This report discusses the implementation plan, tools and techniques for monitoring and control process, project performance evaluation and project closure groups of project management in context to the Renovation project of Royale Pizza. The report also includes the management structure, management style and culture, levels and boundaries of authority & autonomy and attributes & characteristics of project stakeholders, monitoring and control process, project performance evaluation, and project closure steps/tools required to close the project (post-project activities).
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
REPORT OVERVIEW
This report going to discuss implementation plan, tools and techniques for monitoring and
control process, project performance evaluation and project closure groups of project
management in a detailed manner in context to the Renovation project of Royale Pizza.
IMPLEMENTATION PLAN
Conditions required for successful project implementation
The support of shop owner/senior management has required for successful project
implementation.
Proper implementation planning
Judicious equipment procurement
Timely availability of funds
Effective project evaluation and monitoring should be performed by the Project Manager
throughout the project life cycle.
The project team members should be skilled and capable to complete shop renovation within
the estimated budget and time otherwise; the contractor will have to pay AU$300 to the shop
owner as a daily penalty.
The safety inspection would be performed every fortnight and it will take at least four hours.
So, the inspection time and cost should be included in the implementation plan.
The project should be completed in 4 months with AU$ 14,000 budgets.
Actions required for successful project implementation
#1 Actions Resources Project
Status
Notes
Design phase Identify project team
members and assign
responsibilities to them
Project Manager,
Project
Completed _
The layout of the
construction and
renovation project
Architect, designing
tools
Completed _
Identification of raw
materials and equipment’s
required
Technical Manager,
Project Manager
Completed _
#2 Procurement
and delivery
Purchase construction
material (woods, wires,
water, sand, cement)
Equipment suppliers Completed _
Procurement of
1. Deep fryers (3)
2. Dough Rollers (1)
3. Paint
4. Air conditioner
5. Sales system
license
Contractor,
Equipment suppliers
Completed _
This report going to discuss implementation plan, tools and techniques for monitoring and
control process, project performance evaluation and project closure groups of project
management in a detailed manner in context to the Renovation project of Royale Pizza.
IMPLEMENTATION PLAN
Conditions required for successful project implementation
The support of shop owner/senior management has required for successful project
implementation.
Proper implementation planning
Judicious equipment procurement
Timely availability of funds
Effective project evaluation and monitoring should be performed by the Project Manager
throughout the project life cycle.
The project team members should be skilled and capable to complete shop renovation within
the estimated budget and time otherwise; the contractor will have to pay AU$300 to the shop
owner as a daily penalty.
The safety inspection would be performed every fortnight and it will take at least four hours.
So, the inspection time and cost should be included in the implementation plan.
The project should be completed in 4 months with AU$ 14,000 budgets.
Actions required for successful project implementation
#1 Actions Resources Project
Status
Notes
Design phase Identify project team
members and assign
responsibilities to them
Project Manager,
Project
Completed _
The layout of the
construction and
renovation project
Architect, designing
tools
Completed _
Identification of raw
materials and equipment’s
required
Technical Manager,
Project Manager
Completed _
#2 Procurement
and delivery
Purchase construction
material (woods, wires,
water, sand, cement)
Equipment suppliers Completed _
Procurement of
1. Deep fryers (3)
2. Dough Rollers (1)
3. Paint
4. Air conditioner
5. Sales system
license
Contractor,
Equipment suppliers
Completed _
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
6. Software
7. Hardware
#3 Construction Remove wires under the
Rear Stairs
Purchased material,
Contractor, electrician
_ _
Remove rear stairs Purchased material,
Contractor, Installers,
Technical, and safety
compliance
certification bodies
_ _
Staircase repairing Purchased material,
Contractor, Installers
_ _
Flooring Purchased material,
Contractor, Installers
_ _
Increase space for dining Purchased material,
Contractor, Installers,
Technical, and safety
compliance
certification bodies
_ _
Wiring installation Purchased material,
Contractor, Installers,
Technical, and safety
compliance
certification bodies
_ _
#4 Installation Dust free painting Painters _ _
Installation of air
conditioner
Installers _ _
Increase the capacity of the
compressor
Kitchen cleaning
professionals
_ _
Clean exhaust hood system
cleaning
Kitchen cleaning
professionals
_ _
Test and install the
viability of sale system
with hardware and
software
Sales system license,
Technical manager
_ _
7. Hardware
#3 Construction Remove wires under the
Rear Stairs
Purchased material,
Contractor, electrician
_ _
Remove rear stairs Purchased material,
Contractor, Installers,
Technical, and safety
compliance
certification bodies
_ _
Staircase repairing Purchased material,
Contractor, Installers
_ _
Flooring Purchased material,
Contractor, Installers
_ _
Increase space for dining Purchased material,
Contractor, Installers,
Technical, and safety
compliance
certification bodies
_ _
Wiring installation Purchased material,
Contractor, Installers,
Technical, and safety
compliance
certification bodies
_ _
#4 Installation Dust free painting Painters _ _
Installation of air
conditioner
Installers _ _
Increase the capacity of the
compressor
Kitchen cleaning
professionals
_ _
Clean exhaust hood system
cleaning
Kitchen cleaning
professionals
_ _
Test and install the
viability of sale system
with hardware and
software
Sales system license,
Technical manager
_ _
#5 Project
performance
evaluation
Planning Project Manager,
Project
documentation, all
project stakeholders
_ _
Implementation
Reporting
#6 Project
closure
Lessons learned Project Manager,
Project
- -
Relieve team members
Management structure
Management structure will be preferred in which the project manager has a high level of authority to
control and manage project resources.
