Supply Chain Management System Implementation in ERP Software
VerifiedAdded on 2023/05/29
|25
|3972
|182
AI Summary
This report depicts the design and development of Supply Chain Management System in the business organization that helps to provide more interactive opportunities to the suppliers, consumes and distributors as well. The Module of Enterprise Resource Planning system that has been chosen is Supply Chain Management (SCM).
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Module of an ERP (Enterprise Resource Planning) Software Implementation: Supply
Chain Management System Implementation
Name of the student:
Name of the university:
Module of an ERP (Enterprise Resource Planning) Software Implementation: Supply
Chain Management System Implementation
Name of the student:
Name of the university:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Table of Contents
Introduction..................................................................................................................................2
1. Cost management plan.................................................................................................................2
1.1 Schedule Module...................................................................................................................3
1.1 Project schedule model maintenance.....................................................................................3
1.2 Control thresholds..................................................................................................................3
1.3 Rules for performance measurement.....................................................................................4
1.4 Reporting formats..................................................................................................................4
2. Work breakdown structure..........................................................................................................5
3. Direct labour hourly rate table.....................................................................................................7
4. Time phased budget and “S curve” sheet..................................................................................14
5. Resource usage, views, screenshots and tables.........................................................................15
Tracking Gantt chart view.........................................................................................................21
6. EVM Update Report..................................................................................................................23
Conclusion.....................................................................................................................................23
References..................................................................................................................................25
Table of Contents
Introduction..................................................................................................................................2
1. Cost management plan.................................................................................................................2
1.1 Schedule Module...................................................................................................................3
1.1 Project schedule model maintenance.....................................................................................3
1.2 Control thresholds..................................................................................................................3
1.3 Rules for performance measurement.....................................................................................4
1.4 Reporting formats..................................................................................................................4
2. Work breakdown structure..........................................................................................................5
3. Direct labour hourly rate table.....................................................................................................7
4. Time phased budget and “S curve” sheet..................................................................................14
5. Resource usage, views, screenshots and tables.........................................................................15
Tracking Gantt chart view.........................................................................................................21
6. EVM Update Report..................................................................................................................23
Conclusion.....................................................................................................................................23
References..................................................................................................................................25
2SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Introduction
This report depicts the design and development of Supply Chain Management System in
the business organization that helps to provide more interactive opportunities to the suppliers,
consumes and distributors as well. The Module of Enterprise Resource Planning system that has
been chosen is Supply Chain Management (SCM).
In order to develop the SCM system the activities those have been selected to take
effective decision making are considered in this assignment. The Supply Chain Management
(SCM) system is required to be accomplished within 100K. A Strategic Management Plan,
Activity on Node (AON), WBS, Activity duration tables are all elaborated in this assignment. In
addition to this, a Gantt chart and a resource management program are elaborated in this
assignment.
1. Cost management plan
In this new era of technology mostly for managing information, material details, raw
material and cash flow Supply Chain management (SCM) is widely used in both the medium and
large sized enterprises. SMC is an implementation action or integrative business philosophy used
for managing mainly materials. In other words SCM helps to reduce operational cost and delay
distribution by improving the supply flow to satisfy global consumers. The current globalization
scenario shows that, SCM and customer service has become a significant aspect in corporate
world. The SCM will give direct interacting opportunities to the consumers, distributors and
suppliers.
Introduction
This report depicts the design and development of Supply Chain Management System in
the business organization that helps to provide more interactive opportunities to the suppliers,
consumes and distributors as well. The Module of Enterprise Resource Planning system that has
been chosen is Supply Chain Management (SCM).
In order to develop the SCM system the activities those have been selected to take
effective decision making are considered in this assignment. The Supply Chain Management
(SCM) system is required to be accomplished within 100K. A Strategic Management Plan,
Activity on Node (AON), WBS, Activity duration tables are all elaborated in this assignment. In
addition to this, a Gantt chart and a resource management program are elaborated in this
assignment.
1. Cost management plan
In this new era of technology mostly for managing information, material details, raw
material and cash flow Supply Chain management (SCM) is widely used in both the medium and
large sized enterprises. SMC is an implementation action or integrative business philosophy used
for managing mainly materials. In other words SCM helps to reduce operational cost and delay
distribution by improving the supply flow to satisfy global consumers. The current globalization
scenario shows that, SCM and customer service has become a significant aspect in corporate
world. The SCM will give direct interacting opportunities to the consumers, distributors and
suppliers.
3SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
1.1 Schedule Module
AON (Activity on Node) diagram
Figure 1: Activity on Nodes (AON) for the SCM implementation project
(Source: Created by author)
1.1 Project schedule model maintenance
Project schedule model
maintenance
Update frequency By who
Monthly System developer, project
manager
1.2 Control thresholds
Variance
measured
Project level When Units
1.1 Schedule Module
AON (Activity on Node) diagram
Figure 1: Activity on Nodes (AON) for the SCM implementation project
(Source: Created by author)
1.1 Project schedule model maintenance
Project schedule model
maintenance
Update frequency By who
Monthly System developer, project
manager
1.2 Control thresholds
Variance
measured
Project level When Units
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Control
thresholds
Project time Management level Execution phase 50%
Project cost Audit level Project initiation
phase
45%
Project scope Management level Project planning
phase
40%
1.3 Rules for performance measurement
EVM measurement rules Frequency Who
Analysis of the EVM
requirements
Project initiation phase Project manager
Identification of the
components
Planning phase Marketing manager
Variance analysis Planning Management analysis
Performance indicator
identification
Planning Resource manager
1.4 Reporting formats
Report content To whom Done by whom Frequency
Progress status
report
Project manager Team workers Monthly
Control
thresholds
Project time Management level Execution phase 50%
Project cost Audit level Project initiation
phase
45%
Project scope Management level Project planning
phase
40%
1.3 Rules for performance measurement
EVM measurement rules Frequency Who
Analysis of the EVM
requirements
Project initiation phase Project manager
Identification of the
components
Planning phase Marketing manager
Variance analysis Planning Management analysis
Performance indicator
identification
Planning Resource manager
1.4 Reporting formats
Report content To whom Done by whom Frequency
Progress status
report
Project manager Team workers Monthly
5SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Project timeline
management
Project team lead Project team Monthly
Additional needful
resources
Resource manager Project associates Weekly
2. Work breakdown structure
WBS Task Name Description
1.0 Project design phase
1.1 Implementation of project team
1.1.1 performance analysis The performance of the project team
members are analyzed in this phase
1.1.2 Worker's skill measurement The skills of the workers are measured in
this phase
1.2 communication management program
1.2.1 Inventory management plan The inventory management plan for the
project is planned
1.2.2 Team meeting A meeting among the project team members
1.3 Resource identification
1.3.1 Gathering The needful resources are identified in this
activity
1.3.2 Analysis The gathered information are all analyzed in
this phase
1.4 Identification of supply chain
characteristics
1.4.1 Project planning phase In outline of the project is documented in
this phase
1.4.2 SCM tool selection
Specific tools required for the
implementation of the SM are selected in
this phase
1.4.3 Developing strategic objectives The strategic objectives for the project team
are developed
1.4.4 Constructing supply chain structure The exact structure of the supply chain is
designed in this phase
1.4.5 Milestone 1: Project outline submission
1.5 Feasibility study
Project timeline
management
Project team lead Project team Monthly
Additional needful
resources
Resource manager Project associates Weekly
2. Work breakdown structure
WBS Task Name Description
1.0 Project design phase
1.1 Implementation of project team
1.1.1 performance analysis The performance of the project team
members are analyzed in this phase
1.1.2 Worker's skill measurement The skills of the workers are measured in
this phase
1.2 communication management program
1.2.1 Inventory management plan The inventory management plan for the
project is planned
1.2.2 Team meeting A meeting among the project team members
1.3 Resource identification
1.3.1 Gathering The needful resources are identified in this
activity
1.3.2 Analysis The gathered information are all analyzed in
this phase
1.4 Identification of supply chain
characteristics
1.4.1 Project planning phase In outline of the project is documented in
this phase
1.4.2 SCM tool selection
Specific tools required for the
implementation of the SM are selected in
this phase
1.4.3 Developing strategic objectives The strategic objectives for the project team
are developed
1.4.4 Constructing supply chain structure The exact structure of the supply chain is
designed in this phase
1.4.5 Milestone 1: Project outline submission
1.5 Feasibility study
6SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
1.5.1 Contract with suppliers and distributors An accurate contract to the distributors and
suppliers are needed to be established
1.5.2 audit planning The fixed cost of the project is planned in
this phase
1.5.3 Milestone 2: Completion of design phase
2 Project Execution and monitoring phase
2.1 Extraction of suitable attributes
2.1.1 Detailing evaluation contents The content to be evaluated are detailed
2.1.2 Screening the unqualified The unqualified elements are all screened in
this phase
2.2 Closure phase
2.2.1 Monitoring program The program to be executed is monitored in
this phase
2.2.2 Project monitoring The project is properly controlled and
monitored in this phase
2.2.3 Milestone 3: Completion of development
and implementation phase
2.3 Stakeholders signoff
2.3.1 Final SMC document presentation The final document of SCM is presented in
this phase
2.3.2 feedback analysis
The needful feedback are collected from the
consumers and users to understand the
changes that are to be done
2.4 change management plan
2.4.1 change management implementation The change management program is planned
2.4.2 maintenance planning The requested changes are all maintained in
this phase
2.4.3 change management plan
implementation
How to implement the changes are planned
in this phase
2.4.4 Milestone4: Final document submission
2.5 training
2.5.1 technical training
If any additional technical changes are
identified then the technical training should
be planned by the project manager for the
team members
2.5.2 non technical training
Apart from this, during the project ongoing
phase no technical training should also be
arranged.
