Running head:
Project Initiation Planning and Execution: Shifting to Perth
Name of Student
Name of University
Author Note

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
Table of Contents
Introduction..........................................................................................................................2
1. Overview of the Scenario................................................................................................2
2. Criteria and Assumptions................................................................................................3
3. The Milestone Plan: The deliverables.............................................................................5
4. Task List and the Resources............................................................................................5
5. Gantt chart and Task Flow...............................................................................................5
6. Details of the Adjustments...............................................................................................6
7. Reflection.........................................................................................................................6
Conclusion...........................................................................................................................6
References............................................................................................................................8
Appendices........................................................................................................................10
Appendix 1.....................................................................................................................10
Appendix 2.....................................................................................................................12
Appendix 3.....................................................................................................................14
Document Page
2
Introduction
The purpose of this assignment is to plan and execute a shifting project for a family. The
relocation project is complex since the family need to vacate their current property, way in
advance. There are four members in the family, with two children. The family has a dog. For
relocation, a four bedroom flat is already rented in Perth. However, it is essential for the family
to vacate the property way before than they can move to the new house. Thus, the project plan is
prepared considering all the major aspects and constraints in the project. The variances and the
constraints in the project are considered in development of the project schedule. The report
discusses the project overview, the criteria and the assumptions, the list of tasks along with the
adjustments made. The project details are evaluated in the following paragraphs.
1. Overview of the Scenario
The project aims in shifting a family to Perth. The family consists of two adults, Jeff and
Kelly with their two children Lexie and Will. The family has a dog and two cars. Currently the
family is living in a two bedroom rental apartment in Maroochydore and will be moving to their
new house in Perth on 27th January 2019. The main problem behind this relocation is that the
family has to vacate their current property on 20th January 2019. The new job of Jeff starts on 5th
February 2019. In order to ensure that the entire relocation is smoothly completed including the
transfer of all the goods, the family has hired a packers and movers company that will help them
in moving all the goods including their car. After vacating the current property and prior to
moving to the new house, the family needs to stay in a hotel and for that the family needs to pre
book a hotel way in advance. This, is necessary since the family has no relative in Sunshine
Coast. Apart from that, the family needs to apply for admission of their kids to a school in Perth..
Document Page
3
The relocation project has certain operational complexities and therefore, the budget set for the
project is $15,000. Kelly and Jeff needs to plan and manage the entire relocation project on their
own. A plan for relocation is developed considering the complexity and the budget constraints
associated with the project.
The family can move to their new house in 27th of January and therefore, a project plan is
developed accordingly. The school term in Perth commences from 31st January and for that Jeff
and Kelly needs to complete all the works on or before 30th January 2019. It is mandatory for Jeff
and Kelly to attend their children’s school and therefore, the entire shifting is completed before
31st January 2019.
The details about the exception and the assumptions associated with the project is
highlighted in the section below.
2. Criteria and Assumptions
Considering the information available and the key dates related to the project, a project
plan is prepared. The most significant criteria associated with the project are as follows.
1. The Time constraint is considered prior to the development of project plan.
2. The budget constrain is considered prior to the development of the project plan.
3. The family needs to complete the entire shifting project before 31st January since the
school at Perth Commences from January 31st.
4. The family needs to vacate their current property in 20th January 2019.
5. The family cannot move to the new house before the 27th January 2019.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
The above discussed points indicates the major criteria associated with the project. The
project plan and work breakdown structure (WBS) is prepared for this shifting project
considering these significant criteria of the shifting process. The project is a high priority project
since the family will be relocating to a completely new location and therefore, no belongings or
any important documents should be left behind. In order to ensure a smooth relocation, the
family has taken help of Packers and Movers Company who will be helping the family to
transfer all the necessary belongings along with their cars to Perth. The entire transportation of
the goods and the shifting project will be supervised by Jeff and Kelly. The entire shifting is
considered as a project lead by Jeff and Kelly, in order to develop a milestone plan for the
project. The project is associated with two major milestones, which include completion of
packing and Completion of shifting.
The major assumptions related to the shifting project are as follows-
1. It is assumed that the task will be completed in the scheduled time. There will be no
delays in the completion of each scheduled task in the project.
2. It is assumed that the budget of $15,000 will be sufficient for the family to relocate to
the new location with all their belongings including their cars.
3. It is assumed that it is possible to relocate to a new location before 31st January.
4. It is assumed that new house is completely ready for the family to move in.
5. It is assumed that there will be no changes in the rate in which the workers will be paid
for the entire project work.
Document Page
5
The above discussed points indicates the major assumptions related to the packing
process. Since the entire packing will be supervised by Jeff and Kelly, the possibility of any
errors in the relocation project is minimized. The project plan that is prepared should be followed
in order to ensure a successful relocation of the entire family. If the family is able to follow the
project plan in an efficient manner, it is possible to fulfil the most significant criteria of the
project. However, while preparing the project schedule, certain adjustments are made, which are
discussed in the later section of the report.
3. The Milestone Plan: The deliverables
As discussed earlier, the project is associated with two major milestones, which are
completion of the shifting preparation, that is, packing and completion of the shifting project.
Accordingly, a project plan is prepared that highlights the major tasks and deliverables of the
project along with the milestones of the project. The detailed work breakdown structure and the
milestone plan along with the deliverables of the project is discussed in the appendix section
(refer to appendix 1).
4. Task List and the Resources
The tasks related to the project indicates the necessary tasks or works that are needed to
be completed in order to ensure successful project completion. Since the complexity of the
project is quite high, it was essential to complete all the vital tasks that are associated with the
relocation project. The project plan indicates all the major tasks related to the project (refer to
appendix 2).
5. Gantt chart and Task Flow
Document Page
6
Along with the project plan, a schedule Gantt chart is prepared for the project that gives
an idea of the scheduling and the duration of each of the tasks associated with the project. The
task flow is indicated in the Gantt chart along with the indication of the critical tasks associated
with the project (refer to appendix 3).
6. Details of the Adjustments
It is assumed that the project has started on 19th December 2018. The project that that is
prepared indicates that the project followed a sequential structure. The scheduling of the shifting
project are adjusted as per the project criteria, that include, vacating the old house on 20th and
moving to the new house on 27th. The tasks are scheduled in such a way that the entire project is
completed before 30th January so that the children face no problem in attending their school on
31st January.
7. Reflection
The scheduling complexity of this project was quite high that helped me to understand
the different aspects of project scheduling and the need of planning a project prior to its
implementation. I have planned and schedule the project related to shifting to a new house as per
the requirements and the criteria of the project. There were certain constrains in the project, such
as the budget, the time and the dates on which the old property was needed be vacated and
movement to the new property. The entire project had been a good learning experience for me as
it has helped me to understand the basic of project management and decision making.
Conclusion