Management Style and culture
Autocratic management style and culture have been used for this renovation project because tasks
and objectives are set and the project team is expected to do exactly as needed. In this type of
management style, all project team members will be dependent on the supervision of Project
Manager. The benefit of this style is that it will allow the Project Manager to maintain organizational
consistency. The main drawback of this approach is that the success of the project depends on the
efficiency of a leader (Project Manager). Moreover, if the Project Manager will make the wrong
decisions, then it might result in satisfaction among project team members1.
1 Annebel H.B. De Hoogh, Lindred L. Greer and Deanne N. Den Hartog, "Diabolical Dictators Or
Capable Commanders? An Investigation Of The Differential Effects Of Autocratic Leadership On
Team Performance" (2015) 26(5) The Leadership Quarterly.
Shop supervisor
Project Manager
Contractors Installers Technical
Manager
Kitchen cleaning
professionals
Equipment
suppliers
Technical and
safety compliance
certification
bodies
performance
evaluation
Planning Project Manager,
Project
documentation, all
project stakeholders
_ _
Implementation
Reporting
#6 Project
closure
Lessons learned Project Manager,
Project
- -
Relieve team members
Management structure
Management structure will be preferred in which the project manager has a high level of authority to
control and manage project resources.
Management Style and culture
Autocratic management style and culture have been used for this renovation project because tasks
and objectives are set and the project team is expected to do exactly as needed. In this type of
management style, all project team members will be dependent on the supervision of Project
Manager. The benefit of this style is that it will allow the Project Manager to maintain organizational
consistency. The main drawback of this approach is that the success of the project depends on the
efficiency of a leader (Project Manager). Moreover, if the Project Manager will make the wrong
decisions, then it might result in satisfaction among project team members1.
1 Annebel H.B. De Hoogh, Lindred L. Greer and Deanne N. Den Hartog, "Diabolical Dictators Or
Capable Commanders? An Investigation Of The Differential Effects Of Autocratic Leadership On
Team Performance" (2015) 26(5) The Leadership Quarterly.
Shop supervisor
Project Manager
Contractors Installers Technical
Manager
Kitchen cleaning
professionals
Equipment
suppliers
Technical and
safety compliance
certification
bodies
Levels and boundaries of authority & autonomy and attributes & characteristics of project
stakeholders
Project
stakeholders
Authority
level
Autonomy
level
Responsibilities Attributes and
characteristics of
project stakeholders
Project Manager High
(Controlling
)
Medium
(Coordinating)
Assign
responsibilities
to project
team2
Controlling
and directing
project
execution
Project
document
Project
planning
Manager and
leader
Goal oriented
Knowledge
about project
Can deal with
ambiguity,
chaos, and
stress
Effective
communicator
Coordinator
and facilitator
Technical
Manager
Medium
(Guiding) 3
Medium
(Guiding)
To assist shop
re-design,
procurement,
sourcing, and
installation of
new
equipment.
Technical
credibility
Innovator
Facilitator
Coordinator
Contractor Medium
(Guiding)
Medium
(Guiding)
To make sure
that wires
should be
taken carefully
by installers
when
removing
stairs
Facilitator
Coordinator
Balanced
participation
in the project
Job expertise
Equipment
suppliers
Low Medium Supply
material
Facilitator
Coordinator
Balanced
participation
2 Sergio Jiménez, Fernando Fernández and Daniel Borrajo, "INTEGRATING PLANNING,
EXECUTION, AND LEARNING TO IMPROVE PLAN EXECUTION" (2012) 29(1) Computational
Intelligence.
