This article discusses the cost management of the construction project of Sunshine Coast Airport. It covers topics such as estimated cost, cost baseline, cash flow, contingency and specific exclusion, reporting, monitoring and control, change control, and more. The article provides a detailed analysis of the cost management process and its importance in successfully completing the project within the approved budget.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT MANAGEMENT
Case Study- Sunshine Coast Airport
Name of the Student
Name of the University
Author’s Note
Case Study- Sunshine Coast Airport
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1
PROJECT MANAGEMENT
Table of Contents
8. Cost /budget management......................................................................................................2
8.4 Estimated cost..................................................................................................................2
8.5 Cost baseline..................................................................................................................10
8.5.1 Cash Flow................................................................................................................10
8.5.2 Contingency and specific exclusion........................................................................11
8.5.3 Reporting.................................................................................................................11
8.6 Cost monitoring and control...........................................................................................11
8.7 Cost change control........................................................................................................12
8.8 Cost Closing...................................................................................................................12
Bibliography.............................................................................................................................14
PROJECT MANAGEMENT
Table of Contents
8. Cost /budget management......................................................................................................2
8.4 Estimated cost..................................................................................................................2
8.5 Cost baseline..................................................................................................................10
8.5.1 Cash Flow................................................................................................................10
8.5.2 Contingency and specific exclusion........................................................................11
8.5.3 Reporting.................................................................................................................11
8.6 Cost monitoring and control...........................................................................................11
8.7 Cost change control........................................................................................................12
8.8 Cost Closing...................................................................................................................12
Bibliography.............................................................................................................................14
2
PROJECT MANAGEMENT
8. Cost /budget management
8.4 Estimated cost
It is found that in order to construct the runway for the Sunshine Coast Airport, the
council requests the Common wealth Government for investing $122 million. It is analyzed
that the construction of the runway for the Sunshine Coast Airport would be estimated to get
completed within the budget that is around $ 121,582,480.00. The table that is provided
below reflects on the cost that is needed for executing each of the activities of the project.
Task Name Duration Start Finish Predecessors
Resource
Names
Cost
Construction
of runway in
Sunshine
Coast Airport
572 days
Mon 22-
10-18
Tue 29-12-
20
$
121,582,480.00
Initiation
phase
95 days
Mon 22-
10-18
Fri 01-03-
19
$ 73,800.00
Business
case
development
20 days
Mon 22-10-
18
Fri 16-11-
18
Project
manager
$ 9,600.00
Undertaking
feasibility
22 days Mon 19-11-
18
Tue 18-12-
18
2 Financial
manager,
Project
$ 17,600.00
PROJECT MANAGEMENT
8. Cost /budget management
8.4 Estimated cost
It is found that in order to construct the runway for the Sunshine Coast Airport, the
council requests the Common wealth Government for investing $122 million. It is analyzed
that the construction of the runway for the Sunshine Coast Airport would be estimated to get
completed within the budget that is around $ 121,582,480.00. The table that is provided
below reflects on the cost that is needed for executing each of the activities of the project.
Task Name Duration Start Finish Predecessors
Resource
Names
Cost
Construction
of runway in
Sunshine
Coast Airport
572 days
Mon 22-
10-18
Tue 29-12-
20
$
121,582,480.00
Initiation
phase
95 days
Mon 22-
10-18
Fri 01-03-
19
$ 73,800.00
Business
case
development
20 days
Mon 22-10-
18
Fri 16-11-
18
Project
manager
$ 9,600.00
Undertaking
feasibility
22 days Mon 19-11-
18
Tue 18-12-
18
2 Financial
manager,
Project
$ 17,600.00
3
PROJECT MANAGEMENT
study of the
project
planner
Establishing
project charter
26 days
Wed 19-12-
18
Wed 23-
01-19
3
Project
manager,
Project
planner
$ 23,920.00
Appointment
of team
members
27 days
Thu 24-01-
19
Fri 01-03-
19
4
Project
manager,
HR.
