This project plan outlines the scope, time, cost, communication, and risk management for the upcoming academic year. It includes a detailed breakdown of tasks, milestones, and budget. Download now from Desklib.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Project Plan for the academic year it will take place in late September 2020- INDUCTION-event day
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Section 1.Scope Management Plan 1.1Project Description This project is a welcoming and induction event for the next academic year students. This will be a tree day event that is planed to welcome new students in the next academic year and make them aware of institution in which they will complete their education. This report will be providing a complete a outline to make event effective and successful. The planning of the project will be consists of time scheduled for event, financial planning for welcoming and induction program, communication management plan and risk management plan to complete event without any failure. 1.1.1Project Description In the new academic year different new students will be joining the university and will become part of it. This event is all about greet them effectively with people of institution, infrastructure and facilities that will be provided to them with in the promises. The Welcoming program will be all about interaction between institution and new comers. The induction program will be about making new students aware of the organization and make them familiar with different processes and activities of university throughout the complete year. 1.1.2Project Objectives The main objective of this project are- 1.To develop effective Management plan for welcome and induction program for next academic year with in 2 months. 2.Develop sense of belonging in students towards institution 3.To provide required information to the student to develop their knowledge. 4.To develop a complete outline of welcome and induction event for effective completion. 5.To develop a risk management plan to reduce the chances of major and minor failures. 1.2ProjectScope Themainpurposeofthewelcomeandinductioneventistoprovidecrucialand information that students will need to perform efficiently with in the university. They will be introduced to the faculty and education process. This is how students will feel comfortable with in the institution. This is how they will be able to select college for their further education. 1.3Assumptions There are assumption need to be made about the project plan to make it much easier to follow and make whole event systematic. The assumptions that are made for project plan.
1.The resources that will be used in the event will be renewable and sustainable. 2.Complete process will be designed to be effective and influential for students. 3.The welcome and induction event will be more interactive not one way communication. 1.4Constraints Constraints for this project are related to the factors that are not in control of project team. Some of the main constraints for the projects are- 1.the budget of the three event is fixed and it is not possible to extent this budget due to extra expenses, 2.the time of the event is predefined so any kind of timing related issue can not be entertained in the project planning. 3.The changes in the plan can not be implemented on high level at implement stage. 4.The delays in the project implementation should be avoided. 1.5Project Roles and Responsibilities In the project planning different members will required to complete project with high effectiveness. Different roles and responsibility of these members will be- MemberRoleResponsibility Project ManagerThe responsibility of the project manageristomanageallthe operations with in the project. This is responsibility reduce the chancesoffailurewithinthe projectwithcostandtime efficiency. Resource ManagerThe role of the resource manager istoensuretheavailabilityof variousresourcesthatare requiredforthesuccessful implementation of project. Theresponsibilityofresource manageristomakethe resourcesavailablethatare suitable for the project. Team MemberDevelopbettercoordinationto successfulimplementationor project. Makeeffectivecommunication with team members to avoid any kind of failure with in the project. Functional ManagerThemain roleofthefunctional manageristomanagethe Thisisresponsibilityofthe functional manager to effectively
