SCOPE MANAGEMENT PLAN
E-TAXI
COMPANY NAME
STREET ADDRESS
CITY, STATE ZIP CODE
DATE
Table of contents
Project name
Sponsor
Project Manager(s)
Problem Statement or Opportunity
Project Summary
Scope Definition
Scope Statement
Out-of-Scope Items
Constraints
Assumptions
Scope Control
Sign Off
Project Name
The name of the project is E Taxi Project
Sponsor
Please insert the name of your teacher
Project Manager(s)
Please insert your name and name of the group member
Problem Statement or Opportunity
The undertaken project aims in solving the problems that commuters face while waiting for a taxi in peak hours.
Taxi is an important mode of communication. However, in peak hours, many people stand in the road side waiting
for taxis. The proposed project aims in reducing the waiting time for the taxis with the implementation of this
project, taxis can be booked and scheduled through smartphone.
Project Summary
1

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
The project involves development of a vehicle tracking system that will make use of the GPS system. Prior to the
development of the application feedbacks will be collected from common people to understand the need of the
application. The application aims in overcoming the problem of waiting for taxis in the peak hours.
Scope Definition
The E Taxi project’s scope was defined by following a planned information gathering process. A thorough and
detailed analysis of the proposed project was possible by collection of the feedbacks from the daily commuters. The
need for improving the daily commute services have gave rise to the need of similar types of application. The work
breakdown structure for this particular project is prepared by grouping the tasks into manageable units. To keep a
follow up on the tasks, weekly meetings are held in order to discuss the implementation approach of the task, so that
the proposed project can be delivered within the set time frame.
Scope Statement
The following picture (WBS), details the work units that is to be finished for this particular E Taxi project-
2
Document Page
E-Taxi Project
Initiation/Market Research
Understanding the
Requirements Analysis of the Market
Demand
Analysis of the need of
this application
Collection of Feedbacks
Documentation
M1: End of Market
Research
Information Gathering
Analysing the project
Requirements
Analysis of the current
Process
Documentation
M2: Completion of
information collection
Project Planning
Finalizing the
requirements to be
included in the Plan
Development of a Project
Plan
M3: Approval of the
Project Plan
Content Development
Finalizing the
ContentBuilding the software
Content
M4: End of content
Development Phase
Database Design
Input the information into
the database
Organize the information
M5: Completion of
Database Design
Error Testing
Testing the Modules
developed so far
Unit Testing
system testing
Performance testing
Rectification of the Errors
Development of the
Software
Designing user Interface Coding
Coding the front end
Rectification in the
designing errors
Testing the modules
M6: End of Testing Phase
Backend System
Development
Coding
Testing
Development of Database
and Connection
Final database
development
Linking database with the
software
Mobile App Development
Testing of the software to
identify any bugs
Pilot Run
Bug Fixing
User Training
Preparation of Training
modules
Training and procedure
docuements
Project Sign Off
Docuementation
Development of Project
Closure report
Payment Completion
M7: End of Project
Figure 1.: Illustrating the WBS of the Project
3
Document Page
The WBS dictionary in the table below identifies the tasks or the works to be completed along with a detailed
descriptions of each of the tasks.
WBS
Code
Element Name Description of
Work
Outcome/Deliverable Budget Resources Length
(Time)
1 Initiation/Market
Research
Documentation
of market
research
$9,960.00 Project
Manager
10
days
2 Information
Gathering
Documentation
of the
information
required
$6,920.00 Project
Manager
9 days
3 Project Planning Project Plan $1,800.00 Project
Manager
3 days
4 Content
Development
Completion of
content
development
$5,040.00 Content
Writer
10
days
5 Database Design Completion of
database design
$9,680.00 Programmer,
Software
Engineer
10
days
6 Error Testing Fixation of all the
identified errors
$10,920.0
0
Tester 21
days
7 Development of
the Software
The application $81,240.0
0
Programmer,
Software
Engineer
27
days
8 Backend System
Development
The backend of
the application
$35,240.0
0
Programmer,
Software
Engineer
37
days
9 Development of
Database and
Connection
Completion of
database
connection
$25,800.0
0
Programmer,
Software
Engineer
25
days
10 Mobile App
Development
Mobile APP $8,160.00 Programmer,
Software
Engineer
15
days
11 User Training Users’ training $6,000.00 Trainer 10
days
12 Project Sign Off Project Closure
document
$2,720.00 Project
Manager
5 days
Table 1: WBS Dictionary
The above table indicates the main project deliverable of developing an E-Taxi. The project will be accepted only if
the software that is developed is tested and the software is found to be matching the requirements of the project.
Out-of-Scope Items
4

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
The E-Taxi project does not involves maintenance of the software.
Constraints
There are certain critical constraints linked with the project execution which are as follows-
The sponsor will be contacted only twice per week
The project should not take more than 10 months to complete
Assumptions
The main assumptions of the project are indicated as follows-
1. The funds required in the project will be released by the sponsor when required
2. The project can be completed within eight months
Scope Control
The undertaken E Taxi project is implemented by a dedicated project team. Timely supervision of the project is
ascertain to control the identified scope of the project. The project manager along with the project supervisor is in
charge of supervising the project progress. A RACI matrix is developed for depicting the responsibility of the each
resources in each of the project phases.
Tasks Project
Manager/
Asst. PM
Busines
s
Analyst
Supervi
sor
Programmer/
Software
Engineer
Design
er
Traine
r
Teste
r
Initiation/
Market
Research
R R A I I I I
Information
Gathering
R I A C I I I
Project
Planning
R A C I I I I
Content
Developmen
t
I I I R A I I
Database
Design
I I I R C I A
Error
Testing
I I I A A I R
Developmen
t of the
Software
I I I R C I A
Backend
System
Developmen
t
I I I R C I A
Developmen
t of Database
I I I R C I A
5
Document Page
and
Connection
Mobile App
Developmen
t
I I I R C I A
User
Training
I I I I I R/A I
Project Sign
Off
R C A I I I I
Table 2: Representing the RACI Matrix
6
Document Page
SIGN OFF
Approved by the Project Sponsor:
___________________________________________ Date:____________________
Insert the name of your Teacher
<Project Sponsor Title>
In agreement with the Project Manager
___________________________________________ Date:____________________
Insert Your Name
Project Manager
7
1 out of 7
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]