................................................................................................23
2PROJECT MANAGEMENT
Task A
Development of project schedule (ProjectSchedulePartA1.mpp)
Task
Mode
WB
S Task Name Durati
on Start Finish Predecess
ors
Resource
Names
Cost
Variance
Auto
Schedul
ed
0
Timeframe
for
Victoria
Constructi
on Pty Ltd
27
days?
Mon
9/25/1
7
Tue
10/31/
17
$35,520.
00
Auto
Schedul
ed
1 Project
initiation 5 days
Mon
9/25/1
7
Fri
9/29/1
7
$6,160.0
0
Auto
Schedule
d
1.1
Environ
mental
monitoring
1 day
Mon
9/25/1
7
Mon
9/25/1
7
software
analyst or
designer
$720.00
Auto
Schedule
d
1.2
Analysi
s for
requirement
s
2 days
Mon
9/25/1
7
Tue
9/26/1
7
Environmen
tal
analyst ,Soft
ware
engineer
$2,720.0
0
Auto
Schedul
ed
1.3 Hardw
are 4 days
Tue
9/26/1
7
Fri
9/29/1
7
2 $2,720.0
0
Auto
Schedule
d
2 Milestone
1:
Completio
0 days Fri
9/29/1
Fri
9/29/1
7 software
analyst or
$0.00
Task A
Development of project schedule (ProjectSchedulePartA1.mpp)
Task
Mode
WB
S Task Name Durati
on Start Finish Predecess
ors
Resource
Names
Cost
Variance
Auto
Schedul
ed
0
Timeframe
for
Victoria
Constructi
on Pty Ltd
27
days?
Mon
9/25/1
7
Tue
10/31/
17
$35,520.
00
Auto
Schedul
ed
1 Project
initiation 5 days
Mon
9/25/1
7
Fri
9/29/1
7
$6,160.0
0
Auto
Schedule
d
1.1
Environ
mental
monitoring
1 day
Mon
9/25/1
7
Mon
9/25/1
7
software
analyst or
designer
$720.00
Auto
Schedule
d
1.2
Analysi
s for
requirement
s
2 days
Mon
9/25/1
7
Tue
9/26/1
7
Environmen
tal
analyst ,Soft
ware
engineer
$2,720.0
0
Auto
Schedul
ed
1.3 Hardw
are 4 days
Tue
9/26/1
7
Fri
9/29/1
7
2 $2,720.0
0
Auto
Schedule
d
2 Milestone
1:
Completio
0 days Fri
9/29/1
Fri
9/29/1
7 software
analyst or
$0.00
3PROJECT MANAGEMENT
n of project
initiation
phase
7 7 designer
Auto
Schedul
ed
3 Project
planning
17
days
Mon
10/2/1
7
Tue
10/24/
17
$7,440.0
0
Auto
Schedule
d
3.1 Softwar
e 1 day
Mon
10/2/1
7
Mon
10/2/1
7
8
software
analyst or
designer,
Software
engineer
$1,360.0
0
Auto
Schedule
d
3.2
Require
ment of
data
1 day
Tue
10/3/1
7
Tue
10/3/1
7
10 Software
engineer $640.00
Auto
Schedule
d
3.3
Milesto
ne 2:
Completio
n
ofhardwar
e and
software
requireme
nt planning
1 day
Wed
10/4/1
7
Wed
10/4/1
7
11 Electronic
engineer $640.00
Auto
Schedul
ed
3.4
Softwar
e required
for the
tablet
4 days
Wed
10/4/1
7
Mon
10/9/1
7
$2,720.0
0
Auto 3.5 The 1 day Tue Tue 10,17,16 Electronic $1,360.0
n of project
initiation
phase
7 7 designer
Auto
Schedul
ed
3 Project
planning
17
days
Mon
10/2/1
7
Tue
10/24/
17
$7,440.0
0
Auto
Schedule
d
3.1 Softwar
e 1 day
Mon
10/2/1
7
Mon
10/2/1
7
8
software
analyst or
designer,
Software
engineer
$1,360.0
0
Auto
Schedule
d
3.2
Require
ment of
data
1 day
Tue
10/3/1
7
Tue
10/3/1
7
10 Software
engineer $640.00
Auto
Schedule
d
3.3
Milesto
ne 2:
Completio
n
ofhardwar
e and
software
requireme
nt planning
1 day
Wed
10/4/1
7
Wed
10/4/1
7
11 Electronic
engineer $640.00
Auto
Schedul
ed
3.4
Softwar
e required
for the
tablet
4 days
Wed
10/4/1
7
Mon
10/9/1
7
$2,720.0
0
Auto 3.5 The 1 day Tue Tue 10,17,16 Electronic $1,360.0
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT MANAGEMENT
Schedule
d
tablet server
requirement
10/10/
17
10/10/
17
engineer ,En
vironemntal
analyst
0
Auto
Schedule
d
3.6
Develop
ing server
user
interface
1 day
Tue
10/24/
17
Tue
10/24/
17
22,27 Environemn
tal analyst $720.00
Auto
Schedule
d
4
Milestone
3:
Completio
n of project
planning
phase
0 days
Tue
10/10/
17
Tue
10/10/
17
18 Electronic
engineer $0.00
Auto
Schedul
ed
5 Project
execution
24
days?
