Teesside PLC Project Scheduling Plan

Verified

Added on  2023/01/19

|37
|8515
|42
AI Summary
This document provides the project scheduling plan for Teesside PLC Company using MS Project 2013. It includes the Gantt chart, CPM network, work breakdown structure, resource planning, and cost analysis. The plan covers the initial stage, project planning stage, project design stage, project executing stage, and project monitor stage.

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
University
Semester
M Sc PROJECT MANAGEMENT
ASSIGNMENT 2-PROJECT PLANNING
Student ID
Student Name
Submission Date
1

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Table of Contents
PART 1..................................................................................................................................................2
1. Task A CPM & WBS................................................................................................................3
1.1 Gantt-Chart and CPM Network.........................................................................................3
1.2 Work Breakdown Structure.............................................................................................10
1.3 Identification of the Critical Path.....................................................................................11
2. Task B: Resource Planning......................................................................................................16
2.1 Resource Histograms.......................................................................................................16
2.2 Resource Levelling..........................................................................................................20
2.3 Process of Resource Levelling.........................................................................................24
3. Task C: Cost Analysis.............................................................................................................25
3.1 Project Cost......................................................................................................................25
3.2 Cumulative Cost –time Curve..........................................................................................27
PART 2 - 4D Planning.........................................................................................................................28
1. Synchro Pro Software..............................................................................................................28
2. 4D Planning.............................................................................................................................34
References...........................................................................................................................................36
2
Document Page
PART 1
In this section, we are going to prepare the project scheduling plan for Teesside PLC
Company by using the MS Project 2013. These are discussed in below.
1. Task A CPM & WBS
1.1 Gantt-Chart and CPM Network
The Teesside PLC project scheduling Gantt chart is represented as below (Pinto, 2019).
ID Task
Mode
Task Name
0 Project Scheduling for Teesside PLC
1 Initial Stage
2 Identify Goals and Objectives
3 Develop Strategies and Plans
4 Develop Project Charter
5 Develop and Prepare Preliminary Project Scope Statement
6 Conduct Planning Workshop
7 Document Project Costs and Benefits
8 Conduct Peer Review
9 Project Planning Stage
10 Define Scope
11 Develop Project Support Plans
12 Develop and Prepare Financial Plan
13 Document Subcontractor Management Plan
14 Develop Procurement Plans
15 Develop Staffing Plan
16 Document Quality Management Plan
17 Document Risk Management Plan
18 Develop Risk Plans
19 Develop Resource Plans
20 Plan for Quality
21 Document Scope Management Plan
22 Document Communications Management Plan
23 Document Data Management Plan
24 Develop Project Management Plan
25 Document Project Management Plan
26 Project Design Stage
27 Set Up Project Environment
28 Set Up Project Standards and Procedures
29 Specify Deliverables and Acceptance Criteria
Project Manager[33%]
Project Manager
Project Assistant Manager,Acceptor
Project Analyst,Project Assistant Manager
Project Manager
Project Analyst,Technical Analyst,Project Assistant Manager
Project Assistant Manager
Project Analyst,Project Assistant Manager
Quality Assurance Manager
Project Assistant Manager,Project Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Analyst
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Analyst,Project Assistant Manager
Project Assistant Manager,Acceptor
Project Assistant Manager
Project Assistant Manager
Project Manager
Qual
Project Analyst,Project Assistant Ma
M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T
22 Sep '19 06 Oct '19 20 Oct '19 03 Nov '19 17 Nov '19 01 Dec '19 15 Dec '19 29 Dec '19 12 Jan '20 26 Jan '20 09 Feb '20 23 Feb '20
ID Task
Mode
Task Name
24 Develop Project Management Plan
25 Document Project Management Plan
26 Project Design Stage
27 Set Up Project Environment
28 Set Up Project Standards and Procedures
29 Specify Deliverables and Acceptance Criteria
30 Develop Project Schedule
31 Build Work Breakdown Structure
32 Prepare Proje ct Estimates
33 Define Dependencies and Develop Project Schedule
34 Identify and Analyze Risks
35 Organize Project Resources
36 Develop Organization Structure
37 Determine Procurement Requirements
38 Define Subcontractor Scope
39 Identify Potential Subcontractors
40 Identify Subcontract Type
41 Document Assumptions
42 Project Executing Stage
43 Acquire Proje ct Team
44 Obtain Resources
45 Conduct Team Orientation
46 Assign Responsibilities
47 Direct and Manage Proje ct Exe cution
48 Manage Data and Configuration Items
49 Recognize Success
50 Conduct Project Reviews
51 Project Monitor Stage
52 Monitor Project Work
53 Manage Project Records
Project Assistant Manager
Project Assistant Manager
Project Manager
Quality Assurance Manager,Acceptor
Project Analyst,Project Assistant Manager
Project Manager
Project Manager
Project Analyst,Project Assistant Manager
Contracts Manager
Contracts Manager
Contracts Manager
Contracts Manager
Contracts Manager,Acceptor
Project Assistant Manager,Project Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager,Project Manager,Quality Assurance Manager[67%]
Project Manager
Project Manager
Project Assistant Manager
Quality Assurance Manager
Project Assistant Manager
Project Manager,Acceptor
Quality Assurance Manager
Project As
Projec
S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S
26 Jan '20 09 Feb '20 23 Feb '20 08 Mar '20 22 Mar '20 05 Apr '20 19 Apr '20 03 May '20 17 May '20 31 May '20 14 Jun '20 28 Jun '20
3
Document Page
ID WBS Task
Mode
51 5
52 5.1
53 5.2
54 5.3
55 5.4
56 5.5
57 5.6
58 5.7
59 5.8
60 5.9
61 5.10
62 5.11
63 5.12
64 5.13
65 6
66 6.1
67 6.2
68 6.3
69 6.4
70 6.5
71 6.6
72 6.7
73 6.8
74 6.9
75 6.10
76 6.11
77 6.12
78 7
79 7.1
80 7.2
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Quality Assurance Manager,Technical Analyst
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Quality Assurance Manager,Technical Analyst
Project Assistant Manager,Acceptor
Project Analyst,Project Manager
Project Assistant Manager
Project Assistant Manager
Project Analyst,Project Assistant Manager
Project Assistant Manager
Project Manager
Project Manager
Technical Analyst
Quality Assurance Manager
Quality Assurance Manager
Quality Assurance Manager
Quality Assurance Manager,Technical Analyst
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S
12 Jul '20 26 Jul '20 09 Aug '20 23 Aug '20 06 Sep '20 20 Sep '20 04 Oct '20 18 Oct '20 01 Nov '20 15 Nov '20 29 Nov '20
ID WBS Task
Mode
51 5
52 5.1
53 5.2
54 5.3
55 5.4
56 5.5
57 5.6
58 5.7
59 5.8
60 5.9
61 5.10
62 5.11
63 5.12
64 5.13
65 6
66 6.1
67 6.2
68 6.3
69 6.4
70 6.5
71 6.6
72 6.7
73 6.8
74 6.9
75 6.10
76 6.11
77 6.12
78 7
79 7.1
80 7.2
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Quality Assurance Manager,Technical Analyst
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Quality Assurance Manager,Technical Analyst
Project Assistant Manager,Acceptor
Project Analyst,Project Manager
Project Assistant Manager
Project Assistant Manager
Project Analyst,Project Assistant Manager
Project Assistant Manager
Project Manager
Project Manager
Technical Analyst
Quality Assurance Manager
Quality Assurance Manager
Quality Assurance Manager
Quality Assurance Manager,Technical Analyst
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S
28 Jun '20 12 Jul '20 26 Jul '20 09 Aug '20 23 Aug '20 06 Sep '20 20 Sep '20 04 Oct '20 18 Oct '20 01 Nov '20 15 Nov '20 29 Nov '20
4