manager
$ 22,680.00
Milestone
1: Performing
phase review
0 days
Fri 01-03-
19
Fri 01-03-
19
5 $ 0.00
Planning
phase
137 days
Mon 04-
03-19
Tue 10-09-
19
$ 82,000.00
Development
of project plan
25 days
Mon 04-03-
19
Fri 05-04-
19
5
Project
manager,
Project
planner
$ 23,000.00
22 days Mon 08-04- Tue 07-05- 8 Hr. manager $ 7,920.00
PROJECT MANAGEMENT
study of the
project
planner
Establishing
project charter
26 days
Wed 19-12-
18
Wed 23-
01-19
3
Project
manager,
Project
planner
$ 23,920.00
Appointment
of team
members
27 days
Thu 24-01-
19
Fri 01-03-
19
4
Project
manager,
HR.
manager
$ 22,680.00
Milestone
1: Performing
phase review
0 days
Fri 01-03-
19
Fri 01-03-
19
5 $ 0.00
Planning
phase
137 days
Mon 04-
03-19
Tue 10-09-
19
$ 82,000.00
Development
of project plan
25 days
Mon 04-03-
19
Fri 05-04-
19
5
Project
manager,
Project
planner
$ 23,000.00
22 days Mon 08-04- Tue 07-05- 8 Hr. manager $ 7,920.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4
PROJECT MANAGEMENT
Development
of resource
plan
19 19
Development
of financial
plan
20 days
Wed 08-05-
19
Tue 04-06-
19
9
Financial
manager
$ 7,200.00
Development
of quality plan
25 days
Wed 05-06-
19
Tue 09-07-
19
10
Quality
analyst,
Team
members
$ 18,000.00
Development
of risk
management
plan
23 days
Wed 10-07-
19
Fri 09-08-
19
11
Risk
manager
$ 8,280.00
Development
of
communication
22 days Mon 12-08-
19
Tue 10-09-
19
12 Hr.
manager,
Project
$ 17,600.00
PROJECT MANAGEMENT
Development
of resource
plan
19 19
Development
of financial
plan
20 days
Wed 08-05-
19
Tue 04-06-
19
9
Financial
manager
$ 7,200.00
Development
of quality plan
25 days
Wed 05-06-
19
Tue 09-07-
19
10
Quality
analyst,
Team
members
$ 18,000.00
Development
of risk
management
plan
23 days
Wed 10-07-
19
Fri 09-08-
19
11
Risk
manager
$ 8,280.00
Development
of
communication
22 days Mon 12-08-
19
Tue 10-09-
19
12 Hr.
manager,
Project
$ 17,600.00
5
PROJECT MANAGEMENT
plan planner
Milestone
2: Completion
of planning
phase
0 days
Tue 10-09-
19
Tue 10-09-
19
13 $ 0.00
Designing
phase
72 days
Wed 11-
09-19
Thu 19-
12-19
$ 75,160.00
Developing
design for the
development
of runway
27 days
Wed 11-09-
19
Thu 17-10-
19
13
Contractor,
Team
members
$ 20,520.00
Completion of
the design
20 days
Fri 18-10-
19
Thu 14-11-
19
16
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 30,400.00
Cross-
checking of the
design
18 days Fri 15-11-
19
Tue 10-12-
19
17 Supervisor,
Quality
analyst, Risk
$ 20,880.00
PROJECT MANAGEMENT
plan planner
Milestone
2: Completion
of planning
phase
0 days
Tue 10-09-
19
Tue 10-09-
19
13 $ 0.00
Designing
phase
72 days
Wed 11-
09-19
Thu 19-
12-19
$ 75,160.00
Developing
design for the
development
of runway
27 days
Wed 11-09-
19
Thu 17-10-
19
13
Contractor,
Team
members
$ 20,520.00
Completion of
the design
20 days
Fri 18-10-
19
Thu 14-11-
19
16
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 30,400.00
Cross-
checking of the
design
18 days Fri 15-11-
19
Tue 10-12-
19
17 Supervisor,
Quality
analyst, Risk
$ 20,880.00
6
PROJECT MANAGEMENT
manager
Approval
of the design
7 days
Wed 11-12-
19
Thu 19-12-
19
18
Project
manager
$ 3,360.00
Milestone
4: Completion
of the design
0 days
Thu 19-12-
19
Thu 19-12-
19
19 $ 0.00
Execution
phase
238 days
Fri 20-12-
19
Tue 17-11-
20
$
121,333,200.00
Development
of east-west
runway
45 days
Fri 20-12-
19
Thu 20-02-
20
19
Contractor,
Supervisor,
Project
requirements
[1], Sub-
contractor
$
91,054,000.00
Development
of runway
