Running head: PROJECT SCHEDULE, MILESTONES, QUALITY MANAGEMENT PLAN
Project Schedule, Milestones, Quality Management Plan
Name of the Student
Name of the University
Author note
Project Schedule, Milestones, Quality Management Plan_1

PROJECT SCHEDULE, MILESTONES, QUALITY MANAGEMENT PLAN1
1. Project Schedule
ID Outline
Number
Task
Mode
Task Name Duration Start Finish
0 0 Development of a
CustomApplication
105 days Mon 03-02-20Fri 26-06-20
1 1 Function 1 Installing
application to master
server
9 days Mon 03-02-20 Thu
13-02-20
2 1.1 Deliverable
Increase in troubled
patient volumes
9 days Mon 03-02-20 Thu
13-02-20
3 1.1.1 Work Package One
IT admin installs
app during non
business hours
required 3 hours
downtime app on
6 days Mon 03-02-20 Mon
10-02-20
4 1.1.2 Work system
restart and auto
update file is
running in
background
3 days Tue 11-02-20 Thu
13-02-20
5 2 Function 2 Measuring
effectiveness of
application
implementation
9 days Fri 14-02-20 Wed
26-02-20
6 2.1 Deliverable One –
Increase in cancer
patient volumes
9 days Fri 14-02-20 Wed
26-02-20
7 2.1.1 Work Package One
– Extracting data
pre and post
implementation to
measure
9 days Fri 14-02-20 Wed
26-02-20
8 3 Function 3 Surveying
realiability further
future licensing etc
54 days Thu 27-02-20 Tue
12-05-20
9 3.1 Deliverable One –
Furthering reliability
10 days Thu 27-02-20 Wed
11-03-20
10 3.2 Deliverable Two –
Enhance system
reliability involving
receptionist to ensure
if contact
25 days Thu 12-03-20 Wed
15-04-20
11 3.3 Deliverable Three –
involve front line staff
to confirm if contact
number is correct
19 days Thu 16-04-20 Tue
12-05-20
12 4 Function 4 – Increase
in quality of care
19 days Wed 13-05-20 Mon
08-06-20
13 4.1 Deliverable One –
Measurement of
increased quality of
care
9 days Wed 13-05-20 Mon
25-05-20
14 4.2 Deliverable Two –
Application
effectiveness
measured with
practitioner
satisfaction
10 days Tue 26-05-20 Mon
08-06-20
15 4.2.1 Work Package One
– Surveying health
practitioners
measuring
betterment of care
10 days Tue 26-05-20 Mon
08-06-20
16 5 Function 5 – Increase
of patient awareness
14 days Tue 09-06-20 Fri 26-06-20
17 5.1 Deliverable One –
Patient satisfaction –
increased awareness
8 days Tue 09-06-20 Thu
18-06-20
18 5.2 Deliverable Two –
Community
outreach survey
ensure satisfaction
of troubled pop
6 days Fri 19-06-20 Fri 26-06-20
19 5.2.1 Work Package One
– Surveying
patients with phone
and outreach
ensuring contact
6 days Fri 19-06-20 Fri 26-06-20
T W T F S S M T W T F S S M T W T F S S M T
19 Jan '20 09 Feb '20 01 Mar '20 22 Mar '20 12 Apr '20 03 May '20 24 May '20 14 Jun '20 05 Jul '20
(Figure 1: The schedule for the Project)
Project Schedule, Milestones, Quality Management Plan_2

PROJECT SCHEDULE, MILESTONES, QUALITY MANAGEMENT PLAN2
(Source: Created by author)
2. The WBS for the Project
(Figure 2: The schedule for the Project)
(Source: Created by author)
Project Schedule, Milestones, Quality Management Plan_3

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
BISY2004: Fitness APP
|23
|2855
|467

Development of Website for Cinnamon Spices Australia
|3
|460
|51

OF INVITATION TO TENDERS
|13
|384
|37

Information Systems Project Management
|1
|854
|116

Blue Bank Remote Deposit Capture Project
|6
|825
|1285

The Reflection on Project Scheduling
|4
|667
|21