1.5.1 Contract with suppliers and distributors An accurate contract to the distributors and
suppliers are needed to be established
1.5.2 audit planning The fixed cost of the project is planned in
this phase
1.5.3 Milestone 2: Completion of design phase
2 Project Execution and monitoring phase
2.1 Extraction of suitable attributes
2.1.1 Detailing evaluation contents The content to be evaluated are detailed
2.1.2 Screening the unqualified The unqualified elements are all screened in
this phase
2.2 Closure phase
2.2.1 Monitoring program The program to be executed is monitored in
this phase
2.2.2 Project monitoring The project is properly controlled and
monitored in this phase
2.2.3 Milestone 3: Completion of development
and implementation phase
2.3 Stakeholders signoff
2.3.1 Final SMC document presentation The final document of SCM is presented in
this phase
2.3.2 feedback analysis
The needful feedback are collected from the
consumers and users to understand the
changes that are to be done
2.4 change management plan
2.4.1 change management implementation The change management program is planned
2.4.2 maintenance planning The requested changes are all maintained in
this phase
2.4.3 change management plan
implementation
How to implement the changes are planned
in this phase
2.4.4 Milestone4: Final document submission
2.5 training
2.5.1 technical training
If any additional technical changes are
identified then the technical training should
be planned by the project manager for the
team members
2.5.2 non technical training
Apart from this, during the project ongoing
phase no technical training should also be
arranged.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Developing project
schedule for SCM
Project design phase
Implementation of project
team
performance
analysis
Worker's skill
measurement
communication
management program
Inventory
management plan
Team meeting
Resource identification
Gathering
Analysis
Identification of supply
chain characteristics
Project planning
phase
SCM tool selection
Developing strategic
objectives
Constructing supply
chain structure
Milestone 1: Project
outline submission
Feasibility study
Contract with
suppliers and
distributors
audit planning
Milestone 2:
Completion of
design phase
Project Execution and
monitoring phase
Extraction of suitable
attributes
Detailing evaluation
contents
Screening the
unqualified
Closure phase
Monitoring program
Project monitoring
Milestone 3:
Completion of
developmet and
implementation
phase
Stakeholders signoff
Final SMC document
presentation
feedback analysis
change management plan
change management
implementation
maintenance
planning
change
management plan
implemenation
Milestone4: Final
document
submission
training
technical training
non technical
training
Figure 2: WBS for the SCM development project
(Source: Created by author)
3. Direct labour hourly rate table
The hourly rates of the labours are as follows:
Resource Name Wages Rate Overhead factor Personal time
factor
Resource manager $22.00/hr Indirect labour Good work life
project manager $35.00/hr Employee Fringe Benefits Learning
development
Finance manager $18.00/hr Indirect labour Good fixed salary
Worker's tool $50.00 Payroll taxes Financial stability
distributors $18.00/hr Indirect labour Job security
suppliers $25.00/hr Payroll taxes Good relationships
with others
Hardware requirements $3,000.00 Indirect labour Good fixed salary
Software requirements $5,500.00 Employee Fringe Benefits Financial stability
System developer $35.00/hr Payroll taxes Balanced work life
Developing project
schedule for SCM
Project design phase
Implementation of project
team
performance
analysis
Worker's skill
measurement
communication
management program
Inventory
management plan
Team meeting
Resource identification
Gathering
Analysis
Identification of supply
chain characteristics
Project planning
phase
SCM tool selection
Developing strategic
objectives
Constructing supply
chain structure
Milestone 1: Project
outline submission
Feasibility study
Contract with
suppliers and
distributors
audit planning
Milestone 2:
Completion of
design phase
Project Execution and
monitoring phase
Extraction of suitable
attributes
Detailing evaluation
contents
Screening the
unqualified
Closure phase
Monitoring program
Project monitoring
Milestone 3:
Completion of
developmet and
implementation
phase
Stakeholders signoff
Final SMC document
presentation
feedback analysis
change management plan
change management
implementation
maintenance
planning
change
management plan
implemenation
Milestone4: Final
document
submission
training
technical training
non technical
training
Figure 2: WBS for the SCM development project
(Source: Created by author)
3. Direct labour hourly rate table
The hourly rates of the labours are as follows:
Resource Name Wages Rate Overhead factor Personal time
factor
Resource manager $22.00/hr Indirect labour Good work life
project manager $35.00/hr Employee Fringe Benefits Learning
development
Finance manager $18.00/hr Indirect labour Good fixed salary
Worker's tool $50.00 Payroll taxes Financial stability
distributors $18.00/hr Indirect labour Job security
suppliers $25.00/hr Payroll taxes Good relationships
with others
Hardware requirements $3,000.00 Indirect labour Good fixed salary
