logo

ICT Project Management

20 Pages2439 Words276 Views
   

Added on  2023-06-05

About This Document

This article discusses the development of a project schedule for the warehouse construction project and techniques for resource allocation like resource levelling and resource smoothing. It also provides insights into resolving the problem of over-allocation of resources in the project.

ICT Project Management

   Added on 2023-06-05

ShareRelated Documents
Running Head: PROJECT MANAGEMENT
ICT Project Management
Name of the Student
Name of the University
ICT Project Management_1
1PROJECT MANAGEMENT
Table of Contents
Part A: Developing the Schedule.....................................................................................................2
Answer to Question 1..................................................................................................................2
Answer to Question 2................................................................................................................10
Answer to Part a.....................................................................................................................10
Answer to Part b....................................................................................................................11
Answer to Part c.....................................................................................................................11
Answer to Part d....................................................................................................................11
Answer to Question 3................................................................................................................11
Answer to Question 4................................................................................................................13
Answer to Part a.....................................................................................................................13
Answer to Part b....................................................................................................................13
Answer to Part C....................................................................................................................14
Answer to Question 5................................................................................................................14
Answer to Part a.....................................................................................................................14
Answer to Part b....................................................................................................................15
Answer to Question 6................................................................................................................15
Part B: Revising the Plan...............................................................................................................16
Answer to Question 1................................................................................................................16
Answer to Question 2................................................................................................................16
Bibliography..................................................................................................................................18
ICT Project Management_2
2PROJECT MANAGEMENT
Part A: Developing the Schedule
Answer to Question 1
Task Name Duration Start Finish
WHA_PartAQ1 177 days Mon 01-10-18 Mon 01-07-19
Investment Board
Acceptance
1 day Mon 01-10-18 Mon 01-10-18
Workshop
refurbishment
20 days Tue 02-10-18 Mon 29-10-18
Plumbing 2 days Tue 02-10-18 Wed 03-10-18
Leichardt 2 days Tue 02-10-18 Wed 03-10-18
Toowong 1 day Tue 02-10-18 Tue 02-10-18
Hawthorn 1 day Tue 02-10-18 Tue 02-10-18
Electrics 4 days Wed 03-10-18 Mon 08-10-18
Leichardt 3 days Thu 04-10-18 Mon 08-10-18
Toowong 2 days Wed 03-10-18 Thu 04-10-18
Hawthorn 2 days Wed 03-10-18 Thu 04-10-18
Paint 17 days Fri 05-10-18 Mon 29-10-18
ICT Project Management_3
3PROJECT MANAGEMENT
Leichardt 3 wks Tue 09-10-18 Mon 29-10-18
Toowong 2 wks Fri 05-10-18 Thu 18-10-18
Hawthorn 2 wks Fri 05-10-18 Thu 18-10-18
Hardware 53 days Tue 02-10-18 Thu 13-12-18
Hardware Order 18 days Tue 02-10-18 Thu 25-10-18
Develop Tender
Document
6 days Tue 02-10-18 Tue 09-10-18
Open Tender 2 wks Wed 10-10-18 Tue 23-10-18
Award Tender 1 day Wed 24-10-18 Wed 24-10-18
Review & Sign
Contract
1 day Thu 25-10-18 Thu 25-10-18
Hardware Shipping 2 wks Fri 26-10-18 Thu 08-11-18
Workstation
configuration
18 days Fri 09-11-18 Tue 04-12-18
Work bench assembly 2 wks Fri 09-11-18 Thu 22-11-18
Power tool assembly 2 wks Fri 09-11-18 Thu 22-11-18
ICT Project Management_4

End of preview

Want to access all the pages? Upload your documents or become a member.

Related Documents
Project Management: Time Inc.
|16
|2347
|145

Job Duration. Start. Start: Mon 13/01/14 ID: 1. Start:
|115
|2991
|4

Project Management: Benefits Administration Software
|4
|811
|299

Business Project Management
|7
|1291
|18

Project Management Isn't Just For Project
|10
|1445
|19

Project Management for Boeing's Supersonic Commercial Planes
|5
|583
|392