Running head: KNOWLEDGE ASSESSMENT
Knowledge Assessment
National Archives of Australia
Name of the Student:
Student ID:
Name of the University:
Author’s note:

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1KNOWLEDGE ASSESSMENT
Table of Contents
Knowledge Assessment-Written Tasks...........................................................................................2
Task 1- Project Time Management..................................................................................................9
Bibliography..................................................................................................................................25
Document Page
2KNOWLEDGE ASSESSMENT
Knowledge Assessment-Written Tasks
1. Why do we use WBS for Project Management?
The project management is the analysis of the works dependent on the alignment of the
specific and smart alignment of the operations. The WBS stands for work breakdown structure
and it involves the development of the work and aligning the significant listing of functions. The
work breakdown structure would allow the division of the complete project into specific smaller
operations for ensuring that the implication of the works would be implied with the implication
and development. The WBS would be developed for ensuring the division of the smaller work
packages and it would allow the easy division of the works. The complete project would be
subdivided into smaller sub projects for ensuring the work division is aligned cohesively. The
division of the work would be helpful for ensuring the alignment of the specific work allocation
and development.
2. As a project manager, in which document do you track the schedule progress such as activities
completed, activities in program, actual start and finish dates, percentage complete, hours spent,
resource allocations, etc.
(a) Project Schedule
(b) Schedule Baseline
(c) Schedule Management Plan
(d) Schedule Network Diagram
Document Page
3KNOWLEDGE ASSESSMENT
Answer: Schedule Baseline is helpful for keeping track of schedule progress by keeping
accounts of activities completed, activities in program, actual start and finish dates, percentage
complete, hours spent, resource allocations, etc.
3. What is project baseline and what does it include?
The project baseline can be defined as the implication for storing the scheduled values
estimated at the project planning method to act as a reference point.
The project baseline includes the values of schedule, cost, and resource usage that had
been estimated at the initial planning phase. It helps in keeping track of the project progress
enabling whether the project would be completed successfully.
4. Describe how to use milestone tracking as a means of measuring project progress.
The milestone tracking is helpful for enabling the use of tracking methods like checklist,
documentation, and log books for analyzing the progress of the project. The milestone
identification would be done considering the practical perspective of the work. The achievement
of the specific points would be dependent on the alignment of the works and formation of the
smart work development and alignment of the successive work development. The use of the
milestone tracking would be helpful for defining the project milestones, overseeing the project
progress, and identifying the project status. The completion of the project activities would be
implied with the listing of the activities and forming the utilization and information listing for the
operations.
5. What is the percent complete approach to measuring project progress?

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4KNOWLEDGE ASSESSMENT
The project progress would be completed with the formation and listing the application
management. The percent complete approach would be effectively measures with the formation
of the works and allocation of the smart management works. The complete approach would be
implied with the functional listing of the works. The project progress would be effectively
implied with the continuation of the works and development of the implied management works.
The measurement of the project progress would be implied with the continuation management.
The completion of the project would be effectively managed with the utilization management
formation. The measurement of the project progress would be implied for the successful listing
of the alignment management.
6. What is cost variance?
The cost variance is the value difference between the cost’s actual management and the
budgeted amount of utilization. The cost variance calculation would be aligned with implication
management and utilization of the factors. The completion of the smart and effective
management would be implied with the listing of the cost variance calculation. The cost variance
calculation would be required for aligning the management of the information and taking care of
the conceptive management of the works. The calculation of the cost variance is done by
subtracting actual cost from earned value.
CV=EV-AC
Hence, for over budgeted projects, CV would be negative whereas under budgeted
project would have positive value. The value ‘0’ of CV would be helpful for ensuring that the
project final budget and estimated budget is same.
7. What happens during execution phase of the project?
Document Page
5KNOWLEDGE ASSESSMENT
The execution phase is characterized by the use of the proper documents like project
charter, schedule, resource usage, cost budget, risk management plan, and design for achieving
the final output of the project. The development of the works would be effectively implied with
the continuation of the effective work experience. The execution phase involves the
simplification of the improved work experience for forming the utilization management. The
formation of the works would be supported by the utilization of the works and formation of the
smart work development. The project execution would be aligned with the formation of the
implication management. The project execution would be effectively implied for taking care of
the factors for managing the development model. The execution phase would be responsible for
executing the works and forming the successful implication of the works.
8. John is managing a project. The project is three quarters done when the site engineer reports
that due to inherent complexities in a certain task the deliverables would get delayed. This would
involve additional analysis and then implementation. He requests that this new work that was not
envisaged earlier be added to the scope and also the time be added to the schedule. You and the
site engineer have analyzed the impact of this change to cost and have written up a change
request approval from the change control board. Just today you have received approval from the
change control board – what should be the immediate course of action?