infrastructure
40 days Fri 21-02-
20
Thu 16-04-
20
22 Contractor,
Additional
cost [1],
Supervisor,
Sub-
$
30,048,000.00
PROJECT MANAGEMENT
manager
Approval
of the design
7 days
Wed 11-12-
19
Thu 19-12-
19
18
Project
manager
$ 3,360.00
Milestone
4: Completion
of the design
0 days
Thu 19-12-
19
Thu 19-12-
19
19 $ 0.00
Execution
phase
238 days
Fri 20-12-
19
Tue 17-11-
20
$
121,333,200.00
Development
of east-west
runway
45 days
Fri 20-12-
19
Thu 20-02-
20
19
Contractor,
Supervisor,
Project
requirements
[1], Sub-
contractor
$
91,054,000.00
Development
of runway
infrastructure
40 days Fri 21-02-
20
Thu 16-04-
20
22 Contractor,
Additional
cost [1],
Supervisor,
Sub-
$
30,048,000.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7
PROJECT MANAGEMENT
contractor
Accessing
traditional
airside land
35 days
Fri 17-04-
20
Thu 04-06-
20
23
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 53,200.00
Terminal
development
34 days
Fri 05-06-
20
Wed 22-
07-20
24
Contractor,
Hr.
manager,
Sub-
contractor,
Team
members
$ 50,320.00
Enhancement
to the existing
taxiway and
apron system
32 days Thu 23-07-
20
Fri 04-09-
20
25 Contractor,
Supervisor,
Sub-
contractor,
Team
$ 48,640.00
PROJECT MANAGEMENT
contractor
Accessing
traditional
airside land
35 days
Fri 17-04-
20
Thu 04-06-
20
23
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 53,200.00
Terminal
development
34 days
Fri 05-06-
20
Wed 22-
07-20
24
Contractor,
Hr.
manager,
Sub-
contractor,
Team
members
$ 50,320.00
Enhancement
to the existing
taxiway and
apron system
32 days Thu 23-07-
20
Fri 04-09-
20
25 Contractor,
Supervisor,
Sub-
contractor,
Team
$ 48,640.00
8
PROJECT MANAGEMENT
members
Long term
protection of
airspace
30 days
Mon 07-09-
20
Fri 16-10-
20
26
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 45,600.00
Reservation of
land
22 days
Mon 19-10-
20
Tue 17-11-
20
27
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 33,440.00
Milestone
5: Completion
of execution
phase
0 days
Tue 17-11-
20
Tue 17-11-
20
28 $ 0.00
Closure
phase
30 days
Wed 18-
11-20
Tue 29-12-
20
$ 18,320.00
Post 12 days Wed 18-11- Thu 03-12- 28 Project $ 5,280.00
PROJECT MANAGEMENT
members
Long term
protection of
airspace
30 days
Mon 07-09-
20
Fri 16-10-
20
26
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 45,600.00
Reservation of
land
22 days
Mon 19-10-
20
Tue 17-11-
20
27
Contractor,
Supervisor,
Sub-
contractor,
Team
members
$ 33,440.00
Milestone
5: Completion
of execution
phase
0 days
Tue 17-11-
20
Tue 17-11-
20
28 $ 0.00
Closure
phase
30 days
Wed 18-
11-20
Tue 29-12-
20
$ 18,320.00
Post 12 days Wed 18-11- Thu 03-12- 28 Project $ 5,280.00
9
PROJECT MANAGEMENT
project review 20 20 planner
Stakeholder
sign off
8 days
Fri 04-12-
20
Tue 15-12-
20
31
Project
manager
$ 3,840.00
Documentation
10 days
Wed 16-12-
20
Tue 29-12-
20
32
Project
manager,
Project
planner
$ 9,200.00
Milestone
6: Completion
of closure
phase
0 days
Tue 29-12-
20
Tue 29-12-
20
33 $ 0.00
8.5 Cost baseline
8.5.1 Cash Flow
Project cash flow is considered as one of the parts of financial planning in order to
understand the cost that is utilized on a monthly basis in order to complete the progress of the
entire project. The cash flow is helpful in projecting the earnings, schedule planning as well
as for making the operation of the project quite efficiently. Moreover, it is found that the
cash flow assists in organizing the plan as well as helps in improving the incoming cash flow.
