This article provides information on the bill of quantities and general conditions for rehabilitation work, including details on groundworks, concrete, formwork, reinforcement, structural timber, and more. It also outlines the various conditions and requirements that contractors must adhere to when performing this type of work.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
TAKE - OF LIST PROJECT:. TRADE: ItemASMM5 reference Groundworks stabilization of the groundCl. 3.3.2 j Taking the measurement of the site excavationCl. 5.1 foundation workCl. section f load testCl. section g Concrete, formwork and reinforcement preparation of appropriate concrete mixCl. 10.2 Suitable bending of the reinforcement barsCl. section j applicable cutting of the barsCl. 11.2.3.2 (d) Structural timber inspection of the quality of the timberCl. 8.2 making the frame of the doors and windowsCl. .4 - V joining the timber edges warilyCl. 8.2.1 creating the frame work for insulationCl. 13.3 e
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Bill of quantities Basically in QS bill of quantities are the information of work, dimension, work among other information which are needed for the erection of a building by the contract. The major design of a work basically the rehabilitation is managed on documentation survey, tests and investigations as done by the described work. These described may include the following; i.Disassembling as well as devolution of walls partitions, reinforced concrete slabs on the ground having assistant flooring, spoiled flooring on slabs which are very stable, this will actually knock off ceramic tiles and damaged mortar. ii.Concreting, Excavations and insulating operates for work of construction of groundwork walls, lightingshafts and columns. iii.Construction of fresh slabs of protected concrete on the foundation auxiliary groundwork walls and column. iv.Building of new wall partition as a substitute of the disinterested ones also basement walls having lighting shafts v.Putting of a new finishing and flooring of walls and ceilings in the la-di-da parts of the building, vi.Substitution of old sanitary components with new ones on the ground with new ones of a toilet for physically challenged individual persons, vii.Substitution of damaged door and windows in the underground room and some parts of the floor of the ground.
viii.Substitution of derelict steel staircase amid the ground floor and basement. ix.Substitution of components of electrical installation in rooms where the walls are destroyed and then reconstructed, x.Painting and dissembling of painting and radiators of crucial reassembling of radiators and heating pipelines on some part of the groundwork. Several additional works defined in detail in the Bill of Quantities All the operations are described in the information in the Bill of Quantities therefore the key design of rehabilitation. GENERAL CONDITIONS AND WORK EXECUTION CONDITIONS •In all the operations whichshouldbe done itshouldbeacceptedthat thetemporary workerhas includedwithin theunitcostof theestimatedchargeofamountsall requiredpreliminaryand finishing work, any surpluses andunexpectedwork thatmightneed tobe performed toguaranteetallquality of performed work and the completion of thetaskagreeingto standingdirections,standardsand guidelines. •Thetemporary workershouldbecommittedto inducefamiliarized in aconvenientandnitty grittyway with the building, required work and the Bill ofAmountsbased on which the contracted workshouldbe performed and toinquirethe contractingspecialistin anopportunewayfor all and any clarifications with respect toinsulantindicatedthingson theChargeof Quantities. •Thetemporary workermightbecommittedto perform contracted work in awayandinsidethedue datesindicatedwithin thecontract,directionsand rules of thecalling. •Thetemporary workershouldbe considered competent and experiencedwhichthe examination of the building hasgivenhim with anexactgaugeof the scope andsortof work that must be performed in arrangeto hand over the building to theclientin acompletelyutilitarianstate in terms offundamental restorationwork.
•Thetemporary workermightmoreoverbecommittedto perform all and anyunexpectedwork. The costbuilt upwithin theadd up tosumshouldnot be changed due to surpluses ordeficienciesor unexpectedwork of any kind. •The ‘turnkey’arrangementwithin thecontract and othercomparablephrasesshouldinvolvethat the costshouldtooincorporatetheesteemof allunexpectedwork andexcessworkwhichthe contracted costshouldnot beinfluencedby anydeficiencyof work. •All work must becompletelycompleted and the buildingshouldbegivenover ready-to-use; this shouldbe considered as includedwithin thecontractedcost. •Wholework must be performed professionally andabsolutely.Earliertoutilizeall materialsshouldbe checked andaffirmedforutilizeby theBoss, and all and anycomplaintsand orders theBossshouldhave inseeof the quality of work or materialsmightbeofficialfor theTemporary worker. •Itmightbe considered that theTemporary worker, after having familiarized himself with theterritory and building inaddress, has includedwithin thecostallconceivableuncommonconditions and circumstancesbeneathwhich the work inaddressmightbe performed in compliance with the specializeddirectionsfor theexecutionof anysortof work.