(a) Start Work immediately
(b) Ascertain the impact of this change to scope, schedule, and cost before making any change
(c) Perform Quality Assurance
(d) Make sure that the scope baseline and schedule baseline are update to reflect the approved
change before implementing the change
Document Page
6KNOWLEDGE ASSESSMENT
Answer: (d) Make sure that the scope baseline and schedule baseline are update to reflect the
approved change before implementing the change
9. The project time management process consists of following seven processes:
a. Define Activities
b. Develop Schedule
c. Plan Schedule Activities
d. Sequence Activities
e. Estimate Activity Durations
f. Estimate Activity Resources
g. Control Schedule
The correct sequence is:
(a) a-b-c-d-e-f-g
(b) c-a-d-f-e-b-g
(c) b-a-c-d-e-f-g
(d) b-c-a-d-f-e-g
Answer: (b) c-a-d-f-e-b-g
10. The representation of the plan for executing the project’s activities including durations,
dependencies, and other planning information, used to produce project schedule along with other
scheduling artifacts is known as:

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7KNOWLEDGE ASSESSMENT
(a) Schedule Compression
(b) Schedule Model
(c) Schedule Data
(d) None of the above
Answer: (b) Schedule Model
11. The method of estimating project duration or cost by aggregating the estimated of the lower-
level components of the WBS is known as:
(a) Alternative Analysis
(b) Bottom-up Estimating
(c) Parametric Estimating
(d) Three-point Estimating
Answer: (b) Bottom-up Estimating
12. During project execution, a work item has taken twice as long as the estimation. The
estimates were provided for by the Project Architect and an external consultant. The client has
asked if the deadline can be brought forward by a week. Which of the following actions can you
take?
(a) Use the triangle of constraints to understand and explain to the client that if the deadline is
brought forward the scope and/or cost will increase
(b) Analyze the risk and add it to the Risk Breakdown Structure
Document Page
8KNOWLEDGE ASSESSMENT
(c) Use the Delphi Method to determine if this request can be accommodated
(d) Provide the client with the new schedule and communicate the risk of bringing forward the
deadline
Answer: (d) Provide the client with the new schedule and communicate the risk of bringing
forward the deadline
13. During a work breakdown structure meeting you have decomposed the deliverable into the
work packages and created your WBS dictionary. However, you now want to decompose the
work packages to assist you in estimating, executing, and control the project. These decomposed
work packages are called?
(a) Milestone
(b) Work packages can’t be decomposed into smaller units
(c) Activities
(d) Control Accounts
Answer: (c) Activities
14. As the project manager of a project, you needed to estimate certain activity duration before
team members were acquired. In acquisition of the project team, you find that the actual
competency levels of the acquired team members are much lower than what you had anticipated.
In such a case, you will:
(a) Make no changes to the schedule
Document Page
9KNOWLEDGE ASSESSMENT
(b) Make changes to the activity duration and schedule incorporating the changed competency
levels
(c) Inform the customer that the project is behind schedule
(d) Ask the project team members to meet the original schedule by putting in overtime if
required
Answer: (b) Make changes to the activity duration and schedule incorporating the changed
competency levels
15. A Project Manager has finalized scope baseline and started to define activities using
company’s templates and procedures. What is missing to complete the work?
(a) Organizational Process Assets
(b) Enterprise Environmental Factors
(c) Requirements documentation
(d) Activity List
Answer: (d) Activity List
Task 1- Project Time Management
a. Work Breakdown Structure
The work breakdown structure would allow the division of the complete project into
specific smaller operations for ensuring that the implication of the works would be implied with
the implication and development. The WBS would be developed for ensuring the division of the

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10KNOWLEDGE ASSESSMENT
smaller work packages and it would allow the easy division of the works. The following diagram
would show the work breakdown structure for the project,
Document Page
11KNOWLEDGE ASSESSMENT
Redevelopment of
Website for National
Archives of Australia
Initiation Phase Planning Designing Execution Testing and Monitoring Closing
Requirement
Analysis
Charter
Documentation
Submission of
documents
Sign off
Activity Scheduling
Listing of tasks
Completion of Plan
Plan Approval
Website Design
Platform Selection
UI Graphics are
made
Font is selected
Content is listed
Complete
Designing
Design Approval
UI is made
Functions are made
Website Database
is made
Website Domain is
bought
Privacy Policy is
made
Security functions
are made
Integration of work
functions
Complete Website
is made
Website Approved
Simulation
Alpha testing
Beta testing
Testing Completed
Website Domain is
fixed
Go Live of Website
Final
Documentation
Submission of
documents
Sign off
Closure
Document Page
12KNOWLEDGE ASSESSMENT
b. Project Schedule
The project schedule has been developed using the implication of the project adaptive
modulation development management. The scheduling of the adaptive framework would be
effectively implied with the successful completion of the works. The scheduling of the works
would be effectively developed compiling the management of the works would be effectively
managed with the successful alignment of the works and formation of the successful work
development. The project schedule has been divided into the following phases,
Initiation Phase: The first phase of the project development and it would be effectively
implied with the formation of the smart development of works. The initiation phase involves the
accumulation of the information and the alignment of the works cohesively. The utilization of
the activities like requirement analysis, charter documentation, submission of documents, and
sign off are considered in this phase.
