This project charter outlines the plan for developing a SAP application for eFashion Pty Ltd., a Melbourne-based ladies wear retailer. The application aims to streamline warehouse management and improve overall business efficiency. The project will involve various phases, including requirements gathering, design, development, testing, and implementation. The charter details the project objectives, deliverables, schedule, key costs, and quality attributes. It also identifies the key stakeholders and their roles in the project.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
VUIS CONSULTING PTY LTD.
PROJECT CHARTER
Project name: SAP project for eFashion
Projected start date: 20-03-2018
Projected end date: 30-04-2018
Project Manager: [Insert your name here]
Purpose of the project charter
The main objective of this report is to build the SAP application so that the business of the
eFashion Pty Ltd can be increased in a drastic manner. To make the application in easy
manner use of the project charter is done so that the project can be completed easily
manner. Also through project charter, the work can be organised in a proper manner. As I
am selected as the IT project manager for eFashion Pty Ltd, therefore, the allocation of
resources can be done from my side in an efficient manner.
Project summary
eFashion Pty Ltd is situated in Melbourne whose main focus is to provide best ladies wear.
eFahion Pty Ltd consists of big team and managing them become such a big concern. This
organisation consists of CEO, sales manager, customer relationship and warehouse
manager. This application is going to act as plus point for the warehouse. Through this
application, the warehouse manager can get the details of goods that are placed in the
warehouse easily.
Project Requirements
There is the requirement of several things to complete the project easily. I have classified the
requirement into three different parts which are shown below:
High-level Requirements:
Easy to understand Graphical User Interface
High efficient
All functions have to come under a single application
Hardware requirement:
Hard disk
Central Processing Unit
Ethernet Card
Software Requirement:
Mozilla Firefox
Microsoft SQL server
Dynamic link libraries
Microsoft Management Console
The following template is for educational purposes only.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Major Deliverables/Milestones
Development of this SAP application is divided into different deliverables. Through this, the
project can be completed easily. Different Milestones that are going to be used in this
application are shown below:
Findings related to project
Business Necessity
Project commencement
Product purchasing
Designing phase
Testing phase
Project installation
Session for staff training
Brief schedule
Through the project schedule, tracking of the project can be completed easily. To make the
project in an easy manner, project is broken into 8 equal phase. All these phases can be
tracked through 8 milestones.
Table 1 Brief project schedule
Entry type Description
Phase: Findings
related to project
Under this phase, the findings that are associated with the
application of eFashion Pty Ltd. is done.
Task: Meeting with
stakeholders.
In this, meeting with the major stakeholders of the eFashion Pty
Ltd. is done. Through this, all the problems that are facing by
eFashion can be completed easily.
Task: Statistic finding In this, all the records of the eFashion Pty Ltd. are analysed.
Milestone: Finding
associated with the
project completion.
At this point, all the findings of the project are going to be
completed.
Phase: Business
Necessity
Under this phase, all the necessities that are associated with the
eFahion business are going to be planned.
Task: Business Scope In this, all the possibilities that can be placed for the eFahion Pty
Ltd. are done.
Task: Finding
documentation
In this, all the findings that are completed in the business scope
are documented in a proper manner.
Milestone: Business
Necessity completion
At this point, all the necessities that are needed by the
organisation are completed.
Phase: Project
commencement
Under this phase, the project is initiated from scratch.
VUIS Consulting Project Charter Page 2
[Insert Author name here]
Document Page
Task: Possibility In this, all the possibilities that may be there to initiate the
eFahion Pty Ltd. application are done.
Task: Data Migration In this, all the information which is kept in the eFahion Pty Ltd. is
going to be captured and transfer to the cloud.
Milestone: Project
commencement
completion
At this point, all the commencement that is associated with the
eFahion Pty Ltd. project is completed.
Phase: Product
purchasing
Under this phase, all the equipment that is required to build the
application for eFahion Pty Ltd. is purchased.
Task: Software
Packages
In this, all the license of the software that is associated with the
application of the eFahion Pty Ltd. is purchased.