3 Nikos Macheridis, "Balancing Authority And Autonomy In Higher Education By Implementing An
Agile Project Management Approach" (2017) 24(2) Tertiary Education and Management.
stakeholders
Project
stakeholders
Authority
level
Autonomy
level
Responsibilities Attributes and
characteristics of
project stakeholders
Project Manager High
(Controlling
)
Medium
(Coordinating)
Assign
responsibilities
to project
team2
Controlling
and directing
project
execution
Project
document
Project
planning
Manager and
leader
Goal oriented
Knowledge
about project
Can deal with
ambiguity,
chaos, and
stress
Effective
communicator
Coordinator
and facilitator
Technical
Manager
Medium
(Guiding) 3
Medium
(Guiding)
To assist shop
re-design,
procurement,
sourcing, and
installation of
new
equipment.
Technical
credibility
Innovator
Facilitator
Coordinator
Contractor Medium
(Guiding)
Medium
(Guiding)
To make sure
that wires
should be
taken carefully
by installers
when
removing
stairs
Facilitator
Coordinator
Balanced
participation
in the project
Job expertise
Equipment
suppliers
Low Medium Supply
material
Facilitator
Coordinator
Balanced
participation
2 Sergio Jiménez, Fernando Fernández and Daniel Borrajo, "INTEGRATING PLANNING,
EXECUTION, AND LEARNING TO IMPROVE PLAN EXECUTION" (2012) 29(1) Computational
Intelligence.
3 Nikos Macheridis, "Balancing Authority And Autonomy In Higher Education By Implementing An
Agile Project Management Approach" (2017) 24(2) Tertiary Education and Management.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
in the project
Kitchen cleaning
professionals
Low Medium Cleaning Facilitator
Coordinator
Balanced
participation
in the project
Installers Low Medium Installs wires Facilitator
Coordinator
Balanced
participation
Technical and
safety compliance
certification
bodies
Low Medium Checking
mechanical
ventilation
compliance
Implement
required safety
controls
Facilitator
Coordinator
Balanced
participation
MONITORING AND CONTROL PROCESS
Monitoring and control processes will be required to review, track and orchestrate the
performance and progress of Royale Pizza’s renovation project. Below listed tools and
techniques will be used by the Project Manager to assess project performance and identify
any area in which modifications are required. Project scope, project work, schedule, quality,
cost, communication, stakeholder engagement, and risks will be monitored and controlled4.
What will be
assessed
Tool and
techniques
Description Strengths of the
chosen
tool/technique
Weaknesses of
the chosen
tool/technique
Project work Meetings The project manager will
track, review and report
the project progress by
conducting meetings on a
weekly basis with key
project stakeholders. The
Project Manager will
modify the project plan to
accomplish project work
on time and meet project
objectives.
The chosen
technique will
allow the Project
Manager to stay up-
to-date about
project work.
Wastage of
precious time
of project
stakeholders.
Project Scope Inspection Scope validation will be In the inspection It does not
4 Jeroen Colin and Mario Vanhoucke, "Developing A Framework For Statistical Process Control
Approaches In Project Management" (2015) 33(6) International Journal of Project Management.
Kitchen cleaning
professionals
Low Medium Cleaning Facilitator
Coordinator
Balanced
participation
in the project
Installers Low Medium Installs wires Facilitator
Coordinator
Balanced
participation
Technical and
safety compliance
certification
bodies
Low Medium Checking
mechanical
ventilation
compliance
Implement
required safety
controls
Facilitator
Coordinator
Balanced
participation
MONITORING AND CONTROL PROCESS
Monitoring and control processes will be required to review, track and orchestrate the
performance and progress of Royale Pizza’s renovation project. Below listed tools and
techniques will be used by the Project Manager to assess project performance and identify
any area in which modifications are required. Project scope, project work, schedule, quality,
cost, communication, stakeholder engagement, and risks will be monitored and controlled4.
What will be
assessed
Tool and
techniques
Description Strengths of the
chosen
tool/technique
Weaknesses of
the chosen
tool/technique
Project work Meetings The project manager will
track, review and report
the project progress by
conducting meetings on a
weekly basis with key
project stakeholders. The
Project Manager will
modify the project plan to
accomplish project work
on time and meet project
objectives.