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
ID WBS Task
Mode
63 5.12
64 5.13
65 6
66 6.1
67 6.2
68 6.3
69 6.4
70 6.5
71 6.6
72 6.7
73 6.8
74 6.9
75 6.10
76 6.11
77 6.12
78 7
79 7.1
80 7.2
81 7.3
82 7.4
83 7.5
84 7.6
Project Assistant Manager
Project Assistant Manager
Project Analyst,Project Assistant Manager
Project Assistant Manager
Project Manager
Project Manager
Technical Analyst
Quality Assurance Manager
Quality Assurance Manager
Quality Assurance Manager
Quality Assurance Manager,Technical Analyst
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Project Assistant Manager
Contracts Manager
F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W S T M F T S W
28 Jun '20 12 Jul '20 26 Jul '20 09 Aug '20 23 Aug '20 06 Sep '20 20 Sep '20 04 Oct '20 18 Oct '20 01 Nov '20 15 Nov '20 29 Nov '20
The below table is used to provide the calculation about the EST, EFT, LST, LFT
WBS Task Name Early Finish Early Start Late Start Late Finish
0 Project Scheduling for Teesside PLC Tue 10-11-
20
Tue 01-10-
19
Tue 01-10-
19
Tue 10-11-
20
1 Initial Stage Wed 27-11-
19
Tue 01-10-
19
Tue 01-10-
19
Tue 10-11-
20
1.1 Identify Goals and Objectives Fri 04-10-19 Tue 01-10-
19
Tue 01-10-
19
Mon 07-10-
19
1.2 Develop Strategies and Plans Wed 09-10-
19
Mon 07-10-
19
Mon 07-10-
19
Tue 29-10-
19
1.3 Develop Project Charter Wed 27-11-
19
Mon 21-10-
19
Mon 21-10-
19
Tue 10-11-
20
1.4 Develop and Prepare Preliminary
Project Scope Statement
Wed 23-10-
19
Mon 21-10-
19
Mon 21-10-
19
Tue 10-11-
20
1.5 Conduct Planning Workshop Thu 24-10-
19
Mon 21-10-
19
Mon 21-10-
19
Mon 28-10-
19
1.6 Document Project Costs and Benefits Mon 04-11-
19 Fri 25-10-19 Fri 25-10-19 Thu 14-11-
19
1.7 Conduct Peer Review Tue 19-11-
19
Wed 13-11-
19
Wed 13-11-
19
Tue 10-11-
20
2 Planning Stage Thu 13-02-
20
Thu 28-11-
19
Thu 28-11-
19
Tue 10-11-
20
2.1 Define Scope Fri 29-11-
19
Thu 28-11-
19
Thu 28-11-
19
Tue 17-12-
19
2.2 Develop Project Support Plans Wed 04-12-
19
Mon 02-12-
19
Mon 02-12-
19
Tue 10-11-
20
2.3 Develop and Prepare Financial Plan Wed 18-12-
19
Tue 17-12-
19
Tue 17-12-
19
Mon 30-12-
19
2.4 Document Subcontractor Management
Plan
Wed 18-12-
19
Tue 17-12-
19
Tue 17-12-
19
Thu 19-12-
19
2.5 Develop Procurement Plans Fri 20-12-19 Thu 19-12-
19
Thu 19-12-
19
Wed 25-12-
19
2.6 Develop Staffing Plan Fri 27-12-19 Wed 25-12- Wed 25-12- Tue 10-11-
5
Document Page
19 19 20
2.7 Document Quality Management Plan Wed 01-01-
20
Mon 30-12-
19
Mon 30-12-
19
Tue 28-01-
20
2.8 Document Risk Management Plan Wed 01-01-
20
Mon 30-12-
19
Mon 30-12-
19
Thu 02-01-
20
2.9 Develop Risk Plans Tue 07-01-
20
Thu 02-01-
20
Thu 02-01-
20
Thu 09-01-
20
2.10 Develop Resource Plans Wed 15-01-
20
Wed 08-01-
20
Wed 08-01-
20 Fri 17-01-20
2.11 Plan for Quality Wed 22-01-
20
Thu 16-01-
20
Thu 16-01-
20
Thu 23-01-
20
2.12 Document Scope Management Plan Mon 27-01-
20
Thu 23-01-
20
Thu 23-01-
20
Tue 10-11-
20
2.13 Document Communications
Management Plan
Tue 28-01-
20
Tue 28-01-
20
Tue 28-01-
20
Fri 21-02-
20
2.14 Document Data Management Plan Fri 31-01-20 Tue 28-01-
20
Tue 28-01-
20
Tue 04-02-
20
2.15 Develop Project Management Plan Fri 07-02-20 Mon 03-02-
20
Mon 03-02-
20
Mon 10-02-
20
2.16 Document Project Management Plan Thu 13-02-
20
Mon 10-02-
20
Mon 10-02-
20
Thu 20-02-
20
3 Design Stage Tue 07-04-
20 Fri 21-02-20 Fri 21-02-20 Tue 10-11-
20
3.1 Set Up Project Environment Mon 24-02-
20
Fri 21-02-
20
Fri 21-02-
20
Tue 25-02-
20
3.2 Set Up Project Standards and
Procedures
Mon 24-02-
20 Fri 21-02-20 Fri 21-02-20 Tue 10-11-
20
3.3 Specify Deliverables and Acceptance
Criteria
Tue 25-02-
20
Tue 25-02-
20
Tue 25-02-
20
Wed 04-03-
20
3.4 Develop Project Schedule Thu 27-02-
20
Tue 25-02-
20
Tue 25-02-
20 Fri 28-02-20
3.5 Build Work Breakdown Structure Tue 03-03-
20 Fri 28-02-20 Fri 28-02-20 Tue 10-11-
20
3.6 Prepare Project Estimates Wed 04-03-
20
Wed 04-03-
20
Wed 04-03-
20
Mon 30-03-
20
3.7 Define Dependencies and Develop
Project Schedule
Mon 09-03-
20
Wed 04-03-
20
Wed 04-03-
20
Tue 10-03-
20
3.8 Identify and Analyze Risks Fri 13-03-20 Tue 10-03-
20
Tue 10-03-
20
Mon 16-03-
20
3.9 Organize Project Resources Wed 18-03-
20
Mon 16-03-
20
Mon 16-03-
20
Thu 19-03-
20
3.10 Develop Organization Structure Mon 23-03-
20
Thu 19-03-
20
Thu 19-03-
20
Tue 24-03-
20
3.11 Determine Procurement Requirements Fri 27-03-20 Tue 24-03-
20
Tue 24-03-
20
Tue 10-11-
20
3.12 Define Subcontractor Scope Mon 30-03-
20
Mon 30-03-
20
Mon 30-03-
20
Tue 07-04-
20
3.13 Identify Potential Subcontractors Wed 01-04-
20
Mon 30-03-
20
Mon 30-03-
20
Thu 02-04-
20
3.14 Identify Subcontract Type Mon 06-04-
20
Thu 02-04-
20
Thu 02-04-
20
Tue 10-11-
20
6
Document Page
3.15 Document Assumptions Tue 07-04-
20
Tue 07-04-
20
Tue 07-04-
20
Tue 10-11-
20
4 Project Executing Stage Thu 25-06-
20
Tue 21-04-
20
Tue 21-04-
20
Tue 10-11-
20
4.1 Acquire Project Team Thu 23-04-
20
Tue 21-04-
20
Tue 21-04-
20
Tue 05-05-
20
4.2 Obtain Resources Thu 23-04-
20
Tue 21-04-
20
Tue 21-04-
20 Fri 24-04-20
4.3 Conduct Team Orientation Tue 28-04-
20 Fri 24-04-20 Fri 24-04-20 Wed 29-04-
20
4.4 Assign Responsibilities Mon 04-05-
20
Wed 29-04-
20
Wed 29-04-
20
Tue 10-11-
20
4.5 Direct and Manage Project Execution Wed 06-05-
20
Tue 05-05-
20
Tue 05-05-
20
Tue 10-11-
20
4.6 Manage Data and Configuration Items Thu 07-05-
20
Tue 05-05-
20
Tue 05-05-
20
Tue 10-11-
20
4.7 Recognize Success Wed 10-06-
20 Fri 05-06-20 Fri 05-06-20 Tue 10-11-
20
4.8 Conduct Project Reviews Thu 25-06-
20
Mon 22-06-
20
Mon 22-06-
20
Tue 10-11-
20
5 Project Monitor Stage Tue 01-09-
20
Mon 20-07-
20
Mon 20-07-
20
Tue 10-11-
20
5.1 Monitor Project Work Thu 23-07-
20
Mon 20-07-
20
Mon 20-07-
20
Thu 23-07-
20
5.2 Manage Project Records Mon 27-07-
20
Wed 22-07-
20
Wed 22-07-
20
Mon 27-07-
20
5.3 Scope Verification Wed 29-07-
20
Mon 27-07-
20
Mon 27-07-
20
Tue 10-11-
20
5.4 Manage Requirements Thu 30-07-
20
Thu 30-07-
20
Thu 30-07-
20
Thu 20-08-
20
5.5 Manage Project Acceptance Fri 07-08-20 Thu 30-07-
20
Thu 30-07-
20 Fri 07-08-20
5.6 Maintain Project Schedule Tue 11-08-
20
Wed 05-08-
20
Wed 05-08-
20
Tue 11-08-
20
5.7 Risk Monitoring Fri 14-08-20 Mon 10-08-
20
Mon 10-08-
20 Fri 14-08-20
5.8 Maintain Work Plans Wed 19-08-
20
Thu 13-08-
20
Thu 13-08-
20
Tue 10-11-
20
5.9 Manage Finances Thu 20-08-
20
Thu 20-08-
20
Thu 20-08-
20
Mon 24-08-
20
5.10 Monitor Cost/Schedule Variance Fri 21-08-20 Thu 20-08-
20
Thu 20-08-
20
Tue 10-11-
20
5.11 Maintain Financial Plan Mon 24-08-
20
Mon 24-08-
20
Mon 24-08-
20
Mon 07-09-
20
5.12 Measure Quality Levels Thu 27-08-
20
Mon 24-08-
20
Mon 24-08-
20 Fri 28-08-20
5.13 Conduct Team Performance Reviews Tue 01-09-
20 Fri 28-08-20 Fri 28-08-20 Fri 04-09-20
6 Project Control Stage Wed 07-10-
20
Mon 07-09-
20
Mon 07-09-
20
Tue 10-11-
20
6.1 Control Project Work Mon 07-09- Mon 07-09- Mon 07-09- Fri 18-09-
7