Mon
9/25/1
7
Thu
10/26/
17
$19,760.
00
Auto
Schedule
d
5.1
Review
and
approval of
the software
based
requirement
s
1 day
Wed
10/11/
17
Wed
10/11/
17
20
software
analyst or
designer
$720.00
Auto
Schedul
ed
5.2
Require
ment for
reporting
3 days
Thu
10/12/
17
Mon
10/16/
17
$2,720.0
0
Auto
Schedule
5.2. For 1 day Thu
10/12/
Thu
10/12/
22 software
analyst or
$1,360.0
Schedule
d
tablet server
requirement
10/10/
17
10/10/
17
engineer ,En
vironemntal
analyst
0
Auto
Schedule
d
3.6
Develop
ing server
user
interface
1 day
Tue
10/24/
17
Tue
10/24/
17
22,27 Environemn
tal analyst $720.00
Auto
Schedule
d
4
Milestone
3:
Completio
n of project
planning
phase
0 days
Tue
10/10/
17
Tue
10/10/
17
18 Electronic
engineer $0.00
Auto
Schedul
ed
5 Project
execution
24
days?
Mon
9/25/1
7
Thu
10/26/
17
$19,760.
00
Auto
Schedule
d
5.1
Review
and
approval of
the software
based
requirement
s
1 day
Wed
10/11/
17
Wed
10/11/
17
20
software
analyst or
designer
$720.00
Auto
Schedul
ed
5.2
Require
ment for
reporting
3 days
Thu
10/12/
17
Mon
10/16/
17
$2,720.0
0
Auto
Schedule
5.2. For 1 day Thu
10/12/
Thu
10/12/
22 software
analyst or
$1,360.0
5PROJECT MANAGEMENT
d 1 report A 17 17
designer,
Software
engineer
0
Auto
Schedule
d
5.2.
2
For
report B 1 day
Fri
10/13/
17
Fri
10/13/
17
24 Software
engineer $640.00
Auto
Schedule
d
5.2.
3
For
report C 1 day
Mon
10/16/
17
Mon
10/16/
17
25,34
software
analyst or
designer
$720.00
Auto
Schedul
ed
5.3 Softwar
e design
5
days?
Tue
10/17/
17
Mon
10/23/
17
Electronic
engineer
$6,640.0
0
Auto
Schedule
d
5.3.
1
Tablet
server
interface
1 day
Tue
10/17/
17
Tue
10/17/
17
26
software
analyst or
designer
$720.00
Auto
Schedule
d
5.3.
2 1 day?
Wed
10/18/
17
Wed
10/18/
17
28 $0.00
Auto
Schedule
d
5.3.
3
User
server
interface
1 day
Wed
10/18/
17
Wed
10/18/
17
28
software
analyst or
designer
$720.00
Auto
Schedule
d
5.3.
4
Devel
opment of
data layer
1 day
Thu
10/19/
17
Thu
10/19/
17
28,30
Electronic
engineer ,So
ftware
engineer
$1,280.0
0
Auto 5.3. Milest 1 day Fri Fri 31 $0.00
d 1 report A 17 17
designer,
Software
engineer
0
Auto
Schedule
d
5.2.
2
For
report B 1 day
Fri
10/13/
17
Fri
10/13/
17
24 Software
engineer $640.00
Auto
Schedule
d
5.2.
3
For
report C 1 day
Mon
10/16/
17
Mon
10/16/
17
25,34
software
analyst or
designer
$720.00
Auto
Schedul
ed
5.3 Softwar
e design
5
days?
Tue
10/17/
17
Mon
10/23/
17
Electronic
engineer
$6,640.0
0
Auto
Schedule
d
5.3.
1
Tablet
server
interface
1 day
Tue
10/17/
17
Tue
10/17/
17
26
software
analyst or
designer
$720.00
Auto
Schedule
d
5.3.
2 1 day?
Wed
10/18/
17
Wed
10/18/
17
28 $0.00
Auto
Schedule
d
5.3.
3
User
server
interface
1 day
Wed
10/18/
17
Wed
10/18/
17
28
software
analyst or
designer
$720.00
Auto
Schedule
d
5.3.
4
Devel
opment of
data layer
1 day
Thu
10/19/
17
Thu
10/19/
17
28,30
Electronic
engineer ,So
ftware
engineer
$1,280.0
0
Auto 5.3. Milest 1 day Fri Fri 31 $0.00
6PROJECT MANAGEMENT
Schedule
d 5
one 4:
Design
approval
completion
10/20/
17
10/20/
17
Auto
Schedule
d
5.3.
6
Revie
w and
approval of
the software
design
details
1 day
Mon
10/23/
17
Mon
10/23/
17
32
software
analyst or
designer
$720.00
Auto
Schedul
ed
5.4
Softwar
e
developme
nt and
testing
6 days
Mon
9/25/1
7
Mon
10/2/1
7
$2,800.0
0
Auto
Schedule
d
5.4.