Software requirements $5,500.00 Employee Fringe Benefits Financial stability
System developer $35.00/hr Payroll taxes Balanced work life
8SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
System tester $35.00/hr Employee Fringe Benefits Good work life
designer $22.00/hr Payroll taxes Learning
development
computers $36,010.00 Payroll taxes Good fixed salary
additional cost $40,000.00 Employee Fringe Benefits Financial stability
workers $35.00/hr Payroll taxes Job security
other cost $10,500.00 Payroll taxes Good work life
The activity precedence table for the SCM (ERP module) development from the
supplier’s end is elaborated in the below section:
WBS Task Name Predecessors Lead/lag Rationale
1.2.1 Inventory management plan 4FS-1 day
Lag The task will
be completed
1 day late
1.2.2 Team meeting 6FS+1 day
Lead The task will
be completed
one day
earlier
1.4.1 Project planning phase 10FF+1 day
Lead The task will
be completed
one day
earlier
(Laudon &
Laudon,
2016)
1.4.2 SCM tool selection 12SS-1 day
Lag This task will
start 1 day
late
2.1.1 Detailing evaluation contents 19SS+1 day
Lead This task will
start 1 day
earlier
2.2.2 Project monitoring 26FF-1 day
Lag This task will
finish 1 day
later
2.4.1 change management implementation 31,30FF+2 Lead This task will
System tester $35.00/hr Employee Fringe Benefits Good work life
designer $22.00/hr Payroll taxes Learning
development
computers $36,010.00 Payroll taxes Good fixed salary
additional cost $40,000.00 Employee Fringe Benefits Financial stability
workers $35.00/hr Payroll taxes Job security
other cost $10,500.00 Payroll taxes Good work life
The activity precedence table for the SCM (ERP module) development from the
supplier’s end is elaborated in the below section:
WBS Task Name Predecessors Lead/lag Rationale
1.2.1 Inventory management plan 4FS-1 day
Lag The task will
be completed
1 day late
1.2.2 Team meeting 6FS+1 day
Lead The task will
be completed
one day
earlier
1.4.1 Project planning phase 10FF+1 day
Lead The task will
be completed
one day
earlier
(Laudon &
Laudon,
2016)
1.4.2 SCM tool selection 12SS-1 day
Lag This task will
start 1 day
late
2.1.1 Detailing evaluation contents 19SS+1 day
Lead This task will
start 1 day
earlier
2.2.2 Project monitoring 26FF-1 day
Lag This task will
finish 1 day
later
2.4.1 change management implementation 31,30FF+2 Lead This task will
9SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
days finished 2
days earlier
2.5.1 technical training 34SS-1 day
Lag This task will
start 1 day
later
Schedule
WB
S Task Name Duratio
n Start Finish Predecesso
rs Resource Names
1.0 Project design
phase 56 days
Tue
11/20/1
8
Tue
2/5/19
1.1 Implementati
on of project
team
12 days
Tue
11/20/1
8
Wed
12/5/18
1.1.1 performance
analysis
10 days
Tue
11/20/1
8
Mon
12/3/18
Resource
manager,suppliers,Worker's
tool[1],designer,Finance
manager,additional cost[1]
1.1.2
Worker's
skill
measurement
2 days Tue
12/4/18
Wed
12/5/18 3
Resource manager,workers,other
cost[1],System developer,computers
[1],designer
1.2
communicatio
n
management
program
23 days Wed
12/5/18
Fri
1/4/19
1.2.1
Inventory
management
plan
12 days Wed
12/5/18
Thu
12/20/1
8
4FS-1 day
Finance manager,Software
requirements[1],Worker's
tool[1],additional cost[1]
1.2.2 Team
meeting 10 days
Mon
12/24/1
8
Fri
1/4/19
6FS+1
day,4
additional cost[1],Software
requirements[1],System
developer,other cost[1],Finance
manager,Worker's tool[1],workers
1.3 Resource
identification 5 days Mon
1/7/19
Fri
1/11/19
1.3.1 Gathering 2 days Mon
1/7/19
Tue
1/8/19 7
project manager,additional
cost[1],other cost[1],System
developer,Worker's tool[1]
days finished 2
days earlier
2.5.1 technical training 34SS-1 day
Lag This task will
start 1 day
later
Schedule
WB
S Task Name Duratio
n Start Finish Predecesso
rs Resource Names
1.0 Project design
phase 56 days
Tue
11/20/1
8
Tue
2/5/19
1.1 Implementati
on of project
team
12 days
Tue
11/20/1
8
Wed
12/5/18
1.1.1 performance
analysis
10 days
Tue
11/20/1
8
Mon
12/3/18
Resource
manager,suppliers,Worker's
tool[1],designer,Finance
manager,additional cost[1]
1.1.2
Worker's
skill
measurement
2 days Tue
12/4/18
Wed
12/5/18 3
Resource manager,workers,other
cost[1],System developer,computers
[1],designer
1.2
communicatio
n
management
program
23 days Wed
12/5/18
Fri
1/4/19
1.2.1
Inventory
management
plan
12 days Wed
12/5/18
Thu
12/20/1
8
4FS-1 day
Finance manager,Software
requirements[1],Worker's
tool[1],additional cost[1]
1.2.2 Team
meeting 10 days
Mon
12/24/1
8
Fri
1/4/19
6FS+1
day,4
additional cost[1],Software
requirements[1],System
developer,other cost[1],Finance
manager,Worker's tool[1],workers
1.3 Resource
identification 5 days Mon
1/7/19
Fri
1/11/19
1.3.1 Gathering 2 days Mon
1/7/19
Tue
1/8/19 7
project manager,additional
cost[1],other cost[1],System
developer,Worker's tool[1]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
1.3.2 Analysis 5 days Mon
1/7/19
Fri
1/11/19 7
System developer,computers
[1],Hardware
requirements[1],Software
requirements[1]
1.4
Identification
of supply
chain
characteristic
s
15 days Thu
1/10/19
Wed
1/30/19
1.4.1 Project
planning phase 2 days Fri
1/11/19
Mon
1/14/19
10FF+1
day,9
System tester,project
manager,suppliers,additional cost[1]
1.4.2 SCM tool
selection 6 days Thu
1/10/19
Thu
1/17/19 12SS-1 day
Hardware requirements[1],other