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
operationsatimplementation stage. distribute the resources to avoid delays in project. Team LeaderRoleoftheleaderistoguide teamtocompletetheparticular task. The role of the team leader is to effectivelyguideallteam memberstoavoidfailureand miscommunicationwithinthe project. 1.6Responsibility Assignment Matrix (RAM) – Project manager Resource manager Team memberFunctional Manager Team leader Managing activities A,PPSP,A Manage procedure S,PP,A Implementation process AASP,A Budget Planning S,AA,PPP Risk Management A,PSP,A P = Primary Responsibility S = Secondary Responsibility A = Approval 1.7Project Work-breakdown Structure (WBS)
1.8WBS Dictionary –[ Optional ] WBS LevelWBS LevelDiscription Scope Management1Evaluation of Scope of the project Time management2Outline the complete procedure Cost Management3Budget planning Communication Management 4Coordination planning Risk Management5Reduction of the rik
Section 2.Time Management Plan 2.1Project Milestones Project milestone termed out as the management tool that used as delineate a point within project schedule. However, milestones aids to keep projects on track with help of undertaking the effective tracking on major events, dates, decision and deliverable. â—¦Start and end dates for project phases- â—¦Key deliverable â—¦Client and stakeholders approval â—¦Important meetings and presentation- â—¦Key dates and outages 2.2Project Activity/Time/Dependency base table Task NameDura tionStartFinishPredecess ors W BS Project planning 2 days Fri 9/18/2 0 Mon 9/21/2 0 1 Defining induction purpose 2 days Fri 9/18/2 0 Mon 9/21/2 0 1.1 Define project parameters 3 days Tue 9/22/2 0 Thu 9/24/2 0 21.2 Developing preliminary integrated schedules 1 day Fri 9/25/2 0 Fri 9/25/2 0 2,31.3 Schedule designing 2 days Mon 9/28/2 0 Tue 9/29/2 0 4,21.4 Discussion on budget 1 day Wed 9/30/2 0 Wed 9/30/2 0 4,51.5 Approval from authority 1 day Thu 10/1/2 0 Thu 10/1/2 0 61.6
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Draft event program 2 days Fri 10/2/2 0 Mon 10/5/2 0 7,21.7 Implementation2 days Thu 9/24/2 0 Fri 9/25/2 0 2 Guest list preparation 1 day Tue 10/6/2 0 Tue 10/6/2 0 82.1 Prepare communication message for the academic year students 3 days Wed 10/7/2 0 Fri 10/9/2 0 102.2 Produce attendance list 2 days Mon 10/12/ 20 Tue 10/13/ 20 112.3 Fund allocation2 days Mon 10/12/ 20 Tue 10/13/ 20 11,2,82.4 Setting technical team for arrange sound and speakers for induction program 1 day Wed 10/14/ 20 Wed 10/14/ 20 12,132.5 Program3 days Thu 10/1/2 0 Mon 10/5/2 0 3 Drafting of induction program 1 day Thu 10/15/ 20 Thu 10/15/ 20 143.1 Host confirmation 2 days Fri 10/16/ 20 Mon 10/19/ 20 16,2,8,143.2 Organization accommodation facilities 2 days Tue 10/20/ 20 Wed 10/21/ 20 173.3 Communication 1 day Thu 10/22/ 20 Thu 10/22/ 20 183.4 Print invitation3 days Fri 10/23/ 20 Tue 10/27/ 20 19,2,163.5
Post event promotions 2 days Wed 10/28/ 20 Thu 10/29/ 20 203.6 Closure1 day Sat 10/10/ 20 Sat 10/10/ 20 4 End of project1 day Fri 10/30/ 20 Fri 10/30/ 20 214.1 2.3Project Network Diagram 2.4Project Gantt Chart
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Section 3.Cost Management Plan 3.1Cost Breakdown and Budget ActivitiesCost Personal120 Marketing200 Food200 Drinks220 Promotions printing200 Total940£ Henceforth, the estimated cost breakdown for the project is 940$. 3.2Project Cost Baseline Task Name D ur at io n Star t Fini sh Prede cesso rs Reso urce Name s Cost Project planning 2 d a ys Fri 9/1 8/2 0 Mo n 9/2 1/2 0 $410.0 0 Defining induction purpose 2 d a ys Fri 9/1 8/2 0 Mo n 9/2 1/2 0 huma n resou rce $50.00
Define project parameters 3 d a ys Tue 9/2 2/2 0 Thu 9/2 4/2 0 2 huma n resou rce $50.00 Developing preliminary integrated schedules 1 d a y Fri 9/2 5/2 0 Fri 9/2 5/2 0 2,3 finan cial resou rce $100.0 0 Schedule designing 2 d a ys Mo n 9/2 8/2 0 Tue 9/2 9/2 0 4,2 techn ical resou rce $50.00 Discussion on budget 1 d a y We d 9/3 0/2 0 We d 9/3 0/2 0 4,5 huma n resou rce $50.00 Approval from authority 1 d a y Thu 10/ 1/2 0 Thu 10/ 1/2 0 6 huma n resou rce $50.00 Draft event program 2 d a ys Fri 10/ 2/2 0 Mo n 10/ 5/2 0 7,2 huma n resou rce $60.00 Implementa tion 2 d a ys Th u 9/2 4/2 0 Fri 9/2 5/2 0 $290.0 0 Guest list preparation 1 d a y Tue 10/ 6/2 0 Tue 10/ 6/2 0 8 finan cial resou rce, huma n resou rce, techn ical resou rce $50.00