1
User
interface
developmen
t
1 day
Thu
9/28/1
7
Thu
9/28/1
7
5
software
analyst or
designer
$720.00
Auto
Schedule
d
5.4.
2
Data
layer
developmen
t
1 day
Fri
9/29/1
7
Fri
9/29/1
7
35
software
analyst or
designer
$720.00
Auto
Schedule
d
5.4.
3
Field
testing 1 day
Mon
10/2/1
7
Mon
10/2/1
7
4
software
analyst or
designer
$720.00
Auto
Schedule
5.4. Applic
ation layer
1 day Mon
9/25/1
Mon
9/25/1
Software $640.00
Schedule
d 5
one 4:
Design
approval
completion
10/20/
17
10/20/
17
Auto
Schedule
d
5.3.
6
Revie
w and
approval of
the software
design
details
1 day
Mon
10/23/
17
Mon
10/23/
17
32
software
analyst or
designer
$720.00
Auto
Schedul
ed
5.4
Softwar
e
developme
nt and
testing
6 days
Mon
9/25/1
7
Mon
10/2/1
7
$2,800.0
0
Auto
Schedule
d
5.4.
1
User
interface
developmen
t
1 day
Thu
9/28/1
7
Thu
9/28/1
7
5
software
analyst or
designer
$720.00
Auto
Schedule
d
5.4.
2
Data
layer
developmen
t
1 day
Fri
9/29/1
7
Fri
9/29/1
7
35
software
analyst or
designer
$720.00
Auto
Schedule
d
5.4.
3
Field
testing 1 day
Mon
10/2/1
7
Mon
10/2/1
7
4
software
analyst or
designer
$720.00
Auto
Schedule
5.4. Applic
ation layer
1 day Mon
9/25/1
Mon
9/25/1
Software $640.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT MANAGEMENT
d 4 improveme
nt 7 7 engineer
Auto
Schedul
ed
5.5 Testing
the tablet 5 days
Mon
10/16/
17
Fri
10/20/
17
$4,160.0
0
Auto
Schedule
d
5.5.
1
Server
tablet
interface
testing
1 day
Mon
10/16/
17
Mon
10/16/
17
38,25
software
analyst or
designer
$720.00
Auto
Schedule
d
5.5.
2
Softw
are
installation
1 day
Tue
10/17/
17
Tue
10/17/
17
40
software
analyst or
designer
$720.00
Auto
Schedule
d
5.5.
3
Syste
m testing 1 day
Wed
10/18/
17
Wed
10/18/
17
41
software
analyst or
designer
$720.00
Auto
Schedule
d
5.5.
4
Milest
one 5:
Completio
n of field
testing
1 day
Thu
10/19/
17
Thu
10/19/
17
42 Software
engineer $640.00
Auto
Schedule
d
5.5.
5
Softw
are server
developmen
t
1 day
Fri
10/20/
17
Fri
10/20/
17
43
software
analyst or
designer,
Software
engineer
$1,360.0
0
Auto
Schedul
5.6 Hardw
are
4 days Mon
10/23/
Thu
10/26/
$2,720.0
d 4 improveme
nt 7 7 engineer
Auto
Schedul
ed
5.5 Testing
the tablet 5 days
Mon
10/16/
17
Fri
10/20/
17
$4,160.0
0
Auto
Schedule
d
5.5.
1
Server
tablet
interface
testing
1 day
Mon
10/16/
17
Mon
10/16/
17
38,25
software
analyst or
designer
$720.00
Auto
Schedule
d
5.5.
2
Softw
are
installation
1 day
Tue
10/17/
17
Tue
10/17/
17
40
software
analyst or
designer
$720.00
Auto
Schedule
d
5.5.
3
Syste
m testing 1 day
Wed
10/18/
17
Wed
10/18/
17
41
software
analyst or
designer
$720.00
Auto
Schedule
d
5.5.
4
Milest
one 5:
Completio
n of field
testing
1 day
Thu
10/19/
17
Thu
10/19/
17
42 Software
engineer $640.00
Auto
Schedule
d
5.5.
5
Softw
are server
developmen
t
1 day
Fri
10/20/
17
Fri
10/20/
17
43
software
analyst or
designer,
Software
engineer
$1,360.0
0
Auto
Schedul
5.6 Hardw
are
4 days Mon
10/23/
Thu
10/26/
$2,720.0
8PROJECT MANAGEMENT
ed
requireme
nt: Data
entry tablet
17 17 0
Auto
Schedule
d
5.6.
1
Report
testing 1 day
Mon
10/23/
17
Mon
10/23/
17
44 Electronic
engineer $640.00
Auto
Schedule
d
5.6.
2
Report
review 1 day
Tue
10/24/
17
Tue
10/24/
17
36,27,46 Environmen
tal analyst $720.00
Auto
Schedule
d
5.6.
3
Modif
ication as
per the
testing
results
1 day
Wed
10/25/
17
Wed
10/25/
17
47 Electronic
engineer $640.00
Auto
Schedule
d
5.6.