The chosen
technique will
allow the Project
Manager to stay up-
to-date about
project work.
Wastage of
precious time
of project
stakeholders.
Project Scope Inspection Scope validation will be In the inspection It does not
4 Jeroen Colin and Mario Vanhoucke, "Developing A Framework For Statistical Process Control
Approaches In Project Management" (2015) 33(6) International Journal of Project Management.
performed through
inspection technique.
technique, the
actual project scope
will be compared to
acceptance criteria,
defined project
scope, and project
requirements.
support scope
control
mechanism.
variance
analysis
Variance analysis
technique will be used to
identify differences
between the actual and
defined project scope. If
there is a
difference/variance
between actual and
defined renovation
project scope, the project
manager will issue a
change request and
update the project plan5.
It provides a
control mechanism
to project manager
in making detailed,
forward-looking
and efficient
decisions.
Budgeting
exercise might
be loosely
performed by
using variance
analysis
technique.
Cost Earned
value
management
EVM technique can be
utilized for controlling
and monitoring project
cost6.
This technique tries
to make sure that
key project
attributes (time and
schedule) are on the
right track7.
This technique
does not focus
on project
quality.
Quality Cause and
effect
diagram
Cause and effect diagram
quality control tool will
be used to monitor and
record outcomes of
quality activities used for
assessing project
performance8.
The project
stakeholders can
see identify root
causes of safety and
quality issues
which might be
faced by them
during flooring,
professional
kitchen cleaning,
wiring installation,
staircase repairing,
etc. It will allow the
project team to
The Project
Manager
cannot capture
failures or
quality risks
associated
with negative
human
behavior with
the use of
Cause and
effect
diagram.
5 Peng Zhang et al, "Bias–Variance Analysis In Estimating True Query Model For Information
Retrieval" (2014) 50(1) Information Processing & Management.
6 R. Jayaraman, "Project Cost Control: A New Method To Plan And Control Costs In Large Projects"
(2016) 22(6) Business Process Management Journal.
7 Steffen Menze, "Projekt-Controlling Mit Earned Value Und Earned Schedule" (2013) 57(3)
Controlling & Management Review.
8 Greg Indelicato, "Total Quality Management For Project Management" (2013) 44(4) Project
Management Journal.
inspection technique.
technique, the
actual project scope
will be compared to
acceptance criteria,
defined project
scope, and project
requirements.
support scope
control
mechanism.
variance
analysis
Variance analysis
technique will be used to
identify differences
between the actual and
defined project scope. If
there is a
difference/variance
between actual and
defined renovation
project scope, the project
manager will issue a
change request and
update the project plan5.
It provides a
control mechanism
to project manager
in making detailed,
forward-looking
and efficient
decisions.
Budgeting
exercise might
be loosely
performed by
using variance
analysis
technique.
Cost Earned
value
management
EVM technique can be
utilized for controlling
and monitoring project
cost6.
This technique tries
to make sure that
key project
attributes (time and
schedule) are on the
right track7.
This technique
does not focus
on project
quality.
Quality Cause and
effect
diagram
Cause and effect diagram
quality control tool will
be used to monitor and
record outcomes of
quality activities used for
assessing project
performance8.
The project
stakeholders can
see identify root
causes of safety and
quality issues
which might be
faced by them
during flooring,
professional
kitchen cleaning,
wiring installation,
staircase repairing,
etc. It will allow the
project team to
The Project
Manager
cannot capture
failures or
quality risks
associated
with negative
human
behavior with
the use of
Cause and
effect
diagram.
5 Peng Zhang et al, "Bias–Variance Analysis In Estimating True Query Model For Information
Retrieval" (2014) 50(1) Information Processing & Management.
6 R. Jayaraman, "Project Cost Control: A New Method To Plan And Control Costs In Large Projects"
(2016) 22(6) Business Process Management Journal.
7 Steffen Menze, "Projekt-Controlling Mit Earned Value Und Earned Schedule" (2013) 57(3)
Controlling & Management Review.
8 Greg Indelicato, "Total Quality Management For Project Management" (2013) 44(4) Project
Management Journal.
develop superior
and comprehensive
risk controls.
Time Line of
Balance
Scheduling
tool
Scheduling tool can be
used to monitor the
project status and manage
changes in project
scheduling baseline9.
This technique
presents the status,
background,
process, and
phasing of project
activities.
Moreover, the
project manager
will examine the
future project
performance in
terms of time by
using Line of
Balance Scheduling
tool. It is very easy
to modify, change
and update the
schedule with the
use of Line of
Balance Scheduling
tool.
