1PROJECT MANAGEMENT PLAN Table of Contents 1. Introduction to the Project...........................................................................................................3 2. Project Scope Statement..............................................................................................................3 2.1 Project Objectives..................................................................................................................3 2.2 Project Deliverable................................................................................................................4 2.3 Milestones..............................................................................................................................4 2.4 Technical Requirements........................................................................................................5 2.5 Limits and Exclusion.............................................................................................................5 2.6 Review with Customer..........................................................................................................5 3. Establish Project Priorities...........................................................................................................5 3.1 Project Priority Matrix...........................................................................................................6 3.2 Justification of the Priority Matrix........................................................................................6 4. Create Work Breakdown Structure..............................................................................................7 4.1 Work Breakdown Diagram....................................................................................................7 4.2 Indented Work Breakdown Structure....................................................................................8 5. Cost Estimation............................................................................................................................9 5.1 Phases by Cost Expenses.....................................................................................................10 5.2 Resource usage cost estimation...........................................................................................11 Bibliography..................................................................................................................................12
2PROJECT MANAGEMENT PLAN
3PROJECT MANAGEMENT PLAN 1. Introduction to the Project The project of 1 day sports tournament for a company involves the deployment of the effective management of the system integration and development. The project is developed for containing the project plan formation and its implementation for the development of the effective one day sports event for the organization. The implication of the project integration activities should be used for ensuring that the operations of the project are completed in the estimated time duration. The project of 1 day sports tournament for a company includes the activities like project initialization, project planning, plan execution, sports event site development, event invitation and schedule development, sports event day, and project is closed. 2. Project Scope Statement The project scope statement for the project of 1 day sports tournament for a company consists of six points namely project objectives, deliverables, milestones, technical requirements, constraints, and project exclusions. These factors have been explained below, 2.1 Project Objectives The 1 day sports tournament for a company project has been developed for ensuring that the one day sports event would be completed in the estimated time duration and budget estimation. ï‚·To develop an event of one day for organizing sports event for the company ï‚·To complete the project in the estimated time and budget ï‚·To form the operation for the development of the project successfully
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT MANAGEMENT PLAN 2.2 Project Deliverable The 1 day sports tournament for a company project deliverables includes the documents required for the project, project plan, guests list, event site development, and completion of the project of one day sports tournament. The deliverables have been given in the table below, WBSTask NameDurationStartFinish 1.3Submission of documents1 dayTue 12/19/17Tue 12/19/17 2.4Complete Plan is developed4 daysFri 12/29/17Wed 1/3/18 3.1.6Site Review2 daysTue 1/23/18Wed 1/24/18 3.2.1Making list of people as audiences and guests1 dayFri 1/26/18Fri 1/26/18 4Project is Closed1 dayMon 2/12/18Mon 2/12/18 2.3 Milestones The 1 day sports tournament for company project milestones consists of the following achievements, a)Proper Project scheduling that includes the initialization of the project activities along with specific project operations b)Completion of the project in estimated time duration is another major criterion for the project c)Use of the project resources smartly for ensuring the completion of the individual project activities
5PROJECT MANAGEMENT PLAN 2.4 Technical Requirements The 1 day sports tournament for a company project scope description includes the use of the project management concepts and principles for the development of the effective analysis methods. The technical requirements of the project are project plan, cost budget, resource usage, risk management plan, site development, first aid and safety kits, and other equipments. 2.5 Limits and Exclusion The time, budget, and quality of the project outcomes are the limitations of the project of 1 day sports tournament for a company. On the contrary, the availability of the resources, understanding of the project management principles, and use of technology are the acceptance of theprojectof1daysportstournamentforacompany.Thechangemanagementplan, communicationplan,transportationrequirements,andriskmanagementarenotapart (exclusions) of 1 day sports tournament for a company project. 2.6 Review with Customer The review with customers can be achieved by the deployment of the specific project alignment and integration. The customer’s feedbacks and documentation would be helpful in aligning the specific changes and modification as required. The plan for holding the event of 1 day sports for the company would be helpful for aligning the specific alignment of the operations. The customer review feedbacks can be taken by the use of the surveys and questionnaire fill up. 3. Establish Project Priorities