Planning: The planning is the second phase of the project operations including the
development of the activities that are required for execution for project. The planning phase
would involve the identification of the works that are required in the latter phases. The planning
phase involves the activities of activity scheduling, listing of tasks, completion of plan, and plan
approval.
Designing: The designing is the third phase of the project operations that is being made
for making the new design of the website. The website development would be effectively
developed for entrapping the new features and programs in a new design. The design
development would be effectively implied with the involvement of the functions and activities

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13KNOWLEDGE ASSESSMENT
like website design platform selection, UI graphics are made, font is selected, content is listed,
complete designing, and design approval.
Execution: It is the most crucial phase of the project activities as the main generation of
the output is being done in this phase only. The execution of project activities that had been
developed with the consideration of the smart project completion management would be implied
with the consideration of the smart management processing. The activities included in this phase
involves the UI is made, functions are made, website database is made, website domain is
bought, privacy policy is made, security functions are made, integration of work functions,
complete website is made, and website approved.
Testing and Monitoring: This phase is characterized by the analysis of the work
requirements and the output of the project works. The testing and monitoring of the project
outcomes would be effectively implied with the formation of the activities like Simulation,
Alpha testing, Beta testing, and Testing Completed. The completion of this phase would involve
the completion of the works and forming the alignment of the works dependent on the alignment
of the work development.
Closing: The final phase of the project that would involve the activities of website
domain is fixed, go live of website, final documentation, submission of documents, sign off, and
closure. The completion of the phase would be helpful for documenting the project activities so
that it can be used for future references. The project report would serve as the final project
completion work.
WB
S Task Name Duration Start Finish
0 Redevelopment of Website for National Archives 30 days Mon Fri 1/11/19
Document Page
14KNOWLEDGE ASSESSMENT
of Australia 12/3/18
1 Initiation Phase 7 days Mon
12/3/18
Tue
12/11/18
1.1 Requirement Analysis 2 days Mon 12/3/18 Tue 12/4/18
1.2 Charter Documentation 4 days Wed 12/5/18 Mon
12/10/18
1.3 Submission of documents 1 day Tue
12/11/18
Tue
12/11/18
M1 Sign off 0 days Tue
12/11/18
Tue
12/11/18
2 Planning 7 days Wed
12/5/18
Thu
12/13/18
2.1 Activity Scheduling 3 days Wed 12/5/18 Fri 12/7/18
2.2 Listing of tasks 4 days Mon
12/10/18
Thu
12/13/18
2.3 Completion of Plan 7 days Wed 12/5/18 Thu
12/13/18
M2 Plan Approval 0 days Thu
12/13/18
Thu
12/13/18
3 Designing 6 days Fri 12/14/18 Fri 12/21/18
3.1 Website Design Platform Selection 2 days Fri 12/14/18 Mon
12/17/18
3.2 UI Graphics are made 3 days Wed
12/19/18 Fri 12/21/18
3.3 Font is selected 1 day Tue
12/18/18
Tue
12/18/18
3.4 Content is listed 3 days Wed
12/19/18 Fri 12/21/18
3.5 Complete Designing 6 days Fri 12/14/18 Fri 12/21/18
M3 Design Approval 0 days Fri 12/21/18 Fri 12/21/18
4 Execution 15 days Tue
12/18/18 Mon 1/7/19