4
Appro
val on the
production
1 day
Thu
10/26/
17
Thu
10/26/
17
48
software
analyst or
designer
$720.00
Auto
Schedule
d
6
Milestone
6:
Completio
n of project
execution
phase
0 days
Thu
10/26/
17
Thu
10/26/
17
49
software
analyst or
designer
$0.00
Auto
Schedul
ed
7 Project
closure 3 days
Fri
10/27/
17
Tue
10/31/
17
$2,160.0
0
Auto 7.1 Stakeho 1 day Fri Fri 50 Environmen $720.00
ed
requireme
nt: Data
entry tablet
17 17 0
Auto
Schedule
d
5.6.
1
Report
testing 1 day
Mon
10/23/
17
Mon
10/23/
17
44 Electronic
engineer $640.00
Auto
Schedule
d
5.6.
2
Report
review 1 day
Tue
10/24/
17
Tue
10/24/
17
36,27,46 Environmen
tal analyst $720.00
Auto
Schedule
d
5.6.
3
Modif
ication as
per the
testing
results
1 day
Wed
10/25/
17
Wed
10/25/
17
47 Electronic
engineer $640.00
Auto
Schedule
d
5.6.
4
Appro
val on the
production
1 day
Thu
10/26/
17
Thu
10/26/
17
48
software
analyst or
designer
$720.00
Auto
Schedule
d
6
Milestone
6:
Completio
n of project
execution
phase
0 days
Thu
10/26/
17
Thu
10/26/
17
49
software
analyst or
designer
$0.00
Auto
Schedul
ed
7 Project
closure 3 days
Fri
10/27/
17
Tue
10/31/
17
$2,160.0
0
Auto 7.1 Stakeho 1 day Fri Fri 50 Environmen $720.00
9PROJECT MANAGEMENT
Schedule
d lder signoff 10/27/
17
10/27/
17 tal analyst
Auto
Schedule
d
7.2
Final
documentati
on
1 day
Mon
10/30/
17
Mon
10/30/
17
52 Environmen
tal analyst $720.00
Auto
Schedule
d
7.3
Post
project
evaluation
and
maintenanc
e
1 day
Tue
10/31/
17
Tue
10/31/
17
53 Environmen
tal analyst $720.00
Auto
Schedule
d
8
Milestone
7: project
closure
completion
0 days
Tue
10/31/
17
Tue
10/31/
17
54 Electronic
engineer $0.00
Schedule
d lder signoff 10/27/
17
10/27/
17 tal analyst
Auto
Schedule
d
7.2
Final
documentati
on
1 day
Mon
10/30/
17
Mon
10/30/
17
52 Environmen
tal analyst $720.00
Auto
Schedule
d
7.3
Post
project
evaluation
and
maintenanc
e
1 day
Tue
10/31/
17
Tue
10/31/
17
53 Environmen
tal analyst $720.00
Auto
Schedule
d
8
Milestone
7: project
closure
completion
0 days
Tue
10/31/
17
Tue
10/31/
17
54 Electronic
engineer $0.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT MANAGEMENT
Figure 1: Gantt chart for Victoria Construction Pty., Ltd.
(Source: Created by author)
Figure 1: Gantt chart for Victoria Construction Pty., Ltd.
(Source: Created by author)
11PROJECT MANAGEMENT
Figure 2: WBS for Victoria Construction Pty., Ltd
(Source: created by author)
Figure 3: AIB network diagram for Victoria Construction Pty., Ltd
(Source: Created by author)
Figure 2: WBS for Victoria Construction Pty., Ltd
(Source: created by author)
Figure 3: AIB network diagram for Victoria Construction Pty., Ltd
(Source: Created by author)
12PROJECT MANAGEMENT
Task B
Development of project schedule (ProjectSchedulePartA2.mpp)
Task
Mode WBS Task Name Durati
on Start Finis
h
Predecess
ors
Resource
Names
Cost
Variance
Auto
Schedul
ed
1
Timeframe
for
Victoria
Constructi
on Pty Ltd
29
days
Wed
6/1/1
6
Mon
7/11/
16
$54,640.
00
Auto
Schedul
ed
1.1 Project
initiation 5 days
Wed
6/1/1
6
Tue
6/7/1
6
software
analyst or
designer
$7,120.0
0
Auto
Schedul
ed
1.1.1
Enviro
nmental
monitoring
1 day
Wed
6/1/1
6
Wed
6/1/1
6
$0.00
Auto
Schedul
ed
1.1.2
Analys
is for
requireme
nts
2 days
Thu
6/2/1
6
Fri
6/3/1
6
software
analyst or
designer
$2,800.0
0
Auto
Schedul
ed
1.1.2
.1
Hard
ware 1 day
Thu
6/2/1
6
Thu
6/2/1
6
3 Electronic
engineer $640.00
Auto 1.1.2 Table 1 day Fri Fri 5 Environemntal $720.00
Task B
Development of project schedule (ProjectSchedulePartA2.mpp)
Task
Mode WBS Task Name Durati
on Start Finis
h
Predecess
ors
Resource
Names
Cost
Variance
Auto
Schedul
ed
1
Timeframe
for
Victoria
Constructi
on Pty Ltd
29
days
Wed
6/1/1
6
Mon
7/11/
16
$54,640.