Prepare communicati on message for the academic year students 3 d a ys We d 10/ 7/2 0 Fri 10/ 9/2 0 10 huma n resou rce $60.00 Produce attendance list 2 d a ys Mo n 10/ 12/ 20 Tue 10/ 13/ 20 11 techn ical resou rce $50.00 Fund allocation 2 d a ys Mo n 10/ 12/ 20 Tue 10/ 13/ 20 11,2, 8 finan cial resou rce $60.00 Setting technical team for arrange sound and speakers for induction program 1 d a y We d 10/ 14/ 20 We d 10/ 14/ 20 12,13 techn ical resou rce $70.00 Program 3 d a ys Th u 10/ 1/2 0 Mo n 10/ 5/2 0 $230.0 0 Drafting of induction program 1 d a y Thu 10/ 15/ 20 Thu 10/ 15/ 20 14 huma n resou rce $50.00 Host confirmation 2 d a ys Fri 10/ 16/ 20 Mo n 10/ 19/ 20 16,2, 8,14 huma n resou rce $50.00 Organization accommodat ion facilities 2 d a ys Tue 10/ 20/ 20 We d 10/ 21/ 20 17 huma n resou rce $20.00 Communicat 1 d Thu 10/ Thu 10/ 18techn ical $30.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
iona y 22/ 20 22/ 20 resou rce Print invitation 3 d a ys Fri 10/ 23/ 20 Tue 10/ 27/ 20 19,2, 16 finan cial resou rce $30.00 Post event promotions 2 d a ys We d 10/ 28/ 20 Thu 10/ 29/ 20 20 finan cial resou rce $50.00 Closure 1 d a y Sat 10/ 10/ 20 Sat 10/ 10/ 20 $10.00 End of project 1 d a y Fri 10/ 30/ 20 Fri 10/ 30/ 20 21 finan cial resou rce, huma n resou rce, techn ical resou rce $10.00
Section 4.Communication Management Plan 4.1Project Stakeholders Project stakeholder are defined as entities that have an crucial interest in the given project. These stakeholders can be defined as insider and outside of an organization. They are defined as person who are invested in the project and can be affected by project at any point along the way and this input gas direct impact on outcome. These as are-: Sponsor- He is defined as an individual who provides suppliers and support for the project and this is also liable for assisting success. It may be external and internal to enterprise. Customers- They are defined as people or organization who will approve and manage the product, service and result. Sellers- They are also known as vendors and the external firm that enter into the contractual agreement to offer service or resources for project. Business partners-They are defined as external organizations that have effective relationship with enterprise. Organizational groups- They are termed out as internal stakeholders and influenced by the actions of project team. For example- human resource, marketing, sales and legal etc. Functional managers- It is defined as key individuals who plays the effective role of management within the administrative and functional areas of business. Otherstakeholder-theyareadditionalstakeholdersthatinclusiveoffinancialinstitution, government regulators and consultants etc. 4.2Stakeholder Communication Plan Co mm uni cati on typ e Objecti veof commu nicatio n Mediu m Fr e q u e nc y Audi enc e OwnerDeliv erabl e Pro ject tea me Review status ofthe project Face to face and W e ek Proj ect spo Project manager Agen da Meeti
etin g with team. confer ence call lynsorng Tec hni cal des ign me etin g Discus sand develo p technic al solutio nfor project Face to face M o nt hl y Proj ect tea m Project manag er Meeti ng minut er agen da Mo nthl y proj ect stat us me etin g Report ion status of project manag ement Face to face Confe rence call w e ek ly Proj ect tech nical staff Techni cal lead Slide updat es proje ct sche dule Pro ject stat us rep ort Report on status of project thatis inclusiv e of the activitie s progres sand issues. E-mailM o nt hl y Project manag er Proje ct statu s
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Section 5.Risk Management Plan 6.1Risk Identification, Analysis and Action Plan RISKDESC RIPTIO N PROB ABILIT Y Ratin g IMPA CT Strate gy to mitiga te Finan cial risk Financ e related issues can be identifi ed. High3HighBy having better financi al adequ acy Huma n resour ce Risk Thew activitie s needs to be undert ake system atically. Mediu m 4LowWith help of setting up effecti ve rules and regula tions. Risk of scope To identifi cation of risk Low2Mediu m With help of risk identifi cation. Techn ical To measur e out technic al deficie ncy. Moder ate 3Moder ate By hiring techni cal assist ant perso
nal. 6.2Project Risk Matrix – Project risk matrix (1-5= yellow 5=10= green 10-20= red) High =red Low= yellow Medium= Green Likelihood (1=low, 5=high) Consequenc es (1=low, 5=high) Level of risk risk Financial risk 224 Technical risk 339 Schedule risk 122 Human resource risk 4520