cost[1],project
manager,workers,Worker's
tool[1],additional cost[1],designer
1.4.3
Developing
strategic
objectives
10 days Tue
1/15/19
Mon
1/28/19 12
System developer,additional
cost[1],designer,Hardware
requirements[1],Worker's tool[1]
1.4.4 Constructing
supply chain
structure
2 days Tue
1/29/19
Wed
1/30/19 13,14
Software
requirements[1],workers,designer,pr
oject manager,System tester,other
cost[1]
1.4.5
Milestone
1: Project
outline
submission
0 days Fri
1/11/19
Fri
1/11/19 8
1.5 Feasibility
study 4 days Thu
1/31/19
Tue
2/5/19
1.5.1
Contract
with suppliers
and
distributors
2 days Thu
1/31/19
Fri
2/1/19 15
project manager,workers,Worker's
tool[1],additional cost[1],System
developer,Hardware requirements[1]
1.5.2 audit
planning 2 days Mon
2/4/19
Tue
2/5/19 18
additional cost[1],designer,project
manager,System developer,Resource
manager,Worker's tool[1],suppliers
1.5.3
Milestone
2: Completion
of design
phase
0 days Tue
2/5/19
Tue
2/5/19 19
2
Project
Execution and
monitoring
phase
35 days Tue
2/5/19
Mon
3/25/19
2.1 Extraction 11 days Tue Tue
1.3.2 Analysis 5 days Mon
1/7/19
Fri
1/11/19 7
System developer,computers
[1],Hardware
requirements[1],Software
requirements[1]
1.4
Identification
of supply
chain
characteristic
s
15 days Thu
1/10/19
Wed
1/30/19
1.4.1 Project
planning phase 2 days Fri
1/11/19
Mon
1/14/19
10FF+1
day,9
System tester,project
manager,suppliers,additional cost[1]
1.4.2 SCM tool
selection 6 days Thu
1/10/19
Thu
1/17/19 12SS-1 day
Hardware requirements[1],other
cost[1],project
manager,workers,Worker's
tool[1],additional cost[1],designer
1.4.3
Developing
strategic
objectives
10 days Tue
1/15/19
Mon
1/28/19 12
System developer,additional
cost[1],designer,Hardware
requirements[1],Worker's tool[1]
1.4.4 Constructing
supply chain
structure
2 days Tue
1/29/19
Wed
1/30/19 13,14
Software
requirements[1],workers,designer,pr
oject manager,System tester,other
cost[1]
1.4.5
Milestone
1: Project
outline
submission
0 days Fri
1/11/19
Fri
1/11/19 8
1.5 Feasibility
study 4 days Thu
1/31/19
Tue
2/5/19
1.5.1
Contract
with suppliers
and
distributors
2 days Thu
1/31/19
Fri
2/1/19 15
project manager,workers,Worker's
tool[1],additional cost[1],System
developer,Hardware requirements[1]
1.5.2 audit
planning 2 days Mon
2/4/19
Tue
2/5/19 18
additional cost[1],designer,project
manager,System developer,Resource
manager,Worker's tool[1],suppliers
1.5.3
Milestone
2: Completion
of design
phase
0 days Tue
2/5/19
Tue
2/5/19 19
2
Project
Execution and
monitoring
phase
35 days Tue
2/5/19
Mon
3/25/19
2.1 Extraction 11 days Tue Tue
11SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
of suitable
attributes 2/5/19 2/19/19
2.1.1
Detailing
evaluation
contents
6 days Tue
2/5/19
Tue
2/12/19
22,19SS+1
day
Hardware requirements[1],Software
requirements[1],distributors,System
developer,Worker's
tool[1],additional cost[1],project
manager,designer
2.1.2 Screening
the unqualified 5 days Wed
2/13/19
Tue
2/19/19 17,23
designer,Finance
manager,workers,additional
cost[1],Worker's tool[1]
2.2 Closure
phase 21 days Thu
2/14/19
Thu
3/14/19
2.2.1 Monitoring
program 2 days Wed
2/20/19
Thu
2/21/19 24 Resource manager,suppliers,System
tester,Worker's tool[1],other cost[1]
2.2.2 Project
monitoring 5 days Thu
2/14/19
Wed
2/20/19 26FF-1 day
Finance manager,System
developer,Worker's tool[1],project
manager
2.2.3
Milestone
3: Completion
of developmet
and
implementatio
n phase
0 days Thu
3/14/19
Thu
3/14/19 34
2.3 Stakeholders
signoff
6 days Thu
2/21/19
Thu
2/28/19
2.3.1
Final SMC
document
presentation
6 days Thu
2/21/19
Thu
2/28/19 27
project manager,Finance
manager,Software
requirements[1],System
tester,additional cost[1],Worker's
tool[1]
2.3.2 feedback
analysis 5 days Thu
2/21/19
Wed
2/27/19 27
designer,suppliers,Finance
manager,additional cost[1],Software
requirements[1]
2.4
change
management
plan
14 days Thu
2/28/19
Tue
3/19/19
2.4.1
change
management
implementatio
n
6 days Thu
2/28/19
Thu
3/7/19
31,30FF+2
days
additional cost[1],other
cost[1],project manager,Software
requirements[1],suppliers,System
developer,workers
2.4.2 maintenance
planning
5 days Fri
3/8/19
Thu
3/14/19 33
Hardware requirements[1],System
developer,additional
cost[1],Worker's tool[1],designer
of suitable
attributes 2/5/19 2/19/19
2.1.1
Detailing
evaluation
contents
6 days Tue
2/5/19
Tue
2/12/19
22,19SS+1
day
Hardware requirements[1],Software
requirements[1],distributors,System
developer,Worker's
tool[1],additional cost[1],project
manager,designer
2.1.2 Screening
the unqualified 5 days Wed
2/13/19
Tue
2/19/19 17,23
designer,Finance
manager,workers,additional
cost[1],Worker's tool[1]
2.2 Closure
phase 21 days Thu
2/14/19
Thu
3/14/19
2.2.1 Monitoring
program 2 days Wed
2/20/19
Thu
2/21/19 24 Resource manager,suppliers,System
tester,Worker's tool[1],other cost[1]
2.2.2 Project
monitoring 5 days Thu
2/14/19
Wed
2/20/19 26FF-1 day
Finance manager,System
developer,Worker's tool[1],project
manager
2.2.3
Milestone
3: Completion
of developmet
and
implementatio
n phase
0 days Thu
3/14/19
Thu
3/14/19 34
2.3 Stakeholders
signoff
6 days Thu
2/21/19
Thu
2/28/19
2.3.1
Final SMC
document
presentation
6 days Thu
2/21/19
Thu
2/28/19 27
project manager,Finance
manager,Software
requirements[1],System
tester,additional cost[1],Worker's
tool[1]
2.3.2 feedback
analysis 5 days Thu