00
Auto
Schedul
ed
1.1 Project
initiation 5 days
Wed
6/1/1
6
Tue
6/7/1
6
software
analyst or
designer
$7,120.0
0
Auto
Schedul
ed
1.1.1
Enviro
nmental
monitoring
1 day
Wed
6/1/1
6
Wed
6/1/1
6
$0.00
Auto
Schedul
ed
1.1.2
Analys
is for
requireme
nts
2 days
Thu
6/2/1
6
Fri
6/3/1
6
software
analyst or
designer
$2,800.0
0
Auto
Schedul
ed
1.1.2
.1
Hard
ware 1 day
Thu
6/2/1
6
Thu
6/2/1
6
3 Electronic
engineer $640.00
Auto 1.1.2 Table 1 day Fri Fri 5 Environemntal $720.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13PROJECT MANAGEMENT
Schedul
ed .2 t 6/3/1
6
6/3/1
6 analyst
Auto
Schedul
ed
1.1.3
Specifi
c
requirement
for the
tablets
1 day
Mon
6/6/1
6
Mon
6/6/1
6
6
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.1.4
Approv
al and
review of
the tablet
1 day
Tue
6/7/1
6
Tue
6/7/1
6
7 $0.00
Auto
Schedul
ed
1.2
Milestone
1:
Completio
n of
project
initiation
phase
0 days
Tue
6/7/1
6
Tue
6/7/1
6
8 $0.00
Auto
Schedul
ed
1.3 Project
planning 5 days
Wed
6/8/1
6
Tue
6/14/
16
software
analyst or
designer,Soft
ware engineer
$9,520.0
0
Auto
Schedul
ed
1.3.1 Softwar
e 1 day
Wed
6/8/1
6
Wed
6/8/1
6
9 Software
engineer $640.00
Schedul
ed .2 t 6/3/1
6
6/3/1
6 analyst
Auto
Schedul
ed
1.1.3
Specifi
c
requirement
for the
tablets
1 day
Mon
6/6/1
6
Mon
6/6/1
6
6
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.1.4
Approv
al and
review of
the tablet
1 day
Tue
6/7/1
6
Tue
6/7/1
6
7 $0.00
Auto
Schedul
ed
1.2
Milestone
1:
Completio
n of
project
initiation
phase
0 days
Tue
6/7/1
6
Tue
6/7/1
6
8 $0.00
Auto
Schedul
ed
1.3 Project
planning 5 days
Wed
6/8/1
6
Tue
6/14/
16
software
analyst or
designer,Soft
ware engineer
$9,520.0
0
Auto
Schedul
ed
1.3.1 Softwar
e 1 day
Wed
6/8/1
6
Wed
6/8/1
6
9 Software
engineer $640.00
14PROJECT MANAGEMENT
Auto
Schedul
ed
1.3.2
Require
ment of
data
1 day
Thu
6/9/1
6
Thu
6/9/1
6
11 $0.00
Auto
Schedul
ed
1.3.3
Milesto
ne 2:
Completio
n
ofhardwar
e and
software
requireme
nt
planning
0 days
Thu
6/9/1
6
Thu
6/9/1
6
12 $0.00
Auto
Schedul
ed
1.3.4
Softwa
re required
for the
tablet
1 day
Fri
6/10/
16
Fri
6/10/
16
13
Electronic
engineer ,Envi
ronemntal
analyst
$1,360.0
0
Auto
Schedul
ed
1.3.5
The
tablet server
requirement
1 day
Mon
6/13/
16
Mon
6/13/
16
14 Environemntal
analyst $720.00
Auto
Schedul
ed
1.3.6
Develo
ping server
user
interface
1 day
Tue
6/14/
16
Tue
6/14/
16
15 $0.00
Auto
Schedul
ed
1.4 Milestone
3:
Completio
n of
0 days Tue
6/14/
16
Tue
6/14/
16
16 $0.00
Auto
Schedul
ed
1.3.2
Require
ment of
data
1 day
Thu
6/9/1
6
Thu
6/9/1
6
11 $0.00
Auto
Schedul
ed
1.3.3
Milesto
ne 2:
Completio
n
ofhardwar
e and
software
requireme
nt
planning
0 days
Thu
6/9/1
6
Thu
6/9/1
6
12 $0.00
Auto
Schedul
ed
1.3.4
Softwa
re required
for the
tablet
1 day
Fri
6/10/
16
Fri
6/10/
16
13
Electronic
engineer ,Envi
ronemntal
analyst
$1,360.0
0
Auto
Schedul
ed
1.3.5
The
tablet server
requirement
1 day
Mon
6/13/
16
Mon
6/13/
16
14 Environemntal
analyst $720.00
Auto
Schedul
ed
1.3.6
Develo
ping server
user
interface
1 day
Tue
6/14/
16
Tue
6/14/
16
15 $0.00
Auto
Schedul
ed
1.4 Milestone
3:
Completio
n of
0 days Tue
6/14/
16
Tue
6/14/
16
16 $0.00
15PROJECT MANAGEMENT
project
planning
phase
Auto
Schedul
ed
1.5 Project
execution
17
days
Wed
6/15/
16
Thu
7/7/1
6
software
analyst or
designer
$34,640.