4.1 UI is made 5 days Mon Fri 12/28/18
Document Page
15KNOWLEDGE ASSESSMENT
12/24/18
4.2 Functions are made 4 days Tue
12/18/18 Fri 12/21/18
4.3 Website Database is made 3 days Mon
12/24/18
Wed
12/26/18
4.4 Website Domain is bought 1 day Thu
12/27/18
Thu
12/27/18
4.5 Privacy Policy is made 3 days Mon
12/24/18
Wed
12/26/18
4.6 Security functions are made 4 days Thu
12/27/18 Tue 1/1/19
4.7 Integration of work functions 3 days Wed 1/2/19 Fri 1/4/19
4.8 Complete Website is made 8 days Thu
12/27/18 Mon 1/7/19
M4 Website Approved 0 days Mon 1/7/19 Mon 1/7/19
5 Testing and Monitoring 9 days Mon
12/24/18 Thu 1/3/19
5.1 Simulation 3 days Mon
12/24/18
Wed
12/26/18
5.2 Alpha testing 2 days Thu
12/27/18 Fri 12/28/18
5.3 Beta testing 2 days Wed 1/2/19 Thu 1/3/19
M5 Testing Completed 0 days Thu 1/3/19 Thu 1/3/19
6 Closing 11 days Fri 12/28/18 Fri 1/11/19
6.1 Website Domain is fixed 2 days Fri 12/28/18 Mon
12/31/18
6.2 Go Live of Website 2 days Tue 1/1/19 Wed 1/2/19
6.3 Final Documentation 4 days Fri 1/4/19 Wed 1/9/19
6.4 Submission of documents 1 day Thu 1/10/19 Thu 1/10/19
6.5 Sign off 1 day Fri 1/11/19 Fri 1/11/19
M6 Closure 0 days Fri 1/11/19 Fri 1/11/19

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16KNOWLEDGE ASSESSMENT
Document Page
17KNOWLEDGE ASSESSMENT
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Redevelopment of Website
for National Archives of
Australia
30 days Mon 12/3/18 Fri 1/11/19
1 1 Initiation Phase 7 days Mon 12/3/18 Tue 12/11/18
2 1.1 Requirement Analysis 2 days Mon 12/3/18 Tue 12/4/18
3 1.2 Charter Documentation 4 days Wed 12/5/18 Mon 12/10/18
4 1.3 Submission of documents 1 day Tue 12/11/18 Tue 12/11/18
5 M1 Sign off 0 days Tue 12/11/18 Tue 12/11/18
6 2 Planning 7 days Wed 12/5/18 Thu 12/13/18
7 2.1 Activity Scheduling 3 days Wed 12/5/18 Fri 12/7/18
8 2.2 Listing of tasks 4 days Mon 12/10/18 Thu 12/13/18
9 2.3 Completion of Plan 7 days Wed 12/5/18 Thu 12/13/18
10 M2 Plan Approval 0 days Thu 12/13/18 Thu 12/13/18
11 3 Designing 6 days Fri 12/14/18 Fri 12/21/18
12 3.1 Website Design Platform
Selection
2 days Fri 12/14/18 Mon 12/17/18
13 3.2 UI Graphics are made 3 days Wed 12/19/18 Fri 12/21/18
14 3.3 Font is selected 1 day Tue 12/18/18 Tue 12/18/18
15 3.4 Content is listed 3 days Wed 12/19/18 Fri 12/21/18
16 3.5 Complete Designing 6 days Fri 12/14/18 Fri 12/21/18
17 M3 Design Approval 0 days Fri 12/21/18 Fri 12/21/18
18 4 Execution 15 days Tue 12/18/18 Mon 1/7/19
19 4.1 UI is made 5 days Mon 12/24/18 Fri 12/28/18
20 4.2 Functions are made 4 days Tue 12/18/18 Fri 12/21/18
21 4.3 Website Database is made 3 days Mon 12/24/18 Wed 12/26/18
22 4.4 Website Domain is bought 1 day Thu 12/27/18 Thu 12/27/18
23 4.5 Privacy Policy is made 3 days Mon 12/24/18 Wed 12/26/18
24 4.6 Security functions are made4 days Thu 12/27/18 Tue 1/1/19
25 4.7 Integration of work functions3 days Wed 1/2/19 Fri 1/4/19
26 4.8 Complete Website is made 8 days Thu 12/27/18 Mon 1/7/19
27 M4 Website Approved 0 days Mon 1/7/19 Mon 1/7/19
28 5 Testing and Monitoring 9 days Mon 12/24/18 Thu 1/3/19
29 5.1 Simulation 3 days Mon 12/24/18 Wed 12/26/18
30 5.2 Alpha testing 2 days Thu 12/27/18 Fri 12/28/18
31 5.3 Beta testing 2 days Wed 1/2/19 Thu 1/3/19
32 M5 Testing Completed 0 days Thu 1/3/19 Thu 1/3/19
33 6 Closing 11 days Fri 12/28/18 Fri 1/11/19
34 6.1 Website Domain is fixed 2 days Fri 12/28/18 Mon 12/31/18
35 6.2 Go Live of Website 2 days Tue 1/1/19 Wed 1/2/19
36 6.3 Final Documentation 4 days Fri 1/4/19 Wed 1/9/19
37 6.4 Submission of documents 1 day Thu 1/10/19 Thu 1/10/19
38 6.5 Sign off 1 day Fri 1/11/19 Fri 1/11/19