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
20 20 20 20
6.2 Maintain the Integrated Change
Control
Wed 09-09-
20
Mon 07-09-
20
Mon 07-09-
20
Thu 10-09-
20
6.3 Control Decisions and Changes Mon 14-09-
20
Thu 10-09-
20
Thu 10-09-
20
Tue 15-09-
20
6.4 Schedule Control Thu 17-09-
20
Tue 15-09-
20
Tue 15-09-
20
Tue 10-11-
20
6.5 Track Status Fri 18-09-
20
Fri 18-09-
20
Fri 18-09-
20
Fri 02-10-
20
6.6 Control Costs Tue 22-09-
20 Fri 18-09-20 Fri 18-09-20 Wed 23-09-
20
6.7 Perform Quality Control Mon 28-09-
20
Wed 23-09-
20
Wed 23-09-
20
Tue 29-09-
20
6.8 Participate in Testing Fri 02-10-20 Tue 29-09-
20
Tue 29-09-
20
Tue 10-11-
20
6.9 Resolve Issues Mon 05-10-
20
Mon 05-10-
20
Mon 05-10-
20
Tue 10-11-
20
6.10 Risk Control Mon 05-10-
20
Mon 05-10-
20
Mon 05-10-
20
Tue 06-10-
20
6.11 Contract Administration Tue 06-10-
20
Tue 06-10-
20
Tue 06-10-
20
Wed 07-10-
20
6.12 Conduct Team Performance Reviews Wed 07-10-
20
Wed 07-10-
20
Wed 07-10-
20
Tue 10-11-
20
7 Project Closing Stage Tue 10-11-
20
Mon 26-10-
20
Mon 26-10-
20
Tue 10-11-
20
7.1 Assess Satisfaction Tue 27-10-
20
Mon 26-10-
20
Mon 26-10-
20
Wed 28-10-
20
7.2 Summarize Project Results and
Lessons Learned Fri 30-10-20 Wed 28-10-
20
Wed 28-10-
20
Mon 02-11-
20
7.3 Review and Recognize Team
Performance
Tue 03-11-
20
Mon 02-11-
20
Mon 02-11-
20
Wed 04-11-
20
7.4 Close Out the Project Records Thu 05-11-
20
Wed 04-11-
20
Wed 04-11-
20 Fri 06-11-20
7.5 Review and Reconcile Financial
Performance
Mon 09-11-
20 Fri 06-11-20 Fri 06-11-20 Tue 10-11-
20
7.6 Close Contract Tue 10-11-
20
Tue 10-11-
20
Tue 10-11-
20
Tue 10-11-
20
Critical Path
The critical path is represented as below.
8
Document Page
9
Document Page
1.2 Work Breakdown Structure
10
PROJECT SCHEDULING FOR TEESSIDE PLC
Initiation Planning and
Design
Executing Monitoring and
Controlling
Closing
Identify Goals
and
Objectives
Develop
Preliminary
Project Scope
Statement
Set Up
Project
Environment
Direct and
Manage
Project
Execution
Acquire
Project Team
Integrated
Change
Control
Monitor and
Control
Project Work
Contract
Closure
Close Project
Define Scope
Scope
Verification
Schedule
Control
Manage
Finances
Perform
Quality
Control
Manage
Project Team
Risk
Monitoring
and Control
Manage
Team
Performance
Assure
Quality
Manage
Project
Communicat
ion
Develop
Project
Schedule
Develop Risk
Plans
Plan for
Quality
Organize
Project
Resources
Develop
Financial
Plan
Develop
Project
Management
Plan
Develop and
Prepare
Preliminary
Project Scope
Statement
Conduct
Planning
Workshop
Document
Project Costs
and Benefits
Conduct Peer
Review

