Project Network for a New Laptop Computer.

   

Added on  2022-11-15

11 Pages438 Words2 Views
 | 
 | 
 | 
Project Network for a New Laptop
Computer
Name of the Student
Name of the University
Project Network for a New Laptop Computer._1

The AON Diagram
(Figure 1: The AON Diagram for the Project)
(Source: Created by author)
Project Network for a New Laptop Computer._2

Identification of Critical Path
The red highlighted sections from Figure 1 are
identified as critical path activities within the project
Scheduled duration of the project is calculated as:
= Sum of the total tasks in the critical path
= (90 + 25 + 14+ 20 + 45) days
= 194 days
Project Network for a New Laptop Computer._3

Information on Project Network
Management would need to complete the project 5
days prior than the scheduled period
Crashing of the critical activities needs to be done
within 5 days