39 M6 Closure 0 days Fri 1/11/19 Fri 1/11/19
Analyst
Documenter
Documenter
12/11
Planner
Planner
Project Manager
12/13
Designer
Graphicians
Graphicians
Database Admin
Engineer
12/21
Designer
Programmer
Database Admin
Developer
Network Engineer
Network Engineer
Developer
Engineer
1/7
Tester
Tester
Tester
1/3
Vendor
Vendor
Documenter
Documenter
Project Manager
1/11
T S W S T M F T S W
Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19 Mar 10, '19
Document Page
18KNOWLEDGE ASSESSMENT
c. Critical Path
The project has been developed using the alignment of the effective and smart work development
model. The critical path of project comprise of those tasks that cannot be executed with each
other and sum of their individual durations would provide the final project duration. The critical
path is identified as the activities aligning with the progress of the project and developing the
final outcome of the project. The identified critical path for the project is given in the following
table and diagram,
WBS Task Name Duration
1.1 Requirement Analysis 2 days
2.1 Activity Scheduling 3 days
2.2 Listing of tasks 4 days
2.3 Completion of Plan 7 days
M2 Plan Approval 0 days
3.1 Website Design Platform Selection 2 days
4.2 Functions are made 4 days
4.5 Privacy Policy is made 3 days
4.6 Security functions are made 4 days
5.3 Beta testing 2 days
M5 Testing Completed 0 days
6.3 Final Documentation 4 days
6.4 Submission of documents 1 day
6.5 Sign off 1 day
M6 Closure 0 days

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
19KNOWLEDGE ASSESSMENT
ID Task
Mode
WBS Task Name Duration
2 1.1 Requirement Analysis 2 days
7 2.1 Activity Scheduling 3 days
8 2.2 Listing of tasks 4 days
9 2.3 Completion of Plan 7 days
10 M2 Plan Approval 0 days
12 3.1 Website Design Platform
Selection
2 days
20 4.2 Functions are made 4 days
23 4.5 Privacy Policy is made 3 days
24 4.6 Security functions are made4 days
31 5.3 Beta testing 2 days
32 M5 Testing Completed 0 days
36 6.3 Final Documentation 4 days
37 6.4 Submission of documents 1 day
38 6.5 Sign off 1 day
39 M6 Closure 0 days
Analyst
Planner
Planner
Project Manager
12/13
Designer
Programmer
Network Engineer
Network Engineer
Tester
1/3
Documenter
Documenter
Project Manager
1/11
S T T S M W F S T T S M W F S T T S M W F S T T S
Dec 2, '18 Dec 9, '18 Dec 16, '18 Dec 23, '18 Dec 30, '18 Jan 6, '19 Jan 13, '19 Jan 20, '19
Critical Path Description: The critical path of the project include the activities of Requirement
Analysis, Activity Scheduling, Listing of tasks, Completion of Plan, Website Design Platform
Selection, Functions are made, Privacy Policy is made, Security functions are made, Beta testing,
Final Documentation, Submission of documents, and Sign off. The completion of these activities
and the duration would be implied with the formation of the work that has been successfully. The
integration would be effectively developed for integrating the alignment management. The
summarization of the activities and the key listing would be implied with the development.
d. Communication of schedule baseline
The communication of the schedule baseline would be effectively developed considering
the utilization of the factors. Schedule Baseline is helpful for keeping track of schedule progress
by keeping accounts of activities completed, activities in program, actual start and finish dates,
percentage complete, hours spent, and resource allocations. The project baseline includes the
Document Page
20KNOWLEDGE ASSESSMENT
values of schedule, cost, and resource usage that had been estimated at the initial planning phase.