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Importance of WBS Project Management
Work break down structure is used to plan their work more efficiently. It has to plan
for the schedule. It helps make this planning consistent which is used to provide the effective
project execution.
Understand the project scope - The WBS helps to provide the better understand your
project.
Stay on Track - The WBS ensures that project team is headed in the right direction.
Improve the project planning - It will help you to plan better and faster. It accurately
estimates the project cost.
Facilitate Work Allocation - It will help mangers to efficiently distribute the
responsibilities.
Deliver Your Project On Time & Within Budget - It will gain complete visibility over
the progress of project and it can easily track the progress and status of each
component in the WBS.
Improve Communication - It is provides the information regarding the project scope,
deliverables and hierarchy of the project work. The WBS facilitates communication
and coordination between the project manager, his team and all the other stakeholders.
Mitigate Risks - It clearly identifying the all the tasks that are required to complete the
project. It will able to mitigate the risk on when creating a WBS.
Improve Project reporting - The WBS can be used for future similar projects. It helps
to predict the results based on various scenarios and it make the better estimates with
the data found in the WBS.
1.3 Identification of the Critical Path
The critical path in project management as a one of the project modelling technique
which is used to provide the understanding of the longest distance between the start and
finish of the project including the tasks their duration and it provides the clear picture of the
project actual schedule. The critical path method is complete the project which needs to be
broken down and all the activities are needs to be defined. It is provides the information
about the understanding of the project duration. It includes the following techniques such as,
Early Start Time
Early Late Time
Largest Start Time
Largest Late Time
It is illustrated as below.
11
Document Page
WBS Task Name Early Finish Early Start Late Start Late Finish
0 Project Scheduling for Teesside PLC Tue 10-11-
20
Tue 01-10-
19
Tue 01-10-
19
Tue 10-11-
20
1 Initial Stage Wed 27-11-
19
Tue 01-10-
19
Tue 01-10-
19
Tue 10-11-
20
1.1 Identify Goals and Objectives Fri 04-10-19 Tue 01-10-
19
Tue 01-10-
19
Mon 07-10-
19
1.2 Develop Strategies and Plans Wed 09-10-
19
Mon 07-10-
19
Mon 07-10-
19
Tue 29-10-
19
1.3 Develop Project Charter Wed 27-11-
19
Mon 21-10-
19
Mon 21-10-
19
Tue 10-11-
20
1.4 Develop and Prepare Preliminary
Project Scope Statement
Wed 23-10-
19
Mon 21-10-
19
Mon 21-10-
19
Tue 10-11-
20
1.5 Conduct Planning Workshop Thu 24-10-
19
Mon 21-10-
19
Mon 21-10-
19
Mon 28-10-
19
1.6 Document Project Costs and Benefits Mon 04-11-
19 Fri 25-10-19 Fri 25-10-19 Thu 14-11-
19
1.7 Conduct Peer Review Tue 19-11-
19
Wed 13-11-
19
Wed 13-11-
19
Tue 10-11-
20
2 Planning Stage Thu 13-02-
20
Thu 28-11-
19
Thu 28-11-
19
Tue 10-11-
20
2.1 Define Scope Fri 29-11-
19
Thu 28-11-
19
Thu 28-11-
19
Tue 17-12-
19
2.2 Develop Project Support Plans Wed 04-12-
19
Mon 02-12-
19
Mon 02-12-
19
Tue 10-11-
20
2.3 Develop and Prepare Financial Plan Wed 18-12-
19
Tue 17-12-
19
Tue 17-12-
19
Mon 30-12-
19
2.4 Document Subcontractor Management
Plan
Wed 18-12-
19
Tue 17-12-
19
Tue 17-12-
19
Thu 19-12-
19
2.5 Develop Procurement Plans Fri 20-12-19 Thu 19-12-
19
Thu 19-12-
19
Wed 25-12-
19
2.6 Develop Staffing Plan Fri 27-12-19 Wed 25-12-
19
Wed 25-12-
19
Tue 10-11-
20
2.7 Document Quality Management Plan Wed 01-01-
20
Mon 30-12-
19
Mon 30-12-
19
Tue 28-01-
20
2.8 Document Risk Management Plan Wed 01-01-
20
Mon 30-12-
19
Mon 30-12-
19
Thu 02-01-
20
2.9 Develop Risk Plans Tue 07-01-
20
Thu 02-01-
20
Thu 02-01-
20
Thu 09-01-
20
2.10 Develop Resource Plans Wed 15-01-
20
Wed 08-01-
20
Wed 08-01-
20 Fri 17-01-20
2.11 Plan for Quality Wed 22-01-
20
Thu 16-01-
20
Thu 16-01-
20
Thu 23-01-
20
2.12 Document Scope Management Plan Mon 27-01-
20
Thu 23-01-
20
Thu 23-01-
20
Tue 10-11-
20
2.13 Document Communications
Management Plan
Tue 28-01-
20
Tue 28-01-
20
Tue 28-01-
20
Fri 21-02-
20
2.14 Document Data Management Plan Fri 31-01-20 Tue 28-01-
20
Tue 28-01-
20
Tue 04-02-
20
2.15 Develop Project Management Plan Fri 07-02-20 Mon 03-02-
20
Mon 03-02-
20
Mon 10-02-
20
12
Document Page
2.16 Document Project Management Plan Thu 13-02-
20
Mon 10-02-
20
Mon 10-02-
20
Thu 20-02-
20
3 Design Stage Tue 07-04-
20 Fri 21-02-20 Fri 21-02-20 Tue 10-11-
20
3.1 Set Up Project Environment Mon 24-02-
20
Fri 21-02-
20
Fri 21-02-
20
Tue 25-02-
20
3.2 Set Up Project Standards and
Procedures
Mon 24-02-
20 Fri 21-02-20 Fri 21-02-20 Tue 10-11-
20
3.3 Specify Deliverables and Acceptance
Criteria
Tue 25-02-
20
Tue 25-02-
20
Tue 25-02-
20
Wed 04-03-
20
3.4 Develop Project Schedule Thu 27-02-
20
Tue 25-02-
20
Tue 25-02-
20 Fri 28-02-20
3.5 Build Work Breakdown Structure Tue 03-03-
20 Fri 28-02-20 Fri 28-02-20 Tue 10-11-
20
3.6 Prepare Project Estimates Wed 04-03-
20
Wed 04-03-
20
Wed 04-03-
20
Mon 30-03-
20
3.7 Define Dependencies and Develop
Project Schedule
Mon 09-03-
20
Wed 04-03-
20
Wed 04-03-
20
Tue 10-03-
20
3.8 Identify and Analyze Risks Fri 13-03-20 Tue 10-03-
20
Tue 10-03-
20
Mon 16-03-
20
3.9 Organize Project Resources Wed 18-03-
20
Mon 16-03-
20
Mon 16-03-
20
Thu 19-03-
20
3.10 Develop Organization Structure Mon 23-03-
20
Thu 19-03-
20
Thu 19-03-
20
Tue 24-03-
20
3.11 Determine Procurement Requirements Fri 27-03-20 Tue 24-03-
20
Tue 24-03-
20
Tue 10-11-
20
3.12 Define Subcontractor Scope Mon 30-03-
20
Mon 30-03-
20
Mon 30-03-
20
Tue 07-04-
20
3.13 Identify Potential Subcontractors Wed 01-04-
20
Mon 30-03-
20
Mon 30-03-
20
Thu 02-04-
20
3.14 Identify Subcontract Type Mon 06-04-
20
Thu 02-04-
20
Thu 02-04-
20
Tue 10-11-
20
3.15 Document Assumptions Tue 07-04-
20
Tue 07-04-
20
Tue 07-04-
20
Tue 10-11-
20
4 Project Executing Stage Thu 25-06-
20
Tue 21-04-
20
Tue 21-04-
20
Tue 10-11-
20
4.1 Acquire Project Team Thu 23-04-
20
Tue 21-04-
20
Tue 21-04-
20
Tue 05-05-
20
4.2 Obtain Resources Thu 23-04-
20
Tue 21-04-
20
Tue 21-04-
20 Fri 24-04-20
4.3 Conduct Team Orientation Tue 28-04-
20 Fri 24-04-20 Fri 24-04-20 Wed 29-04-
20
4.4 Assign Responsibilities Mon 04-05-
20
Wed 29-04-
20
Wed 29-04-
20
Tue 10-11-
20
4.5 Direct and Manage Project Execution Wed 06-05-
20
Tue 05-05-
20
Tue 05-05-
20
Tue 10-11-
20
4.6 Manage Data and Configuration Items Thu 07-05-
20
Tue 05-05-
20
Tue 05-05-
20
Tue 10-11-
20
4.7 Recognize Success Wed 10-06-
20 Fri 05-06-20 Fri 05-06-20 Tue 10-11-
20
4.8 Conduct Project Reviews Thu 25-06- Mon 22-06- Mon 22-06- Tue 10-11-
13