2/21/19
Wed
2/27/19 27
designer,suppliers,Finance
manager,additional cost[1],Software
requirements[1]
2.4
change
management
plan
14 days Thu
2/28/19
Tue
3/19/19
2.4.1
change
management
implementatio
n
6 days Thu
2/28/19
Thu
3/7/19
31,30FF+2
days
additional cost[1],other
cost[1],project manager,Software
requirements[1],suppliers,System
developer,workers
2.4.2 maintenance
planning
5 days Fri
3/8/19
Thu
3/14/19 33
Hardware requirements[1],System
developer,additional
cost[1],Worker's tool[1],designer
12SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
2.4.3
change
management
plan
implemenation
3 days Fri
3/15/19
Tue
3/19/19 34
2.4.4
Milestone4:
Final
document
submission
0 days Mon
3/18/19
Mon
3/18/19 38
2.5 training 13 days Thu
3/7/19
Mon
3/25/19
2.5.1 technical
training 8 days Thu
3/7/19
Mon
3/18/19 34SS-1 day designer,Finance manager,computers
[1],suppliers,System tester
2.5.2
non
technical
training
5 days Tue
3/19/19
Mon
3/25/19 38
Resource manager,suppliers,System
tester,additional cost[1],computers
[1],designer,distributors,Finance
manager,project manager,workers
2.4.3
change
management
plan
implemenation
3 days Fri
3/15/19
Tue
3/19/19 34
2.4.4
Milestone4:
Final
document
submission
0 days Mon
3/18/19
Mon
3/18/19 38
2.5 training 13 days Thu
3/7/19
Mon
3/25/19
2.5.1 technical
training 8 days Thu
3/7/19
Mon
3/18/19 34SS-1 day designer,Finance manager,computers
[1],suppliers,System tester
2.5.2
non
technical
training
5 days Tue
3/19/19
Mon
3/25/19 38
Resource manager,suppliers,System
tester,additional cost[1],computers
[1],designer,distributors,Finance
manager,project manager,workers
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Figure 3: Project Budget report of the project
(Source: Created by author)
Figure 3: Project Budget report of the project
(Source: Created by author)
14SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Network Diagram
Figure 4: Network Diagram of the SCM implementation project
(Source: Created by author)
4. Time phased budget and “S curve” sheet
The “S Curve” represents or displays cumulative costs, labor hours and the other
quantities against time. The below S curve shows the cost against the budget. The S curve is also
shown in the excel sheet.
Network Diagram
Figure 4: Network Diagram of the SCM implementation project
(Source: Created by author)
4. Time phased budget and “S curve” sheet
The “S Curve” represents or displays cumulative costs, labor hours and the other
quantities against time. The below S curve shows the cost against the budget. The S curve is also
shown in the excel sheet.
15SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
20-Nov-18
22-Nov-18
24-Nov-18
26-Nov-18
28-Nov-18
30-Nov-18
2-Dec-18
4-Dec-18
6-Dec-18
8-Dec-18
10-Dec-18
0
20000
40000
60000
80000
100000
120000
S-Curve
Cumulative Budgeted Cost
Figure 5: “S Curve” of the project
(Source: Created by Author)
5. Resource usage, views, screenshots and tables
The screenshot of the over allocated resources are elaborated in the below section:
The below diagram shows that some of the resources are over allocated and those are
required to be reduced for successfully complete the project within estimated budget and time.
Resource
Name Type Max.
Units Std. Rate Ovt. Rate Cost/Use Accrue At Base
Calendar
Resource
manager Work 100% $22.00/hr $0.00/hr $0.00 Prorated Standard
project
manager Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
20-Nov-18
22-Nov-18
24-Nov-18
26-Nov-18
28-Nov-18
30-Nov-18
2-Dec-18
4-Dec-18
6-Dec-18
8-Dec-18
10-Dec-18
0
20000
40000
60000
80000
100000
120000
S-Curve
Cumulative Budgeted Cost
Figure 5: “S Curve” of the project
(Source: Created by Author)
5. Resource usage, views, screenshots and tables
The screenshot of the over allocated resources are elaborated in the below section:
The below diagram shows that some of the resources are over allocated and those are
required to be reduced for successfully complete the project within estimated budget and time.
Resource
Name Type Max.
Units Std. Rate Ovt. Rate Cost/Use Accrue At Base
Calendar
Resource
manager Work 100% $22.00/hr $0.00/hr $0.00 Prorated Standard
project
manager Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
16SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Finance
manager Work 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
Worker's tool Material $50.00 $0.00 Prorated
distributors Work 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
suppliers Work 100% $25.00/hr $0.00/hr $0.00 Prorated Standard
Hardware
requirements Material $3,000.00 $0.00 Prorated
Software
requirements Material $5,500.00 $0.00 Prorated
System
developer Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
System tester Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
designer Work 100% $22.00/hr $0.00/hr $0.00 Prorated Standard
computers Material $36,010.00 $0.00 Prorated
additional cost Material $40,000.00 $0.00 Prorated
workers Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
other cost Material $10,500.00 $0.00 Prorated
Table 1: Over allocated resources
(Source: Created by author)
WBS Activity Name Rationale/ over allocation elimination
description
1.3.1 Gathering
Based on complexity of this activity the
estimated time span and allocated resources
are high. Hence, it is over allocated.