It helps in keeping track of the project progress enabling whether the project would be completed
successfully. The schedule baseline date of 31st December 2018 has been selected for calculation
of the baseline schedule. The following Gantt chart has been set for the baseline schedule for the
date of 31st December,
Document Page
21KNOWLEDGE ASSESSMENT
ID Task
Mode
WBS Task Name %
Complete
Duration
0 0 Redevelopment of Website
for National Archives of
Australia_Baseline Schedule
77% 30 days
1 1 Initiation Phase 100% 7 days
2 1.1 Requirement Analysis 100% 2 days
3 1.2 Charter Documentation 100% 4 days
4 1.3 Submission of documents 100% 1 day
5 M1 Sign off 100% 0 days
6 2 Planning 100% 7 days
7 2.1 Activity Scheduling 100% 3 days
8 2.2 Listing of tasks 100% 4 days
9 2.3 Completion of Plan 100% 7 days
10 M2 Plan Approval 100% 0 days
11 3 Designing 100% 6 days
12 3.1 Website Design Platform
Selection
100% 2 days
13 3.2 UI Graphics are made 100% 3 days
14 3.3 Font is selected 100% 1 day
15 3.4 Content is listed 100% 3 days
16 3.5 Complete Designing 100% 6 days
17 M3 Design Approval 100% 0 days
18 4 Execution 71% 15 days
19 4.1 UI is made 100% 5 days
20 4.2 Functions are made 100% 4 days
21 4.3 Website Database is made 100% 3 days
22 4.4 Website Domain is bought 100% 1 day
23 4.5 Privacy Policy is made 100% 3 days
24 4.6 Security functions are made 75% 4 days
25 4.7 Integration of work functions 0% 3 days
26 4.8 Complete Website is made 38% 8 days
27 M4 Website Approved 0% 0 days
28 5 Testing and Monitoring 71% 9 days
29 5.1 Simulation 100% 3 days
30 5.2 Alpha testing 100% 2 days
31 5.3 Beta testing 0% 2 days
32 M5 Testing Completed 0% 0 days
33 6 Closing 20% 11 days
34 6.1 Website Domain is fixed 100% 2 days
35 6.2 Go Live of Website 0% 2 days
36 6.3 Final Documentation 0% 4 days
37 6.4 Submission of documents 0% 1 day
38 6.5 Sign off 0% 1 day
39 M6 Closure 0% 0 days
Analyst
Documenter
Documenter
12/11
Planner
Planner
Project Manager
12/13
Designer
Graphicians
Graphicians
Database Admin
Engineer
12/21
Designer
Programmer
Database Admin
Developer
Network Engineer
Network Engineer
Developer
Engineer
1/7
Tester
Tester
Tester
1/3
Vendor
Vendor
Documenter
Documenter
Project Manager
1/11
W T F S S M
Nov 18, '18 Dec 23, '18 Jan 27, '19

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
22KNOWLEDGE ASSESSMENT
e. Tracking Gantt Charts
ID Task
Mode
WBS Task Name
0 0 Redevelopment of Website
for National Archives of
Australia_Baseline Schedule
1 1 Initiation Phase
6 2 Planning
7 2.1 Activity Scheduling
8 2.2 Listing of tasks
9 2.3 Completion of Plan
10 M2 Plan Approval
11 3 Designing
12 3.1 Website Design Platform Selection
13 3.2 UI Graphics are made
14 3.3 Font is selected
15 3.4 Content is listed
16 3.5 Complete Designing
17 M3 Design Approval
18 4 Execution
19 4.1 UI is made
20 4.2 Functions are made
21 4.3 Website Database is made
22 4.4 Website Domain is bought
23 4.5 Privacy Policy is made
24 4.6 Security functions are made
25 4.7 Integration of work functions
26 4.8 Complete Website is made
27 M4 Website Approved
28 5 Testing and Monitoring
29 5.1 Simulation
30 5.2 Alpha testing
31 5.3 Beta testing
32 M5 Testing Completed
33 6 Closing
34 6.1 Website Domain is fixed
35 6.2 Go Live of Website
36 6.3 Final Documentation
37 6.4 Submission of documents
38 6.5 Sign off
39 M6 Closure
77%
100%
100%
100%
100%
100%
12/13
100%
100%
100%
100%
100%
100%
12/21
71%
100%
100%
100%
100%
100%
75%
0%
38%
1/7
71%
100%
100%
0%
1/ 3
20%
100%
0%
0%
0%
0%
1/11
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
Dec 2, '18 Dec 9, '18 Dec 16, '18 Dec 23, '18 Dec 30, '18 Jan 6, '19 Jan 13, '19
Document Page
23KNOWLEDGE ASSESSMENT
f. Time Rescheduling
The time rescheduling would be done by implying the use of the effective work
development and integrating the listing of the effective work management. The time
rescheduling would be effectively managed by the alignment of the implicit work development.
The rescheduling of the work would be effectively managed with the help of resource inclusion,
hiring contractor, and delaying the schedule. The project is largely impacted by the scope trio
constraint and the rescheduling would be largely impacted by the formation of the effective
alignment of works.
Out of the three options of rescheduling, hiring contractor would be selected as it would
help in transferring the risk of delay to an external person that would be solely responsible for
the completion of the work. The completion of the works would be highly impacted by the
formation of the smart work development. The completion of the works would be eased by
inclusion of the external people in the project.
g. What processes will you put in place to:
Measure
Record
Report Progress of activities
in relation to the schedule?
