1 Table of Contents Introduction..........................................................................................................................2 1. Overview of the Scenario................................................................................................2 2. Criteria and Assumptions................................................................................................3 3. The Milestone Plan: The deliverables.............................................................................5 4. Task List and the Resources............................................................................................5 5. Gantt chart and Task Flow...............................................................................................5 6. Details of the Adjustments...............................................................................................6 7. Reflection.........................................................................................................................6 Conclusion...........................................................................................................................6 References............................................................................................................................8 Appendices........................................................................................................................10 Appendix 1.....................................................................................................................10 Appendix 2.....................................................................................................................12 Appendix 3.....................................................................................................................14
2 Introduction The purpose of this assignment is to plan and execute a shifting project for a family. The relocation project is complex since the family need to vacate their current property, way in advance. There are four members in the family, with two children. The family has a dog. For relocation, a four bedroom flat is already rented in Perth. However, it is essential for the family to vacate the property way before than they can move to the new house. Thus, the project plan is prepared considering all the major aspects and constraints in the project.The variances and the constraints in the project are considered in development of the project schedule. The report discusses the project overview, the criteria and the assumptions, the list of tasks along with the adjustments made. The project details are evaluated in the following paragraphs. 1. Overview of the Scenario The project aims in shifting a family to Perth. The family consists of two adults, Jeff and Kelly with their two children Lexie and Will. The family has a dog and two cars. Currently the family is living in a two bedroom rental apartment in Maroochydore and will be moving to their new house in Perth on 27thJanuary 2019. The main problem behind this relocation is that the family has to vacate their current property on 20thJanuary 2019. The new job of Jeff starts on 5th February 2019. In order to ensure that the entire relocation is smoothly completed including the transfer of all the goods, the family has hired a packers and movers company that will help them in moving all the goods including their car. After vacating the current property and prior to moving to the new house, the family needs to stay in a hotel and for that the family needs to pre book a hotel way in advance. This, is necessary since the family has no relative in Sunshine Coast. Apart from that, the family needs to apply for admission of their kids to a school in Perth..
3 The relocation project has certain operational complexities and therefore, the budget set for the project is $15,000. Kelly and Jeff needs to plan and manage the entire relocation project on their own.A plan for relocation is developed considering the complexity and the budget constraints associated with the project. The family can move to their new house in 27thof January and therefore, a project plan is developed accordingly. The school term in Perth commences from 31stJanuary and for that Jeff and Kelly needs to complete all the works on or before 30thJanuary 2019. It is mandatory for Jeff and Kelly to attend their children’s school and therefore, the entire shifting is completed before 31stJanuary 2019. The details about the exception and the assumptions associated with the project is highlighted in the section below. 2. Criteria and Assumptions Considering the information available and the key dates related to the project, a project plan is prepared. The most significant criteria associated with the project are as follows. 1. The Time constraint is considered prior to the development of project plan. 2. The budget constrain is considered prior to the development of the project plan. 3. The family needs to complete the entire shifting project before 31stJanuary since the school at Perth Commences from January 31st. 4. The family needs to vacate their current property in 20thJanuary 2019. 5. The family cannot move to the new house before the 27thJanuary 2019.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4 The above discussed points indicates the major criteria associated with the project. The projectplanandworkbreakdownstructure(WBS)ispreparedforthisshiftingproject considering these significant criteria of the shifting process. The project is a high priority project since the family will be relocating to a completely new location and therefore, no belongings or any important documents should be left behind. In order to ensure a smooth relocation, the family has taken help of Packers and Movers Company who will be helping the family to transfer all the necessary belongings along with their cars to Perth. The entire transportation of the goods and the shifting project will be supervised by Jeff and Kelly. The entire shifting is considered as a project lead by Jeff and Kelly, in order to develop a milestone plan for the project. The project is associated with two major milestones, which include completion of packing and Completion of shifting. The major assumptions related to the shifting project are as follows- 1. It is assumed that the task will be completed in the scheduled time. There will be no delays in the completion of each scheduled task in the project. 2. It is assumed that the budget of $15,000 will be sufficient for the family to relocate to the new location with all their belongings including their cars. 3. It is assumed that it is possible to relocate to a new location before 31stJanuary. 4. It is assumed that new house is completely ready for the family to move in. 5. It is assumed that there will be no changes in the rate in which the workers will be paid for the entire project work.