A clear critical
path of the
project
schedule
cannot be
generated by
LOBST
technique.
Stakeholder
engagement
Project
status
review
meetings
Project status review
meetings will be
conducted to manage and
control stakeholder
engagement in the
proposed renovation
project.
This technique will
be beneficial for the
project manager as
it will allow him to
engage all project
stakeholders
including Technical
Manager,
contractors,
installers, etc.
throughout the
project life cycle.
If project
stakeholders
will not
discuss
problems
related to the
project during
meeting
sessions, then
it might be
difficult for a
project
manager to
track and
control
stakeholder’s
engagement
properly10.
9 Prof: Siddesh K Pai, "Application Of Line Of Balance Scheduling Technique (LOBST) For A Real
Estate Sector" (2013) 2(1) International Journal of Science, Engineering and Technology
Research (IJSETR) <http://ijsetr.org/wp-content/uploads/2013/07/IJSETR-VOL-2-ISSUE-1-82-
95.pdf>.
10 Amira M., Sherief Mazen and Ehab E., "Comparative Study For Software Project Management
Approaches And Change Management In The Project Monitoring & Controlling" (2016) 7(2)
and comprehensive
risk controls.
Time Line of
Balance
Scheduling
tool
Scheduling tool can be
used to monitor the
project status and manage
changes in project
scheduling baseline9.
This technique
presents the status,
background,
process, and
phasing of project
activities.
Moreover, the
project manager
will examine the
future project
performance in
terms of time by
using Line of
Balance Scheduling
tool. It is very easy
to modify, change
and update the
schedule with the
use of Line of
Balance Scheduling
tool.
A clear critical
path of the
project
schedule
cannot be
generated by
LOBST
technique.
Stakeholder
engagement
Project
status
review
meetings
Project status review
meetings will be
conducted to manage and
control stakeholder
engagement in the
proposed renovation
project.
This technique will
be beneficial for the
project manager as
it will allow him to
engage all project
stakeholders
including Technical
Manager,
contractors,
installers, etc.
throughout the
project life cycle.
If project
stakeholders
will not
discuss
problems
related to the
project during
meeting
sessions, then
it might be
difficult for a
project
manager to
track and
control
stakeholder’s
engagement
properly10.
9 Prof: Siddesh K Pai, "Application Of Line Of Balance Scheduling Technique (LOBST) For A Real
Estate Sector" (2013) 2(1) International Journal of Science, Engineering and Technology
Research (IJSETR) <http://ijsetr.org/wp-content/uploads/2013/07/IJSETR-VOL-2-ISSUE-1-82-
95.pdf>.
10 Amira M., Sherief Mazen and Ehab E., "Comparative Study For Software Project Management
Approaches And Change Management In The Project Monitoring & Controlling" (2016) 7(2)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
PROJECT PERFORMANCE EVALUATION
The technique for project performance evaluation
Performance reviews
The Project Manager should ask all project stakeholders to evaluate his/her performance in
context to Royale Pizza’s renovation project. They should consistently and fairly focus
criticism on specific behavior during performance evaluation. The performance review is an
effective technique which provides a periodic and systematic process to assess efficiency,
productivity, and effectiveness of project stakeholders in relation to pre-established
organizational objectives and project success criteria. The performance of the project can be
measured and evaluated based on time, cost and product quality11.
Strengths
Variance in project performance can be detected at an early stage by the project manager
through performance review technique which will help to achieve project quality in an
effective way.
Weaknesses
One-sided feedback
The outcome of performance evaluation can be biased.
List of specific actions required to ensure the quality of the project
Planning – In this phase, the long and short term of all project stakeholders will be defined
properly for setting project evaluation criteria. For example
Pre-defined criteria
Complete shop renovation within 4 months
Effective participation of all project stakeholders in the project
The project will be completed within AU$4000.
All requirements of the shop owner should be fulfilled.
There should be no defect in the renovation project.
Team satisfaction
Flooring, kitchen cleaning, installation of the air-conditioning system, dust
free-painting, increasing compressor capacity tasks should be completed.
Project stakeholders do not encounter safety issues when working on a
renovation project12.
Implementation – The project manager should monitor different aspects of the renovation
International Journal of Advanced Computer Science and Applications.
11 Yemesrach Assefa, Oscar P. Rivera and Désiré Vencatachellum, "Macro And Micro Determinants
Of Project Performance" (2014) 2(1) African Evaluation Journal.