The cash flow for the project “Construction of runway in Sunshine Coast Airport” is provided
below:
PROJECT MANAGEMENT
project review 20 20 planner
Stakeholder
sign off
8 days
Fri 04-12-
20
Tue 15-12-
20
31
Project
manager
$ 3,840.00
Documentation
10 days
Wed 16-12-
20
Tue 29-12-
20
32
Project
manager,
Project
planner
$ 9,200.00
Milestone
6: Completion
of closure
phase
0 days
Tue 29-12-
20
Tue 29-12-
20
33 $ 0.00
8.5 Cost baseline
8.5.1 Cash Flow
Project cash flow is considered as one of the parts of financial planning in order to
understand the cost that is utilized on a monthly basis in order to complete the progress of the
entire project. The cash flow is helpful in projecting the earnings, schedule planning as well
as for making the operation of the project quite efficiently. Moreover, it is found that the
cash flow assists in organizing the plan as well as helps in improving the incoming cash flow.
The cash flow for the project “Construction of runway in Sunshine Coast Airport” is provided
below:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10
PROJECT MANAGEMENT
October 2018
December 2018
February 2019
April 2019
June 2019
August 2019
October 2019
December 2019
February 2020
April 2020
June 2020
August 2020
October 2020
December 2020
$ 0.00
$ 5,000,000.00
$ 10,000,000.00
$ 15,000,000.00
$ 20,000,000.00
$ 25,000,000.00
$ 30,000,000.00
$ 35,000,000.00
$ 40,000,000.00
$ 45,000,000.00
$ 50,000,000.00
Cash Flow
Cost
Figure 1: Cash Flow for the project “Construction of runway in Sunshine Coast
Airport”
(Source: Created by Author)
8.5.2 Contingency and specific exclusion
The specific exclusion contingency as well as exclusion are generally elaborated
below:
The cost that is needed for the project is assumed but however if the time that
is needed for finishing the project extends then there will be rise in the need of
the total budget of the project.
It is found that the budget that is needed for the requirement of the project is
estimated but the rise in the prices of the project requirements is unpredictable.
The cost that is associated with the human resources can enhance with the
enhancing need of the human resources in order to finish the work of the
project quite efficiently.
PROJECT MANAGEMENT
October 2018
December 2018
February 2019
April 2019
June 2019
August 2019
October 2019
December 2019
February 2020
April 2020
June 2020
August 2020
October 2020
December 2020
$ 0.00
$ 5,000,000.00
$ 10,000,000.00
$ 15,000,000.00
$ 20,000,000.00
$ 25,000,000.00
$ 30,000,000.00
$ 35,000,000.00
$ 40,000,000.00
$ 45,000,000.00
$ 50,000,000.00
Cash Flow
Cost
Figure 1: Cash Flow for the project “Construction of runway in Sunshine Coast
Airport”
(Source: Created by Author)
8.5.2 Contingency and specific exclusion
The specific exclusion contingency as well as exclusion are generally elaborated
below:
The cost that is needed for the project is assumed but however if the time that
is needed for finishing the project extends then there will be rise in the need of
the total budget of the project.
It is found that the budget that is needed for the requirement of the project is
estimated but the rise in the prices of the project requirements is unpredictable.
The cost that is associated with the human resources can enhance with the
enhancing need of the human resources in order to finish the work of the
project quite efficiently.
11
PROJECT MANAGEMENT
8.5.3 Reporting
Reporting is very much necessary within the project in order to track the status of the
budget that is generally utilized within the project in order to achieve progress. The
information related with the utilization of project budget should be informed to the higher
management of the project with the help of tracking so that they keep track on the status as
well as utilization of budget. It is found that reporting plays an important role in managing
the budget successfully so that entire project can be successfully completed within the budget
that is approved by the Common wealth Government.