Measure: Calendar
Record: Project Log Book
Report Progress of activities: Gantt chart
Document Page
24KNOWLEDGE ASSESSMENT
h. Describe what you need to do to implement any agreed schedule changes
The following two methods must be followed for implementing any agreed schedule changes
Make sure that the scope baseline and schedule baseline are update to reflect the
approved change before implementing the change
Provide the client with the new schedule and communicate the risk of bringing forward
the deadline
i. Review Project Time Performance
The project time performance can be understood by the following tables and graphs,
WBS Task Name Duration Start Finish Predecessors
1.1 Requirement Analysis 2 days Mon 12/3/18 Tue 12/4/18
1.2 Charter Documentation 4 days Wed 12/5/18 Mon 12/10/18 2
1.3 Submission of documents 1 day Tue 12/11/18 Tue 12/11/18 3
M1 Sign off 0 days Tue 12/11/18 Tue 12/11/18 4
2.1 Activity Scheduling 3 days Wed 12/5/18 Fri 12/7/18 2
2.2 Listing of tasks 4 days Mon 12/10/18 Thu 12/13/18 7
2.3 Completion of Plan 7 days Wed 12/5/18 Thu 12/13/18 2
M2 Plan Approval 0 days Thu 12/13/18 Thu 12/13/18 8,9
3.1 Website Design Platform Selection 2 days Fri 12/14/18 Mon 12/17/18 10
3.2 UI Graphics are made 3 days Wed 12/19/18 Fri 12/21/18 12
3.3 Font is selected 1 day Tue 12/18/18 Tue 12/18/18 12
3.4 Content is listed 3 days Wed 12/19/18 Fri 12/21/18 14
3.5 Complete Designing 6 days Fri 12/14/18 Fri 12/21/18 10
M3 Design Approval 0 days Fri 12/21/18 Fri 12/21/18 16
4.1 UI is made 5 days Mon 12/24/18 Fri 12/28/18 13

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
25KNOWLEDGE ASSESSMENT
4.2 Functions are made 4 days Tue 12/18/18 Fri 12/21/18 12
4.3 Website Database is made 3 days Mon 12/24/18 Wed 12/26/18 15
4.4 Website Domain is bought 1 day Thu 12/27/18 Thu 12/27/18 21
4.5 Privacy Policy is made 3 days Mon 12/24/18 Wed 12/26/18 20
4.6 Security functions are made 4 days Thu 12/27/18 Tue 1/1/19 23
4.7 Integration of work functions 3 days Wed 1/2/19 Fri 1/4/19 19,22,24
4.8 Complete Website is made 8 days Thu 12/27/18 Mon 1/7/19 21
M4 Website Approved 0 days Mon 1/7/19 Mon 1/7/19 25,26
5.1 Simulation 3 days Mon 12/24/18 Wed 12/26/18 16
5.2 Alpha testing 2 days Thu 12/27/18 Fri 12/28/18 20
5.3 Beta testing 2 days Wed 1/2/19 Thu 1/3/19 24
M5 Testing Completed 0 days Thu 1/3/19 Thu 1/3/19 29,30,31
6.1 Website Domain is fixed 2 days Fri 12/28/18 Mon 12/31/18 22
6.2 Go Live of Website 2 days Tue 1/1/19 Wed 1/2/19 34
6.3 Final Documentation 4 days Fri 1/4/19 Wed 1/9/19 32
6.4 Submission of documents 1 day Thu 1/10/19 Thu 1/10/19 36
6.5 Sign off 1 day Fri 1/11/19 Fri 1/11/19 37
M6 Closure 0 days Fri 1/11/19 Fri 1/11/19 35,38
Now according to the given project file (or calendar list) it is possible for keeping track of
the works. The completion of the project would be listed with the help of tracking Gantt chart as
it would help in making sure that the project is working in time.
j. Time Management Issues in Project
Date Description of
problem
Recommended Action for next
time
Lesson Learnt
Raised by
Document Page
26KNOWLEDGE ASSESSMENT
10/12/201
8
Delay in
Documentation
Documentation template must be
followed
Process
Documentation
14/12/18 Website Design
Errors
Design Principles using SDLC
must be followed
Design Principle
Implication
21/12/18 Programming
Issues
External Expert must be followed Debugging of
program bugs
1/1/19 Go Live Issues Vendor must be consulted before
implementing the website
Implicational Issues
Resolution
5/12/18 Over Budget Provisional Budget would be used Budget Performance
Document Page
27KNOWLEDGE ASSESSMENT
Bibliography
Burke, R., 2013. Project management: planning and control techniques. New Jersey, USA.
Carver, C.L. and Klein, C.S., 2013. Action research: A tool for promoting faculty development
and continuous improvement in leadership preparation.