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
20 20 20 20
5 Project Monitor Stage Tue 01-09-
20
Mon 20-07-
20
Mon 20-07-
20
Tue 10-11-
20
5.1 Monitor Project Work Thu 23-07-
20
Mon 20-07-
20
Mon 20-07-
20
Thu 23-07-
20
5.2 Manage Project Records Mon 27-07-
20
Wed 22-07-
20
Wed 22-07-
20
Mon 27-07-
20
5.3 Scope Verification Wed 29-07-
20
Mon 27-07-
20
Mon 27-07-
20
Tue 10-11-
20
5.4 Manage Requirements Thu 30-07-
20
Thu 30-07-
20
Thu 30-07-
20
Thu 20-08-
20
5.5 Manage Project Acceptance Fri 07-08-20 Thu 30-07-
20
Thu 30-07-
20 Fri 07-08-20
5.6 Maintain Project Schedule Tue 11-08-
20
Wed 05-08-
20
Wed 05-08-
20
Tue 11-08-
20
5.7 Risk Monitoring Fri 14-08-20 Mon 10-08-
20
Mon 10-08-
20 Fri 14-08-20
5.8 Maintain Work Plans Wed 19-08-
20
Thu 13-08-
20
Thu 13-08-
20
Tue 10-11-
20
5.9 Manage Finances Thu 20-08-
20
Thu 20-08-
20
Thu 20-08-
20
Mon 24-08-
20
5.10 Monitor Cost/Schedule Variance Fri 21-08-20 Thu 20-08-
20
Thu 20-08-
20
Tue 10-11-
20
5.11 Maintain Financial Plan Mon 24-08-
20
Mon 24-08-
20
Mon 24-08-
20
Mon 07-09-
20
5.12 Measure Quality Levels Thu 27-08-
20
Mon 24-08-
20
Mon 24-08-
20 Fri 28-08-20
5.13 Conduct Team Performance Reviews Tue 01-09-
20 Fri 28-08-20 Fri 28-08-20 Fri 04-09-20
6 Project Control Stage Wed 07-10-
20
Mon 07-09-
20
Mon 07-09-
20
Tue 10-11-
20
6.1 Control Project Work Mon 07-09-
20
Mon 07-09-
20
Mon 07-09-
20
Fri 18-09-
20
6.2 Maintain the Integrated Change
Control
Wed 09-09-
20
Mon 07-09-
20
Mon 07-09-
20
Thu 10-09-
20
6.3 Control Decisions and Changes Mon 14-09-
20
Thu 10-09-
20
Thu 10-09-
20
Tue 15-09-
20
6.4 Schedule Control Thu 17-09-
20
Tue 15-09-
20
Tue 15-09-
20
Tue 10-11-
20
6.5 Track Status Fri 18-09-
20
Fri 18-09-
20
Fri 18-09-
20
Fri 02-10-
20
6.6 Control Costs Tue 22-09-
20 Fri 18-09-20 Fri 18-09-20 Wed 23-09-
20
6.7 Perform Quality Control Mon 28-09-
20
Wed 23-09-
20
Wed 23-09-
20
Tue 29-09-
20
6.8 Participate in Testing Fri 02-10-20 Tue 29-09-
20
Tue 29-09-
20
Tue 10-11-
20
6.9 Resolve Issues Mon 05-10-
20
Mon 05-10-
20
Mon 05-10-
20
Tue 10-11-
20
6.10 Risk Control Mon 05-10-
20
Mon 05-10-
20
Mon 05-10-
20
Tue 06-10-
20
14
Document Page
6.11 Contract Administration Tue 06-10-
20
Tue 06-10-
20
Tue 06-10-
20
Wed 07-10-
20
6.12 Conduct Team Performance Reviews Wed 07-10-
20
Wed 07-10-
20
Wed 07-10-
20
Tue 10-11-
20
7 Project Closing Stage Tue 10-11-
20
Mon 26-10-
20
Mon 26-10-
20
Tue 10-11-
20
7.1 Assess Satisfaction Tue 27-10-
20
Mon 26-10-
20
Mon 26-10-
20
Wed 28-10-
20
7.2 Summarize Project Results and
Lessons Learned Fri 30-10-20 Wed 28-10-
20
Wed 28-10-
20
Mon 02-11-
20
7.3 Review and Recognize Team
Performance
Tue 03-11-
20
Mon 02-11-
20
Mon 02-11-
20
Wed 04-11-
20
7.4 Close Out the Project Records Thu 05-11-
20
Wed 04-11-
20
Wed 04-11-
20 Fri 06-11-20
7.5 Review and Reconcile Financial
Performance
Mon 09-11-
20 Fri 06-11-20 Fri 06-11-20 Tue 10-11-
20
7.6 Close Contract Tue 10-11-
20
Tue 10-11-
20
Tue 10-11-
20
Tue 10-11-
20
The identified critical tasks are illustrated as below.
Name Start Finish %
Complet
e
Remainin
g Work
Resource
Names
Monitor Project Work Mon
20-07-
20
Thu 23-
07-20
25% 12 hrs Project
Assistant
Manager
Manage Project Records Wed
22-07-
20
Mon 27-
07-20
25% 18 hrs Project
Assistant
Manager
Manage Project
Acceptance
Thu 30-
07-20
Fri 07-
08-20
25% 24 hrs Project
Assistant
Manager
Maintain Project
Schedule
Wed
05-08-
20
Tue 11-
08-20
25% 18 hrs Project
Assistant
Manager
15
Document Page
Risk Monitoring Mon
10-08-
20
Fri 14-
08-20
25% 18 hrs Project
Assistant
Manager
Close Contract Tue 10-
11-20
Tue 10-
11-20
25% 6 hrs Contracts
Manager
2. Task B: Resource Planning
2.1 Resource Histograms
Overall the resource and its information are illustrated as below (Heerkens, 2015).
The Resource histogram for the skilled labour resource is illustrated as below.
Project
Manager Project
Assistant
Manager
Acceptor Project
Analyst Technical
Analyst Quality
Assurance
Manager
Contracts
Manager
0 hrs
200 hrs
400 hrs
600 hrs
800 hrs
1,000 hrs
1,200 hrs
1,400 hrs
1,600 hrs
1,800 hrs
Actual Work Remaining Work Baseline Work
16

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Name Start Finish Remaining Work
17
Document Page
Project Manager Tue 01-10-19 Thu 17-09-20 234.5 hrs
Project Assistant Manager Mon 21-10-19 Mon 09-11-
20
1,376.5 hrs
Acceptor Mon 21-10-19 Fri 21-08-20 518 hrs
Project Analyst Mon 21-10-19 Mon 07-09-
20
82 hrs
Technical Analyst Fri 25-10-19 Mon 05-10-
20
26 hrs
Quality Assurance Manager Mon 02-12-19 Mon 05-10-
20
163.33 hrs
Contracts Manager Wed 04-03-20 Tue 10-11-20 114 hrs
The identified maximum numbers unit of each resource for this project is illustrated as below.
WBS Task Name Resource Names
0 Project Scheduling for Teesside PLC
1 Initial Stage
1.1 Identify Goals and Objectives Project Manager[33%]
1.2 Develop Strategies and Plans Project Manager
1.3 Develop Project Charter Project Assistant Manager,Acceptor
1.4 Develop and Prepare Preliminary Project
Scope Statement
Project Analyst,Project Assistant
Manager
1.5 Conduct Planning Workshop Project Manager
1.6 Document Project Costs and Benefits Project Analyst,Technical
Analyst,Project Assistant Manager
1.7 Conduct Peer Review Project Assistant Manager
2 Planning Stage
2.1 Define Scope Project Analyst,Project Assistant
Manager
2.2 Develop Project Support Plans Quality Assurance Manager
2.3 Develop and Prepare Financial Plan Project Assistant Manager,Project
18
Document Page
Manager
2.4 Document Subcontractor Management
Plan Project Assistant Manager
2.5 Develop Procurement Plans Project Assistant Manager
2.6 Develop Staffing Plan Project Assistant Manager
2.7 Document Quality Management Plan Project Analyst
2.8 Document Risk Management Plan Project Assistant Manager
2.9 Develop Risk Plans Project Assistant Manager
2.10 Develop Resource Plans Project Assistant Manager
2.11 Plan for Quality Project Assistant Manager
2.12 Document Scope Management Plan Project Assistant Manager
2.13 Document Communications Management
Plan
Project Analyst,Project Assistant
Manager
2.14 Document Data Management Plan Project Assistant Manager,Acceptor
2.15 Develop Project Management Plan Project Assistant Manager
2.16 Document Project Management Plan Project Assistant Manager
3 Design Stage Project Assistant Manager,Acceptor
3.1 Set Up Project Environment Project Manager
3.2 Set Up Project Standards and Procedures Quality Assurance
Manager,Acceptor
3.3 Specify Deliverables and Acceptance
Criteria
Project Analyst,Project Assistant
Manager
3.4 Develop Project Schedule Project Manager
3.5 Build Work Breakdown Structure Project Manager
3.6 Prepare Project Estimates Project Analyst,Project Assistant
Manager
3.7 Define Dependencies and Develop Project
Schedule Contracts Manager
3.8 Identify and Analyze Risks Contracts Manager
3.9 Organize Project Resources Contracts Manager
3.10 Develop Organization Structure Contracts Manager
3.11 Determine Procurement Requirements Contracts Manager,Acceptor
19