1.3.2 Analysis
The estimated resources for this activity and
the resources are not balanced. With
maximizing the needful resources which are
over allocated this issue can be resolved.
1.4.1 Project planning phase If the resources allocated for this specific
activity is maximized then the over
Finance
manager Work 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
Worker's tool Material $50.00 $0.00 Prorated
distributors Work 100% $18.00/hr $0.00/hr $0.00 Prorated Standard
suppliers Work 100% $25.00/hr $0.00/hr $0.00 Prorated Standard
Hardware
requirements Material $3,000.00 $0.00 Prorated
Software
requirements Material $5,500.00 $0.00 Prorated
System
developer Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
System tester Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
designer Work 100% $22.00/hr $0.00/hr $0.00 Prorated Standard
computers Material $36,010.00 $0.00 Prorated
additional cost Material $40,000.00 $0.00 Prorated
workers Work 100% $35.00/hr $0.00/hr $0.00 Prorated Standard
other cost Material $10,500.00 $0.00 Prorated
Table 1: Over allocated resources
(Source: Created by author)
WBS Activity Name Rationale/ over allocation elimination
description
1.3.1 Gathering
Based on complexity of this activity the
estimated time span and allocated resources
are high. Hence, it is over allocated.
1.3.2 Analysis
The estimated resources for this activity and
the resources are not balanced. With
maximizing the needful resources which are
over allocated this issue can be resolved.
1.4.1 Project planning phase If the resources allocated for this specific
activity is maximized then the over
17SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
allocation of the task will be eliminated.
1.4.2 SCM tool selection
While selecting Supply chain management
tool for implementation of the SCM in the
organization the work pressure was higher
than the assigned resources. If the resource
capacities are maximized from 100 to 200
percent then the over allocation can be
avoided.
1.4.3 Developing strategic objectives
If the resources assigned for this activity are
maximized then this issue can be resolved.
1.5.2 audit planning
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.1.1 Detailing evaluation contents
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.1.2 Screening the unqualified
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.2.1 Monitoring program
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.2.2 Project monitoring
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.3.1 Final SMC document presentation
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.3.2 feedback analysis The resources assigned to this task are
designer, distributors, finance manager and
suppliers and the finance manager. Among
them the finance manager and designer is
allocation of the task will be eliminated.
1.4.2 SCM tool selection
While selecting Supply chain management
tool for implementation of the SCM in the
organization the work pressure was higher
than the assigned resources. If the resource
capacities are maximized from 100 to 200
percent then the over allocation can be
avoided.
1.4.3 Developing strategic objectives
If the resources assigned for this activity are
maximized then this issue can be resolved.
1.5.2 audit planning
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.1.1 Detailing evaluation contents
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.1.2 Screening the unqualified
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.2.1 Monitoring program
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.2.2 Project monitoring
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.3.1 Final SMC document presentation
If the resources assigned for this activity are
maximized then this issue can be resolved.
2.3.2 feedback analysis The resources assigned to this task are
designer, distributors, finance manager and
suppliers and the finance manager. Among
them the finance manager and designer is
18SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
maximized to 200% and through this way
the over allocation can be resolved
2.4.1 change management implementation
The resources assigned to this activity needs
to be increased from 100 to 200 then the
over allocation will be removed
2.4.2 maintenance planning
The resources assigned to this activity needs
to be increased from 100 to 200 then the
over allocation will be removed
2.5.1 technical training
The resources assigned to this activity needs
to be increased from 100 to 200 then the
over allocation will be removed
Figure 6: Resource over allocation view
(Source: created by author)
maximized to 200% and through this way
the over allocation can be resolved
2.4.1 change management implementation
The resources assigned to this activity needs
to be increased from 100 to 200 then the
over allocation will be removed
2.4.2 maintenance planning
The resources assigned to this activity needs
to be increased from 100 to 200 then the
over allocation will be removed
2.5.1 technical training
The resources assigned to this activity needs
to be increased from 100 to 200 then the
over allocation will be removed
Figure 6: Resource over allocation view
(Source: created by author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
19SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Resource Name Max.
Units Std. Rate Ovt. Rate Accrue At Base Calendar
Resource manager 100% $22.00/hr $0.00/hr Prorated Standard
project manager 200% $35.00/hr $0.00/hr Prorated Standard
Finance manager 200% $18.00/hr $0.00/hr Prorated Standard
Worker's tool $50.00 Prorated
distributors 200% $18.00/hr $0.00/hr Prorated Standard
suppliers 200% $25.00/hr $0.00/hr Prorated Standard
Hardware requirements $3,000.00 Prorated
Software requirements $5,500.00 Prorated
System developer 200% $35.00/hr $0.00/hr Prorated Standard
System tester 200% $35.00/hr $0.00/hr Prorated Standard
designer 200% $22.00/hr $0.00/hr Prorated Standard
computers $36,010.00 Prorated
additional cost $40,000.00 Prorated
workers 200% $35.00/hr $0.00/hr Prorated Standard
other cost $10,500.00 Prorated
Table 3: After removing resource over allocation
(Source: Created by author)
Resource Name Max.