00
Auto
Schedul
ed
1.5.1
Review
and
approval of
the software
based
requirement
s
1 day
Wed
6/15/
16
Wed
6/15/
16
17 $0.00
Auto
Schedul
ed
1.5.2
Requir
ement for
reporting
3 days
Thu
6/16/
16
Mon
6/20/
16
software
analyst or
designer,Soft
ware engineer
$5,440.0
0
Auto
Schedul
ed
1.5.2
.1
For
report A 1 day
Thu
6/16/
16
Thu
6/16/
16
19 Software
engineer $640.00
Auto
Schedul
ed
1.5.2
.2
For
report B 1 day
Fri
6/17/
16
Fri
6/17/
16
21
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.2
.3
For
report C 1 day
Mon
6/20/
16
Mon
6/20/
16
22 $0.00
project
planning
phase
Auto
Schedul
ed
1.5 Project
execution
17
days
Wed
6/15/
16
Thu
7/7/1
6
software
analyst or
designer
$34,640.
00
Auto
Schedul
ed
1.5.1
Review
and
approval of
the software
based
requirement
s
1 day
Wed
6/15/
16
Wed
6/15/
16
17 $0.00
Auto
Schedul
ed
1.5.2
Requir
ement for
reporting
3 days
Thu
6/16/
16
Mon
6/20/
16
software
analyst or
designer,Soft
ware engineer
$5,440.0
0
Auto
Schedul
ed
1.5.2
.1
For
report A 1 day
Thu
6/16/
16
Thu
6/16/
16
19 Software
engineer $640.00
Auto
Schedul
ed
1.5.2
.2
For
report B 1 day
Fri
6/17/
16
Fri
6/17/
16
21
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.2
.3
For
report C 1 day
Mon
6/20/
16
Mon
6/20/
16
22 $0.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16PROJECT MANAGEMENT
Auto
Schedul
ed
1.5.3 Softwa
re design 5 days
Tue
6/21/
16
Mon
6/27/
16
software
analyst or
designer
$6,320.0
0
Auto
Schedul
ed
1.5.3
.1
Table
t server
interface
1 day
Tue
6/21/
16
Tue
6/21/
16
23
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.3
.2
User
server
interface
1 day
Wed
6/22/
16
Wed
6/22/
16
25
Electronic
engineer ,Soft
ware engineer
$1,280.0
0
Auto
Schedul
ed
1.5.3
.3
Devel
opment of
data layer
1 day
Thu
6/23/
16
Thu
6/23/
16
26 $0.00
Auto
Schedul
ed
1.5.3
.4
Miles
tone 4:
Design
approval
completion
1 day
Fri
6/24/
16
Fri
6/24/
16
27
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.3
.5
Revie
w and
approval of
the software
design
details
1 day
Mon
6/27/
16
Mon
6/27/
16
28 $0.00
Auto
Schedul
ed
1.5.4 Softwa
re
developme
nt and
4 days Tue
6/28/
16
Fri
7/1/1
6
software
analyst or
designer
$4,960.0
0
Auto
Schedul
ed
1.5.3 Softwa
re design 5 days
Tue
6/21/
16
Mon
6/27/
16
software
analyst or
designer
$6,320.0
0
Auto
Schedul
ed
1.5.3
.1
Table
t server
interface
1 day
Tue
6/21/
16
Tue
6/21/
16
23
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.3
.2
User
server
interface
1 day
Wed
6/22/
16
Wed
6/22/
16
25
Electronic
engineer ,Soft
ware engineer
$1,280.0
0
Auto
Schedul
ed
1.5.3
.3
Devel
opment of
data layer
1 day
Thu
6/23/
16
Thu
6/23/
16
26 $0.00
Auto
Schedul
ed
1.5.3
.4
Miles
tone 4:
Design
approval
completion
1 day
Fri
6/24/
16
Fri
6/24/
16
27
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.3
.5
Revie
w and
approval of
the software
design
details
1 day
Mon
6/27/
16
Mon
6/27/
16
28 $0.00
Auto
Schedul
ed
1.5.4 Softwa
re
developme
nt and
4 days Tue
6/28/
16
Fri
7/1/1
6
software
analyst or
designer
$4,960.0
0
17PROJECT MANAGEMENT
testing
Auto
Schedul
ed
1.5.4
.1
User
interface
developmen
t
1 day
Tue
6/28/
16
Tue
6/28/
16
29
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.4
.2
Data
layer
developmen
t
1 day
Wed
6/29/
16
Wed
6/29/
16
31
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.4
.3
Field
testing
1 day Thu
6/30/
16
Thu
6/30/
16
32 Software
engineer
$640.00
Auto
Schedul
ed
1.5.4
.4
Appli
cation layer
improveme
nt
1 day
Fri
7/1/1
6
Fri
7/1/1
6
33 $0.00
Auto
Schedul
ed
1.5.5
Hardw
are
requireme
nt: Data
entry
tablet
4 days
Mon
7/4/1
6
Thu
7/7/1
6
software
analyst or
designer
$5,680.0
0
Auto
Schedul
ed
1.5.5
.1
Repo
rt testing
1 day Mon
7/4/1
6
Mon
7/4/1
6
34 software
analyst or
designer
$720.00