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
3.12 Define Subcontractor Scope Project Assistant Manager,Project
Manager
3.13 Identify Potential Subcontractors Project Assistant Manager
3.14 Identify Subcontract Type Project Assistant Manager
3.15 Document Assumptions
4 Project Executing Stage
4.1 Acquire Project Team
Project Assistant Manager,Project
Manager,Quality Assurance
Manager[67%]
4.2 Obtain Resources Project Manager
4.3 Conduct Team Orientation Project Manager
4.4 Assign Responsibilities Project Assistant Manager
4.5 Direct and Manage Project Execution Quality Assurance Manager
4.6 Manage Data and Configuration Items Project Assistant Manager
4.7 Recognize Success Project Manager,Acceptor
4.8 Conduct Project Reviews Quality Assurance Manager
5 Project Monitor Stage
5.1 Monitor Project Work Project Assistant Manager
5.2 Manage Project Records Project Assistant Manager
5.3 Scope Verification Project Assistant Manager
5.4 Manage Requirements Quality Assurance
Manager,Technical Analyst
5.5 Manage Project Acceptance Project Assistant Manager
5.6 Maintain Project Schedule Project Assistant Manager
5.7 Risk Monitoring Project Assistant Manager
5.8 Maintain Work Plans Project Assistant Manager
5.9 Manage Finances Quality Assurance
Manager,Technical Analyst
5.10 Monitor Cost/Schedule Variance Project Assistant Manager,Acceptor
5.11 Maintain Financial Plan Project Analyst,Project Manager
5.12 Measure Quality Levels Project Assistant Manager
20
Document Page
5.13 Conduct Team Performance Reviews Project Assistant Manager
6 Project Control Stage Project Assistant Manager
6.1 Control Project Work Project Analyst,Project Assistant
Manager
6.2 Maintain the Integrated Change Control Project Assistant Manager
6.3 Control Decisions and Changes Project Manager
6.4 Schedule Control Project Manager
6.5 Track Status Technical Analyst
6.6 Control Costs Quality Assurance Manager
6.7 Perform Quality Control Quality Assurance Manager
6.8 Participate in Testing Quality Assurance Manager
6.9 Resolve Issues Quality Assurance
Manager,Technical Analyst
6.10 Risk Control Project Assistant Manager
6.11 Contract Administration Project Assistant Manager
6.12 Conduct Team Performance Reviews Project Assistant Manager
7 Project Closing Stage
7.1 Assess Satisfaction Project Assistant Manager
7.2 Summarize Project Results and Lessons
Learned Project Assistant Manager
7.3 Review and Recognize Team Performance Project Assistant Manager
7.4 Close Out the Project Records Project Assistant Manager
7.5 Review and Reconcile Financial
Performance Project Assistant Manager
7.6 Close Contract Contracts Manager
2.2 Resource Levelling
Here, we are set the resource levelling for unskilled resource like Acceptor. It is
illustrated as below.
21
Document Page
Based on resource levelling for unskilled resource like Acceptor, the activities are
delayed beyond the LST. It is illustrated as below.
WBS Task Name Resource Names Late Start
2.6 Develop Staffing Plan Project Assistant
Manager Wed 25-12-19
0 Project Scheduling for Teesside PLC Tue 01-10-19
1 Initial Stage Tue 01-10-19
1.1 Identify Goals and Objectives Project Manager[33%] Tue 01-10-19
1.2 Develop Strategies and Plans Project Manager Mon 07-10-19
1.3 Develop Project Charter Project Assistant
Manager,Acceptor Mon 21-10-19
1.4 Develop and Prepare Preliminary Project Scope
Statement
Project Analyst,Project
Assistant Manager Mon 21-10-19
1.5 Conduct Planning Workshop Project Manager Mon 21-10-19
1.6 Document Project Costs and Benefits
Project
Analyst,Technical
Analyst,Project
Assistant Manager
Fri 25-10-19
1.7 Conduct Peer Review Project Assistant
Manager Wed 13-11-19
2 Planning Stage Thu 28-11-19
2.1 Define Scope Project Analyst,Project
Assistant Manager Thu 28-11-19
2.2 Develop Project Support Plans Quality Assurance
Manager Mon 02-12-19
2.3 Develop and Prepare Financial Plan
Project Assistant
Manager,Project
Manager
Tue 17-12-19
2.4 Document Subcontractor Management Plan Project Assistant
Manager Tue 17-12-19
22

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
2.5 Develop Procurement Plans Project Assistant
Manager Thu 19-12-19
2.7 Document Quality Management Plan Project Analyst Mon 30-12-19
2.8 Document Risk Management Plan Project Assistant
Manager Mon 30-12-19
2.9 Develop Risk Plans Project Assistant
Manager Thu 02-01-20
2.10 Develop Resource Plans Project Assistant
Manager Wed 08-01-20
2.11 Plan for Quality Project Assistant
Manager Thu 16-01-20
2.12 Document Scope Management Plan Project Assistant
Manager Thu 23-01-20
2.13 Document Communications Management Plan
Project
Analyst,Project
Assistant Manager
Tue 28-01-20
2.14 Document Data Management Plan Project Assistant
Manager,Acceptor Tue 28-01-20
2.15 Develop Project Management Plan Project Assistant
Manager Mon 03-02-20
2.16 Document Project Management Plan Project Assistant
Manager Mon 10-02-20
3 Design Stage Project Assistant
Manager,Acceptor Fri 21-02-20
3.1 Set Up Project Environment Project Manager Fri 21-02-20
3.2 Set Up Project Standards and Procedures Quality Assurance
Manager,Acceptor Fri 21-02-20
3.3 Specify Deliverables and Acceptance Criteria
Project
Analyst,Project
Assistant Manager
Tue 25-02-20
3.4 Develop Project Schedule Project Manager Tue 25-02-20
3.5 Build Work Breakdown Structure Project Manager Fri 28-02-20
3.6 Prepare Project Estimates
Project
Analyst,Project
Assistant Manager
Wed 04-03-20
3.7 Define Dependencies and Develop Project
Schedule Contracts Manager Wed 04-03-20
3.8 Identify and Analyze Risks Contracts Manager Tue 10-03-20
3.9 Organize Project Resources Contracts Manager Mon 16-03-20
3.10 Develop Organization Structure Contracts Manager Thu 19-03-20
3.11 Determine Procurement Requirements Contracts
Manager,Acceptor Tue 24-03-20
3.12 Define Subcontractor Scope
Project Assistant
Manager,Project
Manager
Mon 30-03-20
3.13 Identify Potential Subcontractors Project Assistant
Manager Mon 30-03-20
3.14 Identify Subcontract Type Project Assistant
Manager Thu 02-04-20
3.15 Document Assumptions Tue 07-04-20
23
Document Page
4 Project Executing Stage Tue 21-04-20
4.1 Acquire Project Team
Project Assistant
Manager,Project
Manager,Quality
Assurance
Manager[67%]
Tue 21-04-20
4.2 Obtain Resources Project Manager Tue 21-04-20
4.3 Conduct Team Orientation Project Manager Fri 24-04-20
4.4 Assign Responsibilities Project Assistant
Manager Wed 29-04-20
4.5 Direct and Manage Project Execution Quality Assurance
Manager Tue 05-05-20
4.6 Manage Data and Configuration Items Project Assistant
Manager Tue 05-05-20
4.7 Recognize Success Project
Manager,Acceptor Fri 05-06-20
4.8 Conduct Project Reviews Quality Assurance
Manager Mon 22-06-20
5 Project Monitor Stage Mon 20-07-20
5.1 Monitor Project Work Project Assistant
Manager Mon 20-07-20
5.2 Manage Project Records Project Assistant
Manager Wed 22-07-20
5.3 Scope Verification Project Assistant
Manager Mon 27-07-20
5.4 Manage Requirements
Quality Assurance
Manager,Technical
Analyst
Thu 30-07-20
5.5 Manage Project Acceptance Project Assistant
Manager Thu 30-07-20
5.6 Maintain Project Schedule Project Assistant
Manager Wed 05-08-20
5.7 Risk Monitoring Project Assistant
Manager Mon 10-08-20
5.8 Maintain Work Plans Project Assistant
Manager Thu 13-08-20
5.9 Manage Finances
Quality Assurance
Manager,Technical
Analyst
Thu 20-08-20
5.10 Monitor Cost/Schedule Variance Project Assistant
Manager,Acceptor Thu 20-08-20
5.11 Maintain Financial Plan
Project
Analyst,Project
Manager
Mon 24-08-20
5.12 Measure Quality Levels Project Assistant
Manager Mon 24-08-20
5.13 Conduct Team Performance Reviews Project Assistant
Manager Fri 28-08-20
6 Project Control Stage Project Assistant
Manager Mon 07-09-20
6.1 Control Project Work Project Mon 07-09-20
24
Document Page
Analyst,Project
Assistant Manager
6.2 Maintain the Integrated Change Control Project Assistant
Manager Mon 07-09-20
6.3 Control Decisions and Changes Project Manager Thu 10-09-20
6.4 Schedule Control Project Manager Tue 15-09-20
6.5 Track Status Technical Analyst Fri 18-09-20
6.6 Control Costs Quality Assurance
Manager Fri 18-09-20
6.7 Perform Quality Control Quality Assurance
Manager Wed 23-09-20
6.8 Participate in Testing Quality Assurance
Manager Tue 29-09-20
6.9 Resolve Issues
Quality Assurance
Manager,Technical
Analyst
Mon 05-10-20
6.10 Risk Control Project Assistant
Manager Mon 05-10-20
6.11 Contract Administration Project Assistant
Manager Tue 06-10-20
6.12 Conduct Team Performance Reviews Project Assistant
Manager Wed 07-10-20
7 Project Closing Stage Mon 26-10-20
7.1 Assess Satisfaction Project Assistant
Manager Mon 26-10-20
7.2 Summarize Project Results and Lessons Learned Project Assistant
Manager Wed 28-10-20
7.3 Review and Recognize Team Performance Project Assistant
Manager Mon 02-11-20
7.4 Close Out the Project Records Project Assistant
Manager Wed 04-11-20
7.5 Review and Reconcile Financial Performance Project Assistant
Manager Fri 06-11-20
7.6 Close Contract Contracts Manager Tue 10-11-20
2.3 Process of Resource Levelling
The process of resource levelling is used to defining the term resources in the project.
It focuses only on the equipment and people. It begins with the initial schedule and work
package resource requirements. It is used to maintain the schedule optimization in the face of
the resource constraints and dependences. It is an approach to project scheduling where by
the activities are start and end dates are determined by the availability of the external and
internal resources. It is used to resolve the over allocations by moving the task start and end
dates or extending the task durations in order to suit the resource availability (Meredith,
2019).
25