Units Std. Rate Ovt. Rate Accrue At Base Calendar
Resource manager 100% $22.00/hr $0.00/hr Prorated Standard
project manager 200% $35.00/hr $0.00/hr Prorated Standard
Finance manager 200% $18.00/hr $0.00/hr Prorated Standard
Worker's tool $50.00 Prorated
distributors 200% $18.00/hr $0.00/hr Prorated Standard
suppliers 200% $25.00/hr $0.00/hr Prorated Standard
Hardware requirements $3,000.00 Prorated
Software requirements $5,500.00 Prorated
System developer 200% $35.00/hr $0.00/hr Prorated Standard
System tester 200% $35.00/hr $0.00/hr Prorated Standard
designer 200% $22.00/hr $0.00/hr Prorated Standard
computers $36,010.00 Prorated
additional cost $40,000.00 Prorated
workers 200% $35.00/hr $0.00/hr Prorated Standard
other cost $10,500.00 Prorated
Table 3: After removing resource over allocation
(Source: Created by author)
20SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Tracking Gantt chart view
Figure 7: Tracking Gantt chart view
(Source: Created by author)
Tracking Gantt chart view
Figure 7: Tracking Gantt chart view
(Source: Created by author)
21SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
Figure 8: Tracking Gantt chart view
(Source: Created by author)
Figure 8: Tracking Gantt chart view
(Source: Created by author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
22SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
6. EVM Update Report
Project manager, finance manager, suppliers, system tester, designer and system
developer are over allocate and with setting the project baseline the over allocated resources are
updated accordingly. It is defined that with the successful upgradation of the resource report the
project will be able to meet the objectives and can also complete the project within the estimated
budget of 100K. Some of the activities are completed 100% and 90% but some of them are not
yet accomplished.
Conclusion
From the overall discussion it can be concluded that, the ERP module is performing by
the large business organization by a smaller supplier company. The profit structure that can be
obtained from the project is also elaborated in this paper. The two sub deliverables followed by
the project heads are project design phase and project execution and closure phase. The active
6. EVM Update Report
Project manager, finance manager, suppliers, system tester, designer and system
developer are over allocate and with setting the project baseline the over allocated resources are
updated accordingly. It is defined that with the successful upgradation of the resource report the
project will be able to meet the objectives and can also complete the project within the estimated
budget of 100K. Some of the activities are completed 100% and 90% but some of them are not
yet accomplished.
Conclusion
From the overall discussion it can be concluded that, the ERP module is performing by
the large business organization by a smaller supplier company. The profit structure that can be
obtained from the project is also elaborated in this paper. The two sub deliverables followed by
the project heads are project design phase and project execution and closure phase. The active
23SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
precedence table, activity duration table and Excel sheets are being prepared to track the current
status of the project.
precedence table, activity duration table and Excel sheets are being prepared to track the current
status of the project.
24SUPPLY CHAIN MANAGEMENT SYSTEM IMPLEMENTATION
References
Awang, Z., Hashim, N. N., Yaziz, N. M., & Asmuni, N. S. (2015). Assessing customer intention
towards the use of website on online air ticket booking. Editors, 686.
Bowers, J., & Khorakian, A. (2014). Integrating risk management in the innovation
project. European Journal of innovation management, 17(1), 25-40.
Calvo-Mora, A., Navarro-García, A., & Periañez-Cristobal, R. (2015). Project to improve
knowledge management and key business results through the EFQM excellence
model. International Journal of Project Management, 33(8), 1638-1651.
Fernandez-Cavia, J., Rovira, C., Díaz-Luque, P., & Cavaller, V. (2014). Web Quality Index
(WQI) for official tourist destination websites. Proposal for an assessment
system. Tourism management perspectives, 9, 5-13.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Ghosal, S., Chaturvedi, S., Taywade, A., & Jaisankar, N. (2015). Android application for ticket
booking and ticket checking in suburban railways. Indian Journal of Science and
Technology, 8(S2), 171-178.
Larson, E. W., & Gray, C. F. (2014). Project Management: The Managerial Process with MS
Project.
Laudon, K. C., & Laudon, J. P. (2016). Management information system. Pearson Education
India.
References
Awang, Z., Hashim, N. N., Yaziz, N. M., & Asmuni, N. S. (2015). Assessing customer intention
towards the use of website on online air ticket booking. Editors, 686.
Bowers, J., & Khorakian, A. (2014). Integrating risk management in the innovation
project. European Journal of innovation management, 17(1), 25-40.
Calvo-Mora, A., Navarro-García, A., & Periañez-Cristobal, R. (2015). Project to improve
knowledge management and key business results through the EFQM excellence
model. International Journal of Project Management, 33(8), 1638-1651.
Fernandez-Cavia, J., Rovira, C., Díaz-Luque, P., & Cavaller, V. (2014). Web Quality Index
(WQI) for official tourist destination websites. Proposal for an assessment
system. Tourism management perspectives, 9, 5-13.
Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management.
Project Management Institute.
Ghosal, S., Chaturvedi, S., Taywade, A., & Jaisankar, N. (2015). Android application for ticket
booking and ticket checking in suburban railways. Indian Journal of Science and
Technology, 8(S2), 171-178.
Larson, E. W., & Gray, C. F. (2014). Project Management: The Managerial Process with MS
Project.
Laudon, K. C., & Laudon, J. P. (2016). Management information system. Pearson Education
India.
1 out of 25
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.