Project reporting assists in tracking, identifying risks, managing the cost of the
project as well as helps in increasing the visibility of the entire organization. Regression
Moreover, the reporting assists in controlling the project in order to allow the progress,
stagnation as well as regress of certain elements. In addition to this, it assists in checking how
the team members of the project are performing.
8.6 Cost monitoring and control
The steps for monitoring as well as controlling the cost of the project are listed below:
Monitoring project planning: It is necessary to monitor as well as control the
various parameters of the project including schedule costing, timeline. It is quite necessary
for the project managers to successfully track the different project metrics so that cost of the
project can be controlled as well as monitored effectively.
Monitoring commitments: It is also necessary to track the commitment of the
stakeholders within the project including completion of post project reviews and for ensuring
that the entire project gets completed within the budget that is approved.
PROJECT MANAGEMENT
8.5.3 Reporting
Reporting is very much necessary within the project in order to track the status of the
budget that is generally utilized within the project in order to achieve progress. The
information related with the utilization of project budget should be informed to the higher
management of the project with the help of tracking so that they keep track on the status as
well as utilization of budget. It is found that reporting plays an important role in managing
the budget successfully so that entire project can be successfully completed within the budget
that is approved by the Common wealth Government.
Project reporting assists in tracking, identifying risks, managing the cost of the
project as well as helps in increasing the visibility of the entire organization. Regression
Moreover, the reporting assists in controlling the project in order to allow the progress,
stagnation as well as regress of certain elements. In addition to this, it assists in checking how
the team members of the project are performing.
8.6 Cost monitoring and control
The steps for monitoring as well as controlling the cost of the project are listed below:
Monitoring project planning: It is necessary to monitor as well as control the
various parameters of the project including schedule costing, timeline. It is quite necessary
for the project managers to successfully track the different project metrics so that cost of the
project can be controlled as well as monitored effectively.
Monitoring commitments: It is also necessary to track the commitment of the
stakeholders within the project including completion of post project reviews and for ensuring
that the entire project gets completed within the budget that is approved.
12
PROJECT MANAGEMENT
Monitoring risks: The risks as well as challenges which are associated with the
project must be tracked such that the entire project gets completed within the expected
budget.
Conducting progress review: Progress review is quite important for the project as it
helps in tracking the budget utilized in completing each phase of the project successfully.
8.7 Cost change control
Cost control is defined as one of the procedures that is mainly utilized in order to
influence the factors that are generally helpful in developing the variances as well as
controlling changes within the budget of the project. The controlling process of project
control helps in handling influencing factors, managing the changes within the actual cost as
well as comparing the reported real values with the approved baseline of the cost. It is very
much necessary to keep some budget as buffer for the project so that any changes within the
cost of the project can be managed successfully without facing any type of financial issues
and challenges.
The changes within the project generally comes either with the cost or with the
project baseline. In order to support the additional needs, it is quite necessary for the
organization as well as its stakeholders to follow the change control procedure quite
effectively. Changes within the requirement of the project will generally be helpful in
changing the cost of the project. It is quite necessary to follow proper change control
procedure for getting information from the project manager in order to finish the change
request form which will be helpful in reviewing the changes within the team for assessing the
effect on the project. Both the change request as well as the estimated impact on the cost of
the project will be presented to the project sponsor for getting their consideration. The project
PROJECT MANAGEMENT
Monitoring risks: The risks as well as challenges which are associated with the
project must be tracked such that the entire project gets completed within the expected
budget.
Conducting progress review: Progress review is quite important for the project as it
helps in tracking the budget utilized in completing each phase of the project successfully.
8.7 Cost change control
Cost control is defined as one of the procedures that is mainly utilized in order to
influence the factors that are generally helpful in developing the variances as well as
controlling changes within the budget of the project. The controlling process of project
control helps in handling influencing factors, managing the changes within the actual cost as
well as comparing the reported real values with the approved baseline of the cost. It is very
much necessary to keep some budget as buffer for the project so that any changes within the
cost of the project can be managed successfully without facing any type of financial issues
and challenges.