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
3. Task C: Cost Analysis
3.1 Project Cost
The cost of each activity in the project is illustrated as below.
WBS Task Name Duration Start Finish Cost
0 Project Scheduling for Teesside
PLC 291 days Tue 01-10-19 Tue 10-11-
20 £31,160.00
1 Initial Stage 42 days Tue 01-10-19 Wed 27-11-
19 £6,626.67
1.1 Identify Goals and Objectives 4 days Tue 01-10-19 Fri 04-10-19 £106.67
1.2 Develop Strategies and Plans 3 days Mon 07-10-19 Wed 09-10-
19 £240.00
1.3 Develop Project Charter 28 days Mon 21-10-19 Wed 27-11-
19 £4,480.00
1.4 Develop and Prepare Preliminary
Project Scope Statement 3 days Mon 21-10-
19
Wed 23-10-
19 £480.00
1.5 Conduct Planning Workshop 4 days Mon 21-10-19 Thu 24-10-19 £320.00
1.6 Document Project Costs and
Benefits 7 days Fri 25-10-19 Mon 04-11-
19 £600.00
1.7 Conduct Peer Review 5 days Wed 13-11-19 Tue 19-11-19 £400.00
2 Planning Stage 56 days Thu 28-11-19 Thu 13-02-20 £4,880.00
2.1 Define Scope 2 days Thu 28-11-19 Fri 29-11-19 £320.00
2.2 Develop Project Support Plans 3 days Mon 02-12-19 Wed 04-12-
19 £240.00
2.3 Develop and Prepare Financial
Plan 2 days Tue 17-12-19 Wed 18-12-
19 £320.00
2.4 Document Subcontractor
Management Plan 2 days Tue 17-12-19 Wed 18-12-
19 £160.00
2.5 Develop Procurement Plans 2 days Thu 19-12-19 Fri 20-12-19 £160.00
2.6 Develop Staffing Plan 3 days Wed 25-12-19 Fri 27-12-19 £240.00
2.7 Document Quality Management
Plan 3 days Mon 30-12-
19
Wed 01-01-
20 £240.00
2.8 Document Risk Management Plan 3 days Mon 30-12-19 Wed 01-01-
20 £240.00
2.9 Develop Risk Plans 4 days Thu 02-01-20 Tue 07-01-20 £320.00
2.10 Develop Resource Plans 6 days Wed 08-01-20 Wed 15-01-
20 £480.00
2.11 Plan for Quality 5 days Thu 16-01-20 Wed 22-01-
20 £400.00
2.12 Document Scope Management
Plan 3 days Thu 23-01-20 Mon 27-01-
20 £240.00
2.13 Document Communications
Management Plan 1 day Tue 28-01-20 Tue 28-01-
20 £160.00
2.14 Document Data Management Plan 4 days Tue 28-01-20 Fri 31-01-20 £640.00
2.15 Develop Project Management Plan 5 days Mon 03-02-20 Fri 07-02-20 £400.00
2.16 Document Project Management
Plan 4 days Mon 10-02-20 Thu 13-02-20 £320.00
3 Design Stage 33 days Fri 21-02-20 Tue 07-04-20 £8,960.00
3.1 Set Up Project Environment 2 days Fri 21-02-20 Mon 24-02- £160.00
26
Document Page
20
3.2 Set Up Project Standards and
Procedures 2 days Fri 21-02-20 Mon 24-02-
20 £320.00
3.3 Specify Deliverables and
Acceptance Criteria 1 day Tue 25-02-20 Tue 25-02-
20 £160.00
3.4 Develop Project Schedule 3 days Tue 25-02-20 Thu 27-02-20 £240.00
3.5 Build Work Breakdown Structure 3 days Fri 28-02-20 Tue 03-03-20 £240.00
3.6 Prepare Project Estimates 1 day Wed 04-03-
20
Wed 04-03-
20 £160.00
3.7 Define Dependencies and Develop
Project Schedule 4 days Wed 04-03-20 Mon 09-03-
20 £320.00
3.8 Identify and Analyze Risks 4 days Tue 10-03-20 Fri 13-03-20 £320.00
3.9 Organize Project Resources 3 days Mon 16-03-20 Wed 18-03-
20 £240.00
3.10 Develop Organization Structure 3 days Thu 19-03-20 Mon 23-03-
20 £240.00
3.11 Determine Procurement
Requirements 4 days Tue 24-03-20 Fri 27-03-20 £640.00
3.12 Define Subcontractor Scope 1 day Mon 30-03-
20
Mon 30-03-
20 £160.00
3.13 Identify Potential Subcontractors 3 days Mon 30-03-20 Wed 01-04-
20 £240.00
3.14 Identify Subcontract Type 3 days Thu 02-04-20 Mon 06-04-
20 £240.00
3.15 Document Assumptions 1 day Tue 07-04-20 Tue 07-04-
20 £0.00
4 Project Executing Stage 48 days Tue 21-04-20 Thu 25-06-
20 £2,453.33
4.1 Acquire Project Team 2 days Tue 21-04-20 Thu 23-04-
20 £373.33
4.2 Obtain Resources 3 days Tue 21-04-20 Thu 23-04-20 £240.00
4.3 Conduct Team Orientation 3 days Fri 24-04-20 Tue 28-04-20 £240.00
4.4 Assign Responsibilities 4 days Wed 29-04-20 Mon 04-05-
20 £320.00
4.5 Direct and Manage Project
Execution 2 days Tue 05-05-20 Wed 06-05-
20 £160.00
4.6 Manage Data and Configuration
Items 3 days Tue 05-05-20 Thu 07-05-20 £240.00
4.7 Recognize Success 4 days Fri 05-06-20 Wed 10-06-
20 £560.00
4.8 Conduct Project Reviews 4 days Mon 22-06-20 Thu 25-06-20 £320.00
5 Project Monitor Stage 32 days Mon 20-07-
20
Tue 01-09-
20 £3,200.00
5.1 Monitor Project Work 2 days Mon 20-07-20 Thu 23-07-20 £160.00
5.2 Manage Project Records 3 days Wed 22-07-20 Mon 27-07-
20 £240.00
5.3 Scope Verification 3 days Mon 27-07-20 Wed 29-07-
20 £240.00
5.4 Manage Requirements 1 day Thu 30-07-20 Thu 30-07-
20 £160.00
27
Document Page
5.5 Manage Project Acceptance 4 days Thu 30-07-20 Fri 07-08-20 £320.00
5.6 Maintain Project Schedule 3 days Wed 05-08-20 Tue 11-08-20 £240.00
5.7 Risk Monitoring 3 days Mon 10-08-20 Fri 14-08-20 £240.00
5.8 Maintain Work Plans 5 days Thu 13-08-20 Wed 19-08-
20 £400.00
5.9 Manage Finances 1 day Thu 20-08-20 Thu 20-08-
20 £160.00
5.10 Monitor Cost/Schedule Variance 2 days Thu 20-08-20 Fri 21-08-20 £320.00
5.11 Maintain Financial Plan 1 day Mon 24-08-
20
Mon 24-08-
20 £160.00
5.12 Measure Quality Levels 4 days Mon 24-08-20 Thu 27-08-20 £320.00
5.13 Conduct Team Performance
Reviews 3 days Fri 28-08-20 Tue 01-09-20 £240.00
6 Project Control Stage 23 days Mon 07-09-20 Wed 07-10-
20 £4,080.00
6.1 Control Project Work 1 day Mon 07-09-
20
Mon 07-09-
20 £160.00
6.2 Maintain the Integrated Change
Control 3 days Mon 07-09-20 Wed 09-09-
20 £240.00
6.3 Control Decisions and Changes 3 days Thu 10-09-20 Mon 14-09-
20 £240.00
6.4 Schedule Control 3 days Tue 15-09-20 Thu 17-09-20 £240.00
6.5 Track Status 1 day Fri 18-09-20 Fri 18-09-20 £80.00
6.6 Control Costs 3 days Fri 18-09-20 Tue 22-09-20 £240.00
6.7 Perform Quality Control 4 days Wed 23-09-20 Mon 28-09-
20 £320.00
6.8 Participate in Testing 4 days Tue 29-09-20 Fri 02-10-20 £320.00
6.9 Resolve Issues 1 day Mon 05-10-
20
Mon 05-10-
20 £160.00
6.10 Risk Control 1 day Mon 05-10-20 Mon 05-10-
20 £80.00
6.11 Contract Administration 1 day Tue 06-10-20 Tue 06-10-20 £80.00
6.12 Conduct Team Performance
Reviews 1 day Wed 07-10-20 Wed 07-10-
20 £80.00
7 Project Closing Stage 12 days Mon 26-10-
20
Tue 10-11-
20 £960.00
7.1 Assess Satisfaction 2 days Mon 26-10-20 Tue 27-10-20 £160.00
7.2 Summarize Project Results and
Lessons Learned 3 days Wed 28-10-20 Fri 30-10-20 £240.00
7.3 Review and Recognize Team
Performance 2 days Mon 02-11-20 Tue 03-11-20 £160.00
7.4 Close Out the Project Records 2 days Wed 04-11-20 Thu 05-11-20 £160.00
7.5 Review and Reconcile Financial
Performance 2 days Fri 06-11-20 Mon 09-11-
20 £160.00
7.6 Close Contract 1 day Tue 10-11-20 Tue 10-11-20 £80.00
3.2 Cumulative Cost –time Curve
The cumulative cost time curve for this project is illustrated as below.
28