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
The report discusses a case scenario of shifting a family to a new location. The family
will be moving to a new house along with their belongings. The major criteria and the
assumptions associated with the project is discussed in the report. The report gives an overview
of the importance and need of project planning and scheduling. The project plan that is prepared,
if followed without any deviation will ensure successful relocation of the family to Perth. The
project plan is prepared in such a manner that the children will not miss their school while Jeff
will have enough time in hand to join to the new office.
Document Page
8
References
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Heagney, J., 2016. Fundamentals of project management. Amacom.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Leach, L.P., 2014. Critical chain project management. Artech House.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
Lock, D., 2017. The essentials of project management. Routledge.
Martinelli, R.J. and Milosevic, D.Z., 2016. Project management toolbox: tools and
techniques for the practicing project manager. John Wiley & Sons.
Crawford, J.K., 2014. Project management maturity model. Auerbach Publications.
Document Page
9
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10
Appendices
Appendix 1
Document Page
11
Document Page
12
Figure 1: Representing the Milestone Plan
The work breakdown structure of the project is represented below-
Shifting to Perth
Start of the Project Planning and
Requirements Gathering
Development of the
inventory list and the list
of tasks that are needed
to be completed
Hiring a packers and
movers who would help
the family in moving
Gathering the packing
needs with the help of the
packers and movers
Downsizing after listing
the important things that
are needed to be moved
Booking the
transportation needs
Hotel booking for the
family
Making arrangemnets for
storing the goods and
belongings of the family
Completion of
Requirements Gathering
Preparation for Shifting
Start of packing
Labelling each and every
things for better
identification
Arranging and packing
Buddy's belongings
Application for Address
Change
Taking admission of Will
and Lexei at school of
Perth
Appliccation for g utilities
in Perth
Arranging and Finishing
the packing of large items
Listing the Precious Items
Completion of Shifting
Preparation
Shifting
Checking if the gas
cylinders and air bottles
are swiched off
Disposal of the Flamable
liquids from the exisiting
house
Cancelling the
subscription of
newspaper
Making arrangements for
picking up the rubbish and
wastes
Making Partial payment
for relocation
Shifting all the large goods
in advance
Shifting the remaining
goods
Vacating the current
property
Checking in to the
hotelStaying in hotel till new
home is ready
Moving to the new
houseMoving the goods
Payment completion
Project Ends
Figure 2: Representing the WBS of Project
Appendix 2
The tasks and the associated resources are indicated in the figure below-

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13
Document Page
14
Figure 3: Representing the Task and the allocated resources
Appendix 3
The Gantt chart of the project is represented in the figure below-
Document Page
15

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16
Figure 4: Representing the Gantt Chart of the shifting project
(Source: Generated by Author using MS project)
The work activities marked in red in the Gantt chart above depict the critical path of the project