The changes within the project generally comes either with the cost or with the
project baseline. In order to support the additional needs, it is quite necessary for the
organization as well as its stakeholders to follow the change control procedure quite
effectively. Changes within the requirement of the project will generally be helpful in
changing the cost of the project. It is quite necessary to follow proper change control
procedure for getting information from the project manager in order to finish the change
request form which will be helpful in reviewing the changes within the team for assessing the
effect on the project. Both the change request as well as the estimated impact on the cost of
the project will be presented to the project sponsor for getting their consideration. The project
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13
PROJECT MANAGEMENT
sponsor will generally determine that whether the changes is significant enough for making
medications as per the required changes within the cost of the project.
8.8 Cost Closing
It is found that the project “Construction of runway in Sunshine Coast Airport” will
be completed successfully within the budget that is approved. It is found that the entire
activities of the project successfully get completed within the budget that is around
$121,580,482.00 which is under budget. The table reflects that as the entire project gets
completed within the budget that is estimated for each of the project activities is mainly
reflected with the help of the table that is generally provided below:
Task Name Duration Start Finish Cost
Signature of the
stakeholders
Construction of
runway in
Sunshine Coast
Airport
572 days
Mon 22-10-
18
Tue 29-12-
20
$ 121,582,480.00
Initiation
phase
95 days
Mon 22-10-
18
Fri 01-03-19 $ 73,800.00
Business case
development
20 days
Mon 22-10-
18
Fri 16-11-18 $ 9,600.00
Undertaking
feasibility study
22 days Mon 19-11-
18
Tue 18-12-
18
$ 17,600.00
PROJECT MANAGEMENT
sponsor will generally determine that whether the changes is significant enough for making
medications as per the required changes within the cost of the project.
8.8 Cost Closing
It is found that the project “Construction of runway in Sunshine Coast Airport” will
be completed successfully within the budget that is approved. It is found that the entire
activities of the project successfully get completed within the budget that is around
$121,580,482.00 which is under budget. The table reflects that as the entire project gets
completed within the budget that is estimated for each of the project activities is mainly
reflected with the help of the table that is generally provided below:
Task Name Duration Start Finish Cost
Signature of the
stakeholders
Construction of
runway in
Sunshine Coast
Airport
572 days
Mon 22-10-
18
Tue 29-12-
20
$ 121,582,480.00
Initiation
phase
95 days
Mon 22-10-
18
Fri 01-03-19 $ 73,800.00
Business case
development
20 days
Mon 22-10-
18
Fri 16-11-18 $ 9,600.00
Undertaking
feasibility study
22 days Mon 19-11-
18
Tue 18-12-
18
$ 17,600.00
14
PROJECT MANAGEMENT
of the project
Establishing
project charter
26 days
Wed 19-12-
18
Wed 23-01-
19
$ 23,920.00
Appointment
of team members
27 days Thu 24-01-19 Fri 01-03-19 $ 22,680.00
Milestone 1:
Performing phase
review
0 days Fri 01-03-19 Fri 01-03-19 $ 0.00
Planning
phase
137 days
Mon 04-03-
19
Tue 10-09-
19
$ 82,000.00
Development
of project plan
25 days
Mon 04-03-
19
Fri 05-04-19 $ 23,000.00
Development
of resource plan
22 days
Mon 08-04-
19
Tue 07-05-
19
$ 7,920.00
Development
of financial plan
20 days
Wed 08-05-
19
Tue 04-06-
19
$ 7,200.00
Development
of quality plan
25 days
Wed 05-06-
19
Tue 09-07-
19
$ 18,000.00