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4 1 2 3 4
£0.00
£2,000.00
£4,000.00
£6,000.00
£8,000.00
£10,000.00
£12,000.00
£0.00
£5,000.00
£10,000.00
£15,000.00
£20,000.00
£25,000.00
£30,000.00
£35,000.00
Cost Cumulative Cost
Name Remainin
g Cost
Actual
Cost
Cost ACWP BCW
P
BCWS
Initial Stage £4,940.00 £1,686.6
7
£6,626.6
7
£0.00 £0.00 £0.00
Planning Stage £3,740.00 £1,140.0
0
£4,880.0
0
£0.00 £0.00 £0.00
Design Stage £7,860.00 £1,100.0
0
£8,960.0
0
£0.00 £0.00 £0.00
Project Executing
Stage
£1,983.33 £470.00 £2,453.3
3
£0.00 £0.00 £0.00
Project Monitor
Stage
£2,400.00 £800.00 £3,200.0
0
£0.00 £0.00 £0.00
Project Control
Stage
£3,500.00 £580.00 £4,080.0
0
£0.00 £0.00 £0.00
Project Closing
Stage
£720.00 £240.00 £960.00 £0.00 £0.00 £0.00
29
Document Page
PART 2 - 4D Planning
1. Synchro Pro Software
In this section we are going to use the Synchro Pro software and connecting the date of
building project planning with the specified 3D CAD building model. To use the Synchro Pro
by using below steps (blog.synchroltd.com, 2019),
First, convert the MS project file to XML format.
After, open the Synchro Pro software and it is represented as below.
Click file to choose the Import to Import the MS project file. It is illustrated as below
(www.4dplanning.com, 2019).
30
Document Page
31

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Once, import the XML file for project plan, you we will the project scheduling plan
on Synchro Pro software which is illustrated as below.
32
Document Page
After, identified the issue which is occurred on the tasks limit. So, reduce the tasks,
after it supported to successfully import the project management data file. The proposed plans
and changes are listed in below.
33
Document Page
34

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
2. 4D Planning
The 4D planning is used to visualizing the schedule which is based on building the
information modelling. The building information modelling (BIM) is a project that came to
revolutionize the work flow of the AEC industry. It is focuses to linking the 3D geometrical
models with scheduling and time (www.projectcontrolacademy.com, 2019). The 4D planning
is used to combine the other scheduling method which is used to facilitate the communication
35
Document Page
and decision making through the planning and construction phase. It is a rising system which
consolidates the 3D CAD models with exercises of development and furthermore it
sufficiently interfaces the hole between the booking, development and structure. It is very
regular by utilizing the conventional techniques for planning, for example, basic way
strategy, Gantt diagram and these are utilized to recognize the challenges synchronization
either with the structure and continuous development. It additionally bolsters the techniques
for planning strengthening the schedule dependability and makes the exact and subtleties the
work breakdown structure dependent on the sources. It has three methodologies are created
using the BIM promise in planning. Initial one is identified with the time which can be
accomplished by determining the developments period of every individual component that is
imagined by visual recreation of schedule. The second one is familiar to consolidating the
BIM segment and development technique data which is utilized to upgrade the action
arrangement. The third one is to concerns the relationship of 4D planning.
Favourable Benefits of 4D planning is represented as below.
Communication - The representation of the 4D planning is utilized to gives the
productive correspondence among all the venture partners and it abusing the
potential outcomes of catching the both spatial and transient parts of a scheduling.
It is utilized to reduce the irregularities (Heerkens, 2015).
Site Management - It the difficult part in development the executives at the same
time, the 4D planning is effectively deal with the site zone. It effectively assesses
the model based schedule. It guarantees site get to, capacity areas and exchange
stacking.
Cost and Time - The 4D planning is utilized to end up being significant resource as
far as expense and time. It is likewise decrease the time spend in improve. It totals
the all the required data in a single source and distinguish the unanticipated time
clashes to limiting the expense.
Procurement - The planning of material necessities and request and precise time
plan is to accomplish the fruitful material following and acquiring. In obtainment
technique, it is accustomed to following the material and administrations status y
utilizing the exercises of the acquisition in the planning and structure.
Safety Management - In wellbeing the board, the HR are assume a noteworthy job
in undertakings which is enables 4D modelling to impact the spatial requirements
for individuals (www.synchroltd.com, 2019).
36
Document Page
Quality of Schedule - The 4D planning is utilized to improve the by and large the
schedule quality and thus of the activities.
References
blog.synchroltd.com. (2019). 4D Planning: What it can do for you - Synchro. [online]
Available at: http://blog.synchroltd.com/4d-planning-what-it-can-do-for-you [Accessed 4
May 2019].
Heerkens, G. (2015). Project management. [Place of publication not identified]: Mcgraw-Hill
Education.
Meredith, J. (2019). Project Management. New York: Wiley.
Pinto, J. (2019). Project Management. Harlow, United Kingdom: Pearson Education Limited.
www.4dplanning.com. (2019). Planning Consultants London | Planning Applications
Appeals. [online] Available at: https://www.4dplanning.com/ [Accessed 4 May 2019].
www.projectcontrolacademy.com. (2019). 4D Scheduling and Planning Future of Project
Controls. [online] Available at: https://www.projectcontrolacademy.com/4d-scheduling/
[Accessed 4 May 2019].
www.synchroltd.com. (2019). Synchro - Construction project management software │4D ....
[online] Available at: https://www.synchroltd.com/ [Accessed 4 May 2019].
37
1 out of 37
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]