12 Samina Jan, Ali Javed and Muhammad Nadeem Majeed, "Quality Category Matrix To Ensure The
Quality Of Software Product" [2012] International Journal of Computer and Communication
Engineering.
The technique for project performance evaluation
Performance reviews
The Project Manager should ask all project stakeholders to evaluate his/her performance in
context to Royale Pizza’s renovation project. They should consistently and fairly focus
criticism on specific behavior during performance evaluation. The performance review is an
effective technique which provides a periodic and systematic process to assess efficiency,
productivity, and effectiveness of project stakeholders in relation to pre-established
organizational objectives and project success criteria. The performance of the project can be
measured and evaluated based on time, cost and product quality11.
Strengths
Variance in project performance can be detected at an early stage by the project manager
through performance review technique which will help to achieve project quality in an
effective way.
Weaknesses
One-sided feedback
The outcome of performance evaluation can be biased.
List of specific actions required to ensure the quality of the project
Planning – In this phase, the long and short term of all project stakeholders will be defined
properly for setting project evaluation criteria. For example
Pre-defined criteria
Complete shop renovation within 4 months
Effective participation of all project stakeholders in the project
The project will be completed within AU$4000.
All requirements of the shop owner should be fulfilled.
There should be no defect in the renovation project.
Team satisfaction
Flooring, kitchen cleaning, installation of the air-conditioning system, dust
free-painting, increasing compressor capacity tasks should be completed.
Project stakeholders do not encounter safety issues when working on a
renovation project12.
Implementation – The project manager should monitor different aspects of the renovation
International Journal of Advanced Computer Science and Applications.
11 Yemesrach Assefa, Oscar P. Rivera and Désiré Vencatachellum, "Macro And Micro Determinants
Of Project Performance" (2014) 2(1) African Evaluation Journal.
12 Samina Jan, Ali Javed and Muhammad Nadeem Majeed, "Quality Category Matrix To Ensure The
Quality Of Software Product" [2012] International Journal of Computer and Communication
Engineering.
project to overcome issues of budget and schedule overruns. Status reports will be created
by the manager when meeting with team members to ensure whether they are on the right
track or not13.
Completion – The data captured in the above two activities will be analyzed for
identifying existing problems which could affect the overall quality of the Royale Pizza’s
renovation project.
Reporting and disseminating – After successful completion of project performance
evaluation, the project manager will create a project results report and deliver it to all
project stakeholders like Technical Manager, Contractors, Installers, etc.14
PROJECT CLOSURE
Steps/tools required to close the project (post-project activities)
In Project Monitor will this phase, the close the renovation of Royale shop project when all
project objectives will be met by the project team. Key activities of the project closing phase
are listed below:
1. Acceptance of deliverables – The owner of Royale Pizza will review the renovated
shop and examine whether his all project requirements are fulfilled or not as per the
agreement.
2. Finalize the lesson learned – Before the project team members will be assigned to
another project or relieved from this renovation project, it is important for Project
Manager to circulate questionnaire among all stakeholders. The main purpose of
questionnaire distribution is to obtain unbiased views from project stakeholders
regarding critical success factors which have achieved and critical issues faced by
them during the project life cycle. All aspects of renovation project should be
included in the lessons learned such as internal and external communications,
monitoring of project, acceptance criteria of project deliverables, implementation of
project schedule and involvement of users15.
The retrospective technique will be used for lesson learned process.
Strengths of retrospective technique
To stop repetitive mistakes
To reuse learned solutions
Limitations of the retrospective technique
The lesson learned process cannot be accomplished successfully in case of a biased
facilitator.
13 Guang Feng Wang, "Defect Identification And Quality Control Of Steel Structure Installation Projects
Based On Fishbone Diagram" (2013) 340 Applied Mechanics and Materials.
14 Qing Cao and James J. Hoffman, "A Case Study Approach For Developing A Project Performance
Evaluation System" (2011) 29(2) International Journal of Project Management.
15 Enrico Mastrofini, "Project Management Template / Project Management Facile Con Le Mappe
Mentali" [2013] (16) PROJECT MANAGER (IL).
by the manager when meeting with team members to ensure whether they are on the right
track or not13.
Completion – The data captured in the above two activities will be analyzed for
identifying existing problems which could affect the overall quality of the Royale Pizza’s
renovation project.