Auto
Schedul
1.5.5 Repo 1 day Tue
7/5/1
Tue
7/5/1
36 software
analyst or
$720.00
testing
Auto
Schedul
ed
1.5.4
.1
User
interface
developmen
t
1 day
Tue
6/28/
16
Tue
6/28/
16
29
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.4
.2
Data
layer
developmen
t
1 day
Wed
6/29/
16
Wed
6/29/
16
31
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.5.4
.3
Field
testing
1 day Thu
6/30/
16
Thu
6/30/
16
32 Software
engineer
$640.00
Auto
Schedul
ed
1.5.4
.4
Appli
cation layer
improveme
nt
1 day
Fri
7/1/1
6
Fri
7/1/1
6
33 $0.00
Auto
Schedul
ed
1.5.5
Hardw
are
requireme
nt: Data
entry
tablet
4 days
Mon
7/4/1
6
Thu
7/7/1
6
software
analyst or
designer
$5,680.0
0
Auto
Schedul
ed
1.5.5
.1
Repo
rt testing
1 day Mon
7/4/1
6
Mon
7/4/1
6
34 software
analyst or
designer
$720.00
Auto
Schedul
1.5.5 Repo 1 day Tue
7/5/1
Tue
7/5/1
36 software
analyst or
$720.00
18PROJECT MANAGEMENT
ed .2 rt review 6 6 designer
Auto
Schedul
ed
1.5.5
.3
Modi
fication as
per the
testing
results
1 day
Wed
7/6/1
6
Wed
7/6/1
6
37 $0.00
Auto
Schedul
ed
1.5.5
.4
Appr
oval on the
production
1 day
Thu
7/7/1
6
Thu
7/7/1
6
38
software
analyst or
designer,
Software
engineer
$1,360.0
0
Auto
Schedul
ed
1.6
Milestone
5:
Completio
n of
project
execution
phase
1 day
Fri
7/8/1
6
Fri
7/8/1
6
39 $0.00
Auto
Schedul
ed
1.7 Project
closure 2 days
Fri
7/8/1
6
Mon
7/11/
16
Electronic
engineer
$3,360.0
0
Auto
Schedul
ed
1.7.1
Stakeh
older
signoff
1 day
Fri
7/8/1
6
Fri
7/8/1
6
39 Environmental
analyst $720.00
Auto
Schedul
ed
1.7.2
Final
documentat
ion
1 day
Mon
7/11/
16
Mon
7/11/
16
40 Electronic
engineer $640.00
ed .2 rt review 6 6 designer
Auto
Schedul
ed
1.5.5
.3
Modi
fication as
per the
testing
results
1 day
Wed
7/6/1
6
Wed
7/6/1
6
37 $0.00
Auto
Schedul
ed
1.5.5
.4
Appr
oval on the
production
1 day
Thu
7/7/1
6
Thu
7/7/1
6
38
software
analyst or
designer,
Software
engineer
$1,360.0
0
Auto
Schedul
ed
1.6
Milestone
5:
Completio
n of
project
execution
phase
1 day
Fri
7/8/1
6
Fri
7/8/1
6
39 $0.00
Auto
Schedul
ed
1.7 Project
closure 2 days
Fri
7/8/1
6
Mon
7/11/
16
Electronic
engineer
$3,360.0
0
Auto
Schedul
ed
1.7.1
Stakeh
older
signoff
1 day
Fri
7/8/1
6
Fri
7/8/1
6
39 Environmental
analyst $720.00
Auto
Schedul
ed
1.7.2
Final
documentat
ion
1 day
Mon
7/11/
16
Mon
7/11/
16
40 Electronic
engineer $640.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
19PROJECT MANAGEMENT
Auto
Schedul
ed
1.7.3
Post
project
evaluation
and
maintenanc
e
1 day
Mon
7/11/
16
Mon
7/11/
16
42
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.8
Milestone
6 :
Completio
n of
project
closure
phase
0 days
Mon
7/11/
16
Mon
7/11/
16
43 $0.00
Auto
Schedul
ed
1.7.3
Post
project
evaluation
and
maintenanc
e
1 day
Mon
7/11/
16
Mon
7/11/
16
42
software
analyst or
designer
$720.00
Auto
Schedul
ed
1.8
Milestone
6 :
Completio
n of
project
closure
phase
0 days
Mon
7/11/
16
Mon
7/11/
16
43 $0.00
20PROJECT MANAGEMENT
Figure 4: Modified Gantt chart for Victoria Construction Pty., Ltd.
(Source: Created by author)
Figure 4: Modified Gantt chart for Victoria Construction Pty., Ltd.
(Source: Created by author)
21PROJECT MANAGEMENT
Figure 4: Modified WBS for Victoria Construction Pty., Ltd.
(Source: Created by author)
a) The project will be completed in 27 days.
b) The staring and finish date of the project are respectively and 1/6/2016 and
13/6/2016.
c) The list of task following critical path
None of these tasks are critical.
d) No, the annual holidays are not affecting or making difference in the end date of the
project.
e) In order to complete the task instead of 3 weeks in 2 weeks I would have make
changes in the field application phases and for requirement gathering also I would have reduce
the total time.