Task: Hardware
purchasing
In this, all the tools on which software is going to work is
purchased.
Milestone: Product
purchasing
completion
At this point all the purchasing that are needed to build the
application for eFahion Pty Ltd.
Phase: Designing
phase
Under this phase, the scheming of the application is planned to
be initiated.
Task: Coding In this, software coding is going to be initiated. Coding has to be
done in such a manner so that application can run in a smooth
manner by the user.
Task: Setup of
Hardware
In this, setting of the hardware that is necessary for the
application of eFahion Pty Ltd. is done.
Milestone: Designing
phase completion
At this point, all the design aspect that is associated with the
application of eFahion Pty Ltd. is completed.
Phase: Testing
phase
Under this phase, all the testing that is associated with the
application of eFahion Pty Ltd. which is planned to be initiated.
Task: Software
Testing
In this, the software application is run on different setup and
result is checked with the pre-defined solution.
Task: Hardware
Testing
In this, the hardware of the eFahion Pty Ltd. SAP application is
connected.
Milestone: Testing
phase completion
At this point, all the testing of the eFahion Pty Ltd. is completed.
Phase: Project
installation
Under this phase, the installation of the application is done under
the buildings of eFahion Pty Ltd.
Task: Hardware setup In this, all the hardware that are required to run the application is
VUIS Consulting Project Charter Page 3
[Insert Author name here]
Document Page
installed.
Task: Setup of
Software
In this, software of the application is setup that is planned to be
initiated.
Milestone: Installation
of project completion
At this point, all the procedures that are associated with the
installation of the eFahion Pty Ltd. application are going to be
completed.
Phase: Session for
staff training
Under this phase, the training for the staff of eFahion Pty Ltd. is
done.
Task: Training
session
In this, the training session is being conducted so that staff
member of eFahion Pty Ltd. can operate the application easily.
Task: Documentation
handling
In this, the documentation of the eFahion Pty Ltd application is
handed to the technical department.
Milestone: Installation
of project completion
At this point the all the phases of the project is going to be
completed.
Key costs
Name of Task Task cost Description
SAP project for eFashion $17,680.00 Project actual cost spent in making the
application of eFashion.
Findings related to project $2,140.00 All the cost associated with findings related
to project.
Business Necessity $2,220.00 All the cost associated with business
necessity.
Project commencement $2,00.00 All the cost associated with project
commencement.
Product purchasing $3,000.00 All the cost associated with project
purchasing.
Designing phase $2,880.00 All the cost associated with designing phase.
Testing phase $3,550.00 All the cost associated with testing phase.
Project installation $1,890.00 All the cost associated with project
installation.
Session for staff training $2,000.00 All the cost associated with staff training.
VUIS Consulting Project Charter Page 4
[Insert Author name here]

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Associated Quality Attributes
Resource allocation: In every project, resources play important role in success of
project. For that, there is the requirement of allocating the resources in a proper manner
so that there must no case of overlapping as well as over allocation.
Improper documentation: All the problems that come during the building the
application has to be inserted into the documentation. Through this user can solve the
problem that he/she may face during operating the application.
Rigidity: Inside every project rigidity has to be maintained in a proper manner. Through
this project is not going to stuck and can be completed on time.
Lack of communication: While developing the project, communication has to be done
in proper manner. Without proper communication, there may be a chance that some
loopholes may be there. Through these loopholes, the success of project may be
derailed.
Duration
Task Name Duration
Findings related to project 3 days
Business Necessity 4 days
Project commencement 5 days
Product purchasing 3 days
Designing phase 7 days
Testing phase 5 days
Project installation 4 days
Session for staff training 1 day
Authorization to proceed
Project Manager
System Integrator
Technical Writer
Trainer
Technical Officer
Database Programmer
Administrative Officer
Data Entry Officer
VUIS Consulting Project Charter Page 5
[Insert Author name here]
Document Page
Business Analyst
Operational Manager (VUISC) Shah Miah
VUIS Consulting Project Charter Page 6
[Insert Author name here]
1 out of 6
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]