Reporting and disseminating – After successful completion of project performance
evaluation, the project manager will create a project results report and deliver it to all
project stakeholders like Technical Manager, Contractors, Installers, etc.14
PROJECT CLOSURE
Steps/tools required to close the project (post-project activities)
In Project Monitor will this phase, the close the renovation of Royale shop project when all
project objectives will be met by the project team. Key activities of the project closing phase
are listed below:
1. Acceptance of deliverables – The owner of Royale Pizza will review the renovated
shop and examine whether his all project requirements are fulfilled or not as per the
agreement.
2. Finalize the lesson learned – Before the project team members will be assigned to
another project or relieved from this renovation project, it is important for Project
Manager to circulate questionnaire among all stakeholders. The main purpose of
questionnaire distribution is to obtain unbiased views from project stakeholders
regarding critical success factors which have achieved and critical issues faced by
them during the project life cycle. All aspects of renovation project should be
included in the lessons learned such as internal and external communications,
monitoring of project, acceptance criteria of project deliverables, implementation of
project schedule and involvement of users15.
The retrospective technique will be used for lesson learned process.
Strengths of retrospective technique
To stop repetitive mistakes
To reuse learned solutions
Limitations of the retrospective technique
The lesson learned process cannot be accomplished successfully in case of a biased
facilitator.
13 Guang Feng Wang, "Defect Identification And Quality Control Of Steel Structure Installation Projects
Based On Fishbone Diagram" (2013) 340 Applied Mechanics and Materials.
14 Qing Cao and James J. Hoffman, "A Case Study Approach For Developing A Project Performance
Evaluation System" (2011) 29(2) International Journal of Project Management.
15 Enrico Mastrofini, "Project Management Template / Project Management Facile Con Le Mappe
Mentali" [2013] (16) PROJECT MANAGER (IL).
Steps of retrospective technique:
1. Independent facilitator should be hired to guide project stakeholders.
2. Make announcement of exercise so that all project stakeholders should be
involved.
3. Discuss details of exercise
4. Try to focus on tactical implementation and dictions made during project life
cycle.
5. Discuss lessons learned in positively as it will promote best practices of
project management.
6. Ask questions and receive feedback
7. Documentation of outcome of lessons learned exercise.
Conclusion
In the end, it can be summarized that Project scope, project work, schedule, quality, cost,
communication, stakeholder engagement, and risks will be monitored and controlled by the
Project Manager to fulfill all key requirements of the shop owner. The suggested project
monitoring, evaluation, and closing techniques/tools should be utilized by the project
stakeholders to achieve project goals.
REFERENCES
Assefa, Yemesrach, Oscar P. Rivera and Désiré Vencatachellum, "Macro And Micro
Determinants Of Project Performance" (2014) 2(1) African Evaluation Journal
Cao, Qing and James J. Hoffman, "A Case Study Approach For Developing A Project
Performance Evaluation System" (2011) 29(2) International Journal of Project Management
Colin, Jeroen and Mario Vanhoucke, "Developing A Framework For Statistical Process
Control Approaches In Project Management" (2015) 33(6) International Journal of Project
Management
De Hoogh, Annebel H.B., Lindred L. Greer and Deanne N. Den Hartog, "Diabolical
Dictators Or Capable Commanders? An Investigation Of The Differential Effects Of
Autocratic Leadership On Team Performance" (2015) 26(5) The Leadership Quarterly
Indelicato, Greg, "Total Quality Management For Project Management" (2013) 44(4) Project
Management Journal
Jan, Samina, Ali Javed and Muhammad Nadeem Majeed, "Quality Category Matrix To
Ensure The Quality Of Software Product" [2012] International Journal of Computer and
Communication Engineering
Jiménez, Sergio, Fernando Fernández and Daniel Borrajo, "INTEGRATING PLANNING,
EXECUTION, AND LEARNING TO IMPROVE PLAN EXECUTION" (2012) 29(1)
Computational Intelligence
Jayaraman, R., "Project Cost Control: A New Method To Plan And Control Costs In Large
Projects" (2016) 22(6) Business Process Management Journal
1. Independent facilitator should be hired to guide project stakeholders.
2. Make announcement of exercise so that all project stakeholders should be
involved.
3. Discuss details of exercise
4. Try to focus on tactical implementation and dictions made during project life
cycle.
5. Discuss lessons learned in positively as it will promote best practices of
project management.
6. Ask questions and receive feedback
7. Documentation of outcome of lessons learned exercise.
Conclusion
In the end, it can be summarized that Project scope, project work, schedule, quality, cost,
communication, stakeholder engagement, and risks will be monitored and controlled by the
Project Manager to fulfill all key requirements of the shop owner. The suggested project
monitoring, evaluation, and closing techniques/tools should be utilized by the project
stakeholders to achieve project goals.