6PROJECT MANAGEMENT PLAN 3.1 Project Priority Matrix The project of 1 day sports tournament for a company is dependent on the time, performance, and cost factor that is shown below, TimePerformanceCost Constrain Enhance Accept 3.2 Justification of the Priority Matrix The justification of the priority matrix fort the project of 1 day sports tournament for a company is given below, Time: The time taken for the project would be a primary constrain and it would ensure that the project would work simultaneously for developing the effective sports event for a day. The reason behind keeping time as a constraint is because the event is limited to one day and the duration of the event cannot be increased. Performance: The performance plays a crucial factor for project of the 1 day sports tournament for a company as it would involve the limitation of the project for the significant option. The analysis of the performance can assist in increasing the overall pace of operations and hence the performance has been kept in enhance in the priority matrix
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT MANAGEMENT PLAN Cost: The 1 day sports tournament for a company project has cost as the factor of acceptance as it is probable that the overall expenses of the project must be managed. The cost expense have to be accepted by the project managers and there is no exemption from it. 4. Create Work Breakdown Structure A work breakdown structure depicts the activities of the project in terms of a defined sequence of activities in multiple phases. The work breakdown structure for the project of 1 day sports tournament for a company can be shown both in table format and in diagram. 4.1 Work Breakdown Diagram The work breakdown structure for the project of 1 day sports tournament for a company is shown below, 0- 1 day sports tournament for a company 1- Project Initialization 1.1- Development of Initiation Document 1.2- Project Charter Documentation 1.3- Submission of documents 1.4- Signing off the documents 2- Project Planning 2.1- Selection of plan methodology 2.2- Developing Plan outline 2.3- Review of the plan outline 2.4- Complete Plan is developed 2.5- Plan is approved 3- Plan Execution 3.1- Sports Event Site Development 3.1.1- Selection of site 3.1.2- Site Clearance for event 3.1.3- Structure and facilities installation 3.1.4- Seating Arrangement, restroom facilities, and other equipments are installed 3.1.5- Safety and Health kit deployment 3.1.6- Site Review 3.1.7- Site is approved 3.2- Event Invitation and Schedule development 3.2.1- Making list of people as audiences and guests 3.2.2- Participants list is made 3.2.3- Event guests are sent E-vites and invitations by other means 3.2.4- Participants are given time for practicing 3.2.5- RSVPs of guests are collected 3.3- Sports Event Day 3.3.1- Testing of equipments, sounds, and camera 3.3.2- All participants and guests facility arrangement is checked 3.3.3- Welcoming the guests and participants 3.3.4- First half of sports event is done 3.3.5- Lunch Break is taken place 3.3.6- Second half of the sports event is done 3.3.7- Prizes are distributed 3.3.8- Thank you to all 4- Project is Closed
8PROJECT MANAGEMENT PLAN Figure 1: Work Breakdown Structure for the Project (Source: Create by the author) 4.2 Indented Work Breakdown Structure The indented work breakdown structure for the project of 1 day sports tournament for a company is given below, WBSTask Name 01 day sports tournament for a company 1Project Initialization 1.1Development of Initiation Document 1.2Project Charter Documentation 1.3Submission of documents 1.4Signing off the documents 2Project Planning 2.1Selection of plan methodology 2.2Developing Plan outline 2.3Review of the plan outline 2.4Complete Plan is developed 2.5Plan is approved 3Plan Execution 3.1Sports Event Site Development 3.1.1Selection of site 3.1.2Site Clearance for event 3.1.3Structure and facilities installation
9PROJECT MANAGEMENT PLAN 3.1.4Seating Arrangement, restroom facilities, and other equipments are installed 3.1.5Safety and Health kit deployment 3.1.6Site Review 3.1.7Site is approved 3.2Event Invitation and Schedule development 3.2.1Making list of people as audiences and guests 3.2.2Participants list is made 3.2.3Event guests are sent E-vites and invitations by other means 3.2.4Participants are given time for practicing 3.2.5RSVPs of guests are collected 3.3Sports Event Day 3.3.1Testing of equipments, sounds, and camera 3.3.2All participants and guests facility arrangement is checked 3.3.3Welcoming the guests and participants 3.3.4First half of sports event is done 3.3.5Lunch Break is taken place 3.3.6Second half of the sports event is done 3.3.7Prizes are distributed 3.3.8Thank you to all 4Project is Closed Table 1: Indented WBS for the project (Source: Created by the author) 5. Cost Estimation
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT MANAGEMENT PLAN The cost estimation for the project of 1 day sports tournament for a company is shown in the following two sections. 5.1 Phases by Cost Expenses WBSTask NameCost 1Project Initialization$4,720.00 2Project Planning$5,600.00 3.1Sports Event Site Development$28,650.00 3.2Event Invitation and Schedule development$6,673.75 3.3Sports Event Day$3,556.25 4Project is Closed$800.00 Grand Total$50,000.00 Table 2: Cost Estimation in terms of phases for project (Source: Created by the author)
11PROJECT MANAGEMENT PLAN Project InitializationProject PlanningSports Event Site Development Event Invitation and Schedule development Sports Event DayProject is Closed $0.00 $5,000.00 $10,000.00 $15,000.00 $20,000.00 $25,000.00 $30,000.00 $35,000.00 $4,720.00$5,600.00 $28,650.00 $6,673.75 $3,556.25 $800.00 Phase-wise Cost Estimation Figure 2: Bar chart showing Cost Estimation in terms of phases for project (Source: Created by the author) 5.2 Resource usage cost estimation Resource NameResource typeResource UsageStd. RateCost DocumenterHuman56 hrs$70.00/hr$3,920.00 Project ManagerHuman64 hrs$100.00/hr$6,400.00 PlannerHuman64 hrs$50.00/hr$3,200.00 Event CoordinatorHuman120.25 hrs$75.00/hr$9,018.75 ContractorHuman40 hrs$90.00/hr$3,600.00 WorkersHuman16 hrs$80.00/hr$1,280.00 VolunteersHuman1.42 hrs$50.00/hr$70.83 SpeakerHuman25.33 hrs$50.00/hr$1,266.67 ParticipantsHuman6.75 hrs$0.00/hr$0.00 AudienceHuman0.5 hrs$0.00/hr$0.00
12PROJECT MANAGEMENT PLAN Site RentMaterial1.00$6,200.00$6,200.00 EquipmentsMaterial1.00$3,000.00$3,000.00 Sound SystemMaterial1.00$1,500.00$1,500.00 Cameras and RecordingsMaterial1.00$2,000.00$2,000.00 SeatsMaterial1.00$3,000.00$3,000.00 PrizesMaterial1.00$1,400.00$1,400.00 Food and beverageMaterial1.00$2,000.00$2,000.00 Health Kit and Safety EquipmentsMaterial1.00$1,470.00$1,470.00 Invitation CostMaterial1.00$673.75$673.75 Total Budget$50,000.00 Table 3: Project Budget Estimation in terms of resource usages (Source: Created by the author) Bibliography Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute. Kerzner, H. (2013).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Larson, E. W., & Gray, C. (2013).Project Management: The Managerial Process with MS Project. McGraw-Hill. Leach, L. P. (2014).Critical chain project management. Artech House.