Figure 4: Modified WBS for Victoria Construction Pty., Ltd.
(Source: Created by author)
a) The project will be completed in 27 days.
b) The staring and finish date of the project are respectively and 1/6/2016 and
13/6/2016.
c) The list of task following critical path
None of these tasks are critical.
d) No, the annual holidays are not affecting or making difference in the end date of the
project.
e) In order to complete the task instead of 3 weeks in 2 weeks I would have make
changes in the field application phases and for requirement gathering also I would have reduce
the total time.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
22PROJECT MANAGEMENT
If the field testing phases are reduced then, in order to reduce the rate of error the
project manager and the project team members will work harder to avoid application level
issues.
In order to reduce the duration advanced automatic data collection approach and
advanced data gathering approaches are required to be adopted. In addition to this the project
manager should hire expert team who might understand the requirement much accurately.
After Modification
a) In order to reduce the resource over allocation issues I analyzed the time requirement
in details.
b) List of critical tasks
All the activities are critical in this project.
c) No, the resource constraints have no impact on the project requirement and project
detailing.
The student’s Ids are:
s4576393/
s4582178/
s4581505
Thus, the total days of work will be (4+4+4) =12 the project is required to be completed
in 12 days only.
Task C- Presenting Project Management Blogs
Project management hut Blog is evaluated for the creation of the power point presentation.
If the field testing phases are reduced then, in order to reduce the rate of error the
project manager and the project team members will work harder to avoid application level
issues.
In order to reduce the duration advanced automatic data collection approach and
advanced data gathering approaches are required to be adopted. In addition to this the project
manager should hire expert team who might understand the requirement much accurately.
After Modification
a) In order to reduce the resource over allocation issues I analyzed the time requirement
in details.
b) List of critical tasks
All the activities are critical in this project.
c) No, the resource constraints have no impact on the project requirement and project
detailing.
The student’s Ids are:
s4576393/
s4582178/
s4581505
Thus, the total days of work will be (4+4+4) =12 the project is required to be completed
in 12 days only.
Task C- Presenting Project Management Blogs
Project management hut Blog is evaluated for the creation of the power point presentation.
23PROJECT MANAGEMENT
Bibliography
Amrollahi, A., Ghapanchi, A. H., and Talaei-Khoei, A. 2014. Three decades of research on
strategic information system plan development.Communications of the Association for
Information Systems, 34(1), 84.
Braglia, M., and Frosolini, M. 2014. An integrated approach to implement project management
information systems within the extended enterprise.International Journal of Project
Management, 32(1), 18-29.
Coronel, C., and Morris, S. 2016. Database systems: design, implementation, & management.
Cengage Learning.
Galliers, R. D., and Leidner, D. E. 2014. Strategic information management: challenges and
strategies in managing information systems. Routledge.
Garton, C., and McCulloch, E. (2012). Fundamentals of Technology Project Management. MC
Press, LLC.
Goetsch, D. L., and Davis, S. B. 2014. Quality management for organizational excellence.
pearson.
Hubicki, M. 2014. Risk Management Plan.
Kami, N. 2015. U.S. Patent No. 9,116,916. Washington, DC: U.S. Patent and Trademark
Office.
Kendrick, T. 2015. Identifying and managing project risk: essential tools for failure-proofing
your project. AMACOM Div American Mgmt Assn.
Nanda, V. 2016. Quality management system handbook for product development companies.
CRC Press.
Pritchard, C. L., and PMP, P. R. 2014. Risk management: concepts and guidance. CRC Press.
Schwalbe, K. 2015. Information technology project management. Cengage Learning.
Bibliography
Amrollahi, A., Ghapanchi, A. H., and Talaei-Khoei, A. 2014. Three decades of research on
strategic information system plan development.Communications of the Association for
Information Systems, 34(1), 84.
Braglia, M., and Frosolini, M. 2014. An integrated approach to implement project management
information systems within the extended enterprise.International Journal of Project
Management, 32(1), 18-29.
Coronel, C., and Morris, S. 2016. Database systems: design, implementation, & management.
Cengage Learning.
Galliers, R. D., and Leidner, D. E. 2014. Strategic information management: challenges and
strategies in managing information systems. Routledge.
Garton, C., and McCulloch, E. (2012). Fundamentals of Technology Project Management. MC
Press, LLC.
Goetsch, D. L., and Davis, S. B. 2014. Quality management for organizational excellence.
pearson.
Hubicki, M. 2014. Risk Management Plan.
Kami, N. 2015. U.S. Patent No. 9,116,916. Washington, DC: U.S. Patent and Trademark
Office.
Kendrick, T. 2015. Identifying and managing project risk: essential tools for failure-proofing
your project. AMACOM Div American Mgmt Assn.
Nanda, V. 2016. Quality management system handbook for product development companies.
CRC Press.
Pritchard, C. L., and PMP, P. R. 2014. Risk management: concepts and guidance. CRC Press.
Schwalbe, K. 2015. Information technology project management. Cengage Learning.
1 out of 24
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.