5 The above discussed points indicates the major assumptions related to the packing process. Since the entire packing will be supervised by Jeff and Kelly, the possibility of any errors in the relocation project is minimized. The project plan that is prepared should be followed in order to ensure a successful relocation of the entire family. If the family is able to follow the project plan in an efficient manner, it is possible to fulfil the most significant criteria of the project. However, while preparing the project schedule, certain adjustments are made, which are discussed in the later section of the report. 3. The Milestone Plan: The deliverables As discussed earlier, the project is associated with two major milestones, which are completion of the shifting preparation, that is, packing and completion of the shifting project. Accordingly, a project plan is prepared that highlights the major tasks and deliverables of the project along with the milestones of the project. The detailed work breakdown structure and the milestone plan along with the deliverables of the project is discussed in the appendix section (refer to appendix 1). 4. Task List and the Resources The tasks related to the project indicates the necessary tasks or works that are needed to be completed in order to ensure successful project completion. Since the complexity of the project is quite high, it was essential to complete all the vital tasks that are associated with the relocation project. The project plan indicates all the major tasks related to the project (refer to appendix 2). 5. Gantt chart and Task Flow
6 Along with the project plan, a schedule Gantt chart is prepared for the project that gives an idea of the scheduling and the duration of each of the tasks associated with the project. The task flow is indicated in the Gantt chart along with the indication of the critical tasks associated with the project (refer to appendix 3). 6. Details of the Adjustments It is assumed that the project has started on 19thDecember 2018. The project that that is prepared indicates that the project followed a sequential structure. The scheduling of the shifting project are adjusted as per the project criteria, that include, vacating the old house on 20thand moving to the new house on 27th. The tasks are scheduled in such a way that the entire project is completed before 30thJanuary so that the children face no problem in attending their school on 31stJanuary. 7. Reflection The scheduling complexity of this project was quite high that helped me to understand the different aspects of project scheduling and the need of planning a project prior to its implementation. I have planned and schedule the project related to shifting to a new house as per the requirements and the criteria of the project. There were certain constrains in the project, such as the budget, the time and the dates on which the old property was needed be vacated and movement to the new property. The entire project had been a good learning experience for me as it has helped me to understand the basic of project management and decision making. Conclusion
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7 The report discusses a case scenario of shifting a family to a new location. The family will be moving to a new house along with their belongings. The major criteria and the assumptions associated with the project is discussed in the report. The report gives an overview of the importance and need of project planning and scheduling. The project plan that is prepared, if followed without any deviation will ensure successful relocation of the family to Perth. The project plan is prepared in such a manner that the children will not miss their school while Jeff will have enough time in hand to join to the new office.
8 References Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Harrison, F. and Lock, D., 2017.Advanced project management: a structured approach. Routledge. Heagney, J., 2016.Fundamentals of project management. Amacom. Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking projectmanagementperformanceandprojectsuccess.Internationaljournalofproject management,32(2), pp.202-217. Leach, L.P., 2014.Critical chain project management. Artech House. Verzuh, E., 2015.The fast forward MBA in project management. John Wiley & Sons. Too, E.G. and Weaver, P., 2014. The management of projectmanagement: A conceptual framework for project governance.International Journal of Project Management,32(8), pp.1382-1394. Lock, D., 2017.The essentials of project management. Routledge. Martinelli,R.J.andMilosevic,D.Z.,2016.Projectmanagementtoolbox:toolsand techniques for the practicing project manager. John Wiley & Sons. Crawford, J.K., 2014.Project management maturity model. Auerbach Publications.
9 Kerzner,H.,2017.Projectmanagementmetrics,KPIs,anddashboards:aguideto measuring and monitoring project performance. John Wiley & Sons. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
12 Figure 1: Representing the Milestone Plan The work breakdown structure of the project is represented below- Shifting to Perth Start of the ProjectPlanning and Requirements Gathering Development of the inventory list and the list of tasks that are needed to be completed Hiring a packers and movers who would help the family in moving Gathering the packing needs with the help of the packers and movers Downsizing after listing the important things that are needed to be moved Booking the transportation needs Hotel booking for the family Making arrangemnets for storing the goods and belongings of the family Completion of Requirements Gathering Preparation for Shifting Start of packing Labelling each and every things for better identification Arranging and packing Buddy's belongings Application for Address Change Taking admission of Will and Lexei at school of Perth Appliccation for g utilities in Perth Arranging and Finishing the packing of large items Listing the Precious Items Completion of Shifting Preparation Shifting Checking if the gas cylinders and air bottles are swiched off Disposal of the Flamable liquids from the exisiting house Cancelling the subscription of newspaper Making arrangements for picking up the rubbish and wastes Making Partial payment for relocation Shifting all the large goods in advance Shifting the remaining goods Vacating the current property Checking in to the hotelStaying in hotel till new home is ready Moving to the new houseMoving the goods Payment completion Project Ends Figure 2: Representing the WBS of Project Appendix 2 The tasks and the associated resources are indicated in the figure below-
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16 Figure 4: Representing the Gantt Chart of the shifting project (Source: Generated by Author using MS project) The work activities marked in red in the Gantt chart above depict the critical path of the project