Development
of risk
23 days Wed 10-07- Fri 09-08-19 $ 8,280.00
PROJECT MANAGEMENT
of the project
Establishing
project charter
26 days
Wed 19-12-
18
Wed 23-01-
19
$ 23,920.00
Appointment
of team members
27 days Thu 24-01-19 Fri 01-03-19 $ 22,680.00
Milestone 1:
Performing phase
review
0 days Fri 01-03-19 Fri 01-03-19 $ 0.00
Planning
phase
137 days
Mon 04-03-
19
Tue 10-09-
19
$ 82,000.00
Development
of project plan
25 days
Mon 04-03-
19
Fri 05-04-19 $ 23,000.00
Development
of resource plan
22 days
Mon 08-04-
19
Tue 07-05-
19
$ 7,920.00
Development
of financial plan
20 days
Wed 08-05-
19
Tue 04-06-
19
$ 7,200.00
Development
of quality plan
25 days
Wed 05-06-
19
Tue 09-07-
19
$ 18,000.00
Development
of risk
23 days Wed 10-07- Fri 09-08-19 $ 8,280.00
15
PROJECT MANAGEMENT
management plan 19
Development
of
communication
plan
22 days
Mon 12-08-
19
Tue 10-09-
19
$ 17,600.00
Milestone 2:
Completion of
planning phase
0 days Tue 10-09-19
Tue 10-09-
19
$ 0.00
Designing
phase
72 days
Wed 11-09-
19
Thu 19-12-
19
$ 75,160.00
Developing
design for the
development of
runway
27 days
Wed 11-09-
19
Thu 17-10-
19
$ 20,520.00
Completion
of the design
20 days Fri 18-10-19
Thu 14-11-
19
$ 30,400.00
Cross-
checking of the
design
18 days Fri 15-11-19
Tue 10-12-
19
$ 20,880.00
PROJECT MANAGEMENT
management plan 19
Development
of
communication
plan
22 days
Mon 12-08-
19
Tue 10-09-
19
$ 17,600.00
Milestone 2:
Completion of
planning phase
0 days Tue 10-09-19
Tue 10-09-
19
$ 0.00
Designing
phase
72 days
Wed 11-09-
19
Thu 19-12-
19
$ 75,160.00
Developing
design for the
development of
runway
27 days
Wed 11-09-
19
Thu 17-10-
19
$ 20,520.00
Completion
of the design
20 days Fri 18-10-19
Thu 14-11-
19
$ 30,400.00
Cross-
checking of the
design
18 days Fri 15-11-19
Tue 10-12-
19
$ 20,880.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
16
PROJECT MANAGEMENT
Approval of
the design
7 days
Wed 11-12-
19
Thu 19-12-
19
$ 3,360.00
Milestone 4:
Completion of
the design
0 days Thu 19-12-19
Thu 19-12-
19
$ 0.00
Execution
phase
238 days Fri 20-12-19
Tue 17-11-
20
$ 121,333,200.00
Development
of east-west
runway
45 days Fri 20-12-19
Thu 20-02-
20
$ 91,054,000.00
Development
of runway
infrastructure
40 days Fri 21-02-20
Thu 16-04-
20
$ 30,048,000.00
Accessing
traditional airside
land
35 days Fri 17-04-20
Thu 04-06-
20
$ 53,200.00
Terminal
development
34 days Fri 05-06-20
Wed 22-07-
20
$ 50,320.00
Enhancement
to the existing
32 days Thu 23-07-20 Fri 04-09-20 $ 48,640.00
PROJECT MANAGEMENT
Approval of
the design
7 days
Wed 11-12-
19
Thu 19-12-
19
$ 3,360.00
Milestone 4:
Completion of
the design
0 days Thu 19-12-19
Thu 19-12-
19
$ 0.00
Execution
phase
238 days Fri 20-12-19
Tue 17-11-
20
$ 121,333,200.00
Development
of east-west
runway
45 days Fri 20-12-19
Thu 20-02-
20
$ 91,054,000.00
Development
of runway
infrastructure
40 days Fri 21-02-20
Thu 16-04-
20
$ 30,048,000.00
Accessing
traditional airside
land
35 days Fri 17-04-20
Thu 04-06-
20
$ 53,200.00
Terminal
development
34 days Fri 05-06-20
Wed 22-07-
20
$ 50,320.00
Enhancement
to the existing
32 days Thu 23-07-20 Fri 04-09-20 $ 48,640.00
17
PROJECT MANAGEMENT
taxiway and
apron system
Long term
protection of
airspace
30 days
Mon 07-09-
20
Fri 16-10-20 $ 45,600.00
Reservation
of land
22 days
Mon 19-10-
20
Tue 17-11-
20
$ 33,440.00
Milestone 5:
Completion of
execution phase
0 days Tue 17-11-20
Tue 17-11-
20
$ 0.00
Closure phase 30 days
Wed 18-11-
20
Tue 29-12-
20
$ 18,320.00
Post project
review
12 days
Wed 18-11-
20
Thu 03-12-
20
$ 5,280.00
Stakeholder
sign off
8 days Fri 04-12-20
Tue 15-12-
20
$ 3,840.00
Documentation
10 days
Wed 16-12-
20
Tue 29-12-
20
$ 9,200.00
Milestone 6:
Completion of
0 days Tue 29-12-20 Tue 29-12- $ 0.00
