1 PROJECT MANAGEMENT Table of Contents 1. Project goals and objectives.........................................................................................................2 2. Business Value.............................................................................................................................2 3. Project management plan.............................................................................................................3 3.1 Work breakdown structure....................................................................................................3 3.2 Gantt chart.............................................................................................................................4 4. Project Scope statement...............................................................................................................5 5. Project schedule...........................................................................................................................5 Bibliography....................................................................................................................................9
2 PROJECT MANAGEMENT 1. Project goals and objectives The main goal of the project is to construct a bungalow on strip footings by including external walls that are double brick veneer whereas the internal partition walls are generally constructed by using timber studwork. The objectives of the project are reflected below: To construct a bungalow on strip footings To get the work financed by the bank loan which is generally paid in four weeks To complete the construction of six rooms in total, kitchen dining, main bedroom as well as guest bathroom 2. Business Value It is found that the project mainly aims to construct a bungalow which mainly includes six room in total including kitchen dining, lounge, second bedroom, guest bathroom as well as laundry. In addition to this, external walls are double brick veneer whereas the internal partition related walls are generally constructed with the help of timber studwork. The construction of the bungalow will be helpful in earning profit.
3 PROJECT MANAGEMENT 3. Project management plan 3.1 Work breakdown structure Bungalow project Design Design structure, meeting client requirements Appoint project manager Modify till acceptance has been achieved Conduct soil test Receiving design approval from client Drawing plans and schedules Attain enginerring certificate Submit plans to local council Prepare and submit application to QBCC Select Insurance package Engage project management team Site preparation Erecting temporary safety fencing Installing portable WC facilities Installing temporary power hole installing water point Fund site power and water costs Clearing the site Setting out the dwelling Dig foundations Foundation inspection Installing trench mesh Pour footings Building (to Lock up) Erecting double brick external wall system Install windows and doors install glazing Install floor joists Exrect internal timber frame, floor and walls Erecting the roof trusses and battens Install roof railing Fit ceiling joists Fit T & G strip flooring Install guttering Fit roof tiles Rough in electrical Rough in plumbing Building (Hand Over) Install insulation Fit plasterboard to ceilings Fit plasterboard to walls Crane lift pool shell into place Install & connect swimming pool shell pump Conduct second fix Tiles Paint walls and ceilings Fit off electrical points and appliances Fit off plumbing & heating points Installing downpipes and connect to storm water Landscapping Connection to server Connection to water supply Connection to power supply Clean up site Client handover Mortage holder inspection Figure 1: Work breakdown structure (Source: Created by Author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 PROJECT MANAGEMENT 3.2 Gantt chart Figure 2: Gantt chart (Source: Created by Author)
5 PROJECT MANAGEMENT 4. Project Scope statement The scope of the project mainly includes: Construction of bungalow Roof tiled that is further laid on timber trussed rafter Constructingsixroomsintotalincludingkitchendining,mainbedroom,second bedroom, guest bathroom as well as laundry. Financing of work by bank loan Proper schedule and cost management plan 5. Project schedule The schedule for the bungalow project is mainly provided in the table below: WBSTask NameDurationStartFinish 0Bungalow project60 daysMon 01-04-19Fri 21-06-19 1Design51 daysMon 01-04-19Mon 10-06-19 1.1 Design structure, meeting client requirements 2 daysMon 01-04-19Tue 02-04-19 1.2Appoint project manager48 daysWed 03-04-19Fri 07-06-19 1.3 Modify till acceptance has been achieved 1 dayWed 03-04-19Wed 03-04-19 1.4Conduct soil test2 daysWed 03-04-19Thu 04-04-19 1.5 Receiving design approval from client 1 dayMon 10-06-19Mon 10-06-19
6 PROJECT MANAGEMENT 1.6Drawing plans and schedules2 daysThu 04-04-19Fri 05-04-19 1.7Attain engineering certificate2 daysFri 05-04-19Mon 08-04-19 1.8Submit plans to local council6 daysMon 08-04-19Mon 15-04-19 1.9 Prepare and submit application to QBCC 1 dayTue 09-04-19Tue 09-04-19 1.10Select Insurance package2 daysWed 17-04-19Thu 18-04-19 1.11 Engage project management team 38 daysMon 08-04-19Wed 29-05-19 2Site preparation49 daysTue 16-04-19Fri 21-06-19 2.1 Erecting temporary safety fencing 1 dayTue 16-04-19Tue 16-04-19 2.2Installing portable WC facilities48 daysWed 17-04-19Fri 21-06-19 2.3Installing temporary power hole1 dayTue 16-04-19Tue 16-04-19 2.4installing water point1 dayWed 17-04-19Wed 17-04-19 2.5Fund site power and water costs1 dayWed 17-04-19Wed 17-04-19 2.6Clearing the site1 dayTue 16-04-19Tue 16-04-19 2.7Setting out the dwelling1 dayWed 17-04-19Wed 17-04-19 2.8Dig foundations3 daysThu 18-04-19Mon 22-04-19 2.9Foundation inspection1 dayThu 18-04-19Thu 18-04-19 2.10Installing trench mesh1 dayWed 17-04-19Wed 17-04-19 2.11Pour footings1 dayThu 18-04-19Thu 18-04-19 3Building (to Lock up)13.5 daysTue 23-04-19Fri 10-05-19
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
8 PROJECT MANAGEMENT shell pump 4.6Conduct second fix2 daysFri 10-05-19Mon 13-05-19 4.7Tiles4 daysWed 15-05-19Mon 20-05-19 4.8Paint walls and ceilings2 daysTue 14-05-19Wed 15-05-19 4.9 Fit off electrical points and appliances 2 daysTue 21-05-19Wed 22-05-19 4.10 Fit off plumbing & heating points 2 daysTue 14-05-19Wed 15-05-19 4.11 Installing downpipes and connect to storm water 2 daysFri 10-05-19Tue 14-05-19 4.12Landscaping3 daysFri 10-05-19Tue 14-05-19 4.13Connection to server1 dayFri 10-05-19Fri 10-05-19 4.14Connection to water supply1 dayFri 10-05-19Fri 10-05-19 4.15Connection to power supply1 dayThu 16-05-19Thu 16-05-19 4.16Clean up site1 dayTue 14-05-19Wed 15-05-19 4.17Client handover1 dayWed 15-05-19Wed 15-05-19 4.18Mortgage holder inspection1 dayMon 13-05-19Mon 13-05-19
9 PROJECT MANAGEMENT Bibliography Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practicesonprojectsuccess:Towardsdevelopingaprojectbenefitsgovernance framework.International Journal of Project Management,34(4), pp.761-778. Hornstein, H. A. (2015). The integration of project management and organizational change management is now a necessity.International Journal of Project Management,33(2), 291-298. Papke-Shields, K.E.& Boyer-Wright, K.M. (2017). Strategic planning characteristics applied to project management.International Journal of Project Management,35(2), pp.169-179. Svejvig, P. & Andersen, P. (2015). Rethinking project management: A structured literature review with a critical look at the brave new world.International Journal of Project Management,33(2), pp.278-290. Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D. (2015). Projectsuccessanalysisframework:Aknowledge-basedapproachinproject management.International Journal of Project Management,33(4), 772-783.