REFERENCES
Assefa, Yemesrach, Oscar P. Rivera and Désiré Vencatachellum, "Macro And Micro
Determinants Of Project Performance" (2014) 2(1) African Evaluation Journal
Cao, Qing and James J. Hoffman, "A Case Study Approach For Developing A Project
Performance Evaluation System" (2011) 29(2) International Journal of Project Management
Colin, Jeroen and Mario Vanhoucke, "Developing A Framework For Statistical Process
Control Approaches In Project Management" (2015) 33(6) International Journal of Project
Management
De Hoogh, Annebel H.B., Lindred L. Greer and Deanne N. Den Hartog, "Diabolical
Dictators Or Capable Commanders? An Investigation Of The Differential Effects Of
Autocratic Leadership On Team Performance" (2015) 26(5) The Leadership Quarterly
Indelicato, Greg, "Total Quality Management For Project Management" (2013) 44(4) Project
Management Journal
Jan, Samina, Ali Javed and Muhammad Nadeem Majeed, "Quality Category Matrix To
Ensure The Quality Of Software Product" [2012] International Journal of Computer and
Communication Engineering
Jiménez, Sergio, Fernando Fernández and Daniel Borrajo, "INTEGRATING PLANNING,
EXECUTION, AND LEARNING TO IMPROVE PLAN EXECUTION" (2012) 29(1)
Computational Intelligence
Jayaraman, R., "Project Cost Control: A New Method To Plan And Control Costs In Large
Projects" (2016) 22(6) Business Process Management Journal
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
M., Amira, Sherief Mazen and Ehab E., "Comparative Study For Software Project
Management Approaches And Change Management In The Project Monitoring &
Controlling" (2016) 7(2) International Journal of Advanced Computer Science and
Applications
Macheridis, Nikos, "Balancing Authority And Autonomy In Higher Education By
Implementing An Agile Project Management Approach" (2017) 24(2) Tertiary Education
and Management
Mastrofini, Enrico, "Project Management Template / Project Management Facile Con Le
Mappe Mentali" [2013] (16) PROJECT MANAGER (IL)
Menze, Steffen, "Projekt-Controlling Mit Earned Value Und Earned Schedule" (2013) 57(3)
Controlling & Management Review
Pai, Prof: Siddesh K, "Application Of Line Of Balance Scheduling Technique (LOBST) For
A Real Estate Sector" (2013) 2(1) International Journal of Science, Engineering and
Technology Research (IJSETR) <http://ijsetr.org/wp-content/uploads/2013/07/IJSETR-VOL-
2-ISSUE-1-82-95.pdf>
Wang, Guang Feng, "Defect Identification And Quality Control Of Steel Structure
Installation Projects Based On Fishbone Diagram" (2013) 340 Applied Mechanics and
Materials
Zhang, Peng et al, "Bias–Variance Analysis In Estimating True Query Model For
Information Retrieval" (2014) 50(1) Information Processing & Management
Management Approaches And Change Management In The Project Monitoring &
Controlling" (2016) 7(2) International Journal of Advanced Computer Science and
Applications
Macheridis, Nikos, "Balancing Authority And Autonomy In Higher Education By
Implementing An Agile Project Management Approach" (2017) 24(2) Tertiary Education
and Management
Mastrofini, Enrico, "Project Management Template / Project Management Facile Con Le
Mappe Mentali" [2013] (16) PROJECT MANAGER (IL)
Menze, Steffen, "Projekt-Controlling Mit Earned Value Und Earned Schedule" (2013) 57(3)
Controlling & Management Review
Pai, Prof: Siddesh K, "Application Of Line Of Balance Scheduling Technique (LOBST) For
A Real Estate Sector" (2013) 2(1) International Journal of Science, Engineering and
Technology Research (IJSETR) <http://ijsetr.org/wp-content/uploads/2013/07/IJSETR-VOL-
2-ISSUE-1-82-95.pdf>
Wang, Guang Feng, "Defect Identification And Quality Control Of Steel Structure
Installation Projects Based On Fishbone Diagram" (2013) 340 Applied Mechanics and
Materials
Zhang, Peng et al, "Bias–Variance Analysis In Estimating True Query Model For
Information Retrieval" (2014) 50(1) Information Processing & Management
1 out of 11
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.