PROJECT MANAGEMENT
taxiway and
apron system
Long term
protection of
airspace
30 days
Mon 07-09-
20
Fri 16-10-20 $ 45,600.00
Reservation
of land
22 days
Mon 19-10-
20
Tue 17-11-
20
$ 33,440.00
Milestone 5:
Completion of
execution phase
0 days Tue 17-11-20
Tue 17-11-
20
$ 0.00
Closure phase 30 days
Wed 18-11-
20
Tue 29-12-
20
$ 18,320.00
Post project
review
12 days
Wed 18-11-
20
Thu 03-12-
20
$ 5,280.00
Stakeholder
sign off
8 days Fri 04-12-20
Tue 15-12-
20
$ 3,840.00
Documentation
10 days
Wed 16-12-
20
Tue 29-12-
20
$ 9,200.00
Milestone 6:
Completion of
0 days Tue 29-12-20 Tue 29-12- $ 0.00
18
PROJECT MANAGEMENT
closure phase 20
PROJECT MANAGEMENT
closure phase 20
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
19
PROJECT MANAGEMENT
Bibliography
Braglia, M. and Frosolini, M., 2014. An integrated approach to implement project
management information systems within the extended enterprise. International Journal of
Project Management, 32(1), pp.18-29.
Chih, Y.Y. and Zwikael, O., 2015. Project benefit management: A conceptual framework of
target benefit formulation. International Journal of Project Management, 33(2), pp.352-362.
De Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), pp.1509-1522.
Fayard, D., Lee, L.S., Leitch, R.A. and Kettinger, W.J., 2014. Interorganizational cost
management in supply chains: Practices and payoffs. Management accounting
quarterly, 15(3), pp.1-9.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology
and project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Martinsuo, M. and Hoverfält, P., 2018. Change program management: Toward a capability
for managing value-oriented, integrated multi-project change in its context. International
Journal of Project Management, 36(1), pp.134-146.
PROJECT MANAGEMENT
Bibliography
Braglia, M. and Frosolini, M., 2014. An integrated approach to implement project
management information systems within the extended enterprise. International Journal of
Project Management, 32(1), pp.18-29.
Chih, Y.Y. and Zwikael, O., 2015. Project benefit management: A conceptual framework of
target benefit formulation. International Journal of Project Management, 33(2), pp.352-362.
De Carvalho, M.M., Patah, L.A. and de Souza Bido, D., 2015. Project management and its
effects on project success: Cross-country and cross-industry comparisons. International
Journal of Project Management, 33(7), pp.1509-1522.
Fayard, D., Lee, L.S., Leitch, R.A. and Kettinger, W.J., 2014. Interorganizational cost
management in supply chains: Practices and payoffs. Management accounting
quarterly, 15(3), pp.1-9.
Joslin, R. and Müller, R., 2015. Relationships between a project management methodology
and project success in different project governance contexts. International Journal of Project
Management, 33(6), pp.1377-1392.
Kerzner, H., 2017. Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Martinsuo, M. and Hoverfält, P., 2018. Change program management: Toward a capability
for managing value-oriented, integrated multi-project change in its context. International
Journal of Project Management, 36(1), pp.134-146.
20
PROJECT MANAGEMENT
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), pp.772-783.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
PROJECT MANAGEMENT
Todorović, M.L., Petrović, D.Č., Mihić, M.M., Obradović, V.L. and Bushuyev, S.D., 2015.
Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), pp.772-783.
Too, E.G. and Weaver, P., 2014. The management of project management: A conceptual
framework for project governance. International Journal of Project Management, 32(8),
pp.1382-1394.
1 out of 21
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.