Clark, D.M., Silvester, K. and Knowles, S., 2013. Lean management systems: creating a culture
of continuous quality improvement. Journal of clinical pathology, pp.jclinpath-2013.
Cohen-Vogel, L., Tichnor-Wagner, A., Allen, D., Harrison, C., Kainz, K., Socol, A.R. and
Wang, Q., 2015. Implementing educational innovations at scale: Transforming researchers into
continuous improvement scientists. Educational Policy, 29(1), pp.257-277.
Dale, B.G. and Plunkett, J.J., 2017. Quality costing. Routledge.
Dessinger, J.C. and Moseley, J.L., 2015. Confirmative evaluation: Practical strategies for
valuing continuous improvement. John Wiley & Sons.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Fryer, K., Ogden, S. and Anthony, J., 2013. Bessant's continuous improvement model: revisiting
and revising. International Journal of Public Sector Management, 26(6), pp.481-494.
Fuller, M.A., Valacich, J.S., George, J.F. and Schneider, C., 2017. Information Systems Project
Management: A Process and Team Approach, Edition 1.1. Prospect Press.
Goetsch, D.L. and Davis, S.B., 2014. Quality management for organizational excellence. Upper
Saddle River, NJ: pearson.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
28KNOWLEDGE ASSESSMENT
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Holtskog, H., 2013. Continuous Improvement beyond the Lean understanding. Procedia
CIRP, 7, pp.575-579.
Hwang, B.G. and Ng, W.J., 2013. Project management knowledge and skills for green
construction: Overcoming challenges. International Journal of Project Management, 31(2),
pp.272-284.
Intra, C. and Zahn, T., 2014. Transformation-waves–a brick for a powerful and holistic
continuous improvement process of a Lean production system. Procedia CIRP, 17, pp.582-587.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Kerzner, H., 2018. Project management best practices: Achieving global excellence. John Wiley
& Sons.
Lam, M., O'Donnell, M. and Robertson, D., 2015. Achieving employee commitment for
continuous improvement initiatives. International Journal of Operations & Production
Management, 35(2), pp.201-215.
Larson, E.W., Gray, C.F., Danlin, U., Honig, B. and Bacarini, D., 2014. Project management:
The managerial process (Vol. 6). Grandview Heights, OH: McGraw-Hill Education.
Leach, L.P., 2014. Critical chain project management. Artech House.
Document Page
29KNOWLEDGE ASSESSMENT
Lemire, M., Demers-Payette, O. and Jefferson-Falardeau, J., 2013. Dissemination of
performance information and continuous improvement: a narrative systematic review. Journal of
health organization and management, 27(4), pp.449-478.
Magar, V.M. and Shinde, V.B., 2014. Application of 7 quality control (7 QC) tools for
continuous improvement of manufacturing processes. International Journal of Engineering
Research and General Science, 2(4), pp.364-371.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Mitra, A., 2016. Fundamentals of quality control and improvement. John Wiley & Sons.
Nadeem, E., Olin, S.S., Hill, L.C., Hoagwood, K.E. and Horwitz, S.M., 2013. Understanding the
components of quality improvement collaboratives: a systematic literature review. The Milbank
Quarterly, 91(2), pp.354-394.
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Routledge.
Oakland, J.S., 2014. Total quality management and operational excellence: text with cases.
Routledge.
Okongwu, U., Morimoto, R. and Lauras, M., 2013. The maturity of supply chain sustainability
disclosure from a continuous improvement perspective. International Journal of Productivity
and Performance Management, 62(8), pp.827-855.
Document Page
30KNOWLEDGE ASSESSMENT
Owen, M., 2013. SPC and continuous improvement. Springer Science & Business Media.
Ross, J.E., 2017. Total quality management: Text, cases, and readings. Routledge.
Sahno, J., Shevtshenko, E., Karaulova, T. and Tahera, K., 2015. Framework for continuous
improvement of production processes. Engineering Economics, 26(2), pp.169-180.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Singh, J. and Singh, H., 2015. Continuous improvement philosophy–literature review and
directions. Benchmarking: An International Journal, 22(1), pp.75-119.
Swartling, D. and Poksinska, B., 2013. Management initiation of continuous improvement from
a motivational perspective. Journal of Applied Economics and Business Research, 3(2), pp.81-
94.
von Thiele Schwarz, U., Augustsson, H., Hasson, H. and Stenfors-Hayes, T., 2015. Promoting
employee health by integrating health protection, health promotion, and continuous
improvement: a longitudinal quasi-experimental intervention study. Journal of Occupational and
Environmental medicine, 57(2), pp.217-225.
Walker, A., 2015. Project management in construction. John Wiley & Sons.